CN105757167A - Bonding repairing technology for conveyer belt crack - Google Patents

Bonding repairing technology for conveyer belt crack Download PDF

Info

Publication number
CN105757167A
CN105757167A CN201410770168.0A CN201410770168A CN105757167A CN 105757167 A CN105757167 A CN 105757167A CN 201410770168 A CN201410770168 A CN 201410770168A CN 105757167 A CN105757167 A CN 105757167A
Authority
CN
China
Prior art keywords
joint
bonding
layer
conveyer belt
cut
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410770168.0A
Other languages
Chinese (zh)
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Jiajia Machinery Manufacturing Co Ltd
Original Assignee
Chongqing Jiajia Machinery Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Jiajia Machinery Manufacturing Co Ltd filed Critical Chongqing Jiajia Machinery Manufacturing Co Ltd
Priority to CN201410770168.0A priority Critical patent/CN105757167A/en
Publication of CN105757167A publication Critical patent/CN105757167A/en
Pending legal-status Critical Current

Links

Landscapes

  • Belt Conveyors (AREA)

Abstract

The invention discloses a bonding repairing technology for conveyer belt crack. The bonding repairing technology is characterized by comprising the following steps of (1) designing a joint, (2) manufacturing the joint, (3) processing the surface, (4) bonding and (5) solidifying. In the (1) step, an oblique angle ladder-shaped joint is employed; in the (3) step, the surface is roughened via a grinding machine or a wood rasp and wiped by cotton yarn dipped with acetone and then dried; in the (4) step, a layer of glue is coated on a bonding surface by a hair brush in the same direction and then coated again after 5min drying via solvent evaporation; then the bonding surface is dried for 5 minutes; when the glue layer is not adhesive, the upper and lower bonding surfaces are overallped in a ladder-shaped way; center lines are aligned before bonding and then two sides are evenly pressed from the center, so the air can be discharged; after the joint is tightly pressed, a layer of canvas is bonded to protect binding seams; and in the (5) step, the joint is placed at the temperature of indoor temperature for 40 to 48 hours. The procedure is rational and low cost is required; parameters can be rationally cooperated; and short time is required and simple operation is achieved.

Description

A kind of vertex-gluing graph technique of conveyer belt fracture
Technical field
The present invention relates to the vertex-gluing graph technique of a kind of conveyer belt fracture.
Background technology
Industrial various conveyer belt is all formed by multilamellar belt carcass and rubber layer pressing, uses middle through frequently existing damaged, fracture, thus conveyer belt maintenance is a very common industrial maintenance.And existing maintenance program, and its procedure arrangement is unreasonable, operation is various, the time is long, can not meet requirement, it is necessary to improved to improve performance.
Summary of the invention
Because the drawbacks described above of prior art, the technical problem to be solved is to provide the vertex-gluing graph technique that a kind of operation is reasonable, simple to operate, the time is short, the conveyer belt of low cost of manufacture ruptures.
For achieving the above object, the invention provides the vertex-gluing graph technique of a kind of conveyer belt fracture, it is characterized in that, including following requirement:
(1) joint design: adopt oblique angle staged joint;
(2) joint makes: be first used that on the positive and negative of conveyer belt that line of cut drawn by chalk, the line drawing of upper joining seam is at lower surface, the line drawing of lower joining seam is at upper surface, a centrage is drawn again along conveyer belt length direction, diagonal joint redundance is cut with sharp knife, so as to show for hypotenuse, then it is cut into stepped successively by step number and the belt carcass number of plies;In order to not injure the belt carcass of next layer when with cutter, can first entering to need in the band sandwich layer cut off by punching bottle opener wedge, form a cavity there, cavity place of lancinating stops immediately;
(3) surface treatment: frustrate coarse surface with sand mill or wood, dips in acetone wiping surface with cotton yarn, dries;
(4) bonding: with hairbrush along between a side at one layer of glue of bonding topcoating, a layer of brush again after dry about 5min solvent volatilization, then dry 5min;During but also some viscosity not only tack-free until glue-line, upper and lower bonding plane being pressed flight stacking and closes, centrage Zai You center of first aliging time viscous uniformly extrudes to both sides, makes air discharge, after joint compacting, for protecting cemented side seam can also paste one layer of canvas;
(5) solidify: room temperature places 40-48h.
The invention has the beneficial effects as follows: operation of the present invention is reasonable, and cost is low, each parameter collocation reasonable coordination, the time is short, simple to operate, improves and keeps in repair service life, and then the loss of the time of minimizing and cost.
Detailed description of the invention
Below in conjunction with embodiment, the invention will be further described:
The vertex-gluing graph technique of a kind of conveyer belt fracture, is characterized in that, including following requirement:
(1) joint design: adopt oblique angle staged joint.This joint bond area is bigger, moreover it is possible to bear lateral stress;
(2) joint makes: be first used that on the positive and negative of conveyer belt that line of cut drawn by chalk, the line drawing of upper joining seam is at lower surface, the line drawing of lower joining seam is at upper surface, a centrage is drawn again along conveyer belt length direction, diagonal joint redundance is cut with sharp knife, so as to show for hypotenuse, then it is cut into stepped successively by step number and the belt carcass number of plies;In order to not injure the belt carcass of next layer when with cutter, can first entering to need in the band sandwich layer cut off by punching bottle opener wedge, form a cavity there, cavity place of lancinating stops immediately;
(3) surface treatment: frustrate coarse surface with sand mill or wood, dips in acetone wiping surface with cotton yarn, dries;
(4) bonding: with hairbrush along between a side at one layer of glue of bonding topcoating, a layer of brush again after dry about 5min solvent volatilization, then dry 5min;During but also some viscosity not only tack-free until glue-line, upper and lower bonding plane being pressed flight stacking and closes, centrage Zai You center of first aliging time viscous uniformly extrudes to both sides, makes air discharge, after joint compacting, for protecting cemented side seam can also paste one layer of canvas;
(5) solidify: room temperature places 40-48h.
Described glue is 450 glue that Ge Zhou Ba binding agent development company produces.
The preferred embodiment of the present invention described in detail above.Should be appreciated that those of ordinary skill in the art just can make many modifications and variations according to the design of the present invention without creative work.All technical staff in the art, all should in the protection domain being defined in the patent claims under this invention's idea on the basis of existing technology by the available technical scheme of logical analysis, reasoning, or a limited experiment.

Claims (1)

1. a vertex-gluing graph technique for conveyer belt fracture, is characterized in that, including following requirement:
(1) joint design: adopt oblique angle staged joint;
(2) joint makes: be first used that on the positive and negative of conveyer belt that line of cut drawn by chalk, the line drawing of upper joining seam is at lower surface, the line drawing of lower joining seam is at upper surface, a centrage is drawn again along conveyer belt length direction, diagonal joint redundance is cut with sharp knife, so as to show for hypotenuse, then it is cut into stepped successively by step number and the belt carcass number of plies;In order to not injure the belt carcass of next layer when with cutter, can first entering to need in the band sandwich layer cut off by punching bottle opener wedge, form a cavity there, cavity place of lancinating stops immediately;
(3) surface treatment: frustrate coarse surface with sand mill or wood, dips in acetone wiping surface with cotton yarn, dries;
(4) bonding: with hairbrush along between a side at one layer of glue of bonding topcoating, a layer of brush again after dry about 5min solvent volatilization, then dry 5min;During but also some viscosity not only tack-free until glue-line, upper and lower bonding plane being pressed flight stacking and closes, centrage Zai You center of first aliging time viscous uniformly extrudes to both sides, makes air discharge, after joint compacting, for protecting cemented side seam can also paste one layer of canvas;
(5) solidify: room temperature places 40-48h.
CN201410770168.0A 2014-12-15 2014-12-15 Bonding repairing technology for conveyer belt crack Pending CN105757167A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410770168.0A CN105757167A (en) 2014-12-15 2014-12-15 Bonding repairing technology for conveyer belt crack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410770168.0A CN105757167A (en) 2014-12-15 2014-12-15 Bonding repairing technology for conveyer belt crack

Publications (1)

Publication Number Publication Date
CN105757167A true CN105757167A (en) 2016-07-13

Family

ID=56336345

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410770168.0A Pending CN105757167A (en) 2014-12-15 2014-12-15 Bonding repairing technology for conveyer belt crack

Country Status (1)

Country Link
CN (1) CN105757167A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107791529A (en) * 2017-10-25 2018-03-13 刘创 A kind of repairing adhesion technique of conveyer belt
CN113277284A (en) * 2021-05-25 2021-08-20 济南建设设备安装有限责任公司 Anti-swing deviation method of belt conveyor

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107791529A (en) * 2017-10-25 2018-03-13 刘创 A kind of repairing adhesion technique of conveyer belt
CN113277284A (en) * 2021-05-25 2021-08-20 济南建设设备安装有限责任公司 Anti-swing deviation method of belt conveyor
CN113277284B (en) * 2021-05-25 2022-04-05 济南建设设备安装有限责任公司 Anti-swing deviation method of belt conveyor

Similar Documents

Publication Publication Date Title
CN104742210B (en) A kind of manufacture craft of solid wood composite door
CN202336906U (en) Plate plying machine
CN105173109A (en) Repairing method for honeycomb sandwich structure
CN104454853A (en) Automatic pasting production line for scrapers, sponges and felts
CN105757167A (en) Bonding repairing technology for conveyer belt crack
CN105473294A (en) Method for edging composite panels, strip for implementing the method and panel obtained by this method
CN109501334A (en) A kind of high intensity aramid fiber conveying belt joint process
CN105690814A (en) Conveyor belt damage repairing method
CN108880139A (en) A kind of processing method of iron core lamination assembly
CN109253903A (en) A kind of composite material technique for sticking that adhesive thickness is controllable
CN103363021B (en) The hot adhering method of a kind of steel wire stripe
CN204282858U (en) A kind of carbon fiber reinforcement cloth structure of concrete structure
CN102213294A (en) Cold vulcanization connecting method of conveying belt
CN205630872U (en) Formula plank is renovated in wood waste combination
CN104139534B (en) A kind of restorative procedure of filter press polypropylene material filter plate
CN103934869B (en) A kind of splice plate dry cleansing trimmer
CN113007042B (en) Blade repairing method of wind generating set, blade cementing structure and blade
CN104215035B (en) A kind of chain-belt conveyer veneer drier
CN113415005A (en) Outfield repairing method for debonding and breaking of honeycomb in composite material
CN105499932A (en) Closestool cover plate machining process
CN105754498A (en) Repair bonding process of glass fiber reinforced plastic container
CN105751535A (en) Repair technology for damaged large rubber wheel
CN205310472U (en) A thick grinding device for suit door
CN106696245A (en) Composite material glue joint surface roughening treatment method
CN113942657B (en) Repair method for rear edge and tip rear edge of composite blade

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160713