CN105839903A CN201610242626.2A CN201610242626A CN105839903A CN 105839903 A CN105839903 A CN 105839903A CN 201610242626 A CN201610242626 A CN 201610242626A CN 105839903 A CN105839903 A CN 105839903A
Authority
CN
China
Prior art keywords
wall brick
slip casting
plastering
storage case
pulp
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610242626.2A
Other languages
Chinese (zh)
Other versions
CN105839903B (en
Inventor
刘合敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangtze Normal University
Original Assignee
Yangtze Normal University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yangtze Normal University filed Critical Yangtze Normal University
Priority to CN201610242626.2A priority Critical patent/CN105839903B/en
Publication of CN105839903A publication Critical patent/CN105839903A/en
Application granted granted Critical
Publication of CN105839903B publication Critical patent/CN105839903B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/18Implements for finishing work on buildings for setting wall or ceiling slabs or plates
    • E04F21/1838Implements for finishing work on buildings for setting wall or ceiling slabs or plates for setting a plurality of similar elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a plastering and grouting device. The plastering and grouting device is characterized by comprising a grouting offcut protection block extending forwards from two sides of an outlet of a wall brick accommodating box for a preset length, and the front end side surface of the grouting offcut protection block is made of an elastic material; the plastering and grouting device also comprises a grouting container arranged above one end of the outlet of the wall brick accommodating box, the grouting container comprises a slurry outlet part located above the outlet of the wall brick accommodating box and is rectangular in the overlook direction, a grouting port which is consistent with the outlet in length and located in the upper side edge of the outlet of the wall brick accommodating box is formed in the slurry outlet part, and a plastering piece which is made of the elastic material, is used for plaster leveling and extends forwards as a whole is arranged on the lower surface of the grouting port. The plastering and grouting device has the advantages that plastering and control can be realized conveniently, and the wall brick laying quality can be improved.

Description

One is plastered grouting device
Technical field
The present invention relates to the automatic installation apparatus of exterior wall tile in a kind of house decoration field, be specifically related to one plaster slip casting dress Put.
Background technology
When modern high building is built, decoration of exterior wall is typically to select the mode pasting exterior wall tile.Building wall for a long time The laying of brick is all completed by artificial manual operations, and hand lay-up first has to unwrapping wire, then relies on one piece one piece manually Laying, stickup, its labor intensity is big, inefficiency, and the uniformity of the flatness of ceramic tile, gap is uneven, empty Drum rate is higher, and construction quality is difficult to ensure.
China's number of patent application 201510439456.2 once disclosed a kind of tile lying device, and it belongs to construction and decoration neck Territory.It mainly includes ceramic tile bracing frame, is provided with the peaceful bar that puts one's child in a boarding nursery of vacuum cup, after ceramic tile bracing frame before ceramic tile bracing frame Face is provided with vacuum pump and taps hammer, and vacuum cup is connected with vacuum pump;It is provided with vertical masonry joint mark post bottom described ceramic tile bracing frame;Described It is provided with buffer spring between vacuum cup and ceramic tile bracing frame.This invention achieves polylith ceramic tile and lays simultaneously, settles rammer simultaneously Real, and the ceramic tile surface laid is smooth, gap uniform, without hollowing.But the more laying being mainly used in floor tile of this invention, is used for When walltile is laid, it is difficult to form the automatic laying effect of streamlined, equally exist labor intensity big, ineffective scarce Fall into.
In order to solve the problems referred to above, applicant considers to devise a kind of external wall brick installation apparatus, and its feature is, bag Include one and can supply the wall brick of vertical state for the wall brick storage case being horizontally arranged at building exterior wall face, wall brick storage case inner chamber Arrangement is stacked, and wall brick storage case one end is open end and forms outlet, and the other end is provided with wall brick pushing means, and wall brick promotes dress Put the wall brick that can be used in vertical array in wall brick storage case inner chamber being stacked to release from outlet, described wall brick storage case open end Upside is provided with and realizes the grouting device of plastering that slip casting is plastered for wall brick is pushed out front body of wall, also includes supporting and promotes dress Put, support lifting device for by wall brick storage case outlet rectify to be supported on body of wall and be capable of wall brick storage case to Upper lifting.So, when this equipment uses, the order first wall brick of vertical state laid as required being aligned to by rows In wall brick storage case, then by supporting lifting device by proper for the outlet of wall brick storage case to being supported on body of wall.First by note of plastering Sizing device realizes being pushed out wall brick front body of wall and realizes slip casting and plaster, and controls wall brick pushing means by forefront after plastering The the first vertical setting of types wall brick being positioned at wall brick storage case exit position is released, it is achieved the laying of this row's wall brick.Support is relied on to carry the most again Rising device drives wall brick storage case to rise the distance of a wall brick height, synchronizes realization by grouting device of plastering and plaster during being somebody's turn to do Slip casting, then by wall brick pushing means forefront is positioned at wall brick storage case exit position this vertical setting of types wall brick release realize this row's wall Brick is laid, and circulates successively, it is achieved automatization's flowing water of external wall face brick is laid.Therefore reduce wall brick and lay labor intensity, carry High work efficiency, and ensure that construction quality concordance.
But wherein, the most how this grouting device structure of plastering is arranged, and realization could be facilitated to plaster and control, improve wall brick Laying quality, becomes the problem having considered solution.
Summary of the invention
For above-mentioned the deficiencies in the prior art, the technical problem to be solved is: how to provide a kind of convenient real Now plaster and control, to improve the grouting device of plastering of wall brick laying quality.
In order to solve above-mentioned technical problem, present invention employs following technical scheme: the application uses based on equipment State carries out orientation description.
One is plastered grouting device, it is characterised in that grouting device of plastering include wall brick storage case export two side positions to Before extend one section of slip casting rim charge protective block of preset length, side, slip casting rim charge protective block front end is that elastomeric material prepares;Smear Ash grouting device also includes the slip casting container above an exit end being arranged on wall brick storage case, and slip casting container has one Being positioned at above the outlet of wall brick storage case the pulp portion that direction is rectangular of overlooking, pulp portion is positioned on the upside of the outlet of wall brick storage case Seamed edge position has the grouting port consistent with outlet length, and grouting port lower surface has the elastomeric material that one section of entirety extends forward The sheet of plastering smoothed that is used for plastering prepared.
So, during wall brick storage case rises and realizes plastering, slurry can enter into lower section and lay on wall brick Realizing in the regional space between wall brick and slip casting rim charge protective block in end face and wall brick storage case plastering, slip casting rim charge is prevented Protect block it can be avoided that slurry leaks;When specifically plastering, slurry flows out from grouting port, and relies on the elastic force of sheet of plastering to make it be smeared On metope, plaster effect is better achieved.Sheet of wherein plastering preferably employs elastomeric material to be worth, and has with low cost, elastic Can convenient, flexible adjustment to ensure to plaster the advantages such as effect.Further, the elastomeric material of side, slip casting rim charge protective block front end Preferably employ elastomeric material, with low cost and elastic effect is good.Further, slip casting rim charge protective block along wall brick storage case to Under extend out to the distance of a few wall brick height.As such, it is possible to the pulp layer both sides in the wall brick laid for lower section are continued There is provided a support, it is to avoid slurry drops, and ensures bond effect.
As optimization, being additionally provided with grout injection control mechanism in grouting device of plastering, described grout injection control mechanism includes slip casting Container is connected the upright cylindric measure control portion arranging pulp portion behind pulp portion, in measure control portion inner chamber Heart position direct-axis, to being provided with spiral feeding axis, spiral feeding axis is provided with feeding screw blade, and spiral feeding axis one end passes slip casting Container and a feeding being fixed on slip casting external container control motor and are connected.
As such, it is possible to the rotation output relying on feeding to control motor controls, it is achieved to the slurry output component plastered every time Control, it is ensured that the slurry component every time plastered is required component, it is ensured that effect of plastering, improve construction quality concordance.
As optimization, grout injection control mechanism also includes that the pulp being positioned at the suitable grouting port length direction setting of pulp portion turns Axle, pulp rotating shaft one end extends slip casting container and a pulp being fixed on slip casting external container controls motor and is connected, pulp In rotating shaft along axis centre position the symmetrical helical blade that is distributed, described measure control portion is just to pulp rotating shaft medium position Arrange.So, after measure control portion measure control slurry arrives pulp portion, by helical blade symmetrical in pulp rotating shaft by slurry Spread out even toward direction, the left and right sides, the most again from grouting port pulp, better assure that the uniformity that slip casting is plastered.Further Ground, between described pulp portion and measure control portion, also linking has one to overlook direction is trapezoidal towards pulp portion of larger diameter end Convergence part;So, the helical blade on this convergence part and pulp rotating shaft coordinates, and better ensures that pulp uniformity.
Further, be additionally provided with send slurry pipeline be connected with slip casting container.Ensure that the without interruption of slurry, alleviate wall brick Storage case deadweight promotes control with convenient to it.
As optimization, also including that wall brick is plastered strengthening mechanism, described wall brick is plastered strengthening mechanism, accommodates including being positioned at wall brick Below the outlet of case, distance outlet is less than a horizontally disposed reinforcing bar of one piece of wall brick height, reinforces bar by flexible connecting rod Being connected to wall brick storage case, flexible connecting rod is for applying the elastic force of inwardly top and realize adding spreading wall brick reinforcing bar Solid pressure is tight.
So, reinforce bar and can further the wall brick just laid be carried out smooth, it is ensured that its laying quality;And this knot The setting of structure makes when, in the process of deployment of this equipment row's wall brick in realization, next row has laid wall brick can rely on reinforcing Bar is able to bracing reinforcement, it is to avoid has just laid wall brick and has dropped owing to slurry adhesion is strong not.
Further, reinforce on bar rotatably arranged with there being row's pinch rollers, and lean on pinch rollers and spread wall brick table Face contact realizes reinforcing.So, when wall brick storage case rises, contact pressure reinforcing by roller with spreading wall brick surface, preferably Reduce friction, improve consolidation effect, beneficially holding means improving stability.Further, pinch rollers surface is arranged with one layer The resilient sleeve that elastomeric material prepares, preferably improves and compresses effect and ensure device improving stability, meanwhile, different thick when laying During the wall brick spent, thickness can be changed to adapt to by changing resilient sleeve.Resilient sleeve preferably employs elastomeric material and obtains, with low cost And it is elastic preferable.
In sum, the present invention has realization can be facilitated to plaster and control, it is possible to increase the advantage of wall brick laying quality.
Accompanying drawing illustrates:
Fig. 1 is the structural representation of a kind of a kind of external wall brick installation apparatus embodiment that have employed present configuration.
Fig. 2 is the sectional view that Fig. 1 overlooks direction.
Fig. 3 be Fig. 1 individually plasters grouting device slip casting container in can show that the schematic diagram of slurry portion partial structurtes.
Fig. 4 is the top view of Fig. 3.
Fig. 1 individually supports in lifting device during Fig. 5 the structural representation showing that guide rail and elevator wheel coordinate.
Detailed description of the invention
Below in conjunction with a kind of a kind of external wall brick installation apparatus that have employed present configuration and accompanying drawing thereof to the present invention It is described in further detail.
Embodiment: as Figure 1-5, a kind of external wall brick installation apparatus, build for being horizontally arranged at including one Building the wall brick storage case 1 of wall face, wall brick storage case 1 inner chamber can be stacked for wall brick 2 arrangement of vertical state, wall brick storage case One end is open end and forms outlet 3, and the other end is provided with wall brick pushing means, and wall brick pushing means can be used in holding wall brick Receive vertical array is stacked in box cavity wall brick 2 from outlet 3 release, be provided with on the upside of described wall brick storage case 1 open end for Wall brick is pushed out front body of wall and realizes the grouting device of plastering that slip casting is plastered, also include supporting lifting device, support and promote dress Put and be lifted up being supported on body of wall and be capable of wall brick storage case for the outlet of wall brick storage case is rectified.
So, when the said equipment uses, the order first wall brick of vertical state laid as required row by rows Row arrive in wall brick storage case, then by supporting lifting device by proper for the outlet of wall brick storage case to being supported on body of wall.First by smearing Ash grouting device realizes being pushed out wall brick front body of wall and realizes slip casting and plaster, and controlling wall brick pushing means after plastering will be Front is positioned at the first vertical setting of types wall brick of wall brick storage case exit position and releases, it is achieved the laying of this row's wall brick.Rely on the most again and prop up Support lifting device drives wall brick storage case to rise the distance of a wall brick height, synchronizes to realize by grouting device of plastering during being somebody's turn to do Plaster slip casting, then by wall brick pushing means, forefront is positioned at this vertical setting of types wall brick of wall brick storage case exit position and releases that realize should Row's wall brick is laid, and circulates successively, it is achieved automatization's flowing water of external wall face brick is laid.Therefore reduce wall brick and lay work by force Degree, improves work efficiency, and ensure that construction quality concordance.During enforcement, wall brick storage case is rectangular profile and has rectangle The body structure of inner chamber, to facilitate wall brick to stack.Preferably selecting is that wall brick storage case cavity heights is slightly above one piece of wall brick height Degree distance (typically exceeding 2-50mm), can preferably facilitate wall brick vertically to stack, does not the most affect its level and slides It is as the criterion.
Wherein, described wall brick storage case 1 exports two side positions and has the one section of slip casting rim charge extending anteriorly out preset length Protective block 4, side, slip casting rim charge protective block 4 front end is that elastomeric material prepares.
So, dependence plaster grouting device carry out slip casting time, slurry can enter into lower section laid wall brick upper surface And in the regional space between wall brick and the slip casting rim charge protective block in wall brick storage case, plaster so that slip casting is better achieved, Slurry is avoided to leak.Side, slip casting rim charge protective block 4 front end is that elastomeric material is prepared can preferably block gap, it is ensured that slip casting Effect.Wherein said preset length is that one piece of wall brick thickness is added for slip casting rim charge protective block plus the coat of plaster thickness preset Front end elastomeric material can produce deformation preferably to block the elastic deformation surplus in gap, to guarantee above-mentioned slip casting effect.Note The elastomeric material of slurry side, rim charge protective block front end preferably employs elastomeric material, with low cost and elastic effect is good.Further Ground, slip casting rim charge protective block 4 downwardly extends out the distance of at least one wall brick height along wall brick storage case.As such, it is possible under being Pulp layer both sides in the wall brick that side has laid continue to provide a support, it is to avoid slurry drops, and ensures bond effect.
Wherein, described wall brick pushing means includes that one is vertically arranged in wall brick storage case and is just going out wall brick storage case The push pedal 5 that mouth is arranged, push pedal 5 rear is provided with translation controlling organization and can control push pedal toward wall brick appearance by translation controlling organization Case Way out of receiving moves horizontally.
So, control push pedal by translation controlling organization and wall brick level is released, be more favorable for ensureing what wall brick level was released Stationarity and reliability.
Wherein, described wall brick storage case 1 bottom surface and both sides inwall are provided with push pedal chute, described push pedal 5 lower surface It is correspondingly arranged on roller with two end surfaces to be slidably fit in push pedal chute.
So, further, improve stationarity and reliability that push pedal promotes, improve the smooth and easy degree of work.
Wherein, described translation controlling organization includes being arranged at the interior push-and-pull motor 6 away from outlet side of wall brick storage case, pushes away Drawing motor 6 output shaft to connect one and wall brick storage case exports the power transmission shaft 7 be arrangeding in parallel, translation controlling organization also includes at least A piece horizontally disposed actuator push rod 8, actuator push rod 8 one end is vertically connected on push pedal 5 and deviates from outlet side, side, the other end Being slidably fit in the push-rod hole 14 that wall brick storage case deviates from exit end end, actuator push rod 8 lower surface is provided with biography Carry-over bar 9, described power transmission shaft 7 is installed with travelling gear 10 and driving rack 9 engages.
So, rely on push-and-pull motor by rack and pinion engagement transmission, drive actuator push rod to promote push pedal, there is structure letter Advantage singly, easy to control, that stationarity is good.This structure is convenient simultaneously sets up the many actuator push rod 8 being set up in parallel as required, To improve the stationarity of pushing course further.
Wherein, push-and-pull motor 6 output shaft is in transmission connection by reductor 11 and power transmission shaft 7.So, can be more through reductor Control well the output of push-and-pull motor, it is ensured that control accuracy.Further, described power transmission shaft 7 is installed in rotation on interval setting Away from the drive axle support 12 in the inner chamber of outlet side in wall brick storage case, described actuator push rod 8 is arranged at intervals with side by side Many.So, structure is more stable, runs more steady.Further, described actuator push rod 8 both side surface is axially disposed Push rod chute 13, push rod chute 13 is had to be slidably fit in the projection of push-rod hole 14 inwall both sides so that under actuator push rod The driving rack on surface is formed unsettled in push-rod hole.In such manner, it is possible to better ensure that the stationarity that actuator push rod is movable And reliability.Further, actuator push rod outer end is provided with the diameter spacing head more than push-rod hole diameter.So can play limit Position effect, prevents actuator push rod from passing push-rod hole.
Wherein, grouting device of plastering includes described slip casting rim charge protective block, also includes that is arranged on a wall brick storage case Slip casting container 15 above exit end, slip casting container 15 have above an outlet being positioned at wall brick storage case overlook direction in The pulp portion 16 of rectangle, pulp portion 16 is positioned at lateral edges position in the outlet 3 of wall brick storage case and has consistent with outlet length Grouting port, grouting port lower surface has the sheet 1 of plastering smoothed for plastering that the elastomeric material that one section of entirety extends forward prepares 7.
So, during wall brick storage case rises and realizes plastering, slurry flows out from grouting port, and relies on sheet of plastering Elastic force makes it be applied on metope, and plaster effect is better achieved.Sheet of wherein plastering preferably employs elastomeric material to be worth, and has With low cost, elasticity can convenient, flexible adjustment to ensure to plaster the advantages such as effect.
Wherein, being additionally provided with grout injection control mechanism in grouting device of plastering, described grout injection control mechanism includes slip casting container Middle it is connected behind pulp portion the upright cylindric measure control portion 18 that pulp portion is arranged, in measure control portion 18 inner chamber Heart position direct-axis, to being provided with spiral feeding axis 19, spiral feeding axis is provided with feeding screw blade, and spiral feeding axis 19 one end passes Slip casting container 15 is fixed on the feeding control motor 20 of slip casting external container and is connected with one.
As such, it is possible to the rotation output relying on feeding to control motor controls, it is achieved to the slurry output component plastered every time Control, it is ensured that the slurry component every time plastered is required component, it is ensured that effect of plastering, improve construction quality concordance.
Wherein, grout injection control mechanism also includes being positioned at the pulp rotating shaft 21 that pulp portion is arranged along grouting port length direction, Pulp rotating shaft 21 one end extend slip casting container 15 be fixed on one slip casting external container pulp control motor 22 be connected, go out Slurry rotating shaft 21 on along axis centre position the symmetrical helical blade 23 that is distributed, described measure control portion 18 is just to pulp rotating shaft 21 medium positions are arranged.So, after measure control portion measure control slurry arrives pulp portion, by spiral symmetrical in pulp rotating shaft Slurry is spread out even toward direction, the left and right sides by blade, the most again from grouting port pulp, better assures that slip casting is plastered equal Even property.Further, between described pulp portion 16 and measure control portion 18, also linking has one to overlook direction is larger diameter end court To the trapezoidal convergence part 24 in pulp portion;So, the helical blade on this convergence part and pulp rotating shaft coordinates, and better ensures that out Slurry uniformity.Further, described convergence part 24 and measure control portion 18 are inclined upwardly setting away from the one end in direction, pulp portion, So it is more favorable for pulp flow feeding, it is ensured that slip casting smoothness.
Wherein, be additionally provided with send slurry pipeline 25 be connected with slip casting container.Ensure that the without interruption of slurry, alleviate wall brick and hold Case of receiving deadweight promotes control with convenient to it.
Wherein, also including that wall brick is plastered strengthening mechanism, described wall brick is plastered strengthening mechanism, including being positioned at wall brick storage case Below outlet, distance outlet is less than a horizontally disposed reinforcing bar 26 of one piece of wall brick height, reinforces bar 26 by flexible connecting rod 27 are connected to wall brick storage case, and flexible connecting rod 27 is for applying the elastic force of inwardly top to reinforcing bar 26 and realize spreading wall The reinforcing of brick compresses.
So, reinforce bar and the elastic force of flexible connecting rod can be relied on to carry out smooth to the wall brick just laid further, protect Demonstrate,prove its laying quality;And the setting of this structure makes when in the process of deployment of this equipment row's wall brick in realization, next row Having laid wall brick can rely on reinforcing bar to be able to bracing reinforcement, it is to avoid has just laid wall brick and has fallen owing to slurry adhesion is strong not Fall.When being embodied as, flexible connecting rod and is connected up firmly at the stiff rod of wall brick storage case lower surface by a upper end thereof Tension spring between bar and wall brick storage case lower surface realizes, and is so convenient for changing tension spring moderate with regulation elastic force Make it can either ensure to support and compress consolidation effect, again will not be excessive and to affect wall brick storage case up.
Wherein, reinforce on bar 26 rotatably arranged with there being row's pinch rollers 28, and lean on pinch rollers 28 and spread wall brick Surface contact realizes reinforcing.So, when wall brick storage case rises, contact pressure reinforcing by roller with spreading wall brick surface, more preferably Ground reduces friction, improves consolidation effect, beneficially holding means improving stability.Further, pinch rollers 28 surface is arranged with The resilient sleeve 29 that one layer of elastomeric material prepares, preferably improves and compresses effect and ensure device improving stability, meanwhile, work as laying During the wall brick of different-thickness, thickness can be changed to adapt to by changing resilient sleeve.Resilient sleeve preferably employs elastomeric material and obtains, and becomes This is cheap and elastic preferably.
Wherein, support lifting device and include being preset in two guide rails 30 of both sides, wall brick region to be spread, institute in external wall State that wall brick storage case 1 both sides are the most extended has support arm 32 and support arm 32 front end to be coordinated at guide rail 30 by elevator wheel 33 On, supporting lifting device and also include hoisting mechanism, hoisting mechanism includes the elevator being arranged on wall brick overlying regions building to be spread body Motor 31 and fixed pulley group 34, elevator motor 31 outfan connecting steel wire ropes 35, steel wire rope 35 is through fixed pulley group 34 downwards It is connected on wall brick storage case 1.
So, wall brick storage case direction of improvement is guided by the guide rail by presetting, it is ensured that the concordance of laying is with reliable Property, meanwhile, rely on hoisting mechanism by rope hoisting wall brick storage case;The convenient control realizing wall brick storage case being risen and stopping, It is beneficial to ensure the controllability of its work process and reliability.
Wherein, described guide rail 30 is i shaped steel, and each supporting arm front end is arranged at intervals with two elevator wheel 33 also side by side Inside two elevator wheel snap-fit engagement to i shaped steel grooves on two sides.So simple in construction, guide rail and elevator wheel stress The most reliable, and it is spacing to be capable of the clamping to elevator wheel, it is ensured that during promoting wall brick, wall brick storage case will not Outwards ejected.
Wherein, each support arm 32 is all axially installed with spring shock (absorber) strut 36 along support arm.The most not only there is damping effect Really, and the Dai Pu wall brick district not exported to external wall so that spring shock (absorber) strut by wall brick storage case during external force can be set Field surface distance adds the distance of the coat of plaster thickness preset less than one piece of wall brick thickness.So, push pedal is being promoted to realize wall brick During laying, need the elastic force overcoming some spring shock (absorber) struts that wall brick storage case entirety is outwards overhanged some distances, could realize The laying of wall brick puts in place so that after wall brick laying, wall brick storage case can continue to ensure the wall to just having laid during being lifted up Brick applies certain pressure, improves it and metope combines effect, it is ensured that overall laying effect is excellent.

Claims (7)

1. a grouting device of plastering, it is characterised in that grouting device of plastering includes that wall brick storage case exports two side positions forward Extending one section of slip casting rim charge protective block of preset length, side, slip casting rim charge protective block front end is that elastomeric material prepares;Plaster Grouting device also includes the slip casting container above an exit end being arranged on wall brick storage case, and slip casting container has a position Overlooking the pulp portion that direction is rectangular above the outlet of wall brick storage case, pulp portion is positioned at incline in the outlet of wall brick storage case Position, limit has the grouting port consistent with outlet length, and grouting port lower surface has one section of elastomeric material system that entirety extends forward The sheet of plastering smoothed that is used for plastering obtained.
Plaster the most as claimed in claim 1 grouting device, it is characterised in that grouting device of plastering is additionally provided with grout injection control Mechanism, described grout injection control mechanism includes being connected in slip casting container the upright cylindrical shape arranging pulp portion behind pulp portion Measure control portion, lumen centers position, measure control portion direct-axis, to being provided with spiral feeding axis, spiral feeding axis is provided with feeding Helical blade, spiral feeding axis one end passes slip casting container and a feeding being fixed on slip casting external container controls motor and is connected.
Plaster the most as claimed in claim 2 grouting device, it is characterised in that grout injection control mechanism also includes being positioned at pulp portion Along grouting port length direction arrange pulp rotating shaft, pulp rotating shaft one end extend slip casting container and one be fixed on slip casting container Outside pulp controls motor and is connected, in pulp rotating shaft along axis centre position the symmetrical helical blade that is distributed, described meter Pulp rotating shaft medium position is just arranged by amount control portion.
Plaster the most as claimed in claim 3 grouting device, it is characterised in that also hold in the mouth between described pulp portion and measure control portion Being connected to one and overlooking direction is the larger diameter end trapezoidal convergence part towards pulp portion.
Plaster the most as claimed in claim 1 grouting device, it is characterised in that be additionally provided with and send slurry pipeline and slip casting container phase Even.
Plaster the most as claimed in claim 1 grouting device, it is characterised in that also include that wall brick is plastered strengthening mechanism, described wall Brick is plastered strengthening mechanism, including being positioned at distance outlet being horizontally disposed with less than one piece of wall brick height below the outlet of wall brick storage case A reinforcing bar, reinforce bar be connected to wall brick storage case by flexible connecting rod, flexible connecting rod for reinforce bar applying to The elastic force of interior top also realizes the reinforcing to spreading wall brick and compresses.
Plaster the most as claimed in claim 6 grouting device, it is characterised in that reinforce on bar tight rotatably arranged with there being a row pressure Roller, and contact realization reinforcing by pinch rollers with spreading wall brick surface.
CN201610242626.2A 2016-04-19 2016-04-19 A kind of plastering grouting device Expired - Fee Related CN105839903B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610242626.2A CN105839903B (en) 2016-04-19 2016-04-19 A kind of plastering grouting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610242626.2A CN105839903B (en) 2016-04-19 2016-04-19 A kind of plastering grouting device

Publications (2)

Publication Number Publication Date
CN105839903A true CN105839903A (en) 2016-08-10
CN105839903B CN105839903B (en) 2019-04-05

Family

ID=56589651

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610242626.2A Expired - Fee Related CN105839903B (en) 2016-04-19 2016-04-19 A kind of plastering grouting device

Country Status (1)

Country Link
CN (1) CN105839903B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108726962A (en) * 2018-07-11 2018-11-02 江苏尼高科技有限公司 The inorganic anchoring adhesive of rapid-hardening and mortar depositing construction equipment
CN111287418A (en) * 2020-04-09 2020-06-16 华新建工集团有限公司 Building wall gets rid of thick liquid device
CN111550065A (en) * 2020-04-23 2020-08-18 黄�益 Hollow block grouting reinforcement equipment

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB214773A (en) * 1923-02-19 1924-05-01 Stewart Kaye Improvements in and relating to machines for erecting walls of bricks and the like
GB247256A (en) * 1925-08-26 1926-02-18 Charles Downs Apparatus for plastering ceilings, walls and the like
GB1148441A (en) * 1966-01-21 1969-04-10 Duncan Stewart Bonnybridge Ltd Improvements in or relating to a method and apparatus for automatically laying bricks
CN2140404Y (en) * 1992-08-11 1993-08-18 谢鸿琴 Machine for sticking ceramic tile
CN1241673A (en) * 1999-07-07 2000-01-19 阎金江 Universal building decorating machine
CN2388260Y (en) * 1998-02-18 2000-07-19 易国英 External wall plastering glazed tile laying machine
CN201033939Y (en) * 2005-12-25 2008-03-12 吴增成 Changeable multifunctional full-automatic plastering machine
CN101338615A (en) * 2007-07-03 2009-01-07 刘国臣 Automatic plastering machine
CN201202281Y (en) * 2007-06-24 2009-03-04 史文章 Vibrating formwork walling machine
CN201254824Y (en) * 2008-08-11 2009-06-10 赵国富 Wall pasting machine
CN103074994A (en) * 2013-01-16 2013-05-01 余选兵 Synchronous all-in-one machine for automatically pasting ceramic tile and whitewashing wall

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB214773A (en) * 1923-02-19 1924-05-01 Stewart Kaye Improvements in and relating to machines for erecting walls of bricks and the like
GB247256A (en) * 1925-08-26 1926-02-18 Charles Downs Apparatus for plastering ceilings, walls and the like
GB1148441A (en) * 1966-01-21 1969-04-10 Duncan Stewart Bonnybridge Ltd Improvements in or relating to a method and apparatus for automatically laying bricks
CN2140404Y (en) * 1992-08-11 1993-08-18 谢鸿琴 Machine for sticking ceramic tile
CN2388260Y (en) * 1998-02-18 2000-07-19 易国英 External wall plastering glazed tile laying machine
CN1241673A (en) * 1999-07-07 2000-01-19 阎金江 Universal building decorating machine
CN201033939Y (en) * 2005-12-25 2008-03-12 吴增成 Changeable multifunctional full-automatic plastering machine
CN201202281Y (en) * 2007-06-24 2009-03-04 史文章 Vibrating formwork walling machine
CN101338615A (en) * 2007-07-03 2009-01-07 刘国臣 Automatic plastering machine
CN201254824Y (en) * 2008-08-11 2009-06-10 赵国富 Wall pasting machine
CN103074994A (en) * 2013-01-16 2013-05-01 余选兵 Synchronous all-in-one machine for automatically pasting ceramic tile and whitewashing wall

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨振宇,巩传根,刘芝霞,武爱华: "新型抹灰机的设计", 《建筑机械》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108726962A (en) * 2018-07-11 2018-11-02 江苏尼高科技有限公司 The inorganic anchoring adhesive of rapid-hardening and mortar depositing construction equipment
CN111287418A (en) * 2020-04-09 2020-06-16 华新建工集团有限公司 Building wall gets rid of thick liquid device
CN111550065A (en) * 2020-04-23 2020-08-18 黄�益 Hollow block grouting reinforcement equipment

Also Published As

Publication number Publication date
CN105839903B (en) 2019-04-05

Similar Documents

Publication Publication Date Title
CN105863228A (en) External wall brick paving method
CN105863229B (en) A kind of external wall face brick laydown machine
CN105839903A (en) Plastering and grouting device
CN104213703B (en) A kind of mortar spray coating machine and utilize the method that mortar spray coating machine carries out metope powder mortar
CN111424935B (en) Interior decoration decorates wall brick laying device
CN111255208B (en) Wall tile laying device for building engineering construction
CN108532925A (en) A kind of assisted tiles device
CN106429394A (en) Automatic bar loading device
CN205000608U (en) Automatic mechanical float of preparation screed -coat on wall
CN205502535U (en) Slip casting containment structure
CN205502537U (en) Wall brick laying machine is with supporting hoisting device
CN205502533U (en) Wall brick laying machine is with mechanism that plasters
CN205502538U (en) Wall brick strengthening mechanism that plasters
CN205502536U (en) Slip casting control mechanism
CN205502539U (en) Wall brick is translation control mechanism for push pedal
CN205502540U (en) Wall brick thrust unit
CN205502541U (en) Wall brick holds case exit structure
CN105863227A (en) Wall brick containing box
CN208168279U (en) The hand-held vibration mechanical float of suspension type
CN107642246A (en) A kind of build concrete hollow brick masonry device
CN218708966U (en) Quick loading device for pipes
CN110921379A (en) Full-automatic paper feeding system and method for gypsum board production line
CN213537073U (en) Channel is hoist device for lining board
CN110331844A (en) A kind of house ornamentation engineering tile laying equipment
CN110029803A (en) A kind of ceramic tile is laid with facility and method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190405

Termination date: 20210419