CN105809214A - RFID based switchgear data managing system and data transmitting method - Google Patents

RFID based switchgear data managing system and data transmitting method Download PDF

Info

Publication number
CN105809214A
CN105809214A CN201610123462.1A CN201610123462A CN105809214A CN 105809214 A CN105809214 A CN 105809214A CN 201610123462 A CN201610123462 A CN 201610123462A CN 105809214 A CN105809214 A CN 105809214A
Authority
CN
China
Prior art keywords
file
data
read
partial discharge
rfid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610123462.1A
Other languages
Chinese (zh)
Other versions
CN105809214B (en
Inventor
陈�光
陶加贵
潘志新
周志成
刘洋
黄成军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610123462.1A priority Critical patent/CN105809214B/en
Publication of CN105809214A publication Critical patent/CN105809214A/en
Application granted granted Critical
Publication of CN105809214B publication Critical patent/CN105809214B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06KGRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
    • G06K17/00Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations
    • G06K17/0022Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/12Testing dielectric strength or breakdown voltage ; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Information Retrieval, Db Structures And Fs Structures Therefor (AREA)
  • Testing Relating To Insulation (AREA)

Abstract

The invention discloses a RFID based switchgear data managing system which comprises a RFID electronic label, a partial discharge tester and a computer. The partial discharge tester is provided with a RFID accessing module therein that matches with the RFID electronic label, and the partial discharge tester is connected to the computer through a USB interface. The computer is provided with a user's data managing terminal therein, and the user's data managing terminal is provided with plug-ins. The plug-ins access the directory of a switchgear data file and standardize and convert the files in the directory that are to be uploaded, and the standardized files are then transmitted to a remote data managing center through the internet. The invention also discloses the data transmitting method for this system. According to the invention, a user can log in and manage data conveniently; with one single operation, distant logging of data can be realized, and therefore, the data logging efficiency is improved.

Description

Switch cubicle data management system and data transmission method based on RFID
Technical field
The present invention relates to a kind of switch cubicle data management system based on RFID and data transmission method, belong to the technical field of insulation detection of power equipment.
Background technology
Electric Power Equipment Insulation ability is to determine that power equipment can the important indicator of safe and stable operation.High-tension electricity number of devices gets more and more, and electric industry grade is more and more higher, the safe operation of the insulation fault serious threat power system that the deficiency of electric power equipment on-site test method and the power equipment put into operation occur.Partial Discharge Detection is the effective means reflecting apparatus insulated situation, also it is the focus of current research and application, at present in power equipment Partial Discharge Detection, conventional is ultra-high-frequency detection, ultrasonic, high frequency electric and ground electric wave detection equipment, the application of these equipment, find many defects and solve lot of accident hidden danger, obtaining and well apply effect.
In current Partial Discharge Detection application, there is problems in that
1, the more than shelf depreciation of power equipment monitoring parameter is a kind of, and the data type that some switch cubicle data management systems are supported at present is single.
2, the commonly used C/S structure of data management system structure, it does not have utilize Web technology to build server formula data management system, it does not have utilize network technology transmission data.
3, data management is time-consuming, after on-the-spot test completes, it is necessary to all instrument for measuring partial discharge are brought back to and carries out typing by data management system, or each tester installation data management system on the computer of oneself, this mode is not easy to the management of data and safeguards, virtually adds cost.
Summary of the invention
In order to solve above-mentioned technical problem, the invention provides a kind of switch cubicle data management system based on RFID and data transmission method.
In order to achieve the above object, the technical solution adopted in the present invention is:
Based on the switch cubicle data management system of RFID, including RFID, instrument for measuring partial discharge and computer;With the relevant information of high-tension switch cabinet to be detected in described RFID, and it is installed on high-voltage switch gear to be detected cashier's office in a shop;Being provided with the RFID read module coordinated with RFID in described instrument for measuring partial discharge, described instrument for measuring partial discharge is connected with computer by USB interface;Data management client is installed in described computer, it is provided with plug-in unit in described data management client, described plug-in unit in order to obtain switch cubicle data file content in instrument for measuring partial discharge, file to be uploaded in switch cubicle data file content is carried out standardization conversion, and the files through network after conversion is committed to remote data management center.
Described instrument for measuring partial discharge is hand-held.
Based on the data transmission method of the switch cubicle data management system of RFID, comprise the following steps,
Step 1, reads the high-tension switch cabinet information in RFID by instrument for measuring partial discharge;
Step 2, by instrument for measuring partial discharge's test site local discharge signal;
Step 3, after having tested, instrument for measuring partial discharge is connected with computer by USB interface;
Step 4, logs in data management client, installs plug-in unit;
Step 5, obtains the switch cubicle data file content in instrument for measuring partial discharge by plug-in unit;
Step 6, selects the file to be uploaded in switch cubicle data file content;
Step 7, carries out standardization by plug-in unit by file to be uploaded and changes, and the files through network after conversion is committed to remote data management center.
The process being obtained the switch cubicle data file content in instrument for measuring partial discharge by plug-in unit is,
A1) communication thread is started;
A2) judge currently whether there is the data type needing to obtain data directory, if it has, then go to A3, otherwise terminate communication;
A3) the root name obtaining the data type of data directory will be needed to add in catalogue queue to be read;
A4) judge whether catalogue queue to be read is empty, if being empty, then go to A2, otherwise go to A5;
A5) to row take out 1 directory name;
A6) open catalogue, open successfully, then go to A7, otherwise reopen, repeatedly opening failure and reaching, in maximum reattempt times situation, to go to A2;
A7) judge that whether the catalogue opened is the root of current data type, if it is, added by directory name in facility inventory tree, otherwise go to A8;
A8) read this directory entry, read successfully, then go to A9, and directory name is added in facility inventory tree, otherwise re-read, repeatedly reading failure and reaching, in maximum reattempt times situation, to go to A2;
A9) judge that whether current directory reads complete, if it is, go to A10, otherwise goes to A4;
A10) judge that the title currently read is file or file, if file, then title is added in catalogue queue to be read, otherwise go to A8.
The concrete communication process of step 7 is,
B1) communication thread is started;
B2) determine whether the file to open, if it has, then go to step B3, otherwise terminate communication;
B3) file is opened;
B4) judge whether file is opened successfully, if it succeeds, go to B5, otherwise judge whether to reach to open the maximum reattempt times of file, if it is, terminate communication, otherwise go to B3;
B5) file opened is read;
B6) judge whether to read successfully, if it succeeds, go to step B7, otherwise judge whether the maximum reattempt times reaching to read file, if it is, terminate communication, otherwise go to B5;
B7) judge that file reads whether to terminate, if it is, go to step B8, otherwise go to step B5;
B8) file that verification is read, if verifying successfully, then going to step B9, otherwise abandoning file, and terminating communication;
B9) file is carried out standardization conversion, if translated into merit, then goes to B10, otherwise terminate communication;
B10) files through network after conversion is committed to remote data management center, terminates communication.
The beneficial effect that the present invention reaches: 1, the present invention facilitates user's typing to data and manages, disposable operation can complete the distant inputing of data, improves the efficiency of data road typing;2, the present invention is by instrument for measuring partial discharge and seamless the linking up by plug-in unit of control data corporation, makes system more uniformity and integrity;3, the present invention supports a greater variety of data type;4, invention enhances the safety of data management, data are unified to be stored on the server computer at control data corporation place;5, the present invention meets the trend of electric power detection development, utilizes network technology transmission data.
Accompanying drawing explanation
Fig. 1 is the structured flowchart of present system.
Fig. 2 is the flow chart that the plug-in unit of the present invention obtains the switch cubicle data file content in instrument for measuring partial discharge.
Fig. 3 is the flow chart uploaded.
Detailed description of the invention
Below in conjunction with accompanying drawing, the invention will be further described.Following example are only for clearly illustrating technical scheme, and can not limit the scope of the invention with this.
As it is shown in figure 1, based on the switch cubicle data management system of RFID, including RFID, instrument for measuring partial discharge and computer.
With the relevant information of high-tension switch cabinet to be detected in RFID, and it is installed on high-voltage switch gear to be detected cashier's office in a shop.Being provided with the RFID read module coordinated with RFID in instrument for measuring partial discharge, described instrument for measuring partial discharge is connected with computer by USB interface.Data management client is installed in computer, it is provided with plug-in unit in data management client, plug-in unit in order to obtain switch cubicle data file content in instrument for measuring partial discharge, file to be uploaded in switch cubicle data file content is carried out standardization conversion, and the files through network after conversion is committed to remote data management center.
Above-mentioned instrument for measuring partial discharge is hand-held, and RFID adopts anti-metal RFID.
Based on the data transmission method of the switch cubicle data management system of RFID, comprise the following steps:
Step 1, reads the high-tension switch cabinet information in RFID by instrument for measuring partial discharge.
Step 2, by instrument for measuring partial discharge's test site local discharge signal.
Step 3, after having tested, instrument for measuring partial discharge is connected with computer by USB interface.
Step 4, logs in data management client, installs plug-in unit.
Step 5, obtains the switch cubicle data file content in instrument for measuring partial discharge by plug-in unit.
Detailed process is as in figure 2 it is shown, detailed step is as follows:
A1) communication thread is started;
A2) judge currently whether there is the data type needing to obtain data directory, if it has, then go to A3, otherwise terminate communication;
A3) the root name obtaining the data type of data directory will be needed to add in catalogue queue to be read;
A4) judge whether catalogue queue to be read is empty, if being empty, then go to A2, otherwise go to A5;
A5) to row take out 1 directory name;
A6) open catalogue, open successfully, then go to A7, otherwise reopen, repeatedly opening failure and reaching, in maximum reattempt times situation, to go to A2;
A7) judge that whether the catalogue opened is the root of current data type, if it is, added by directory name in facility inventory tree, otherwise go to A8;
A8) read this directory entry, read successfully, then go to A9, and directory name is added in facility inventory tree, otherwise re-read, repeatedly reading failure and reaching, in maximum reattempt times situation, to go to A2;
A9) judge that whether current directory reads complete, if it is, go to A10, otherwise goes to A4;
A10) judge that the title currently read is file or file, if file, then title is added in catalogue queue to be read, otherwise go to A8.
Step 6, selects the file to be uploaded in switch cubicle data file content.
Step 7, carries out standardization by plug-in unit by file to be uploaded and changes, and the files through network after conversion is committed to remote data management center.
Concrete steps as it is shown on figure 3,
B1) communication thread is started;
B2) determine whether the file to open, if it has, then go to step B3, otherwise terminate communication;
B3) file is opened;
B4) judge whether file is opened successfully, if it succeeds, go to B5, otherwise judge whether to reach to open the maximum reattempt times of file, if it is, terminate communication, otherwise go to B3;
B5) file opened is read;
B6) judge whether to read successfully, if it succeeds, go to step B7, otherwise judge whether the maximum reattempt times reaching to read file, if it is, terminate communication, otherwise go to B5;
B7) judge that file reads whether to terminate, if it is, go to step B8, otherwise go to step B5;
B8) file that verification is read, if verifying successfully, then going to step B9, otherwise abandoning file, and terminating communication;
B9) file is carried out standardization conversion, if translated into merit, then goes to B10, otherwise terminate communication;
B10) files through network after conversion is committed to remote data management center, terminates communication.
The present invention facilitates user's typing to data and manages, and disposable operation can complete the distant inputing of data, improves the efficiency of data road typing;The present invention, by instrument for measuring partial discharge and seamless being linked up by plug-in unit of control data corporation, makes system more uniformity and integrity;The present invention supports a greater variety of data type, it is only necessary to arrange different transformational rulees;Invention enhances the safety of data management, data are unified to be stored on the server computer at control data corporation place;One's duty meets the trend of electric power detection development, utilizes network technology transmission data.
The above is only the preferred embodiment of the present invention; it should be pointed out that, for those skilled in the art, under the premise without departing from the technology of the present invention principle; can also making some improvement and deformation, these improve and deformation also should be regarded as protection scope of the present invention.

Claims (5)

1. based on the switch cubicle data management system of RFID, it is characterised in that: include RFID, instrument for measuring partial discharge and computer;
With the relevant information of high-tension switch cabinet to be detected in described RFID, and it is installed on high-voltage switch gear to be detected cashier's office in a shop;
Being provided with the RFID read module coordinated with RFID in described instrument for measuring partial discharge, described instrument for measuring partial discharge is connected with computer by USB interface;
Data management client is installed in described computer, it is provided with plug-in unit in described data management client, described plug-in unit in order to obtain switch cubicle data file content in instrument for measuring partial discharge, file to be uploaded in switch cubicle data file content is carried out standardization conversion, and the files through network after conversion is committed to remote data management center.
2. the switch cubicle data management system based on RFID according to claim 1, it is characterised in that: described instrument for measuring partial discharge is hand-held.
3. based on the data transmission method of the switch cubicle data management system based on RFID described in claim 1, it is characterised in that: comprise the following steps,
Step 1, reads the high-tension switch cabinet information in RFID by instrument for measuring partial discharge;
Step 2, by instrument for measuring partial discharge's test site local discharge signal;
Step 3, after having tested, instrument for measuring partial discharge is connected with computer by USB interface;
Step 4, logs in data management client, installs plug-in unit;
Step 5, obtains the switch cubicle data file content in instrument for measuring partial discharge by plug-in unit;
Step 6, selects the file to be uploaded in switch cubicle data file content;
Step 7, carries out standardization by plug-in unit by file to be uploaded and changes, and the files through network after conversion is committed to remote data management center.
4. the data transmission method of the switch cubicle data management system based on RFID according to claim 3, it is characterised in that: the process being obtained the switch cubicle data file content in instrument for measuring partial discharge by plug-in unit is:
A1) communication thread is started;
A2) judge currently whether there is the data type needing to obtain data directory, if it has, then go to A3, otherwise terminate communication;
A3) the root name obtaining the data type of data directory will be needed to add in catalogue queue to be read;
A4) judge whether catalogue queue to be read is empty, if being empty, then go to A2, otherwise go to A5;
A5) to row take out 1 directory name;
A6) open catalogue, open successfully, then go to A7, otherwise reopen, repeatedly opening failure and reaching, in maximum reattempt times situation, to go to A2;
A7) judge that whether the catalogue opened is the root of current data type, if it is, added by directory name in facility inventory tree, otherwise go to A8;
A8) read this directory entry, read successfully, then go to A9, and directory name is added in facility inventory tree, otherwise re-read, repeatedly reading failure and reaching, in maximum reattempt times situation, to go to A2;
A9) judge that whether current directory reads complete, if it is, go to A10, otherwise goes to A4;
A10) judge that the title currently read is file or file, if file, then title is added in catalogue queue to be read, otherwise go to A8.
5. the data transmission method of the switch cubicle data management system based on RFID according to claim 3, it is characterised in that: the concrete communication process of step 7 is,
B1) communication thread is started;
B2) determine whether the file to open, if it has, then go to step B3, otherwise terminate communication;
B3) file is opened;
B4) judge whether file is opened successfully, if it succeeds, go to B5, otherwise judge whether to reach to open the maximum reattempt times of file, if it is, terminate communication, otherwise go to B3;
B5) file opened is read;
B6) judge whether to read successfully, if it succeeds, go to step B7, otherwise judge whether the maximum reattempt times reaching to read file, if it is, terminate communication, otherwise go to B5;
B7) judge that file reads whether to terminate, if it is, go to step B8, otherwise go to step B5;
B8) file that verification is read, if verifying successfully, then going to step B9, otherwise abandoning file, and terminating communication;
B9) file is carried out standardization conversion, if translated into merit, then goes to B10, otherwise terminate communication;
B10) files through network after conversion is committed to remote data management center, terminates communication.
CN201610123462.1A 2016-03-03 2016-03-03 Switchgear data management system based on RFID and data transmission method Active CN105809214B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610123462.1A CN105809214B (en) 2016-03-03 2016-03-03 Switchgear data management system based on RFID and data transmission method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610123462.1A CN105809214B (en) 2016-03-03 2016-03-03 Switchgear data management system based on RFID and data transmission method

Publications (2)

Publication Number Publication Date
CN105809214A true CN105809214A (en) 2016-07-27
CN105809214B CN105809214B (en) 2018-08-03

Family

ID=56466801

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610123462.1A Active CN105809214B (en) 2016-03-03 2016-03-03 Switchgear data management system based on RFID and data transmission method

Country Status (1)

Country Link
CN (1) CN105809214B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106646169A (en) * 2017-01-04 2017-05-10 华北电力大学 Electrical device partial discharge detection data collection cloud strategy
CN107367671A (en) * 2017-06-29 2017-11-21 国网辽宁省电力有限公司电力科学研究院 GIS partial discharge live detection and data management platform based on Internet of Things mark
CN107871146A (en) * 2017-10-20 2018-04-03 柴建霖 A kind of high-tension apparatus partial discharge electrification detection intelligent management system based on Internet of Things

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204270327U (en) * 2014-11-13 2015-04-15 国家电网公司 Based on the switch cubicle data management system of RFID
CN204374731U (en) * 2014-09-11 2015-06-03 广西电网公司电力科学研究院 Based on high voltage electric equipment information acquisition and the evaluation system of EMS-API
CN204422708U (en) * 2015-03-04 2015-06-24 苏州华天国科电力科技有限公司 With Partial discharge detector's device of RFID

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204374731U (en) * 2014-09-11 2015-06-03 广西电网公司电力科学研究院 Based on high voltage electric equipment information acquisition and the evaluation system of EMS-API
CN204270327U (en) * 2014-11-13 2015-04-15 国家电网公司 Based on the switch cubicle data management system of RFID
CN204422708U (en) * 2015-03-04 2015-06-24 苏州华天国科电力科技有限公司 With Partial discharge detector's device of RFID

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106646169A (en) * 2017-01-04 2017-05-10 华北电力大学 Electrical device partial discharge detection data collection cloud strategy
CN107367671A (en) * 2017-06-29 2017-11-21 国网辽宁省电力有限公司电力科学研究院 GIS partial discharge live detection and data management platform based on Internet of Things mark
CN107367671B (en) * 2017-06-29 2020-10-23 国网辽宁省电力有限公司电力科学研究院 GIS partial discharge live detection and data management platform based on Internet of things identification
CN107871146A (en) * 2017-10-20 2018-04-03 柴建霖 A kind of high-tension apparatus partial discharge electrification detection intelligent management system based on Internet of Things

Also Published As

Publication number Publication date
CN105809214B (en) 2018-08-03

Similar Documents

Publication Publication Date Title
US11754997B2 (en) Devices, systems and methods for predicting future consumption values of load(s) in power distribution systems
KR101709795B1 (en) Intelligent monitoring of an electrical utility grid
CN101581752B (en) Power transmission line parameter online measurement method based on fault wave recording
CN109270482B (en) Online evaluation method for metering accuracy of voltage transformer and terminal equipment
CN102368634A (en) Unified information platform system for state monitoring of intelligent transformer substation
WO2013123055A1 (en) Power line management system
Kunicki et al. Data acquisition system for on-line temperature monitoring in power transformers
CN110188888A (en) Power equipments defect management method, system and terminal based on AHP and remote support
CN105809214A (en) RFID based switchgear data managing system and data transmitting method
CN109962527B (en) Power distribution terminal fault recording system
CN108289119A (en) Become platform data monitoring system and method on a kind of integrated column based on embedded Web
CN104793038A (en) All-optical overvoltage monitoring device for electric power system
JP2006204041A (en) Power system supervisory control system, method and program, and management server
Shuang et al. Research on technical scheme of outdoor‐layout relay protection in smart substation
CN205622318U (en) Power consumption monitoring system and distribution network
CN110535972B (en) Centralized control and communication system, equipment and readable storage medium for platform gas detection equipment
CN112330142A (en) Multi-access electric automobile charging pile electric energy quality operation and maintenance management platform
CN103413190A (en) Real-time auditing system of operation ticket and method
CN113113972B (en) Monitoring information generation method and device, electronic equipment and computer readable medium
CN103647760B (en) The MMS communication platforms and its access method of a kind of intelligent transformer substation digital protection device
CN104655994B (en) GIS partial discharge on-line monitoring systems
CN109193926B (en) Transformer substation monitoring system
EP2498062A2 (en) System and Method for Communicating Device Specific Data Over an Advanced Metering Infrastructure (AMI) Network
Bai et al. Digital metering system of new generation smart substation in China
CN109581215A (en) A kind of high-voltage circuitbreaker intelligent checking system with compbined test function

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant