CN105720575B - Consider that the electric power system operation standby partition zone optimizing method with profile constraints is supported in section - Google Patents

Consider that the electric power system operation standby partition zone optimizing method with profile constraints is supported in section Download PDF

Info

Publication number
CN105720575B
CN105720575B CN201610128610.9A CN201610128610A CN105720575B CN 105720575 B CN105720575 B CN 105720575B CN 201610128610 A CN201610128610 A CN 201610128610A CN 105720575 B CN105720575 B CN 105720575B
Authority
CN
China
Prior art keywords
mrow
msub
standby
power
munder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610128610.9A
Other languages
Chinese (zh)
Other versions
CN105720575A (en
Inventor
孙吉波
别朝红
易杨
刘凡
王延纬
寇宇
钱峰
姜江枫
谭伟
段秦刚
吴国炳
杨银国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian Jiaotong University
Electric Power Dispatch Control Center of Guangdong Power Grid Co Ltd
Original Assignee
Xian Jiaotong University
Electric Power Dispatch Control Center of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Jiaotong University, Electric Power Dispatch Control Center of Guangdong Power Grid Co Ltd filed Critical Xian Jiaotong University
Priority to CN201610128610.9A priority Critical patent/CN105720575B/en
Publication of CN105720575A publication Critical patent/CN105720575A/en
Application granted granted Critical
Publication of CN105720575B publication Critical patent/CN105720575B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/30Circuit design
    • G06F30/36Circuit design at the analogue level
    • G06F30/367Design verification, e.g. using simulation, simulation program with integrated circuit emphasis [SPICE], direct methods or relaxation methods
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Engineering & Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Public Health (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Human Resources & Organizations (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Water Supply & Treatment (AREA)
  • Power Engineering (AREA)
  • Microelectronics & Electronic Packaging (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

Consider that the electric power system operation standby partition zone optimizing method with profile constraints is supported in section the invention discloses a kind of.This method determines the spare type and demand of required optimization first, subregion is carried out to power network and zonal reserve requirement is converted into system integrally standby requirement, equivalent process is made in the electric power to external electrical network and standby support afterwards, and with cost of electricity-generating and the minimum target of stand-by cost sum, consider the standby capacity-constrained of the standby climbing rate constraint of power balance equation, generated output power constraint, all kinds, all kinds and transmission line and section power constraint, solve the allocative decision of each zonal reserve of power system.This method, to each subregion active power output and the standby carry out combined optimization of all kinds, realizes distributing rationally for resource well on the premise of making full use of section to support and meet profile constraints, has certain reference value to Electric Power Network Planning and operation.

Description

Consider that the electric power system operation standby partition zone optimizing method with profile constraints is supported in section
Technical field
It is more particularly to a kind of to consider section support and section the present invention relates to a kind of electric power system operation standby optimization method The electric power system operation standby partition zone optimizing method of constraint.
Background technology
Standby operation of power networks is to safeguard power network safety operation, ensures that power network Quality and economy runs essential technology Means.Certain quantity of electricity deposit should be left in operation of power networks, is changed suddenly with dealing with load, electric network fault, generating equipment The appearance of random situations such as stopping transport, so as to which imbalance between power supply and demand is minimized into journey to the adverse effect that society and enterprise bring Degree.The ratio that general spare capacity accounts for system total load is higher, and the power supply reliability of system is higher, but spare capacity was reserved It is more, generating equipment utilization rate can be caused low, influence the economy of system operation.China's power system development is rapid, area power grid Scale is increasing, and regional power grid interconnection degree is increasingly close, surpasses, extra-high voltage alternating current-direct current fast development, single time high capacity transmission Passage gradually increases, and adds the uncertainty of system operation, right in order to safeguard the security of power system and power supply reliability The standby configuration of power system proposes new demand, particularly power system spare partitions optimization method face under new development situation Face new challenge.
Power system spare capacity is typically determined using Deterministic Methods or probabilistic approach at present, wherein certainty side Method is to determine spare capacity according to the certain proportion of maximum unit capacity or system peak load in system.This method is one Method of the kind based on operating experience, does not account for whole parameters of system, may cause standby redundancy and the wasting of resources.With right The raising of Power System Reliability requirement, determines that power system spare capacity seems excessively coarse using certainty criterion, more The spare capacity of power system is determined using probabilistic approach come more grid companies.Probabilistic approach is in quantitative analysis electricity On the basis of Force system reliability index, whether reasonable carry out the reserved spare capacity of decision-making system according to reliability criterion, still This method can not provide quantization for economy and support.How both approaches do not solve spare capacity in each generating simultaneously Assignment problem on unit.In recent years, domestic and foreign scholars have been carried out a series of for the optimization method of power system spare capacity Research, mainly consider the factors such as power supply uncertainty, dominant eigenvalues constraint, forecast accident, integrated economics index pair Minute spinning reserve of spare capacity, particularly 10 is optimized.But spinning reserve be run it is standby in one kind, in order to Preferably safeguard that power system security is stable, improve the distributing rationally, it is necessary to which, spinning reserve standby to load, accident are standby of resource With etc. polytype operation standby coordinated and optimized.At the same time, because power network has power supply and power load distributing is uneven The problem of, in order to make full use of the standby support ability inside power network between each subregion, power network spare partitions optimization method is not Carry out the important development direction of standby optimization, power network physical planning and operation are had great significance.
The content of the invention
Consider that the electric power system operation standby subregion with profile constraints is supported in section it is an object of the invention to provide a kind of Optimization method, it is optimal for target with economy, it is standby to polytype operation to optimize and obtain each subregion inside power network The method of salary distribution of generated output and all kinds spare capacity.
Step 1:It is determined that the operation spare type of required optimization and standby on capacity and response time to all kinds Demand;The operation of required optimization is standby to be divided into that load is standby and the major class of emergency duty two, and wherein emergency duty is by spinning reserve Start cold standby two parts composition with quick;
Step 2:Subregion is carried out to the power system in dispatching management scope, counts the generating set information in each subregion, And determine the method for salary distribution standby in subregion;
Step 3:Equivalent process is made to the electric power outside the power system and standby support, by equivalent process by described in Electric power and standby support outside power system are reduced to several the non-online equivalent generator groups of nuclear power for reflecting electricity transaction; The equivalent generator group is included in same subregion, and a subregion using the subregion as the power system;
Step 4:With the optimal Optimized model that power system spare partitions are established for object function of economy;
Step 5:The Optimized model is solved according to the initial data of the power system, draws and considers that section is supported and expired The active power output of every generating set and all kinds spare capacity that should bear in the power system after sufficient profile constraints, And the total active power output of each subregion and all kinds that should bear in the power system are further determined according to partition information Spare capacity, while obtain the active power output and spare capacity that should be supported outside the power system;Solve the Optimized model It is middle to consider following constraints:The standby climbing rate of power balance equation, the constraint of generating set power output, all kinds is about The standby capacity-constrained of beam, all kinds and transmission line and section power constraint, the capacity-constrained utilize the power train The mutual standby support ability of the internal each subregion of system, zonal reserve requirement is converted into system integrally standby requirement.
In the step 1), load it is standby needs recalled in 5 minutes, capacity be taken as maximum generation load 2%~ 3%;And emergency duty then needs to recall in 10 minutes, capacity is taken as the 8%~10% of maximum generation load, wherein rotating standby With capacity of the capacity not less than maximum generation unit in the power system or maximum N-1 outage capacities.
The step 2) specifically includes following steps:By the power system according to generating set distribution situation according to power supply Area and it is divided into different regions by electric zoning, or is divided into different regions according to geographical position and administrative division;Then, count Type, installed capacity, climbing rate and the open state of generating set in each subregion;In each subregion, all kinds are standby The method of salary distribution be:Load is standby and spinning reserve undertakes by online non-nuclear power generating sets, and the quick cold standby that starts is then by non- Online water power, pneumoelectric and pump-storage generator undertakes.
It is equivalent to the electric power outside the power system and standby support progress in the step 3), it is reduced to be located at institute The single generator group of power system alternating current-direct current pick-up point is stated, according to the power system and the power trade of external power system Plan, the limitation of AC-DC tie line transimission power, the standby support ability of external power system and the expense of outer power purchase, it is determined that Bound, climbing rate and the cost of generating and standby support of equivalent generator pool-size.
The capacity-constrained is not to propose spare capacity requirement respectively for each subregion, but the power system is full On the premise of the limitation of sufficient transmission-line power and section power, it is only necessary to integrally can be provided standby to meet all kinds standby total Capacity requirement.
The economy is optimal to refer to that the power system cost of electricity-generating and stand-by cost summation are minimum, and object function is specific It is shown below:
Wherein, online is the set of all online generating sets in the electricity generation system, PiFor i-th online generator Group is actual to contribute, cenergy,iFor i-th online generating set cost of electricity-generating, loadRiUndertaken for i-th online generating set Load is standby, cloadR,iFor the load stand-by cost of i-th online generating set, spinRiUndertaken for i-th online generating set Spinning reserve, cspinR,iFor the spinning reserve cost of i-th online generating set;
Offline is water power, pneumoelectric and water-storage that be all non-online in the electricity generation system but can quickly starting The set of unit, rapidRiThe quick startup cold standby undertaken for i-th non-online generating set, crapidR,iFor i-th it is non- The quick startup cold standby cost of line generating set.
The power balance equation is expressed as:
Wherein, S be all nodes for belonging to the power system set, DiRepresent the load of i-th of node;
The generating set power output constraint representation is:
0≤rapidRi≤Pimax i∈offline
Wherein, PimaxFor the maximum active power output of i-th generating set, PiminMinimum technology for i-th generating set goes out Power;
The standby climbing rate constraint representation of all kinds is:
0≤loadRi≤5·RampRatei i∈online
0≤spinRi≤10·RampRatei i∈online
0≤rapidRi≤10·RampRatei i∈offline
Wherein, RampRateiFor the climbing rate of i-th generating set;
The standby capacity-constrained of all kinds is expressed as:
Wherein, conRiThe emergency reserve capacity provided for i-th generating set,For the power system maximum N-1 Outage capacity;α values are that 2%~3%, β values are 8%~10%;
The transmission-line power constraint representation is:
Wherein, lkFor kth bar circuit in the electricity generation system,For the active power after standby response on kth bar circuit, HkiFor breadth coefficient matrix H the i-th column element of row k, represent the injecting power of i-th of node to the wattful power on kth bar circuit The influence of rate,For the maximum transmission power of kth bar circuit;
The section power constraint representation is:
Wherein, j represents the set for belonging to all circuits of j-th of section, PjmaxFor the maximum transmitted work(of j-th of section Rate.
Beneficial effects of the present invention are embodied in:
The present invention is taking into full account each standby support ability in by stages and the premise for meeting section power requirement inside power network Under, standby active power output, load that each online generating set should provide and spinning reserve and each non-online is quantitatively determined The quick startup cold standby that generating set should provide, while give active power output that each subregion should arrange and all kinds are standby Total amount so that the economy of power network overall operation more preferably, realizes distributing rationally for resource, and the planning to power system and fortune Row work provides certain reference.
Brief description of the drawings
Fig. 1 is that consideration section of the present invention is supported and the electric power system operation standby partition zone optimizing method of profile constraints Flow chart;
Fig. 2 is the example sub-area division schematic diagram in the embodiment of the present invention;
Fig. 3 is the standby method of salary distribution schematic diagram of all kinds in the embodiment of the present invention.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples The present invention is further described.It should be appreciated that embodiment described herein is not used to limit only to explain the present invention The present invention
Below by taking the standby partition zone optimizing of province of China operation of power networks as an example, the present invention is specifically introduced, but should What is understood is that invention is not limited thereto, and is applied equally to that remaining power network is carried out to run standby partition zone optimizing.
As shown in figure 1, the present invention provides a kind of electric power system operation standby subregion for considering section support and profile constraints Optimization method, comprise the following steps:
The first step:It is determined that the spare type and demand of optimization.According to《Power system technology directive/guide》、《Operation of power networks is accurate Then》、《CHINA SOUTHERN POWER runs standby administrative provisions》And external power system is on running standby relevant regulations, this reality Apply the operation spare type optimized in example and be divided into that load is standby and the major class of emergency duty two, wherein emergency duty by spinning reserve and It is quick to start cold standby two parts composition;At the same time provide, the standby needs of load recalled in 5 minutes, and capacity is taken as maximum The 2% of generation load, the maximum generation load of example power network is 90036.76MW;Emergency duty needs to recall in 10 minutes, Capacity is taken as the 8% of maximum generation load, and wherein spinning reserve capacity is not less than the capacity or maximum of one maximum unit of system N-1 outage capacities, maximum outage capacity 5000MW caused by system dc bipolar locking is taken as in the present embodiment.
Second step:Sub-area division simultaneously determines the standby method of salary distribution.According to service area and by electric area, example power network is divided into 8 regions, numbering is 1~8 respectively.The subregion of example power network is as shown in Figure 2.Count power supply (i.e. generating set) in each subregion The information such as type, installed capacity, climbing rate and open state, the number of units and appearance of each online unit of subregion and non-online unit Amount is as shown in table 1.In each subregion, the standby method of salary distribution of all kinds is as shown in figure 3, namely:Load is standby and rotates Standby to be undertaken by online non-nuclear power generating sets, the quick cold standby that starts is held by non-online water power, pneumoelectric and pump-storage generator Load.
3rd step:Zonal reserve requirement is changed as system integrally standby requirement.Make full use of each subregion of internal system mutual Standby support ability, zonal reserve requirement is converted into the overall standby requirement of system, that is to say, that, it is contemplated that example power network In each subregion power supply and power load distributing unbalanced phenomenon be present, no longer for each subregion propose respectively spare capacity will Ask, but the example power network is on the premise of transmission-line power and section power limitation is met, it is only necessary to integrally can be provided It is standby to meet the standby total capacity requirement of all kinds.
4th step:The electric power in equivalent other provinces and standby support.In view of alternating current-direct current interconnection phenomenon between each province's power network be present, The electric power in other provinces and standby support are equivalent to single generator group (the online non-core positioned at alternating current-direct current pick-up point in example power network Group of motors), one shares eight DC links and eight alternating current interconnections between example power network and other provinces, inside example power network Alternating current-direct current pick-up point shares 11, therefore is equivalent to 11 generating sets positioned at alternating current-direct current pick-up point in example power network, with province Interior unit combined optimization.The equivalent source in other provinces is divided into an area, numbering 0, according to the power trade plan between province, handed over The information such as the expense of the limitation of DC link transimission power, the standby support ability in other provinces and outer power purchase, determine equivalent generating Bound, climbing rate and the cost of generating and standby support of unit capacity, the basic condition such as institute of table 1 that outer electric power saving is supported Show.
The example sub-area division information of table 1
5th step:With the optimal Optimized model that power system spare partitions are established for object function of economy.It is, with Cost of electricity-generating and the minimum target of stand-by cost sum, object function expression are as follows:
Wherein, online is all online (synchronization) generating sets, P inside example power networki、cenergy,iIt is online for i-th The actual output of unit and cost of electricity-generating, loadRi、cloadR,iThe load undertaken for i-th online unit is standby and load it is standby into This, spinRi、cspinR,iThe spinning reserve and spinning reserve cost undertaken for i-th online unit.Offline is example power network Internal all non-online (asynchronous) but water power, pneumoelectric and the pump-storage generator that can quickly start, rapidRi、crapidR,i The quick startup cold standby undertaken for i-th non-online unit and quick startup cold standby cost.
6th step:Increase constraints.Constraints in the present invention has power balance equation, generated output power about The standby capacity-constrained of the standby climbing rate constraint of beam, all kinds, all kinds and transmission line and section power constraint.Examine The characteristic for considering nuclear power generating sets makes it completely send out not providing standby support, i.e. it is defeated that the power bounds of nuclear power generating sets is set to its maximum Go out power, climbing rate is set to 0;Consider when most harsh conditions are that other provinces can not provide standby support, each point inside example power network The standby assignment problem of area's generating set, it is therefore assumed that other provinces equivalent source is completely sent out and do not provide standby support.
1) power balance equation
Wherein, S is all nodes for belonging to the example power network, DiRepresent the load of the node.
2) generated output power constrains
0≤rapidRi≤Pimax(i∈offline)
Wherein, PimaxFor the maximum active power output of i-th generating set, PiminMinimum technology for i-th generating set goes out Power.
3) the standby climbing rate constraint of all kinds
0≤loadRi≤5·RampRatei(i∈online)
0≤spinRi≤10·RampRatei(i∈online)
0≤rapidRi≤10·RampRatei(i∈offline)
Wherein, RampRateiFor the climbing rate of i-th unit, the standby needs of load recalled in 5 minutes, emergency duty Then need to recall in 10 minutes including spinning reserve and the quick cold standby that starts.
4) the standby capacity-constrained of all kinds
Wherein, conRiThe emergency reserve capacity provided for i-th generating set,For maximum N-1 events in example power network Hinder capacity.Above formula shows that the standby total amount of load is not less than the 2% of maximum generation load, and spinning reserve total amount is not less than maximum N-1 Outage capacity, emergency reserve capacity is spinning reserve capacity and quick cold standby capacity sum, and total amount is not less than maximum generation The 8% of load.
5) transmission-line power constrains
Wherein, lkFor kth bar circuit,For the active power after standby response on kth bar circuit, HkiFor breadth coefficient square Battle array H the i-th column elements of row k, influence of the injecting power of i-th of node to the active power on kth bar circuit is represented,For The maximum transmission power of kth bar circuit.
6) section power constrains
Wherein, j represents all circuits for belonging to j-th of section, PjmaxFor the maximum transmission power of j-th of section.
7th step:Establish Optimized model and calculated according to initial data and solved.According to above-mentioned optimization method, in Matlab It is modeled, and is solved using Mosek optimization tools, obtains the optimization knot of each subregion active power output and all kinds of spare capacities Fruit.
In the present embodiment, using example power network summer in 2015 big mode initial data, according to above-mentioned optimization method, draw Consider the standby appearance of all kinds that section is supported and met after profile constraints the active power output of every generating set and should bear Amount, and further obtain considering each subregion active power output of example power network of section support and profile constraints according to partition information, bear Lotus is standby, spinning reserve and the quick allocative decision for starting cold standby, as shown in table 2.Now, the cost of electricity-generating of the example power network Reach minimum with stand-by cost sum.
The example power network spare partitions optimum results of table 2
Analyze above-mentioned optimum results and understand that each subregion active power output sum is 90036.76MW in embodiment, meet maximum The active power output of the demand of generation load, wherein 55452.26MW is provided by example power network internal generator, 34584.50MW active power output is come by the conveying of other provinces power network.
The reserve capacity for load variation in power that each subregion should bear in embodiment shares 1800.74MW, the maximum generation load more than 2% (1800.7352MW), meet the standby requirement of partition load, wherein as it is assumed that other provinces do not provide standby support, therefore other provinces (subregion 0) the standby result of load of optimization is 0MW.
The spinning reserve capacity that each subregion should bear in embodiment shares 6761.95MW, more than the N-1 outage capacities of maximum (5000MW), meet subregion spinning reserve requirement, wherein as it is assumed that other provinces do not provide standby support, therefore other provinces (subregion 0) is excellent The spinning reserve result of change is 0MW.
Each subregion should bear in embodiment quick startup cold standby capacity shares 441MW, therefore each subregion is provided Emergency reserve capacity is that spinning reserve starts cold standby sum, i.e. 7207.95MW, the maximum generation load more than 8% with quick (7202.9408MW), meet subregion emergency duty requirement, wherein as it is assumed that other provinces do not provide standby support, therefore other provinces (subregion 0) the quick startup cold standby result of optimization is 0MW.At the same time, as can be seen from Table 1, do not opened although many subregions have Generating set, but only subregion 4 and subregion 7 can be provided soon containing non-online water power, pneumoelectric and pump-storage generator Speed starts cold standby, therefore it is rational quickly to start cold standby in the optimum results of table 2 all to be undertaken by subregion 4 and subregion 7.
Finally it should be noted that:The above embodiments are merely illustrative of the technical scheme of the present invention and are not intended to be limiting thereof, to the greatest extent The present invention is described in detail with reference to above-described embodiment for pipe, those of ordinary skills in the art should understand that:Still The embodiment of the present invention can be modified or equivalent substitution, and without departing from any of spirit and scope of the invention Modification or equivalent substitution, it all should cover among scope of the presently claimed invention.

Claims (7)

1. a kind of consider that the electric power system operation standby partition zone optimizing method with profile constraints is supported in section, it is characterised in that:Bag Include following steps:
Step 1:It is determined that the operation spare type of required optimization and to the standby need on capacity and response time of all kinds Ask;The operation of required optimization is standby to be divided into that load is standby and the major class of emergency duty two, and wherein emergency duty is by spinning reserve and fast Speed starts cold standby two parts composition;
Step 2:Subregion is carried out to the power system in dispatching management scope, counts the generating set information in each subregion, and really Determine the method for salary distribution standby in subregion;
Step 3:Equivalent process is made to the electric power outside the power system and standby support, by equivalent process by the electric power The electric power of its exterior and standby support are reduced to several the non-online equivalent generator groups of nuclear power for reflecting electricity transaction;By institute State equivalent generator group and be included in same subregion, and a subregion using the subregion as the power system;
Step 4:With the optimal Optimized model that power system spare partitions are established for object function of economy;
Step 5:The Optimized model is solved according to the initial data of the power system, draws and considers that section is supported and met disconnected The active power output of every generating set and all kinds spare capacity that should bear in the power system after the constraint of face, go forward side by side One step determines that the total active power output of each subregion and all kinds that should bear are standby in the power system according to partition information Capacity, while obtain the active power output and spare capacity that should be supported outside the power system;Solve and examined in the Optimized model Consider following constraints:The standby climbing rate of power balance equation, the constraint of generating set power output, all kinds constrains, is each The standby capacity-constrained of type, transmission-line power constraint and section power constraint, the capacity-constrained utilize the power train The mutual standby support ability of the internal each subregion of system, zonal reserve requirement is converted into system integrally standby requirement.
2. a kind of as claimed in claim 1 consider that the electric power system operation standby partition zone optimizing side with profile constraints is supported in section Method, it is characterised in that:In the step 1), the standby needs of load recalled in 5 minutes, and capacity is taken as maximum generation load 2%~3%;And emergency duty then needs to recall in 10 minutes, capacity is taken as the 8%~10% of maximum generation load, wherein Capacity of the spinning reserve capacity not less than maximum generation unit in the power system or maximum N-1 outage capacities.
3. a kind of as claimed in claim 1 consider that the electric power system operation standby partition zone optimizing side with profile constraints is supported in section Method, it is characterised in that:The step 2) specifically includes following steps:The power system is pressed according to generating set distribution situation It is divided into different regions according to service area and by electric zoning, or is divided into different regions according to geographical position and administrative division;So Afterwards, the type of generating set in each subregion, installed capacity, climbing rate and open state are counted;It is various types of in each subregion The standby method of salary distribution of type is:Load is standby and spinning reserve undertakes by online non-nuclear power generating sets, quickly starts cold standby Then undertaken by non-online water power, pneumoelectric and pump-storage generator.
4. a kind of as claimed in claim 1 consider that the electric power system operation standby partition zone optimizing side with profile constraints is supported in section Method, it is characterised in that:It is equivalent to the electric power outside the power system and standby support progress in the step 3), it is reduced to Single generator group positioned at the power system alternating current-direct current pick-up point, according to the power system and the electricity of external power system Can trading program, the limitation of AC-DC tie line transimission power, the standby support ability of external power system and taking for outer power purchase With determining the bound, climbing rate and the cost of generating and standby support of equivalent generator pool-size.
5. a kind of as claimed in claim 1 consider that the electric power system operation standby partition zone optimizing side with profile constraints is supported in section Method, it is characterised in that:The capacity-constrained is not to propose that spare capacity requires respectively for each subregion, but the power train System is on the premise of meeting that transmission-line power and section power limit, it is only necessary to which what integrally be can be provided standby meets all kinds Standby total capacity requirement.
6. a kind of as claimed in claim 1 consider that the electric power system operation standby partition zone optimizing side with profile constraints is supported in section Method, it is characterised in that:The economy is optimal to refer to that the power system cost of electricity-generating and stand-by cost summation are minimum, target letter Shown in number formula specific as follows:
<mrow> <mi>min</mi> <mrow> <mo>(</mo> <munder> <mo>&amp;Sigma;</mo> <mrow> <mi>i</mi> <mo>&amp;Element;</mo> <mi>o</mi> <mi>n</mi> <mi>l</mi> <mi>i</mi> <mi>n</mi> <mi>e</mi> </mrow> </munder> <mo>(</mo> <mrow> <msub> <mi>c</mi> <mrow> <mi>e</mi> <mi>n</mi> <mi>e</mi> <mi>r</mi> <mi>g</mi> <mi>y</mi> <mo>,</mo> <mi>i</mi> </mrow> </msub> <msub> <mi>P</mi> <mi>i</mi> </msub> <mo>+</mo> <msub> <mi>c</mi> <mrow> <mi>l</mi> <mi>o</mi> <mi>a</mi> <mi>d</mi> <mi>R</mi> <mo>,</mo> <mi>i</mi> </mrow> </msub> <msub> <mi>loadR</mi> <mi>i</mi> </msub> <mo>+</mo> <msub> <mi>c</mi> <mrow> <mi>s</mi> <mi>p</mi> <mi>i</mi> <mi>n</mi> <mi>R</mi> <mo>,</mo> <mi>i</mi> </mrow> </msub> <msub> <mi>spinR</mi> <mi>i</mi> </msub> </mrow> <mo>)</mo> <mo>+</mo> <munder> <mo>&amp;Sigma;</mo> <mrow> <mi>i</mi> <mo>&amp;Element;</mo> <mi>o</mi> <mi>f</mi> <mi>f</mi> <mi>l</mi> <mi>i</mi> <mi>n</mi> <mi>e</mi> </mrow> </munder> <msub> <mi>c</mi> <mrow> <mi>r</mi> <mi>a</mi> <mi>p</mi> <mi>i</mi> <mi>d</mi> <mi>R</mi> <mo>,</mo> <mi>i</mi> </mrow> </msub> <msub> <mi>rapidR</mi> <mi>i</mi> </msub> <mo>)</mo> </mrow> </mrow>
Wherein, online is the set of all online generating sets in power system, PiFor i-th online generating set it is actual go out Power, cenergy,iFor i-th online generating set cost of electricity-generating, loadRiThe load undertaken for i-th online generating set is standby, cloadR,iFor the load stand-by cost of i-th online generating set, spinRiThe rotation undertaken for i-th online generating set is standby With cspinR,iFor the spinning reserve cost of i-th online generating set;
Offline is the collection of water power, pneumoelectric and pump-storage generator all non-online in power system but can quickly start Close, rapidRiThe quick startup cold standby undertaken for i-th non-online generating set, crapidR,iFor i-th non-online generator The quick startup cold standby cost of group.
7. a kind of as claimed in claim 1 consider that the electric power system operation standby partition zone optimizing side with profile constraints is supported in section Method, it is characterised in that:The power balance equation is expressed as:
<mrow> <munder> <mo>&amp;Sigma;</mo> <mrow> <mi>i</mi> <mo>&amp;Element;</mo> <mi>o</mi> <mi>n</mi> <mi>l</mi> <mi>i</mi> <mi>n</mi> <mi>e</mi> </mrow> </munder> <msub> <mi>P</mi> <mi>i</mi> </msub> <mo>=</mo> <munder> <mo>&amp;Sigma;</mo> <mrow> <mi>i</mi> <mo>&amp;Element;</mo> <mi>S</mi> </mrow> </munder> <msub> <mi>D</mi> <mi>i</mi> </msub> </mrow>
Wherein, S be all nodes for belonging to the power system set, DiRepresent the load of i-th of node;
The generating set power output constraint representation is:
<mrow> <mfenced open = "{" close = ""> <mtable> <mtr> <mtd> <mrow> <msub> <mi>P</mi> <mi>i</mi> </msub> <mo>+</mo> <msub> <mi>loadR</mi> <mi>i</mi> </msub> <mo>+</mo> <msub> <mi>spinR</mi> <mi>i</mi> </msub> <mo>&amp;le;</mo> <msub> <mi>P</mi> <mrow> <mi>i</mi> <mi>max</mi> </mrow> </msub> </mrow> </mtd> </mtr> <mtr> <mtd> <mrow> <msub> <mi>P</mi> <mi>i</mi> </msub> <mo>-</mo> <msub> <mi>loadR</mi> <mi>i</mi> </msub> <mo>&amp;GreaterEqual;</mo> <msub> <mi>P</mi> <mrow> <mi>i</mi> <mi>min</mi> </mrow> </msub> </mrow> </mtd> </mtr> </mtable> </mfenced> <mo>,</mo> <mi>i</mi> <mo>&amp;Element;</mo> <mi>o</mi> <mi>n</mi> <mi>l</mi> <mi>i</mi> <mi>n</mi> <mi>e</mi> </mrow>
0≤rapidRi≤Pimax i∈offline
Wherein, PimaxFor the maximum active power output of i-th generating set, PiminContributed for the minimum technology of i-th generating set;
The standby climbing rate constraint representation of all kinds is:
0≤loadRi≤5·RampRatei i∈online
0≤spinRi≤10·RampRatei i∈online
0≤rapidRi≤10·RampRatei i∈offline
Wherein, RampRateiFor the climbing rate of i-th generating set;
The standby capacity-constrained of all kinds is expressed as:
<mrow> <munder> <mo>&amp;Sigma;</mo> <mrow> <mi>i</mi> <mo>&amp;Element;</mo> <mi>o</mi> <mi>n</mi> <mi>l</mi> <mi>i</mi> <mi>n</mi> <mi>e</mi> </mrow> </munder> <msub> <mi>loadR</mi> <mi>i</mi> </msub> <mo>&amp;GreaterEqual;</mo> <mi>&amp;alpha;</mi> <mo>&amp;CenterDot;</mo> <munder> <mo>&amp;Sigma;</mo> <mrow> <mi>i</mi> <mo>&amp;Element;</mo> <mi>S</mi> </mrow> </munder> <msub> <mi>D</mi> <mi>i</mi> </msub> </mrow>
<mrow> <munder> <mo>&amp;Sigma;</mo> <mrow> <mi>i</mi> <mo>&amp;Element;</mo> <mi>o</mi> <mi>n</mi> <mi>l</mi> <mi>i</mi> <mi>n</mi> <mi>e</mi> </mrow> </munder> <msub> <mi>spinR</mi> <mi>i</mi> </msub> <mo>&amp;GreaterEqual;</mo> <msubsup> <mi>&amp;Delta;P</mi> <mrow> <mi>m</mi> <mi>a</mi> <mi>x</mi> </mrow> <mrow> <mi>N</mi> <mo>-</mo> <mn>1</mn> </mrow> </msubsup> </mrow>
<mrow> <munder> <mo>&amp;Sigma;</mo> <mrow> <mi>i</mi> <mo>&amp;Element;</mo> <mi>o</mi> <mi>n</mi> <mi>l</mi> <mi>i</mi> <mi>n</mi> <mi>e</mi> <mo>&amp;cup;</mo> <mi>o</mi> <mi>f</mi> <mi>f</mi> <mi>l</mi> <mi>i</mi> <mi>n</mi> <mi>e</mi> </mrow> </munder> <msub> <mi>conR</mi> <mi>i</mi> </msub> <mo>=</mo> <munder> <mo>&amp;Sigma;</mo> <mrow> <mi>i</mi> <mo>&amp;Element;</mo> <mi>o</mi> <mi>n</mi> <mi>l</mi> <mi>i</mi> <mi>n</mi> <mi>e</mi> </mrow> </munder> <msub> <mi>spinR</mi> <mi>i</mi> </msub> <mo>+</mo> <munder> <mo>&amp;Sigma;</mo> <mrow> <mi>i</mi> <mo>&amp;Element;</mo> <mi>o</mi> <mi>f</mi> <mi>f</mi> <mi>l</mi> <mi>i</mi> <mi>n</mi> <mi>e</mi> </mrow> </munder> <msub> <mi>rapidR</mi> <mi>i</mi> </msub> <mo>&amp;GreaterEqual;</mo> <mi>&amp;beta;</mi> <mo>&amp;CenterDot;</mo> <munder> <mo>&amp;Sigma;</mo> <mrow> <mi>i</mi> <mo>&amp;Element;</mo> <mi>S</mi> </mrow> </munder> <msub> <mi>D</mi> <mi>i</mi> </msub> </mrow>
Wherein, conRiThe emergency reserve capacity provided for i-th generating set,For the power system maximum N-1 failures Capacity;α values are that 2%~3%, β values are 8%~10%;
The transmission-line power constraint representation is:
<mrow> <mo>-</mo> <msub> <mi>P</mi> <mrow> <msub> <mi>l</mi> <mi>k</mi> </msub> <mi>m</mi> <mi>a</mi> <mi>x</mi> </mrow> </msub> <mo>&amp;le;</mo> <msubsup> <mi>P</mi> <msub> <mi>l</mi> <mi>k</mi> </msub> <mo>&amp;prime;</mo> </msubsup> <mo>&amp;le;</mo> <msub> <mi>P</mi> <mrow> <msub> <mi>l</mi> <mi>k</mi> </msub> <mi>m</mi> <mi>a</mi> <mi>x</mi> </mrow> </msub> </mrow>
<mrow> <msubsup> <mi>P</mi> <msub> <mi>l</mi> <mi>k</mi> </msub> <mo>&amp;prime;</mo> </msubsup> <mo>=</mo> <munder> <mo>&amp;Sigma;</mo> <mrow> <mi>i</mi> <mo>&amp;Element;</mo> <mi>o</mi> <mi>n</mi> <mi>l</mi> <mi>i</mi> <mi>n</mi> <mi>e</mi> </mrow> </munder> <msub> <mi>H</mi> <mrow> <mi>k</mi> <mi>i</mi> </mrow> </msub> <mo>&amp;CenterDot;</mo> <mrow> <mo>(</mo> <msub> <mi>P</mi> <mi>i</mi> </msub> <mo>+</mo> <msub> <mi>loadR</mi> <mi>i</mi> </msub> <mo>+</mo> <msub> <mi>spinR</mi> <mi>i</mi> </msub> <mo>)</mo> </mrow> <mo>+</mo> <munder> <mo>&amp;Sigma;</mo> <mrow> <mi>i</mi> <mo>&amp;Element;</mo> <mi>o</mi> <mi>f</mi> <mi>f</mi> <mi>l</mi> <mi>i</mi> <mi>n</mi> <mi>e</mi> </mrow> </munder> <msub> <mi>H</mi> <mrow> <mi>k</mi> <mi>i</mi> </mrow> </msub> <mo>&amp;CenterDot;</mo> <msub> <mi>rapidR</mi> <mi>i</mi> </msub> <mo>-</mo> <munder> <mo>&amp;Sigma;</mo> <mrow> <mi>i</mi> <mo>&amp;Element;</mo> <mi>S</mi> </mrow> </munder> <msub> <mi>H</mi> <mrow> <mi>k</mi> <mi>i</mi> </mrow> </msub> <mo>&amp;CenterDot;</mo> <msub> <mi>D</mi> <mi>i</mi> </msub> </mrow>
Wherein, lkFor kth bar circuit in power system,For the active power after standby response on kth bar circuit, HkiFor distribution Coefficient matrix H the i-th column elements of row k, influence of the injecting power of i-th of node to the active power on kth bar circuit is represented,For the maximum transmission power of kth bar circuit;
The section power constraint representation is:
<mrow> <mo>-</mo> <msub> <mi>P</mi> <mrow> <mi>j</mi> <mi>m</mi> <mi>a</mi> <mi>x</mi> </mrow> </msub> <mo>&amp;le;</mo> <munder> <mo>&amp;Sigma;</mo> <mrow> <msub> <mi>l</mi> <mi>k</mi> </msub> <mo>&amp;Element;</mo> <msub> <mi>j</mi> <mi>k</mi> </msub> </mrow> </munder> <msubsup> <mi>P</mi> <msub> <mi>l</mi> <mi>k</mi> </msub> <mo>&amp;prime;</mo> </msubsup> <mo>&amp;le;</mo> <msub> <mi>P</mi> <mrow> <mi>j</mi> <mi>m</mi> <mi>a</mi> <mi>x</mi> </mrow> </msub> </mrow>
Wherein, j represents the set for belonging to all circuits of j-th of section, PjmaxFor the maximum transmission power of j-th of section.
CN201610128610.9A 2016-03-07 2016-03-07 Consider that the electric power system operation standby partition zone optimizing method with profile constraints is supported in section Active CN105720575B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610128610.9A CN105720575B (en) 2016-03-07 2016-03-07 Consider that the electric power system operation standby partition zone optimizing method with profile constraints is supported in section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610128610.9A CN105720575B (en) 2016-03-07 2016-03-07 Consider that the electric power system operation standby partition zone optimizing method with profile constraints is supported in section

Publications (2)

Publication Number Publication Date
CN105720575A CN105720575A (en) 2016-06-29
CN105720575B true CN105720575B (en) 2017-12-12

Family

ID=56157476

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610128610.9A Active CN105720575B (en) 2016-03-07 2016-03-07 Consider that the electric power system operation standby partition zone optimizing method with profile constraints is supported in section

Country Status (1)

Country Link
CN (1) CN105720575B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106384162B (en) * 2016-09-06 2019-08-23 西安交通大学 Consider electric system electric energy-spare joint optimal operation method of zonal reserve and N-1 verification
CN106602568B (en) * 2016-12-23 2019-05-31 国网浙江省电力公司 A kind of power balance method and device between sub-area division
CN108869059B (en) * 2018-06-26 2020-06-02 广东电网有限责任公司 Cold standby compensation calculation method, device, equipment and storage medium for gas unit
CN108964059B (en) * 2018-06-29 2021-10-29 中国电力科学研究院有限公司 Method and system for calculating active standby shared capacity of interconnected power grid
CN111784021B (en) * 2020-05-08 2021-05-07 国网浙江省电力有限公司 Unit partition identification and effective standby allocation method based on key section
CN112184009B (en) * 2020-05-11 2022-11-18 国网宁夏电力有限公司 Method and device for clearing paid reactive auxiliary service and storage medium
CN113852134B (en) * 2021-09-18 2024-04-26 广东电网有限责任公司 Network limited capacity assessment method and device based on power grid operation constraint

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103296677A (en) * 2013-05-09 2013-09-11 国家电网公司 On-line large power grid recovery assistant decision-making system
CN103701212A (en) * 2013-12-23 2014-04-02 国家电网公司 Method and system for monitoring and analyzing power grid safety and stability control device
CN104300535A (en) * 2014-10-17 2015-01-21 华中电网有限公司 In-network quick standby coordination and optimization scheduling method used after high-power vacancy accidents

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9657973B2 (en) * 2008-06-02 2017-05-23 Hill Phoenix, Inc. Refrigeration system with photovoltaic power source
AU2013201985B2 (en) * 2013-03-26 2015-02-19 Empower Energy Pty Ltd Power module system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103296677A (en) * 2013-05-09 2013-09-11 国家电网公司 On-line large power grid recovery assistant decision-making system
CN103701212A (en) * 2013-12-23 2014-04-02 国家电网公司 Method and system for monitoring and analyzing power grid safety and stability control device
CN104300535A (en) * 2014-10-17 2015-01-21 华中电网有限公司 In-network quick standby coordination and optimization scheduling method used after high-power vacancy accidents

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
计及检修需求不确定性的电力***检修备用容量评估;郑秀波等;《电力自动化设备》;20141031;第34卷(第10期);第144-149页 *

Also Published As

Publication number Publication date
CN105720575A (en) 2016-06-29

Similar Documents

Publication Publication Date Title
CN105720575B (en) Consider that the electric power system operation standby partition zone optimizing method with profile constraints is supported in section
Liu et al. Optimal planning of AC-DC hybrid transmission and distributed energy resource system: Review and prospects
CN103812131B (en) A kind of urban distribution network isolated island black starting-up system and method based on multiple agent
Xu et al. Multi-objective dynamic VAR planning against short-term voltage instability using a decomposition-based evolutionary algorithm
Liu et al. Operational reliability assessment for gas-electric integrated distribution feeders
CN108122068A (en) A kind of power distribution network risk-averse retailer method and system
Zhou et al. What's the difference between traditional power grid and smart grid?—From dispatching perspective
CN106384162B (en) Consider electric system electric energy-spare joint optimal operation method of zonal reserve and N-1 verification
CN107181253A (en) A kind of Electric power network planning method based on power network dynamic reliability probability level
CN107622360A (en) A kind of critical circuits recognition methods for considering subjective and objective factor
CN109873421A (en) A kind of provincial power network abundant intensity online evaluation method and system
CN111049132B (en) Large-area power failure dynamic island recovery method for active power distribution network
CN106096751A (en) Consider that new forms of energy access and participate in Short Term Generation Schedules arrangement and standby Optimal Configuration Method with Demand Side Response
CN106549420A (en) Consider the electric power system operation standby optimization method of risk and wind-power electricity generation
Li et al. Researches on the reliability evaluation of integrated energy system based on Energy Hub
Nawaz et al. Risk-aware distributed optimal power flow in coordinated transmission and distribution system
CN105896533B (en) A kind of active distribution network Static security assessment method
CN113868814A (en) Multi-direct-current outgoing power grid planning method considering frequency safety constraint
Liu et al. A resilience enhancement scheme of cyber-physical power system for extreme natural disasters
CN110518633A (en) Consider that the grid nodes new energy of capacity of trunk abundant intensity receives capacity preparation method
Li et al. Coordinated Dispatching of Active Power and Reserve in Power System Based on Steady-State Security Region
Xiao-hui et al. Research on smart distribution network system architecture
Kong et al. Spatial-Temporal Scheduling of Commercial EVs for System Restoration of a Damaged Power-Transportation Coupled Network
Lu et al. Comprehensive Evaluation of Grid Adaptability Considering Rolling Access of Cascade Power Stations
Bai et al. A DC Interconnection Transformation Method of Low-Voltage Distribution Network Considering Power Outage Risk Assessment in Station Area

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant