CN105780662B - A kind of Long span support amount of deflection controls construction method - Google Patents

A kind of Long span support amount of deflection controls construction method Download PDF

Info

Publication number
CN105780662B
CN105780662B CN201610213775.6A CN201610213775A CN105780662B CN 105780662 B CN105780662 B CN 105780662B CN 201610213775 A CN201610213775 A CN 201610213775A CN 105780662 B CN105780662 B CN 105780662B
Authority
CN
China
Prior art keywords
concrete beam
beam body
concrete
end bay
tensioning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610213775.6A
Other languages
Chinese (zh)
Other versions
CN105780662A (en
Inventor
叶智勇
陈立生
赵国强
徐伟忠
郑杰
戴慧丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Municipal Engineering Group Co Ltd
Original Assignee
Shanghai Urban Construction Municipal Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Municipal Engineering Group Co Ltd filed Critical Shanghai Urban Construction Municipal Engineering Group Co Ltd
Priority to CN201610213775.6A priority Critical patent/CN105780662B/en
Publication of CN105780662A publication Critical patent/CN105780662A/en
Application granted granted Critical
Publication of CN105780662B publication Critical patent/CN105780662B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

Construction method is controlled the invention discloses a kind of Long span support amount of deflection, is comprised the following steps:Required according to detail design, apply foundation pile, and rack platform is set up on the foundation pile;Divide three sections by the concrete beam on the rack platform to pour, two end bay concrete beam bodies are poured first, and the interim external beam body prestressing force of two end bay concrete beam bodies described in tensioning, i.e. every temporary pre-stressed concentration in the two end bays concrete beam body carries out two ends tensioning by 15~18T stretching force;After-pouring in across concrete beam body, and the prestressing force of the whole concrete beam of tensioning;Release the interim external beam body prestressing force applied in the two end bays concrete beam body.It is an advantage of the invention that(1)It compared to traditional support construction process, can solve that due to the amount of deflection index of supporting structure the construction compared with Long span can not be implemented;(2)Compared to disposable one-piece casting, the beam body poured stage by stage is due to the reduction of concrete quantity, and the construction quality to concrete is more easy to control.

Description

A kind of Long span support amount of deflection controls construction method
Technical field
The invention belongs to technical field of bridge engineering, and in particular to a kind of Long span support amount of deflection controls construction method.
Background technology
It is a kind of method commonly used in bridge construction for pouring concrete beam on support.Have stress clear and definite, square by land Just, simply, material is the features such as be easy to get.But for being limited across river and by navigation waterborne, building limit height etc., it is necessary to which finding can be with There is the method for relatively large across footpath, i.e. amount of deflection control is necessarily less than L/400.Wherein, the simple rack of beret truss formation is first One of method of choosing.
But, the across footpath scope that conventional individual layer beret truss is applicable, typically less than 18M is in the majority.For more than 18M and More than, or even 30M or so structure need to be crossed over, except the interim pile pier of setting is come in addition to reducing its across footpath, other do without good solution Method.Particularly the solution of amount of deflection technical indicator, i.e. amount of deflection are difficult to control to less than L/400.
The content of the invention
According to the deficiencies of the prior art described above, It is an object of the present invention to provide a kind of control of Long span support amount of deflection is applied Work method, the amount of deflection controls construction method to pour the progress segmentation of concrete beam, applies interim in the end bay concrete beam body poured in advance External beam body prestressing force, to reduce the load effect of across the concrete beam body underlying holder platform of centering, so as to use foot support to greatest extent The mechanical characteristic of platform.
The object of the invention is realized and completed by following technical scheme:
A kind of Long span support amount of deflection controls construction method, is related to the concrete beam that across footpath is more than 18m, it is characterised in that described to scratch Degree control construction method comprises the following steps:Required according to detail design, apply foundation pile, and set up on the foundation pile branch Body panel;Divide three sections by the concrete beam on the rack platform to pour, two end bay concrete beam bodies are poured first, and two described in tensioning The interim external beam body prestressing force of end bay concrete beam body, i.e. every temporary pre-stressed concentration in the two end bays concrete beam body by 15~ 18T stretching force carries out two ends tensioning;After-pouring in across concrete beam body, and the prestressing force of the whole concrete beam of tensioning;Release institute State the interim external beam body prestressing force applied in two end bay concrete beam bodies.
The end bay concrete beam body with it is described in across concrete beam body length ratio be 1.45~1.60:1.
At least 20 temporary pre-stressed concentrations are set up in the end bay concrete beam body top plate, at the end bay concrete beam body bottom At least 8 temporary pre-stressed concentrations are set up in plate.
It is an advantage of the invention that(1)Compared to traditional support construction process, it can solve because the amount of deflection of supporting structure refers to Mark and the construction compared with Long span can not be implemented;(2)Compared to disposable one-piece casting, the beam body poured stage by stage is due to concrete quantity Reduce, the construction quality to concrete is more easy to control.
Brief description of the drawings
Fig. 1 is Long span support amount of deflection control construction method schematic diagram in the present invention;
Fig. 2 is newly-increased temporary pre-stressed concentration sectional schematic diagram in end bay in the present invention.
Embodiment
The feature and other correlated characteristics of the present invention are described in further detail by embodiment below in conjunction with accompanying drawing, with It is easy to the understanding of technical staff of the same trade:
Mark 1-5 is respectively in such as Fig. 1-2, figure:End bay concrete beam body 1, temporary pre-stressed concentration 2, in across concrete beam body 3, basis Stake 4, rack platform 5.
Embodiment:When making large-span concrete support using Bailey beam support in bridge construction, its amount of deflection is suffered from Limitation, it is impossible to used in slightly larger across footpath, thus, the present embodiment will specifically disclose a kind of applying for Long span support amount of deflection control Work method, it is adaptable to single-box multi-cell, the concrete box beam of many case multicells, the amount of deflection control method one-piece casting concrete traditional by improving The thinking of beam, classifying rationally is poured into three sections by concrete beam(I.e. two end bay beam sections and a middle bridge section)Implemented, Then interim external beam body prestressing force, to reduce the load effect to span centre, profit are applied in the end bay concrete beam body implemented in advance The amount of deflection of span centre rack platform is undertaken with itself of two end bay concrete beam bodies, so as to greatest extent with the power of sufficient beret truss beam Characteristic is learned, reduces mid-span deflection, reaches structure safety requirements, specifically include following steps:
(1)As shown in Figure 1, 2, required according to former detail design, injection foundation pile 4, and set up on foundation pile 4 and apply branch Body panel 5, the rack platform 5 is specifically what is be made up of beret truss beam;
(2)The structure of two end bay concrete beam bodies 1 is poured in advance, and is extended gently towards span centre;
(3)Some temporary pre-stressed concentrations 2 are set up in box beam in end bay concrete beam body 1, corresponding increased interim prestressing force The arrangement rule of beam 2 is:20, top plate, bottom plate 8;The interim external beam body for the two end bay concrete beam bodies 1 that tensioning has been poured is pre- Stress, i.e. every temporary pre-stressed concentration 2 carries out two ends tensioning according to 15~18T stretching force, so that rack platform 5 can Resistance overcomes moment of flexure of the engineering body i.e. produced by concrete external load;
(4)After-pouring span centre position in across concrete beam body 3;
(5)Tensioning by two end bay concrete beam bodies 1 and in the prestressing force of whole concrete beam that is constituted of across concrete beam body 3;
(6)The interim external beam body prestressing force of two end bay concrete beam bodies 1 is released, so as to form the engineering sheet for meeting design requirement Body structure, reaches structure safety requirements.
In the present embodiment, the load by concrete beam effect on rack platform 5, by it is original it is whole across be divided into three across, wherein, The segmental length of the end bay concrete beam body 1 on both sides is respectively 12m, in across concrete beam body 3 segmental length be 8m so that effectively reduce across Amount of deflection size at middle position;For rack platform 5, that is, form three stride continuous structure, although under conditions of continuous structure, Positioned at span centre rack platform moment of flexure due to the load action of the end bay concrete beam body 1 on both sides, relative is slightly favourable, but by Caused by the characteristic of beret truss beam, its amount of deflection is difficult to by calculating;Ensureing calculating of the rack platform 5 in addition to amount of deflection all Can be on the premise of, by the way that two end bay concrete beam bodies 1 are applied with interim external beam body prestressing force, so as to help to reduce span centre position The amount of deflection of the rack platform 5 at place, to reach the purpose calculated by amount of deflection.

Claims (2)

1. a kind of Long span support amount of deflection controls construction method, it is related to the concrete beam that across footpath is more than 18m, it is characterised in that the amount of deflection Control construction method comprises the following steps:Required according to detail design, apply foundation pile, and support is set up on the foundation pile Platform;Divide three sections by the concrete beam on the rack platform to pour, two end bay concrete beam bodies, and two side described in tensioning are poured first Across the interim external beam body prestressing force of concrete beam body, i.e. every temporary pre-stressed concentration in the two end bays concrete beam body presses 15~18T Stretching force carry out two ends tensioning;After-pouring in across concrete beam body, and the prestressing force of the whole concrete beam of tensioning;Release described two The interim external beam body prestressing force applied in end bay concrete beam body;The end bay concrete beam body with it is described in across concrete beam body length ratio For 1.45~1.60:1.
2. a kind of Long span support amount of deflection control construction method according to claim 1, it is characterised in that in the end bay At least 20 temporary pre-stressed concentrations are set up in concrete beam body top plate, at least 8 institutes are set up in the end bay concrete beam body bottom plate State temporary pre-stressed concentration.
CN201610213775.6A 2016-04-08 2016-04-08 A kind of Long span support amount of deflection controls construction method Active CN105780662B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610213775.6A CN105780662B (en) 2016-04-08 2016-04-08 A kind of Long span support amount of deflection controls construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610213775.6A CN105780662B (en) 2016-04-08 2016-04-08 A kind of Long span support amount of deflection controls construction method

Publications (2)

Publication Number Publication Date
CN105780662A CN105780662A (en) 2016-07-20
CN105780662B true CN105780662B (en) 2017-09-08

Family

ID=56395025

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610213775.6A Active CN105780662B (en) 2016-04-08 2016-04-08 A kind of Long span support amount of deflection controls construction method

Country Status (1)

Country Link
CN (1) CN105780662B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115233831B (en) * 2022-08-19 2023-09-15 湖南建工集团有限公司 Integral continuous lifting method for multi-point large-span space steel structure with freely controlled deflection

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090030908A (en) * 2007-09-21 2009-03-25 주식회사 동성엔지니어링 Support structure using diaphragm introduced prestress and steel bridge having it
CN101613996A (en) * 2008-06-24 2009-12-30 龙建路桥股份有限公司 Sliding type lower cable-stayed cradle construction method
CN102121234A (en) * 2011-04-23 2011-07-13 中铁三局集团有限公司 Quick construction method of two-tower five-span steel truss girder cable-stayed bridge
CN102704400A (en) * 2012-05-28 2012-10-03 宁波二十冶建设有限公司 Tensioning method for prestressed concrete
CN104264592A (en) * 2014-10-14 2015-01-07 中国水利水电第四工程局有限公司 Construction method of continuous beam

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090030908A (en) * 2007-09-21 2009-03-25 주식회사 동성엔지니어링 Support structure using diaphragm introduced prestress and steel bridge having it
CN101613996A (en) * 2008-06-24 2009-12-30 龙建路桥股份有限公司 Sliding type lower cable-stayed cradle construction method
CN102121234A (en) * 2011-04-23 2011-07-13 中铁三局集团有限公司 Quick construction method of two-tower five-span steel truss girder cable-stayed bridge
CN102704400A (en) * 2012-05-28 2012-10-03 宁波二十冶建设有限公司 Tensioning method for prestressed concrete
CN104264592A (en) * 2014-10-14 2015-01-07 中国水利水电第四工程局有限公司 Construction method of continuous beam

Also Published As

Publication number Publication date
CN105780662A (en) 2016-07-20

Similar Documents

Publication Publication Date Title
CN103938546B (en) Simply supported non-uniform construction method
CN205205635U (en) Stride footpath bailey frame steel suspension bridge structure greatly
CN205501791U (en) Two recessed arch integrated configurations of steel binder - entity jib -
CN104695979B (en) A kind of method using tall and big chassis whole lateral moving high and big die plate
CN103276893A (en) Novel composite structure for supporting rigid building template and construction method
CN109505222A (en) A kind of netted sunpender bowstring arch bridge of assembled
CN107795124A (en) A kind of laminated floor slab truss support device for steel building
CN205421019U (en) Pretension steel-concrete composite beam bridge deck
CN108049666B (en) A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction
CN108060634A (en) Duplexing font ultra-high performance concrete-normal concrete composite beam bridge girder construction and its construction method
CN105780662B (en) A kind of Long span support amount of deflection controls construction method
CN105133484A (en) Cable-stayed bridge structure with high and low towers for partial ground anchors
CN102251535A (en) Construction method for long-span concrete pile-beamslab structure
CN102168487A (en) Surface layer template connecting structure of cast-in-place concrete sloping roof
CN105672145B (en) A kind of pier top sets up the structure that steel lid beam widens bridge
CN108396632A (en) Reduce the method for PK combination girder stayed-cable bridge auxiliary pier pier top girder hogging moments
CN112663486A (en) Steel-concrete combined beam structure with increased steel beam in hogging moment area and construction method
CN108708292A (en) A kind of I-shaped steel reinforced concrete combination beam concrete folding constructing device and construction method
CN204876339U (en) A a superimposed sheet supporting beam for steel construction building
CN102206934A (en) Method for block-by-block casting of concrete continuous beam bridge by using military truss shift mould
CN207131070U (en) A kind of Concrete Double wall formwork support process improves construction
CN206034304U (en) Adjustable cross slope's T roof beam, case beam mold board
CN108004908A (en) A kind of lattice-type steel truss pylon cable-stayed bridge
CN202865731U (en) Saddle weight steel box structure of steel truss cable-stayed bridge
CN205115988U (en) Part earth anchor height tower cable -stay bridge structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant