CN105714752A - Static sounding construction technology for pavement of urban road - Google Patents

Static sounding construction technology for pavement of urban road Download PDF

Info

Publication number
CN105714752A
CN105714752A CN201610103043.1A CN201610103043A CN105714752A CN 105714752 A CN105714752 A CN 105714752A CN 201610103043 A CN201610103043 A CN 201610103043A CN 105714752 A CN105714752 A CN 105714752A
Authority
CN
China
Prior art keywords
static sounding
urban road
counterforce device
construction technology
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610103043.1A
Other languages
Chinese (zh)
Other versions
CN105714752B (en
Inventor
魏义强
武军
郝卫国
隋来才
师永翔
高辉
杨振江
吴天军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Jiao Ke geotechnical engineering Co., Ltd
Shanxi Province Transport Science Research Institute
Original Assignee
Shanxi Province Transport Science Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Province Transport Science Research Institute filed Critical Shanxi Province Transport Science Research Institute
Priority to CN201610103043.1A priority Critical patent/CN105714752B/en
Publication of CN105714752A publication Critical patent/CN105714752A/en
Application granted granted Critical
Publication of CN105714752B publication Critical patent/CN105714752B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ
    • E02D1/02Investigation of foundation soil in situ before construction work
    • E02D1/022Investigation of foundation soil in situ before construction work by investigating mechanical properties of the soil

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Road Repair (AREA)

Abstract

The invention belongs to the technical field of road exploitation and particularly relates to a static sounding construction technology for the pavement of an urban road. The static sounding construction technology for the pavement of the urban road specifically includes the steps of paying off in a positioned mode, tapping, installation of a counter-force device, leveling, static sounding and treatment after construction, wherein in the process of installation of the counter-force device, the corresponding ground position of the counter-force device is drilled with a hole through an electric drill, the hole diameter is matched with the diameter of an expansion bolt, the depth of the hole needs to be 5-10 cm larger than the length of the expansion bolt, and the counter-force device is mounted after drilling. Compared with the prior art, the static sounding construction technology for the pavement of the urban road can complete the static sounding construction operation of the pavement of the urban road quickly on the premise of not affecting normal traffic, primary data are provided for design of a next procedure, input of manpower and material resources is greatly lowered, and social influence is reduced. Therefore, the static sounding construction technology for the pavement of the urban road has the following characteristics that the range of damage to the pavement is small, the pavement is likely to recover, construction noise is low, and environmental protection and cleanliness are achieved.

Description

A kind of urban road surfaces static sounding construction technology
Technical field
The invention belongs to road exploratory techniques field, it particularly relates to touch to a kind of urban road surfaces static(al) Visit construction technology.
Background technology
Quiet spy is the important component part of engineering investigation, and existing quiet spy technique is the region of soil layer mainly for earth's surface, Quiet spy technique for urban road surfaces rarely has discussion.One technological difficulties of quiet spy technique are to provide enough Counter-force, current counterforce device mostly uses hydraulic to be screwed in soil by the screw mandrel of band earth anchor and provides counter-force. When urban road surfaces quiet spy construction, owing to road deck and the steady layer of water are hard so that the method is the most applicable, If rotating by force anchors in road surface, not only can destroy large area road surface, and the effect that counter-force is provided can not be played. Also have a kind of ending fitting to need manually to buttress lower rock bolt head, during operation, run into hard thing, difficulty of casting anchor, produce Counter-force, easily causes casualties.
Summary of the invention
For solving above-mentioned technical problem, the invention provides one urban road surfaces static sounding safely and efficiently Construction technology.
A kind of urban road surfaces static sounding construction technology of the present invention, described construction technology concrete steps Including:
1) line setting: first carry out the collection and analysis of underground utilities data, is fully understood by underground utilities distribution feelings Condition, secondly carries out field survey unwrapping wire with total powerstation according to the coordinate of design boring, deviations of actual position of holing 2m;
2) perforate: use Φ 73mm punching water drilling in the position that unwrapping wire is complete, road pavement surface layer and water are steady Layer carries out perforate, is drilled into till exposing undisturbed soil, guarantees drill bit straight down in drilling process, holes complete After should carry out protective measure;
3) counterforce device is installed: adjust the orientation of quiet spy car according to position of opening so that quiet spy alignment probe is opened The center in hole, determines quantity and the position installing counterforce device further according to the position of quiet spy car and counter-force size;Really After determining the quantity of counterforce device, counterforce device is installed;First electricity consumption is drilled in the corresponding ground location of counterforce device Upper boring, aperture matches with expansion bolt diameter, and the degree of depth in hole should be greater than expansion bolt length 5-10cm;Bore The installation of row counterforce device after hole;
4) leveling: carry out twice leveling from belting by quiet spy car, it is ensured that quiet spy probe is pressed into ground straight down In Ceng;The most pre-leveling, flattens under counterforce device is in relaxed state;Second time flattens pre-whole again After reef knot bundle, by rotating turnbuckle stretch-draw counterforce device, again flatten after stretch-draw, it is ensured that quiet spy work When making, probe is straight down;
5) static sounding: counterforce device fastens, proceeds by static sounding construction, constructed after the leveling of quiet spy car Journey is paid close attention to probe resistance and the deformation of detection bar, in case causing press-bending to break static(al) because counter-force is excessive Sounding rod;
6) work post processing: after quiet spy terminates, should carry out road surface recovery process, including process and the counter-force of quiet inspecting hole The process of device lower end expansion bolt.
A kind of urban road surfaces static sounding construction technology of the present invention, described step 6) in, described quiet The process of inspecting hole is to be filled by quiet inspecting hole plain-water slurry liquid, carries out and protects.
A kind of urban road surfaces static sounding construction technology of the present invention, described step 6) in, described swollen The process of swollen bolt hole is the nut twisting off expansion bolt top, removes pad, then with iron hammer by expansion bolt Squeezing in the hole of preboring, 5-10cm plain-water slurry liquid in top has filled.
A kind of urban road surfaces static sounding construction technology of the present invention, described step 1) in, boring is real Border site error 0.5m.
A kind of urban road surfaces static sounding construction technology of the present invention, described step 3) in, install anti- Counterforce device should be kept during power apparatus to be in relaxed state.
A kind of urban road surfaces static sounding construction technology of the present invention, described step 6) in, described element The little Hua Herba Carpesii Divaricati element diethyl ether solution of 1% mass concentration, diethyl ether solution quality are also spilt in the surface that cement grout is formed For plain-water slurry liquid 1/3rd.
Compared with prior art, urban road surfaces static sounding construction technology of the present invention can not affect In the case of normal traffic, it is rapidly completed urban road surfaces quiet spy construction working, designs offer one for next step Hands data, greatly reduces the input of manpower and materials, reduces social influence.Therefore, the present invention has as follows Feature: destruction road surface scope is little, be prone to recovery, construction noise is little, environment-protecting clean.
Accompanying drawing explanation
Fig. 1: static sounding construction flow chart;Fig. 2: quiet spy counterforce device figure;Upper attachment-1, flower Basket screw-2, lower attachment-3, expansion bolt-4.
Detailed description of the invention
Below in conjunction with specific embodiment urban road surfaces static sounding construction technology of the present invention done into One step explanation, but protection scope of the present invention is not limited to this.
Embodiment 1
A kind of urban road surfaces static sounding construction technology, concrete steps include:
1) line setting: first carry out the collection and analysis of underground utilities data, is fully understood by underground utilities distribution feelings Condition, secondly carries out field survey setting-out with total powerstation according to the coordinate of design boring, deviations of actual position of holing 0.5m;Because of underground utilities, the impact of earth's surface buildings or structures, may be designed and retrodisplacement is agreed in management, move Position ultimate range 2m.The bore position of displacement should carry out transposed recording signature work.
2) perforate: use Φ 73mm punching water drilling in the position that unwrapping wire is complete, road pavement surface layer and water are steady Layer carries out perforate, and water drilling is drilled into and exposes undisturbed soil under road surface.In water drilling drilling process it is ensured that drill bit vertical to Under, protective measure should be carried out after boring.
3) counterforce device is installed: adjust the orientation of quiet spy car according to position of opening so that quiet spy alignment probe is opened Center, hole.Quantity and the position installing counterforce device is determined further according to the position of quiet spy car and counter-force size.Determine After the quantity of counterforce device, counterforce device is installed.First electricity consumption is drilled in the corresponding ground location of counterforce device Upper boring, aperture matches with expansion bolt diameter, and the degree of depth should be greater than expansion bolt length 10cm.Hole Carry out the installation of counterforce device according to figure two after Biing.Counterforce device should be kept to be in absent-mindedness shape when counterforce device is installed State.
4) leveling: carry out secondary leveling from belting by quiet spy car, it is ensured that quiet spy probe is pressed into ground straight down In Ceng.The most pre-leveling, flattens under counterforce device is in relaxed state.Second time flattens pre-whole again After reef knot bundle, by rotating turnbuckle stretch-draw counterforce device, again flatten after stretch-draw, it is ensured that quiet spy work When making, probe is straight down.
5) static sounding: counterforce device fastens, proceeds by static sounding construction, constructed after the leveling of quiet spy car Journey is paid close attention to probe resistance and the deformation of detection bar, in case causing press-bending to break static(al) because counter-force is excessive Sounding rod.
6) work post processing: after quiet spy terminates, should carry out road surface recovery process, including process and the counter-force of quiet inspecting hole The process of device lower end expansion bolt.Quiet inspecting hole plain-water slurry liquid fills, and carries out and protects.Expansion bolt The process in hole is the nut twisting off expansion bolt top, removes pad, is then squeezed into by expansion bolt pre-with iron hammer In the hole bored, 10cm plain-water slurry liquid in top has filled.
Embodiment 2
A kind of urban road surfaces static sounding construction technology, concrete steps include:
1) line setting: first carry out the collection and analysis of underground utilities data, is fully understood by underground utilities distribution feelings Condition, secondly carries out field survey setting-out with total powerstation according to the coordinate of design boring, deviations of actual position of holing 0.4m;Because of underground utilities, the impact of earth's surface buildings or structures, may be designed and retrodisplacement is agreed in management, move The distance of positions is from 1.5m.The bore position of displacement should carry out transposed recording signature work.
2) perforate: use Φ 73mm punching water drilling in the position that unwrapping wire is complete, road pavement surface layer and water are steady Layer carries out perforate, and water drilling is drilled into and exposes undisturbed soil under road surface.In water drilling drilling process it is ensured that drill bit vertical to Under, protective measure should be carried out after boring.
3) counterforce device is installed: adjust the orientation of quiet spy car according to position of opening so that quiet spy alignment probe is opened Center, hole.Quantity and the position installing counterforce device is determined further according to the position of quiet spy car and counter-force size.Determine After the quantity of counterforce device, counterforce device is installed.First electricity consumption is drilled in the corresponding ground location of counterforce device Upper boring, aperture matches with expansion bolt diameter, and the degree of depth should be greater than expansion bolt length 5cm.Hole Carry out the installation of counterforce device according to figure two after Biing.Counterforce device should be kept to be in absent-mindedness shape when counterforce device is installed State.
4) leveling: carry out secondary leveling from belting by quiet spy car, it is ensured that quiet spy probe is pressed into ground straight down In Ceng.The most pre-leveling, flattens under counterforce device is in relaxed state.Second time flattens pre-whole again After reef knot bundle, by rotating turnbuckle stretch-draw counterforce device, again flatten after stretch-draw, it is ensured that quiet spy work When making, probe is straight down.
5) static sounding: counterforce device fastens, proceeds by static sounding construction, constructed after the leveling of quiet spy car Journey is paid close attention to probe resistance and the deformation of detection bar, in case causing press-bending to break static(al) because counter-force is excessive Sounding rod.
6) work post processing: after quiet spy terminates, should carry out road surface recovery process, including process and the counter-force of quiet inspecting hole The process of device lower end expansion bolt.Quiet inspecting hole plain-water slurry liquid fills, and carries out and protects.Expansion bolt The process in hole is the nut twisting off expansion bolt top, removes pad, is then squeezed into by expansion bolt pre-with iron hammer In the hole bored, 5cm plain-water slurry liquid in top has filled.
Embodiment 3
A kind of urban road surfaces static sounding construction technology, concrete steps include:
1) line setting: first carry out the collection and analysis of underground utilities data, is fully understood by underground utilities distribution feelings Condition, secondly carries out field survey setting-out with total powerstation according to the coordinate of design boring, deviations of actual position of holing 0.4m;Because of underground utilities, the impact of earth's surface buildings or structures, may be designed and retrodisplacement is agreed in management, move The distance of positions is from 1.5m.The bore position of displacement should carry out transposed recording signature work.
2) perforate: use Φ 73mm punching water drilling in the position that unwrapping wire is complete, road pavement surface layer and water are steady Layer carries out perforate, and water drilling is drilled into and exposes undisturbed soil under road surface.In water drilling drilling process it is ensured that drill bit vertical to Under, protective measure should be carried out after boring.
3) counterforce device is installed: adjust the orientation of quiet spy car according to position of opening so that quiet spy alignment probe is opened Center, hole.Quantity and the position installing counterforce device is determined further according to the position of quiet spy car and counter-force size.Determine After the quantity of counterforce device, counterforce device is installed.First electricity consumption is drilled in the corresponding ground location of counterforce device Upper boring, aperture matches with expansion bolt diameter, and the degree of depth should be greater than expansion bolt length 5cm.Hole Carry out the installation of counterforce device according to figure two after Biing.Counterforce device should be kept to be in absent-mindedness shape when counterforce device is installed State.
4) leveling: carry out secondary leveling from belting by quiet spy car, it is ensured that quiet spy probe is pressed into ground straight down In Ceng.The most pre-leveling, flattens under counterforce device is in relaxed state.Second time flattens pre-whole again After reef knot bundle, by rotating turnbuckle stretch-draw counterforce device, again flatten after stretch-draw, it is ensured that quiet spy work When making, probe is straight down.
5) static sounding: counterforce device fastens, proceeds by static sounding construction, constructed after the leveling of quiet spy car Journey is paid close attention to probe resistance and the deformation of detection bar, in case causing press-bending to break static(al) because counter-force is excessive Sounding rod.
6) work post processing: after quiet spy terminates, should carry out road surface recovery process, including process and the counter-force of quiet inspecting hole The process of device lower end expansion bolt.Quiet inspecting hole plain-water slurry liquid fills, the surface that this plain-water slurry liquid is formed Also spill 1% mass concentration little Hua Herba Carpesii Divaricati element (4 β-acetoxyl group-puppet guainane-11 (13)-alkene-12,8 α- Lactone) diethyl ether solution, diethyl ether solution quality is 1/3rd of plain-water slurry liquid, then carries out and protects.Swollen The process of swollen bolt hole is the nut twisting off expansion bolt top, removes pad, then with iron hammer by expansion bolt Squeezing in the hole of preboring, 5cm plain-water slurry liquid in top fills, and 1% mass has also been spilt on this plain-water slurry liquid surface The little Hua Herba Carpesii Divaricati element diethyl ether solution of concentration, diethyl ether solution quality is 1/3rd of plain-water slurry liquid,. After the diethyl ether solution of little Hua Herba Carpesii Divaricati element of 1% mass concentration is spilt on plain-water slurry liquid surface, it is possible to accelerate rapidly The solidification of plain-water slurry liquid, compared with being added without, hardening time shortens 22%.
Compared with prior art, urban road surfaces static sounding construction technology of the present invention can not affect In the case of normal traffic, it is rapidly completed urban road surfaces quiet spy construction working, designs offer one for next step Hands data, greatly reduces the input of manpower and materials, reduces social influence.Therefore, the present invention has as follows Feature: destruction road surface scope is little, be prone to recovery, construction noise is little, environment-protecting clean.

Claims (6)

1. a urban road surfaces static sounding construction technology, it is characterised in that described construction technology specifically walks Suddenly include:
1) line setting: first carry out the collection and analysis of underground utilities data, is fully understood by underground utilities distribution feelings Condition, secondly carries out field survey unwrapping wire with total powerstation according to the coordinate of design boring, deviations of actual position of holing 2m;
2) perforate: use Φ 73mm punching water drilling in the position that unwrapping wire is complete, road pavement surface layer and water are steady Layer carries out perforate, is drilled into till exposing undisturbed soil, guarantees drill bit straight down in drilling process, holes complete After should carry out protective measure;
3) counterforce device is installed: adjust the orientation of quiet spy car according to position of opening so that quiet spy alignment probe is opened The center in hole, determines quantity and the position installing counterforce device further according to the position of quiet spy car and counter-force size;Really After determining the quantity of counterforce device, counterforce device is installed;First electricity consumption is drilled in the corresponding ground location of counterforce device Upper boring, aperture matches with expansion bolt diameter, and the degree of depth in hole should be greater than expansion bolt length 5-10cm;Bore The installation of counterforce device is carried out after hole;
4) leveling: carry out twice leveling from belting by quiet spy car, it is ensured that quiet spy probe is pressed into ground straight down In Ceng;The most pre-leveling, flattens under counterforce device is in relaxed state;Second time flattens, in advance again After leveling terminates, by rotating turnbuckle stretch-draw counterforce device, again flatten after stretch-draw, it is ensured that quiet spy During work, probe is straight down;
5) static sounding: counterforce device fastens, proceeds by static sounding construction, constructed after the leveling of quiet spy car Journey is paid close attention to probe resistance and the deformation of detection bar, in case causing press-bending to break static(al) because counter-force is excessive Sounding rod;
6) work post processing: after quiet spy terminates, should carry out road surface recovery process, including process and the counter-force of quiet inspecting hole The process of device lower end expansion bolt.
A kind of urban road surfaces static sounding construction technology the most according to claim 1, it is characterised in that Described step 6) in, the process of described quiet inspecting hole is to be filled by quiet inspecting hole plain-water slurry liquid, carries out and protects.
A kind of urban road surfaces static sounding construction technology the most according to claim 1, it is characterised in that Described step 6) in, the process of described hole for the expansion bolt is the nut twisting off expansion bolt top, removes pad, Then being squeezed into by expansion bolt with iron hammer in the hole of preboring, 5-10cm plain-water slurry liquid in top has filled.
A kind of urban road surfaces static sounding construction technology the most according to claim 1, it is characterised in that Described step 1) in, hole deviations of actual position 0.5m.
A kind of urban road surfaces static sounding construction technology the most according to claim 1, it is characterised in that Described step 3) in, counterforce device should be kept to be in relaxed state when counterforce device is installed.
6. according to a kind of urban road surfaces static sounding construction technology described in Claims 2 or 3, its feature It is, described step 6) in, the little Hua gold of 1% mass concentration is also spilt on the surface that described plain-water slurry liquid is formed Earpick element diethyl ether solution, diethyl ether solution quality is 1/3rd of plain-water slurry liquid.
CN201610103043.1A 2016-02-25 2016-02-25 A kind of urban road surfaces static sounding construction technology Active CN105714752B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610103043.1A CN105714752B (en) 2016-02-25 2016-02-25 A kind of urban road surfaces static sounding construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610103043.1A CN105714752B (en) 2016-02-25 2016-02-25 A kind of urban road surfaces static sounding construction technology

Publications (2)

Publication Number Publication Date
CN105714752A true CN105714752A (en) 2016-06-29
CN105714752B CN105714752B (en) 2018-01-02

Family

ID=56157066

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610103043.1A Active CN105714752B (en) 2016-02-25 2016-02-25 A kind of urban road surfaces static sounding construction technology

Country Status (1)

Country Link
CN (1) CN105714752B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106940453A (en) * 2017-03-30 2017-07-11 长江岩土工程总公司(武汉) It is a kind of to exist at underground utilities carry out shallow-layer integrated exploration method and device
CN110471128A (en) * 2019-08-30 2019-11-19 天津核源工程勘察有限公司 A kind of great burying pipeline detection method and visit pressure device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010189944A (en) * 2009-02-19 2010-09-02 Penta Ocean Construction Co Ltd Portable cone penetration test device
CN203947460U (en) * 2014-06-26 2014-11-19 常州市规划设计院 A kind of counterforce device of static sounding
CN204212140U (en) * 2014-10-27 2015-03-18 浙江华东建设工程有限公司 The ground anchorage of the quiet spy equipment of formula of casting anchor
CN104846800A (en) * 2015-03-24 2015-08-19 北京市市政工程研究院 Deep-stratum in-situ penetrometer, penetration sounding trolley comprising the same and using method thereof
CN204959749U (en) * 2015-09-29 2016-01-13 贵州电力设计研究院 Static sounding counter -force device that contains reducing spiral line earth anchor and afterburning dish

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010189944A (en) * 2009-02-19 2010-09-02 Penta Ocean Construction Co Ltd Portable cone penetration test device
CN203947460U (en) * 2014-06-26 2014-11-19 常州市规划设计院 A kind of counterforce device of static sounding
CN204212140U (en) * 2014-10-27 2015-03-18 浙江华东建设工程有限公司 The ground anchorage of the quiet spy equipment of formula of casting anchor
CN104846800A (en) * 2015-03-24 2015-08-19 北京市市政工程研究院 Deep-stratum in-situ penetrometer, penetration sounding trolley comprising the same and using method thereof
CN204959749U (en) * 2015-09-29 2016-01-13 贵州电力设计研究院 Static sounding counter -force device that contains reducing spiral line earth anchor and afterburning dish

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106940453A (en) * 2017-03-30 2017-07-11 长江岩土工程总公司(武汉) It is a kind of to exist at underground utilities carry out shallow-layer integrated exploration method and device
CN106940453B (en) * 2017-03-30 2019-05-07 长江岩土工程总公司(武汉) A kind of pair there are the method and devices that shallow-layer integrated exploration is carried out at underground utilities
CN110471128A (en) * 2019-08-30 2019-11-19 天津核源工程勘察有限公司 A kind of great burying pipeline detection method and visit pressure device
CN110471128B (en) * 2019-08-30 2023-02-28 天津核源工程勘察有限公司 Large buried depth pipeline detection method and device

Also Published As

Publication number Publication date
CN105714752B (en) 2018-01-02

Similar Documents

Publication Publication Date Title
Wang et al. Evolution mechanism of water-flowing zones and control technology for longwall mining in shallow coal seams beneath gully topography
CN106121661A (en) A kind of tunnel trunk is by loess separating surface water rich strata construction method
CN107476301A (en) A kind of full casing follow-up step construction method of bridge pile foundation
CN105137488B (en) Ground water field based on artificial fluid injection describes method
CN104102525A (en) Method of risk ranking control of crossing engineering of urban rail transit
Perello et al. Excavation of the Aica-Mules pilot tunnel for the Brenner base tunnel: information gained on water inflows in tunnels in granitic massifs
CN111828031B (en) Method for directionally reinforcing soft broken water-rich stratum tunnel face of open TBM tunnel
Loew et al. Engineering geology of Alpine tunnels: Past, present and future
Li et al. The integrated drainage technique of directional high-level borehole of super large diameter on roof replacing roof extraction roadway: A case study of the underground Zhaozhuang Coal Mine
CN107700479A (en) A kind of construction method of large diameter drill hole pile
CN205804433U (en) Metro Deep Excavation water sealing structure seepage defect sonar seepage detector
Goel Tunnelling through weak and fragile rocks of Himalayas
CN105714752A (en) Static sounding construction technology for pavement of urban road
Ouzaid et al. FEM optimisation of seepage control system used for base stability of excavation
CN103628914B (en) The separate zone production of a kind of low-angle dip coal seam is visited to lower and is oozed the method for low-permeability thick-layer bedrock aquifer
Qi et al. Instability Analysis of a Low‐Angle Low‐Expansive Soil Slope under Seasonal Wet‐Dry Cycles and River‐Level Variations
Shinsaka et al. Development of high-speed type jet grouting method
Charlton et al. Comprehensive Foundation Rehabilitation at Bear Creek Dam
CN107964990A (en) Lower embedding type concrete slab no-dig technique measuring thickness device and its thickness measuring method
CN207703246U (en) Debris flow early-warning monitors system
TW463011B (en) Ground base modification: horizontal compaction method
CN107012865A (en) The construction method of the anti-collapse hole of anchor pole
Dong et al. Prevention and Control of Mine Water Hazards from Underlying Aquifers
RU2212494C1 (en) Method testing soil by static load
Ho Jet grouting field trial in Manhattan soil deposits, New York

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Wei Yiqiang

Inventor after: Zhang Xiao

Inventor after: Liu Wei

Inventor after: Guan Yongwei

Inventor after: Yan Guiwen

Inventor after: An Gaijun

Inventor after: Hu Yongchun

Inventor after: Wu Jun

Inventor after: Hao Weiguo

Inventor after: Sui Laicai

Inventor after: Shi Yongxiang

Inventor after: Gao Hui

Inventor after: Yang Zhenjiang

Inventor after: Wu Tianjun

Inventor after: Peng Xiaoqing

Inventor before: Wei Yiqiang

Inventor before: Wu Jun

Inventor before: Hao Weiguo

Inventor before: Sui Laicai

Inventor before: Shi Yongxiang

Inventor before: Gao Hui

Inventor before: Yang Zhenjiang

Inventor before: Wu Tianjun

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20171122

Address after: 030006 Taiyuan, Xiaodian District, Shanxi city street, No. 79

Applicant after: Shanxi Province Transport Science Research Institute

Applicant after: Shanxi Jiao Ke geotechnical engineering Co., Ltd

Address before: 030006 Taiyuan, Xiaodian District, Shanxi city street, No. 79

Applicant before: Shanxi Province Transport Science Research Institute

TA01 Transfer of patent application right