CN105804760A - Super-large section tunnel drilling and blasting method in-situ expansion construction structure and construction method - Google Patents

Super-large section tunnel drilling and blasting method in-situ expansion construction structure and construction method Download PDF

Info

Publication number
CN105804760A
CN105804760A CN201610326428.4A CN201610326428A CN105804760A CN 105804760 A CN105804760 A CN 105804760A CN 201610326428 A CN201610326428 A CN 201610326428A CN 105804760 A CN105804760 A CN 105804760A
Authority
CN
China
Prior art keywords
tunnel
super
apply
section tunnel
inverted arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610326428.4A
Other languages
Chinese (zh)
Other versions
CN105804760B (en
Inventor
陈良兵
王事成
张红华
李永山
宋永乐
关振长
徐森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Xiamen Rongshan Expressway Zhanglong Section Extension Engineering Co ltd
China Railway 15th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd
Original Assignee
China Railway 15th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 15th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd filed Critical China Railway 15th Bureau Group Co Ltd
Priority to CN201610326428.4A priority Critical patent/CN105804760B/en
Publication of CN105804760A publication Critical patent/CN105804760A/en
Application granted granted Critical
Publication of CN105804760B publication Critical patent/CN105804760B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention relates to an in-situ expansion construction structure and a construction method for a super-large section tunnel by a drilling and blasting method, which are characterized in that: the tunnel comprises an existing tunnel, a supporting structure arranged in the existing tunnel and the existing tunnel are filled, an extra-large section tunnel is formed after surrounding rocks are excavated on the peripheral side of the existing tunnel, and a plurality of foot locking anchor rods are arranged on the left side and the right side of the extra-large section tunnel. The invention simplifies the construction steps, greatly improves the vertical rigidity and the vertical bearing capacity of the intermediate wall, is beneficial to reducing the convergence of the cavern and improves the construction safety.

Description

Super-large-section tunnel drilling and blasting method original position enlarging constructing structure and construction method
Technical field:
The present invention relates to the construction of mountain tunnel, specifically adopt drilling and blasting method that existing tunnel original position is extended into a kind of construction method and the constructing structure of Super-large-section tunnel.
Background technology:
Along with developing rapidly of national economy, the volume of traffic increases day by day, many town road tunnels, High Grade Highway Tunnel oneself can not meet trip demand, must extend on existing tunnel former address, can be only achieved corresponding service level.Original position enlarging scheme generally includes following two: list hole tunnel is extended into multiple-arch tunnel, or list hole tunnel is extended into Super-large-section tunnel.Relative multiple-arch tunnel, the unfavorable factors such as Super-large-section tunnel scheme has the advantages such as road show line is convenient, level of service is high, social benefit is good, but to be also faced with tunnel span relatively big simultaneously, and support structure design is complicated, working procedure conversion is frequent.
Original position enlarging is formed in the process of Super-large-section tunnel, digged, again apply the Super-large-section tunnel of newly-built formation under the disturbance repeatedly of the operations such as supporting, its surrouding rock deformation and pressure from surrounding rock and initial land form by existing demolition of support structure, country rock explosion and have essential distinction.Simultaneously take account of existing tunnel supporting construction and be inevitably present relaxation zone or the situation such as come to nothing behind, consider temporary support structures is inevitably caused by blasting process the reality of damage, therefore the Super-large-section tunnel that original position enlarging is formed, in design concept and construction with build common Super-large-section tunnel and have dramatically different.
Along with the volume of traffic increases sharply, many build town road tunnel of the remote past, High Grade Highway Tunnel all suffers from enlarging problem, the enlarging of existing tunnel original position is formed Super-large-section tunnel, it it is then an important directions of development from now on, therefore, successfully grope a set of reasonable construction method adapted with it and seem very urgent.
Summary of the invention:
It is an object of the invention to solve above-mentioned technical problem, it is provided that a kind of reduce country rock disturbance, accelerate efficiency of construction, improve the Super-large-section tunnel original position enlarging constructing structure and construction method of working security.
Super-large-section tunnel drilling and blasting method original position of the present invention enlarging constructing structure, it is characterized in that: include existing tunnel and the supporting construction being located in existing tunnel and existing tunnel is filled, all sidepieces of described existing tunnel form Super-large-section tunnel after excavating country rock, and the left and right side of described Super-large-section tunnel is provided with many lock foot anchoring stocks.
Further, above-mentioned Super-large-section tunnel has been horizontally set with diaphragm plate (34) and the perpendicular mid-board (33) that is provided with, described diaphragm plate (34) and mid-board (33) square crossing setting.
Further, inverted arch steel arch-shelf and gunite concrete (35) it are provided with bottom above-mentioned Super-large-section tunnel.
Further, above-mentioned inverted arch steel arch-shelf and gunite concrete (35) inverted arch secondary lining (41) and inverted arch filling (42) have been built.
Further, the medial surface of above-mentioned Super-large-section tunnel is provided with steel arch-shelf and gunite concrete (32).
Construction method of the present invention includes following seven steps, wherein the first five step is that country rock partial excavation and the preliminary bracing of Super-large-section tunnel applies, the secondary lining that rear two steps are Super-large-section tunnel is built, seven steps are followed successively by 1) utilize slag backfill existing tunnel in hole to haunch, then excavate upper right pilot tunnel and apply corresponding preliminary bracing, 2) excavate upper left pilot tunnel and apply corresponding preliminary bracing, 3) excavate bottom right pilot tunnel and apply corresponding preliminary bracing, 4) excavate lower-left pilot tunnel and apply corresponding preliminary bracing, 5) after cavern's convergence is stable, excavation inverted arch also applies corresponding preliminary bracing, 6) the inverted arch secondary lining of Super-large-section tunnel is built, 7) abutment wall of Super-large-section tunnel is built, haunch and vault secondary lining.
Wherein 1) utilize hole slag backfill existing tunnel to haunch, then excavation upper right pilot tunnel apply corresponding preliminary bracing, specifically include: remove the supporting construction of more than existing tunnel haunch;Blasting Excavation upper right pilot tunnel country rock;Apply upper right quarter steel arch-shelf and gunite concrete;Apply upper right quarter lock foot anchoring stock;Apply interim mid-board.Wherein interim mid-board adopts stalk formula, is reliably connected by crab-bolt and existing tunnel supporting construction bottom it;Simultaneously interim between mid-board and the upper left pilot tunnel country rock not excavated, leave certain interval, and fill with cystosepiment.
2) excavate upper left pilot tunnel and apply corresponding preliminary bracing, being maintained with the delayed upper right pilot tunnel certain distance of upper left pilot drift, specifically include: Blasting Excavation upper left pilot tunnel country rock;Apply upper left quarter steel arch-shelf and gunite concrete;Apply upper left quarter lock foot anchoring stock.
3) excavate bottom right pilot tunnel and apply corresponding preliminary bracing, it is maintained with the delayed upper right pilot tunnel certain distance of bottom right pilot drift, specifically include: remove filling and the supporting construction of below existing tunnel haunch, but should partly retain existing tunnel supporting construction and filling, as a bearing of interim mid-board;Apply right lower quadrant steel arch-shelf and gunite concrete;Apply right lower quadrant lock foot anchoring stock;Apply the interim diaphragm plate in right side.
4) excavate lower-left pilot tunnel and apply corresponding preliminary bracing, it is maintained with lower-left pilot drift delayed upper left pilot tunnel certain distance, specifically include: Blasting Excavation lower-left pilot tunnel country rock, but a part of country rock should be retained, together with the existing tunnel supporting construction do not removed, it is beneficial to face as back-pressure Core Soil stable;Apply lower left quarter steel arch-shelf and gunite concrete;Apply lower left quarter lock foot anchoring stock;Apply the interim diaphragm plate in left side.
5) after cavern's convergence is stable, excavation inverted arch also applies corresponding preliminary bracing, specifically includes: remove filling and the supporting construction of existing tunnel remainder;Blasting Excavation inverted arch country rock;Apply inverted arch steel arch-shelf and gunite concrete;Bottom mid-board spreading to inverted arch, the preliminary bracing of Super-large-section tunnel will be made to close cyclization simultaneously.
6) build the inverted arch secondary lining of Super-large-section tunnel, specifically include: remove the latter half of interim mid-board, build inverted arch secondary lining and inverted arch is filled.
7) abutment wall of Super-large-section tunnel, haunch and vault secondary lining are built.Specifically include: remove interim diaphragm plate and the first half of interim mid-board, apply the waterproof and drain measure such as draining blind pipe, splash guard, and build abutment wall, haunch and vault secondary lining.
The present invention is compared with traditional large-section tunnel construction method (such as CRD method), or compared with Super-large-section tunnel original position enlarging construction method (such as application for a patent for invention 201410044970.1) that forefathers research and propose, construction method of the present invention has following 3 remarkable advantages.
1) both methodical interim mid-board, generally adopts bent wall, and lower support is not being excavated on country rock, and adds interim lock foot anchoring stock and be beneficial to improve its vertical bearing capacity.Interim mid-board in the present invention adopts stalk formula, and bottom is directly supported in existing tunnel supporting construction, this not only eliminates interim lock foot anchoring stock, simplify construction way, and substantially increase vertical rigidity and the vertical bearing capacity of mid-board, contribute to reducing cavern's convergence, improve working security.
2) both methodical interim mid-board, is generally closely attached to and does not excavate on country rock, interim mid-board in the present invention and do not excavate between country rock, leaves certain interval, and fills with cystosepiment, it is possible to prevents the impact damage that interim mid-board is caused by next-door neighbour's country rock explosion.
3) utilizing a part for existing tunnel supporting construction as Core Soil in the present invention, excavate when the 5th excavation step together with inverted arch country rock, it is stable that this contributes to face, improves working security.
Accompanying drawing illustrates:
Fig. 1 is existing tunnel before enlarging;
Fig. 2 is enlarging construction procedure one (upper right pilot drive and preliminary bracing);
Fig. 3 is enlarging construction procedure two (upper left pilot drive and preliminary bracing);
Fig. 4 is enlarging construction procedure three (bottom right pilot drive and preliminary bracing);
Fig. 5 is enlarging construction procedure four (lower-left pilot drive and preliminary bracing);
Fig. 6 is enlarging construction procedure five (Core Soil and inverted arch excavate and preliminary bracing);
Fig. 7 is enlarging construction procedure six (building inverted arch secondary lining);
Fig. 8 is enlarging construction procedure seven (building abutment wall, haunch and vault secondary lining).
Detailed description of the invention:
Below in conjunction with accompanying drawing, feature of present invention and application flow are further described, in order to understand.
Super-large-section tunnel drilling and blasting method original position of the present invention enlarging constructing structure (as shown in Figure 7), 22 are filled with the supporting construction 21 being located in existing tunnel and existing tunnel including existing tunnel A, all sidepieces of described existing tunnel form Super-large-section tunnel B after excavating country rock, and the left and right side of described Super-large-section tunnel is provided with many lock foot anchoring stocks 31.
Further, above-mentioned Super-large-section tunnel has been horizontally set with diaphragm plate 34 and the perpendicular mid-board 33 that is provided with, described diaphragm plate 34 and mid-board 33 square crossing setting.
Further, inverted arch steel arch-shelf and gunite concrete 35 it are provided with bottom above-mentioned Super-large-section tunnel.
Further, above-mentioned inverted arch steel arch-shelf and gunite concrete 35 inverted arch secondary lining 41 and inverted arch filling 42 have been built.Inverted arch secondary lining 41 can be armored concrete, and it can be soil rock layers and concrete layer that inverted arch fills 42.Diaphragm plate 34 and mid-board 33 can be I-beam or reinforced concrete slab.Mid-board 33 arranges position deviation Super-large-section tunnel centrage and accounts for the 1/10-1/6 of Super-large-section tunnel cross section transverse width.
Further, the medial surface of above-mentioned Super-large-section tunnel is provided with steel arch-shelf and gunite concrete 32.
Lock foot anchoring stock 31 is metal rod, and it forms one group between two, and two lock foot anchoring stocks form 20-50 degree.
As shown in Fig. 2-Fig. 8, Super-large-section tunnel drilling and blasting method original position of the present invention enlarging construction method, including following seven steps:
1) utilize hole slag backfill existing tunnel to haunch, then excavate upper right pilot tunnel and apply corresponding preliminary bracing, as in figure 2 it is shown, specifically include: removing the supporting construction 21 of more than existing tunnel haunch;Blasting Excavation upper right pilot tunnel country rock 1;Apply upper right quarter steel arch-shelf and gunite concrete 32;Apply upper right quarter lock foot anchoring stock 31;Apply interim mid-board 33.Wherein interim mid-board 33 adopts stalk formula, is reliably connected by crab-bolt and existing tunnel supporting construction 21 bottom it;Simultaneously interim between mid-board 33 and the upper left pilot tunnel country rock 1 not excavated, leave the gap of 30cm, and fill with cystosepiment.
2) excavate upper left pilot tunnel and apply corresponding preliminary bracing, being maintained with the delayed upper right pilot tunnel 15m of upper left pilot drift, as it is shown on figure 3, specifically include: Blasting Excavation upper left pilot tunnel country rock 1;Apply upper left quarter steel arch-shelf and gunite concrete 3201;Apply upper left quarter lock foot anchoring stock 3101.
3) excavate bottom right pilot tunnel and apply corresponding preliminary bracing, it is maintained with the delayed upper right pilot tunnel 30m of bottom right pilot drift, as shown in Figure 4, specifically include: remove filling 22 and the supporting construction 21 of below existing tunnel haunch, but should partly retain existing tunnel supporting construction 2101 and fill 2201, as a bearing of interim mid-board 33;Apply right lower quadrant steel arch-shelf and gunite concrete 3202;Apply right lower quadrant lock foot anchoring stock 3102;Apply the interim diaphragm plate 34 in right side.
4) excavate lower-left pilot tunnel and apply corresponding preliminary bracing, it is maintained with the delayed upper left pilot tunnel 30m of lower-left pilot drift, as shown in Figure 5, specifically include: Blasting Excavation lower-left pilot tunnel country rock 1, but a part of country rock should be retained, together with the existing tunnel supporting construction do not removed, it is beneficial to face as back-pressure Core Soil stable;Apply lower left quarter steel arch-shelf and gunite concrete 3203;Apply lower left quarter lock foot anchoring stock 3103;Apply the interim diaphragm plate 3401 in left side.
5) after cavern's convergence is stable, excavation inverted arch also applies corresponding preliminary bracing, as shown in Figure 6, specifically includes: remove filling 22 and the supporting construction 21 of existing tunnel remainder;Blasting Excavation inverted arch country rock 1;Apply inverted arch steel arch-shelf and gunite concrete 35;Bottom mid-board 33 spreading to inverted arch, the preliminary bracing of Super-large-section tunnel will be made to close cyclization simultaneously.
6) build the inverted arch secondary lining of Super-large-section tunnel, as it is shown in fig. 7, specifically include: remove the latter half of interim mid-board 33, once remove length (axial along tunnel) no more than 10m;Building inverted arch secondary lining 41 and inverted arch fills 42, one-time-concreting length (axial along tunnel) is no more than 10m.
7) build the abutment wall of Super-large-section tunnel, haunch and vault secondary lining, as shown in Figure 8, specifically include: remove the first half of interim diaphragm plate 34 and interim mid-board 33, once remove length (axial along tunnel) no more than 30m;Applying the waterproof and drain measure such as draining blind pipe, splash guard, and build abutment wall, haunch and vault secondary lining, one-time-concreting length (axial along tunnel) is no more than 30m.
The foregoing is only embodiments of the invention; not thereby the scope of the claims of the present invention is limited; every equivalent structure utilizing description of the present invention and accompanying drawing content to make or equivalence flow process conversion; or directly or indirectly it is used in other relevant technical fields, all in like manner include in the scope of patent protection of the present invention.

Claims (7)

1. a Super-large-section tunnel drilling and blasting method original position enlarging constructing structure, it is characterized in that: include existing tunnel (A) and the supporting construction (21) being located in existing tunnel and existing tunnel fills (22), all sidepieces of described existing tunnel form Super-large-section tunnel (B) after excavating country rock, and the left and right side of described Super-large-section tunnel is provided with many lock foot anchoring stocks (31).
2. Super-large-section tunnel drilling and blasting method original position according to claim 1 enlarging constructing structure, it is characterized in that: described Super-large-section tunnel has been horizontally set with diaphragm plate (34) and the perpendicular mid-board (33) that is provided with, described diaphragm plate (34) and mid-board (33) square crossing setting.
3. Super-large-section tunnel drilling and blasting method original position according to claim 2 enlarging constructing structure, it is characterised in that: it is provided with inverted arch steel arch-shelf and gunite concrete (35) bottom described Super-large-section tunnel.
4. Super-large-section tunnel drilling and blasting method original position according to claim 3 enlarging constructing structure, it is characterised in that: described inverted arch steel arch-shelf and gunite concrete (35) have built inverted arch secondary lining (41) and inverted arch filling (42).
5. Super-large-section tunnel drilling and blasting method original position according to claim 4 enlarging constructing structure, it is characterised in that: the medial surface of described Super-large-section tunnel is provided with steel arch-shelf and gunite concrete (32).
6. a Super-large-section tunnel drilling and blasting method original position enlarging construction method, it is characterized in that: include following seven steps, wherein the first five step is that country rock partial excavation and the preliminary bracing of Super-large-section tunnel applies, the secondary lining that rear two steps are Super-large-section tunnel is built, seven steps are followed successively by 1) utilize slag backfill existing tunnel in hole to haunch, then excavate upper right pilot tunnel and apply corresponding preliminary bracing, 2) excavate upper left pilot tunnel and apply corresponding preliminary bracing, 3) excavate bottom right pilot tunnel and apply corresponding preliminary bracing, 4) excavate lower-left pilot tunnel and apply corresponding preliminary bracing, 5) after cavern's convergence is stable, excavation inverted arch also applies corresponding preliminary bracing, 6) the inverted arch secondary lining of Super-large-section tunnel is built, 7) abutment wall of Super-large-section tunnel is built, haunch and vault secondary lining.
7. Super-large-section tunnel drilling and blasting method original position according to claim 6 enlarging construction method, it is characterised in that:
Wherein 1) utilize hole slag backfill existing tunnel to haunch, then excavation upper right pilot tunnel apply corresponding preliminary bracing, specifically include: remove the supporting construction (21) of more than existing tunnel haunch;Blasting Excavation upper right pilot tunnel country rock (1);Apply upper right quarter steel arch-shelf and gunite concrete (32);Apply upper right quarter lock foot anchoring stock (31);Applying interim mid-board (33), wherein interim mid-board (33) adopts stalk formula, is reliably connected by crab-bolt and existing tunnel supporting construction (21) bottom it;Simultaneously interim between mid-board (33) and upper left pilot tunnel country rock (1) do not excavated, leave the gap of 30cm, and fill with cystosepiment;
2) excavate upper left pilot tunnel and apply corresponding preliminary bracing, being maintained with the delayed upper right pilot tunnel 15m of upper left pilot drift, specifically include: Blasting Excavation upper left pilot tunnel country rock (1);Apply upper left quarter steel arch-shelf and gunite concrete (3201);Apply upper left quarter lock foot anchoring stock (3101);
3) excavate bottom right pilot tunnel and apply corresponding preliminary bracing, it is maintained with the delayed upper right pilot tunnel 30m of bottom right pilot drift, specifically include: remove filling (22) and the supporting construction (21) of below existing tunnel haunch, but should partly retain existing tunnel supporting construction (2101) and fill (2201), as a bearing of interim mid-board (33);Apply right lower quadrant steel arch-shelf and gunite concrete (3202);Apply right lower quadrant lock foot anchoring stock (3102);Apply the interim diaphragm plate (34) in right side;
4) excavate lower-left pilot tunnel and apply corresponding preliminary bracing, it is maintained with the delayed upper left pilot tunnel 30m of lower-left pilot drift, specifically include: Blasting Excavation lower-left pilot tunnel country rock (1), but a part of country rock should be retained, together with the existing tunnel supporting construction do not removed, it is beneficial to face as back-pressure Core Soil stable;Apply lower left quarter steel arch-shelf and gunite concrete (3203);Apply lower left quarter lock foot anchoring stock (3103);Apply the interim diaphragm plate (3401) in left side;
5) after cavern's convergence is stable, excavation inverted arch also applies corresponding preliminary bracing, specifically includes: remove filling (22) and the supporting construction (21) of existing tunnel remainder;Blasting Excavation inverted arch country rock (1);Apply inverted arch steel arch-shelf and gunite concrete (35);Bottom mid-board (33) spreading to inverted arch, the preliminary bracing of Super-large-section tunnel will be made to close cyclization simultaneously;
6) build the inverted arch secondary lining of Super-large-section tunnel, specifically include: remove the latter half of interim mid-board (33), axially once remove length along tunnel no more than 10m;Building inverted arch secondary lining (41) and inverted arch fills (42), along tunnel, axial one-time-concreting length is no more than 10m;
7) build the abutment wall of Super-large-section tunnel, haunch and vault secondary lining, specifically include: remove interim diaphragm plate (34) and the first half of interim mid-board (33), axially once remove length along tunnel no more than 30m;Applying the waterproof and drain measure such as draining blind pipe, splash guard, and build abutment wall, haunch and vault secondary lining, along tunnel, axial one-time-concreting length is no more than 30m.
CN201610326428.4A 2016-05-17 2016-05-17 Super-large section tunnel drilling and blasting method in-situ expansion construction structure and construction method Active CN105804760B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610326428.4A CN105804760B (en) 2016-05-17 2016-05-17 Super-large section tunnel drilling and blasting method in-situ expansion construction structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610326428.4A CN105804760B (en) 2016-05-17 2016-05-17 Super-large section tunnel drilling and blasting method in-situ expansion construction structure and construction method

Publications (2)

Publication Number Publication Date
CN105804760A true CN105804760A (en) 2016-07-27
CN105804760B CN105804760B (en) 2018-05-25

Family

ID=56451387

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610326428.4A Active CN105804760B (en) 2016-05-17 2016-05-17 Super-large section tunnel drilling and blasting method in-situ expansion construction structure and construction method

Country Status (1)

Country Link
CN (1) CN105804760B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106499417A (en) * 2016-10-25 2017-03-15 中铁隧道集团二处有限公司 The reserved T word rock beam rock pillar constructions of extra-large cross-section resistant Capacity of Shallow-buried Subway Station
CN106968678A (en) * 2017-03-30 2017-07-21 唐山市交通运输局公路管理站 A kind of overall cavitation machine of stone matter surrounding rock tunnel and construction technology
CN107060825A (en) * 2017-05-04 2017-08-18 山东省交通规划设计院 Construction method is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock
CN107654239A (en) * 2017-09-20 2018-02-02 中铁十四局集团有限公司 A kind of tunnel bottom is excavated and inverted arch construction method
CN109594993A (en) * 2019-01-23 2019-04-09 四川交通职业技术学院 A kind of tunnel enlarging construction method in the case of uninterrupted traffic
CN109695457A (en) * 2018-12-21 2019-04-30 中铁四局集团有限公司 In-situ expansion super-large section tunnel of hard rock and step construction method
CN109899092A (en) * 2017-12-08 2019-06-18 中铁二局集团有限公司 A kind of soft rock extrusion pressing type large deformation tunnel arch lock solid structure and method
CN110905524A (en) * 2019-11-08 2020-03-24 中建隧道建设有限公司 Method for excavating and supporting subway station tunnel by adopting underground excavation construction channel
CN114152159A (en) * 2021-12-09 2022-03-08 中国葛洲坝集团国际工程有限公司 Full-section synchronous blasting tunneling construction method for side wall on reserved side of large-section tunnel crown arch
CN114961739A (en) * 2022-05-16 2022-08-30 中铁五局集团有限公司 Construction method for re-excavation and expanded excavation of abandoned tunnel

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101737061A (en) * 2009-12-24 2010-06-16 中国水电顾问集团华东勘测设计研究院 Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel
CN102865084A (en) * 2012-09-29 2013-01-09 中铁二局股份有限公司 Expanding excavation method of underground tunnel from fracture surface of double-track tunnel to ultra-large fracture surface of triple-track tunnel
CN103306680A (en) * 2013-03-23 2013-09-18 中铁二院工程集团有限责任公司 Construction method for extending single-track tunnel to multi-track tunnel
CN103485791A (en) * 2013-09-27 2014-01-01 福州大学 Construction method for in-situ maintenance or extension of road tunnel
CN103953351A (en) * 2014-05-20 2014-07-30 长安大学 Existing tunnel down-digging extension construction method without traffic interruption
CN205778879U (en) * 2016-05-17 2016-12-07 中铁十五局集团有限公司 Super large section tunnel bores and explodes method normal position enlargement construction structures

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101737061A (en) * 2009-12-24 2010-06-16 中国水电顾问集团华东勘测设计研究院 Method for constructing double-arch tunnel by rebuilding and expanding existing single-hole tunnel
CN102865084A (en) * 2012-09-29 2013-01-09 中铁二局股份有限公司 Expanding excavation method of underground tunnel from fracture surface of double-track tunnel to ultra-large fracture surface of triple-track tunnel
CN103306680A (en) * 2013-03-23 2013-09-18 中铁二院工程集团有限责任公司 Construction method for extending single-track tunnel to multi-track tunnel
CN103485791A (en) * 2013-09-27 2014-01-01 福州大学 Construction method for in-situ maintenance or extension of road tunnel
CN103953351A (en) * 2014-05-20 2014-07-30 长安大学 Existing tunnel down-digging extension construction method without traffic interruption
CN205778879U (en) * 2016-05-17 2016-12-07 中铁十五局集团有限公司 Super large section tunnel bores and explodes method normal position enlargement construction structures

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王跃东: "大断面扩挖隧道分部开挖施工技术研究", 《交通建设与管理》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106499417B (en) * 2016-10-25 2019-01-08 中铁隧道集团二处有限公司 Extra-large cross-section resistant Capacity of Shallow-buried Subway Station reserves T word rock beam rock pillar construction
CN106499417A (en) * 2016-10-25 2017-03-15 中铁隧道集团二处有限公司 The reserved T word rock beam rock pillar constructions of extra-large cross-section resistant Capacity of Shallow-buried Subway Station
CN106968678A (en) * 2017-03-30 2017-07-21 唐山市交通运输局公路管理站 A kind of overall cavitation machine of stone matter surrounding rock tunnel and construction technology
CN106968678B (en) * 2017-03-30 2018-06-15 唐山市交通运输局公路管理站 A kind of stone matter surrounding rock tunnel entirety cavitation machine and construction technology
CN107060825B (en) * 2017-05-04 2024-02-02 山东省交通规划设计院 Single hole applied to III-level surrounding rock four-lane tunnel subsection coordination construction method
CN107060825A (en) * 2017-05-04 2017-08-18 山东省交通规划设计院 Construction method is coordinated by a kind of single-hole with four lanes tunnel branch for being applied to III grade of country rock
CN107654239A (en) * 2017-09-20 2018-02-02 中铁十四局集团有限公司 A kind of tunnel bottom is excavated and inverted arch construction method
CN109899092A (en) * 2017-12-08 2019-06-18 中铁二局集团有限公司 A kind of soft rock extrusion pressing type large deformation tunnel arch lock solid structure and method
CN109695457A (en) * 2018-12-21 2019-04-30 中铁四局集团有限公司 In-situ expansion super-large section tunnel of hard rock and step construction method
CN109594993A (en) * 2019-01-23 2019-04-09 四川交通职业技术学院 A kind of tunnel enlarging construction method in the case of uninterrupted traffic
CN110905524A (en) * 2019-11-08 2020-03-24 中建隧道建设有限公司 Method for excavating and supporting subway station tunnel by adopting underground excavation construction channel
CN114152159A (en) * 2021-12-09 2022-03-08 中国葛洲坝集团国际工程有限公司 Full-section synchronous blasting tunneling construction method for side wall on reserved side of large-section tunnel crown arch
CN114961739A (en) * 2022-05-16 2022-08-30 中铁五局集团有限公司 Construction method for re-excavation and expanded excavation of abandoned tunnel

Also Published As

Publication number Publication date
CN105804760B (en) 2018-05-25

Similar Documents

Publication Publication Date Title
CN105804760A (en) Super-large section tunnel drilling and blasting method in-situ expansion construction structure and construction method
CN102733827B (en) Tunnel arch exchanging construction method and construction structure in tunnel arch exchanging construction
CN205778879U (en) Super large section tunnel bores and explodes method normal position enlargement construction structures
CN101338678B (en) Supporting arch hidden digging top-down construction method
CN105064397B (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
CN105041349A (en) Underground excavation construction method for expanded excavation of station on basis of metro regional shield tunnel
CN105862930B (en) A kind of protection structure to creating existing tunnel below underground engineering
CN101769154A (en) Excavation supporting method for tunnel construction
CN104329095B (en) A kind of existing tunnel Widening Construction method
CN109723085B (en) Deep foundation pit division construction rib wall support replacing structure and construction method thereof
CN105178327A (en) Composite retaining structure of foundation pit project and construction method thereof
CN203239357U (en) Adjacent tunnel supporting structure suitable for collapsible loess
CN105089670B (en) Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel
CN109322330A (en) A kind of light and dark digging combination Metro Station Structure avoiding housing demolition and its construction method
CN102660955B (en) Quick construction method for foundation pit slope support
CN108797641A (en) A kind of structure and its construction method of Underground Subway Station construction period full station sealing
CN108589771A (en) One kind having runed underground station increasing layer transfer node construction method
CN103696784A (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN103362513A (en) Transformation and construction method for existing cavity in underground excavation region
CN109056810B (en) Transverse expanding excavation structure of underground main body structure of open excavation or cover excavation below existing building and construction method thereof
CN104453948B (en) A kind of construction technology of big cross section bored tunnel vertical prestressing steel pipe support
CN107869351A (en) A kind of method of the high narrow large-scale solution cavity Cavity treatment security protection of type
CN106758890B (en) Campshed box culvert structure and its construction method
CN204940298U (en) A kind of Composite Enclosure Structure of base pit engineering
CN112922646B (en) Building method of underground excavation station excavated by large-section single-span support through superposed arch-wall integrated type

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20200616

Address after: 200040 No. 666, Gonghe new road, Jing'an District, Shanghai

Co-patentee after: China Railway 15th Bureau Group Second Engineering Co.,Ltd.

Patentee after: CHINA RAILWAY 15TH BUREAU GROUP Co.,Ltd.

Co-patentee after: THE 5TH CONSTRUCTION COMPANY LTD. OF CHINA RAILWAY 15TH BUREAU GROUP Co.,Ltd.

Co-patentee after: Fujian Xiamen-Rongshan Expressway Zhanglong Section Extension Engineering Co.,Ltd.

Address before: 200070 No. 666, Gonghe Road, Shanghai, Zhabei District

Co-patentee before: China Railway 15th Bureau Group Second Engineering Co.,Ltd.

Patentee before: CHINA RAILWAY 15TH BUREAU GROUP Co.,Ltd.

TR01 Transfer of patent right