CN105798541B - A kind of manufacture method of high building damper - Google Patents

A kind of manufacture method of high building damper Download PDF

Info

Publication number
CN105798541B
CN105798541B CN201410845139.6A CN201410845139A CN105798541B CN 105798541 B CN105798541 B CN 105798541B CN 201410845139 A CN201410845139 A CN 201410845139A CN 105798541 B CN105798541 B CN 105798541B
Authority
CN
China
Prior art keywords
steel
equipment
component
high building
manufacture method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410845139.6A
Other languages
Chinese (zh)
Other versions
CN105798541A (en
Inventor
蔡静
周靖
王俊芳
赵春阳
何平
周建建
吴寒君
钱奕江
申洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201410845139.6A priority Critical patent/CN105798541B/en
Publication of CN105798541A publication Critical patent/CN105798541A/en
Application granted granted Critical
Publication of CN105798541B publication Critical patent/CN105798541B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

A kind of manufacture method of high building damper, it is characterised in that comprise the following steps:(1)Material selects,(2)Operational preparation,(3)Steel blanking,(4)Drilling,(5)Welding,(6)Manufacturing deviation,(7)Derusting, application,(8)Mark,(9)Workshop is assembled,(10)Packaging and transport.The manufacture method of the high building damper of the present invention has drilling precision high, eliminates the influence of welding deformation, and part machine adds precision high, implements factory's simulated test and ensures the advantages of being assembled in narrow space.

Description

A kind of manufacture method of high building damper
Technical field
The present invention relates to a kind of manufacture method of damper, is a kind of manufacture method of high building damper specifically.
Background technology
Chinese patent CN102864853 B disclosed a kind of tuning matter for towering tower vibration damping on the 17th in September in 2014 Damper is measured, wherein the tuned mass damper for towering tower vibration damping, it is arranged in the top of tower body or top, including:Matter Gauge block, damping system, spring system, the mass are connected with damping system, spring system respectively, and by hanging or supporting It is removable.Although this tuned mass damper for towering tower vibration damping is arranged in the top or top of towering tower, pass through matter The damping action of damper is measured, can effectively mitigate the vibration of towering tower.But accurate calculate is needed when being actually designed Structure dynamic parameter, particularly fundamental vibration frequency, error, or manufacture are produced when estimating main structure natural frequency or identifying Or error during construction, deviation can be produced to optimum frequency design load, cause the missing of practical application.
Therefore known high building damper manufacture there are problems that above-mentioned a variety of inconvenience and.
The content of the invention
The purpose of the present invention, it is to propose a kind of manufacture method of the high building damper of box frame type counterweight steel construction.
To achieve the above object, technical solution of the invention is:
A kind of manufacture method of high building damper, it is characterised in that comprise the following steps:
(1)Material selects
The selection of steel, welding material, bolt material meets the requirement of construction drawing, and should have steel mill and welding material The quality certificate or survey report of factory;Its chemical composition, mechanical property and other quality requirements have to comply with regulation;
(2)Operational preparation
Steel construction works out production program, checks the technological preparation situation of each procedure, and carry out fabrication drawing before manufacture From examining and mutually careful work;Various materials and equipment needed for manufacturing are checked, technological equipment meets wanting for technological procedure Ask;
(3)Steel blanking
Steel should carry out dispensing and typesetting before blanking, avoid blanking mistake;After steel cutting, notching edge is beaten Mill, smooth processing;
(4 )Drilling
All High-strength bolt holes of component use numerical control drilling machine drilling, or to be carried out with brill, guarantee drilling using radial drill Precision;Bore diameter is consistent with size shown on construction drawing;
(5)Welding
Welding quality grade and test stone meet design drawing requirement, and detection unit carries out seam inspection and goes out to examine report Accuse;
(6)Manufacturing deviation
All parts preferably carry out dimensional gaughing, and inspection result need to meet to make specification;
(7)Derusting, application
Component is thoroughly removed totally before application, by the burr of component surface, iron rust, oxide skin, greasy dirt and attachment etc., Surface derusting grade reaches Sa2.5 levels;
(8)Mark
Corresponding component numbering must accurately be write after completing to the component to have completed according to drawing;Need existing Splice plate, fixture and other small parts of field connection are attached temporarily on corresponding component;Bolt, nuts and washers are mounted in conjunction In suitable sack and mark is carried out, so as to ensure to be used on correct position;
(9)Assemble at workshop
Framework and weight shelf should assemble after being made to whole shock-absorption, to confirm that joint aligns;Put with three-level 400 tons of the shock-absorption of weighing is hung up, and is installed under its driver framework base with servomotor, steel wire rope, roller Drive device, with active drive shock-absorption;Servo motor driving system need be equipped with control panel, servo-driver panel, Sensor attendant equipment;An equipment must be assembled temporarily, can be by confirm the size of framework bolt etc. as illustrated in the drawings It is required that assembled, another equipment must whole completed assembled, to complete performance validation tests, look at that can equipment with entirety System works;
(10)Packaging and transport
To performance test complete equipment dismount, the project of all manufactures be furnished with Part No., so as to in-site installation with Projects are identified during assembling;Extreme care when component entrucking and colligation, in order to avoid the deformation of member, impaired or paint film spalling, after entrucking By providing to be checked, it is damaged or shakes off to prevent tote.
The manufacture method of the high building damper of the present invention can also be further achieved by the following technical measures.
Foregoing method, wherein in the step 9, the maximum length of driver framework base reaches 8m, and surface planarity reaches 0.05mm, length variation are not more than 0.2mm, and the perpendicularity of horizontal plane and facade is not more than 0.05mm.
Foregoing method, wherein in the step 9, the depth of parallelism of track and the screw mandrel correction of drive device reaches 0.05mm。
After adopting the above technical scheme, the manufacture method of the high building damper of the present invention has advantages below:
1st, drilling precision is high
The frame structure of shock absorber is box-shaped steel structure, ensure box-structure high-strength bolt joint group's pore geometry size and The machining accuracy of High-strength bolt hole.
2nd, the influence of welding deformation is eliminated
Welding stress after welding structure machines is in delivery mode, during welding stress release during due to normal weld Between it is longer, welding deformation can be caused after release, and these parts need to be machined, required precision is high, is such as machined No longer it is deformed afterwards, meets class fit requirement.
3rd, part machine adds precision height
The control and detection of big machinery process component machining accuracy, the maximum length of driver framework base reach 8m, table Facial plane degree reaches 0.05mm, and length variation is not more than 0.2mm, and the perpendicularity of horizontal plane and facade is not more than 0.05mm, and needs Can the selection of Three-dimension process, manufacturing process and detection means be directly connected to the required precision that realize Japanese side.
4th, factory's simulated test is implemented
Due to there is larger horizontal force action in building main body when shock absorber operates, field test is carried out.
5th, ensure and assembled in narrow space
Ensure and framework assembling and steel cable hanging assembling are completed in limited working space.
Brief description of the drawings
Fig. 1 is the high building damper structure schematic diagram of the embodiment of the present invention;
Fig. 2 is the A-A sectional views in Fig. 1;
Fig. 3 is the floor plan of the high building damper of the embodiment of the present invention;
Fig. 4 is the structure manufacture process chart of the high building damper of the embodiment of the present invention;
Fig. 5 is the component layout drawing of the high building damper of the embodiment of the present invention.
In figure:1 motor, 2 balancing weights, 3 outer frameworks, 4 middle frames, 5 inner frames, 6 counterweight frames, 7 drive screws, 8 Free period adjusting apparatus is swung, 9 swing steel cable, 10XY beams, 11 driving mandrels, 12 outer frameworks basis.
Embodiment
With reference to embodiments and its accompanying drawing illustrates further to the present invention.
Embodiment 1
The high building number of plies of safety financial center project is 118 layers, agent structure is highly 558.45 meters, high building of the invention Damper is separately positioned in two cylinders in L113-L115 layer Core Walls Structure northwest corners and southeast corner.
Referring now to Fig. 1, Fig. 1 Fig. 1 is the high building damper structure schematic diagram of the embodiment of the present invention;Fig. 2 is the A- in Fig. 1 A sectional views;Fig. 3 is the floor plan of the high building damper of the embodiment of the present invention.
Fig. 4 is the structure manufacture process chart of the high building damper of the embodiment of the present invention.Fig. 5 is the embodiment of the present invention The component layout drawing of high building damper.
The manufacture method of the high building damper of the present invention, it is characterised in that comprise the following steps:
(1)Material selects
The selection of the materials such as steel, welding material, bolt meets the requirement of construction drawing, and should have steel mill and welding material Expect the quality certificate or survey report of factory;Its chemical composition, mechanical property and other quality requirements have to comply with regulation.
This project material is national standard material, and national standard material capability must not be less than the mark performance of day shown in drawing;Entered material should Meet the internal inspection standard of Mitsubishi.
(2)Operational preparation
Steel construction works out production program, conscientiously checks the technological preparation situation of each procedure, and carry out manufacture before manufacture Drawing examines work from careful with mutual.
Technological equipment, which should meet the requirement of technological procedure, to be checked to the various materials and equipment needed for manufacturing.
Operating personnel on duty are carried out with necessary training and examination in advance, qualification confirmation is carried out to special work post, determines it Operation is carried out in the quality certification term of validity.
(3)Steel blanking
Steel should carry out dispensing and typesetting before blanking, avoid blanking mistake, and saving steel to greatest extent.
Permit without Mitsubishi, joints must not be set to parts.
After steel cutting, notching edge should be polished, smooth processing;Require to beat groove on drawing, in strict accordance with Drawing requirement beveling, groove section should be clean, smooth.
(4)Drilling
The method that all High-strength bolt holes of component all should use drilling drilling, best numerical control drilling machine drilling, according to rocking arm Brill must be carried out with brill, strict guarantee drilling precision.
Bore diameter should be consistent with size shown on construction drawing.
(5)Welding
Welding quality grade and test stone should meet design drawing requirement, and weld seam is carried out by the detection unit of Mitsubishi's accreditation Detect a flaw and go out survey report.
(6)Manufacturing deviation
All parts preferably carry out dimensional gaughing, and inspection result need to meet the making specification that Mitsubishi provides.
(7)Derusting, application
Component is before application, it is necessary to thoroughly removes the burr of component surface, iron rust, oxide skin, greasy dirt and attachment etc. Totally, surface derusting grade reaches Sa2.5 levels.
It is as follows using Northwest company coating, specification requirement:
Priming paint:SD ZINC 100, thickness 15um.
Middle touch-up paint(Impaired or welding region):ESCO NB SAFETY, thickness 40um.
Intermediate coat:ESCO NB SAFETY, thickness 60um.
Intermediate coat(Post coat):CELATECT MILD, thickness 30um.
Finish paint(Post coat):CELATECT U, thickness 25um.
The last gross thickness of coating is 130um, and film thickness should meet the making specification of Mitsubishi.
(8)Mark
Corresponding component numbering must accurately be write after completing to the component to have completed according to drawing.
The splice plate, fixture and other small parts of joint connection in site is needed to be attached temporarily to carry out on corresponding component Delivery.Bolt, nuts and washers should be mounted in suitable sack and carry out mark, so as to ensure to make on correct position With.
(9 )Assemble at workshop
Framework and weight shelf should assemble after being made to whole shock-absorption, to confirm joint alignment condition etc..
Should completely install a shock-absorption in the case of this, include the project that MBE is provided, for example, steel wire rope, drive device, Electric control unit etc., to complete operation acknowledgement experiment.
Workshop linkage editor
Hung up with will weigh 400 tons of shock-absorption of three-level pendulum, and in its bottom servomotor, steel wire rope, rolling Cylinder etc. installs drive device, with active drive shock-absorption.
Servo motor driving system needs to be equipped with the attendant equipments such as control panel, servo-driver panel, sensor.
An equipment must be assembled temporarily, to confirm the size of framework bolt etc. as illustrated in the drawings, can be entered on request Row assembling.
Another equipment must whole completed assembled, to complete performance validation tests, look at that can equipment with total system Work.
(10)Packaging and transport
The equipment completed to performance test dismounts, and the project of all manufactures should be furnished with Part No., so as to in-site installation Projects are identified during with assembling.
Press《Convey main points book》Requirement packed.
Pack and be not capped in principle.
It is easily damaged or need the project of waterproof to answer properly pack in transit, to keep its quality.
Entrucking and colligation
Extreme care is answered when component entrucking and colligation, in order to avoid the deformation of member, impaired or paint film spalling.
After entrucking, it should be damaged, shake off to prevent tote by providing to be checked.
The manufacture method of the high building damper of the present invention is sent someone to stay factory by Mitsubishi, and product quality and progress are supervised, Manufacturer must actively coordinate the work of Party A and owner, and manufacturer must carry out 100% quality examination to product and form word Record.Party A personnel in the factory requirement manufacturer that has the right rectifies and improves to the quality problems occurred in manufacture course of products, thus Caused economic loss and construction delay are undertaken by manufacturer.Per pass inspection process, should be according to drawing and Mitsubishi's relative production Specification is tested.
The present invention has substantive distinguishing features and a significant technological progress, the manufacture method of high building damper of the invention, its Middle damper frame structure is made up of outer framework, middle frame, inner frame, and the precision of priority control High-strength bolt hole, is adopted during construction Take the supporting drilling of motherboard, it is pre-assembled the methods of ensure easily connecting for framework.Track girder below its other transmission device Very high is required to top surface horizontal accuracy, linearity, end face squareness, needs to be sent to the progress of biography industry heat treatment factory after factory's preliminary working Weld stress eliminates heat treatment, then carries out end face, the finishing of horizontal plane, to cause structure because weld stress discharges behind preventing Part is crept.
Above example is used for illustrative purposes only, rather than limitation of the present invention, the technology people about technical field Member, without departing from the spirit and scope of the present invention, can also make various conversion or change.Therefore, it is all equivalent Technical scheme should also belong to scope of the invention, should be limited by each claim.

Claims (3)

1. a kind of manufacture method of high building damper, it is characterised in that comprise the following steps:
(1)Material selects
The selection of steel, welding material, bolt material meets the requirement of construction drawing, and should have steel mill and welding material factory Quality certificate or survey report;Its chemical composition, mechanical property and other quality requirements have to comply with regulation;
(2)Operational preparation
Steel construction works out production program, checks the technological preparation situation of each procedure before manufacture, and carries out oneself of fabrication drawing Examine and mutually examine work;Technological equipment, which meets the requirement of technological procedure, to be checked to the various materials and equipment needed for manufacturing;
(3)Steel blanking
Steel should carry out dispensing and typesetting before blanking, avoid blanking mistake;After steel cutting, notching edge is polished, Smooth processing;
(4)Drilling
All High-strength bolt holes of component use numerical control drilling machine drilling, or to be carried out with brill, guarantee drilling precision using radial drill; Bore diameter is consistent with size shown on construction drawing;
(5)Welding
Welding quality grade and test stone meet design drawing requirement, and detection unit carries out seam inspection and goes out survey report;
(6)Manufacturing deviation
All parts preferably carry out dimensional gaughing, and inspection result need to meet to make specification;
(7)Derusting, application
Component thoroughly removes the burr of component surface, iron rust, oxide skin, greasy dirt and attachment etc. on clean, surface before application Derusting grade reaches Sa2.5 levels;
(8)Mark
Corresponding component numbering must accurately be write after completing to the component to have completed according to drawing;Need scene even Splice plate, fixture and other small parts connect are attached temporarily on corresponding component;Bolt, nuts and washers are mounted in suitable In sack and mark is carried out, so as to ensure to be used on correct position;
(9)Assemble at workshop
Framework and weight shelf should assemble after being made to whole shock-absorption, to confirm that joint aligns;Will weight with three-level pendulum Hung up up to 400 tons of shock-absorptions, and driving is installed with servomotor, steel wire rope, roller under its driver framework base Device, with active drive shock-absorption;Servo motor driving system needs to be equipped with control panel, servo-driver panel, sensing Device attendant equipment;An equipment must be assembled temporarily, can be on request to confirm the size of framework bolt etc. as illustrated in the drawings Assembled, another equipment must whole completed assembled, to complete performance validation tests, look at that can equipment with total system Work;
(10)Packaging and transport
The equipment completed to performance test dismounts, and the project of all manufactures is furnished with Part No., so as to in-site installation and assembling When identify projects;Extreme care when component entrucking and colligation, in order to avoid the deformation of member, impaired or paint film spalling, by rule after entrucking Surely it must be checked, be damaged or shake off to prevent tote.
2. the manufacture method of high building damper as claimed in claim 1, it is characterised in that the step(9)In, driver framework The maximum length of base reaches 8m, and surface planarity reaches 0.05mm, and length variation is not more than 0.2mm, horizontal plane and facade it is vertical Degree is not more than 0.05mm.
3. the manufacture method of high building damper as claimed in claim 1, it is characterised in that the step(9)In, drive device Track and screw mandrel correction the depth of parallelism reach 0.05mm.
CN201410845139.6A 2014-12-31 2014-12-31 A kind of manufacture method of high building damper Active CN105798541B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410845139.6A CN105798541B (en) 2014-12-31 2014-12-31 A kind of manufacture method of high building damper

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410845139.6A CN105798541B (en) 2014-12-31 2014-12-31 A kind of manufacture method of high building damper

Publications (2)

Publication Number Publication Date
CN105798541A CN105798541A (en) 2016-07-27
CN105798541B true CN105798541B (en) 2017-12-29

Family

ID=56420177

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410845139.6A Active CN105798541B (en) 2014-12-31 2014-12-31 A kind of manufacture method of high building damper

Country Status (1)

Country Link
CN (1) CN105798541B (en)

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4598503A (en) * 1984-06-04 1986-07-08 Berger Richard C Vibration absorption mounting for a rooftop air handling unit or the like (II)
CN101691787B (en) * 2009-09-22 2011-07-20 中铁十二局集团建筑安装工程有限公司 Converse construction process for middle-high steel structure building
CN101832358B (en) * 2010-03-26 2011-11-09 北京工业大学 Peg-top vibration-reducing damper for controlling structure to vibrate in multiple dimensions and manufacturing method thereof
CN101812879B (en) * 2010-03-26 2012-07-25 北京工业大学 Tuned mass damper for controlling tri-dimensional translation and horizontal torsion of building structure and manufacturing method thereof
CN102864853B (en) * 2012-09-29 2014-09-17 浙江工业大学 Tuned mass damper for performing vibration attenuation on tall tower
CN103774845A (en) * 2014-01-24 2014-05-07 成张佳宁 Construction method for high-rise large-span stiff damping structure

Also Published As

Publication number Publication date
CN105798541A (en) 2016-07-27

Similar Documents

Publication Publication Date Title
CN101487765B (en) Three-axial vibration composite testing apparatus
CN101323351B (en) Shipping rudder system lighting and mounting method
US8103374B2 (en) Processing apparatus, center-hole working system, center-hole position deciding program, and center-hole position deciding method
JP5930103B2 (en) Pressurized strain relief
CN105149803A (en) Welding device applied to fully-welded ball valve body and welding technology of welding device
CN106592454A (en) Offset steel stand column for railway sound barrier
CN105798541B (en) A kind of manufacture method of high building damper
CN114043171B (en) Manufacturing method of curve cable tower steel anchor box
JP5064740B2 (en) Maximum response member angle measuring device for viaduct columns
CN201425544Y (en) Triaxial vibration composite test device
CN111014299B (en) Online mounting method for hot rolling coiler wrapper roller frame bearing pedestal
CN102371362B (en) Static and dynamic balance processing method for heavy-duty hollow roller way
CN101823204B (en) Method for machining crankcase bearing seat holes of large multi-column labyrinth compressor
CN110158774A (en) A kind of construction method that large span grid double-machine lifting crane subregion closes up
CN104526398B (en) Curb girder centering and processing equipment
CN206346127U (en) Railway sound barrier biases steel column
CN110907163B (en) Friction type high-strength bolt connection performance detection test method
CN205981063U (en) Angle detecting means is expected to bend by panel beating
CN204397189U (en) Multifunctional split-type group is to platform
CN112091466B (en) Welding process method and flow for integrated frame of DDS (direct digital synthesizer) structure manipulator frame
Pathak et al. Manufacturing of ITER vacuum vessel in-wall shielding
CN107695551A (en) A kind of assembly tooling of ring beam and assembly method
CN108544190A (en) A kind of bending box-shaped head tower segment manufacturing method
CN109079407B (en) Steel structure turning tool equipment and control method thereof
CN102179661A (en) Method for machining frame of cold continuous rolling mill

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant