CN105672667A - Installation process for electric coal wharf screening system - Google Patents

Installation process for electric coal wharf screening system Download PDF

Info

Publication number
CN105672667A
CN105672667A CN201610223689.3A CN201610223689A CN105672667A CN 105672667 A CN105672667 A CN 105672667A CN 201610223689 A CN201610223689 A CN 201610223689A CN 105672667 A CN105672667 A CN 105672667A
Authority
CN
China
Prior art keywords
installation
lifting
steel
post
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610223689.3A
Other languages
Chinese (zh)
Inventor
王贵阳
于宗松
陈惠龙
�田�浩
李松
樊龙要
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Installation Engineering Co Ltd
Original Assignee
CCCC First Harbor Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Installation Engineering Co Ltd filed Critical CCCC First Harbor Installation Engineering Co Ltd
Priority to CN201610223689.3A priority Critical patent/CN105672667A/en
Publication of CN105672667A publication Critical patent/CN105672667A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Ship Loading And Unloading (AREA)

Abstract

The invention provides an installation process for an electric coal wharf screening system.The installation process includes the sequential construction steps of 1, installation of a screening tower steel structure; 2, hoisting of classifying screen equipment, wherein the installation sequence of a vibrating screen includes basic check, basic scribing, installation of a chute below the screen, installation of a vibrating screen support, connection between a bearing spring and the support, in-place installation of the vibrating screen and installation of a driving device support and a driving device; 3, installation of a scrapper, wherein the step of installation of the screening tower steel structure includes the procedures of a, hoisting of steel columns and b, hoisting of steel beams.The installation steps are reasonably arranged, the construction period, investment of manpower resources and investment of equipment are reasonably arranged in the installation process of the screening system, reworking and quality problems are avoided, construction time is saved, and construction cost is reduced.

Description

Electricity coaling wharf screening system mounting process
Technical field
The present invention relates to the installation work between electricity coaling wharf screening car, particularly relate to vibratory screening apparatus between screening car, scrape trigger and the mounting process of screening tower steel construction.
Background technology
It it is multi-storey steel structure industry factory building between electricity coaling wharf screening car, steel construction total amount is 460t, lifting equipment between screening car has 6, sizing screen 4,2, heavy type scratch board machine, its middle scraper machine is other equipment of bulk parts is integral hoisting, rationally to be arranged the installation order of steel construction and vibratory screening apparatus when mounted, to guarantee construction card quality, accelerate speed of application.
Summary of the invention
It is an object of the invention to provide and a set of can rationally arrange the mounting process sieving the main equipments such as tower machine room steel construction and vibratory screening apparatus between electricity coaling wharf screening car.
The technical solution used in the present invention:
Electricity coaling wharf screening system mounting process, construction procedure is followed successively by: sieves installation, the sizing screen equipment hoisting of tower steel construction and scrapes trigger and installs,
(1) installation of tower steel construction is sieved: the lifting of a. steel post: prepare before post lifting: treat that spot inspection is qualified, after stacking and traffic route are determined, namely embedded board is checked, the axis of pre-embedded bolt, planeness, absolute altitude, examine, measure qualified after, base nut under post is screwed on pre embedded bolt, with spirit-leveling instrument base nut leveling to same level, and suitably fixed, automobile is adopted to lift with rotational method during lifting, namely scene transported to by steel post, lifting machine hooks up while turn round and make pillar rotate around suspension column and be sling by steel post, process mainly comprises colligation, lifting, contraposition, interim fixing, correction is with last fixing, b. the lifting of girder steel: before lifting, centre of gravity adjustment balance has been tied up with wireline, and tie up at the both ends rope made of hemp, as pin down slip rope adjustment direction, steel beam lifting adopt monolithic lifting, before lifting on request prepare adjustment plate, bolt and draw cable rope at two ends, should be connected with bolt in time after hoisted in position, and by beam between edge with post web plate be connected, align with water level gauge and band line, after meeting specification, bolt tightened,
(2) sizing screen equipment hoisting: the installation order of vibratory screening apparatus is: basis checks, basis line, the lower chute of sieve is installed, vibratory screening apparatus bearing is installed, spring is connected with bearing, vibratory screening apparatus is in place in supporting, drive unit support and drive unit installation;
(3) installation of trigger is scraped: scrape trigger erecting equipment and mainly contain drive unit, head, tail and equipment box, after civil engineering completes, line setting by drawing, based on 5 tons of stable cars, in conjunction with 3 tons of chain blocks, all devices lifting is put in place, install according to drawing again, when medial launder is installed, install successively by the sequence number (SN) outside medial launder.When chain assembles, by vertical for chain link cup soldering opening upwards, flat boxing interface is to chain medullary ray. Upwards, plane is downward for shack boss.
The useful effect of the present invention: the present invention rationally arranges installation steps, the installation process of screening system rationally arranges the input of duration, manpower input and equipment, avoid and do over again and the generation of quality problems, saved the engineering time simultaneously, reduce construction cost.
Embodiment
Electricity coaling wharf screening system mounting process, construction procedure is followed successively by: sieves installation, the sizing screen equipment hoisting of tower steel construction and scrapes trigger and installs,
(1) installation of tower steel construction is sieved:
A. the lifting of steel post: prepare before post lifting: treat that spot inspection is qualified, after stacking and traffic route are determined, namely embedded board is checked, the axis of pre-embedded bolt, planeness, absolute altitude, examine, measure qualified after, base nut under post is screwed on pre embedded bolt, with spirit-leveling instrument base nut leveling to same level, and suitably fixed, automobile is adopted to lift with rotational method during lifting, after the front preparation work of lifting is ready, first carry out examination to hang, sling when one end height is 100 200 and stop hanging, check the verticality of rigging stability and crane stability and steel post, then crane is commanded slowly to decline, with two transit instruments centrally axis become 90 degree of placements, adjustment position is also debugged, to correct post position and verticality, slowly transfer after column base plate and embedded board cross centre line position alignment, control post verticality and off centering with transit instrument simultaneously, operator winch to after above bolt at steel post, stand separately good position, hold suspension column by the pre-opened hole alignment bolt on suspension column plate, it is inserted into, the ditch that falls is stopped when pillar is down on setting nut, pillar is prized with crowbar, make its center line alignment basis center line, and tighten suspension column nut, reach secure side and can extract suspension hook. for the column of single root unstable structure, wind cable temporary protection measure must be added. lifting group must be divided the work clearly before lifting, and utensils such as measuring, lift, be fastening is complete, and each one does his duty for each quality safety slip-stick artist of crane, commander, measurement, contraposition, colligation and site operation, and to reduce idler close as far as possible.
B. the lifting of girder steel: after steel post has lifted, before steel girder erection, reply beam check, distortion, defect overproof time, could install after process. Remove the greasy dirt on crane girder surface, silt, dust and other impurities, before lifting, tied up centre of gravity adjustment balance with wireline, and tied up at the both ends rope made of hemp, as pining down the adjustment direction slipping and restricting. After the front preparation work of lifting is ready, first carries out examination and hang, stop hanging when height of lift is 100 200, check rigging stability and crane stability. Through confirm errorless after crane can be commanded slowly to rise, when at the bottom of beam higher than bracket face 150~200, adjustment beam at the bottom of with bracket face two reference line reach accurate position, commander's crane decline is in place, girder steel is hung on vertical rear placement bracket face, crane girder is reinforced temporarily, reach secure side and can pluck hook. Steel beam lifting adopt monolithic lifting, before lifting on request prepare adjustment plate, bolt and draw cable rope at two ends. Should be connected with bolt in time after hoisted in position, and by beam between edge with post web plate be connected, align with water level gauge and band line, after meeting specification, bolt tightened, main lifting operation is: post, beam pack, stops an inspection, lifting, beam and support are installed, quality inspection, and steel ladder platform plate is installed.It is assembled that Steel Structure Installation adopts sheet frame ground to expand, the method that combined hanging and single Components installation combine, and installs secondary beam, connection beam, support afterwards, and stay according to the requirement of equipment hoisting and establish indivedual walking beam, fastening again after equipment is installed. Frame installation order is upper strata after first lower floor; First main structure, rear aggregated(particle) structure; The inside structure is first installed, the outer bilge construction of rear installation. The first primary member of the fastening order of component, rear secondary member. The fastening order of each beam on same framework is: first fastening upper node, more fastening bottom node, last fastening middle part node. The installation method adopting single-column single-beam is installed in screening tower workshop, it may also be useful to 2 25 tons are hung machine and coordinate installation. First steel post low for dedusting platform is filled during installation, pull on guy, and be linked to be entirety with crossbeam, then hoisting machine room main post, now uses two to hang machine and coordinates, an installation column, one crossbeam is installed, it is ensured that column installs rear frame member and also can connect immediately, makes to be linked to be between column entirety. Machine room inner funnel, end to end cylinder support, cylinder all should be placed in machine room with erection schedule end to end, otherwise subsequent installation is very difficult.
(2) sizing screen equipment hoisting: the installation order of vibratory screening apparatus is: basis checks, basis line, the lower chute of sieve is installed, vibratory screening apparatus bearing is installed, spring is connected with bearing, vibratory screening apparatus is in place in supporting, drive unit support and drive unit installation; Basis checks: check outside surface do not have crackle, hole, peel off and the phenomenon such as reinforcing bar is exposed; Check physical dimension and the position on basis; Check surface level; Check reserved bolt relative deviation; Basis line: with reference to drawing, marks the longitudinal cenlerline of vibratory screening apparatus to sieve tower column axis as benchmark; Mark the longitudinal and transverse medullary ray of vibratory screening apparatus bearing and drive unit support; Fundamentals of Measurement absolute altitude; The permissible variation that vibratory screening apparatus bearing is installed: levelness: 2/1000, checks with water level gauge; Diagonal lines deviation: 1/1000, checks with dipstick metering; Relative level is poor: 2mm, checks with spirit-leveling instrument; Holding spring support to install: should fully contacting with upper undersetting, spring should be contour, entering discharge end must not more than 5mm with the end contour deviation of spring, and each spring verticality is no more than the 25/1000 of spring height. The hoisted in position of vibratory screening apparatus: vibratory screening apparatus is in place, due to the volume of vibratory screening apparatus bigger and heavier, so the lifting of vibratory screening apparatus can according to on-site actual situations, first it is discharged at smooth good equipment after sizing screen equipment to goods and stacks field, steel construction hangs with 200T crane master after possessing lifting condition, and 50T crane coordinates transhipment with flat-bed trailer. 200T crane first time lifts 2 sizing screens in 2 positions, station, axis southern side, first fills 2,1-3 axle, and then 200T crane lifts 2 sizing screens in 4 positions, station, axis southern side two times. Scrape trigger segmentation 50T crane and winch to 3rd floors planes, the mode installation in position gathered mutually with thick stick and jack.
(3) installation of trigger is scraped: scrape trigger erecting equipment and mainly contain drive unit, head, tail and equipment box, after civil engineering completes, line setting by drawing, based on 5 tons of stable cars, in conjunction with 3 tons of chain blocks, all devices lifting is put in place, install according to drawing again, when medial launder is installed, install successively by the sequence number (SN) outside medial launder. When chain assembles, by vertical for chain link cup soldering opening upwards, flat boxing interface is to chain medullary ray. Upwards, plane is downward for shack boss. Scrape to be arranged on by flap type again after trigger installs and scrape above trigger outlet.

Claims (1)

1. electricity coaling wharf screening system mounting process, construction procedure is followed successively by: sieves installation, the sizing screen equipment hoisting of tower steel construction and scrapes trigger and installs, it is characterised in that,
(1) installation of tower steel construction is sieved: the lifting of a. steel post: prepare before post lifting: treat that spot inspection is qualified, after stacking and traffic route are determined, namely embedded board is checked, the axis of pre-embedded bolt, planeness, absolute altitude, examine, measure qualified after, base nut under post is screwed on pre embedded bolt, with spirit-leveling instrument base nut leveling to same level, and suitably fixed, automobile is adopted to lift with rotational method during lifting, namely scene transported to by steel post, lifting machine hooks up while turn round and make pillar rotate around suspension column and be sling by steel post, process mainly comprises colligation, lifting, contraposition, interim fixing, correction is with last fixing, b. the lifting of girder steel: before lifting, centre of gravity adjustment balance has been tied up with wireline, and tie up at the both ends rope made of hemp, as pin down slip rope adjustment direction, steel beam lifting adopt monolithic lifting, before lifting on request prepare adjustment plate, bolt and draw cable rope at two ends, should be connected with bolt in time after hoisted in position, and by beam between edge with post web plate be connected, align with water level gauge and band line, after meeting specification, bolt tightened,
(2) sizing screen equipment hoisting: the installation order of vibratory screening apparatus is: basis checks, basis line, the lower chute of sieve is installed, vibratory screening apparatus bearing is installed, spring is connected with bearing, vibratory screening apparatus is in place in supporting, drive unit support and drive unit installation;
(3) installation of trigger is scraped: scrape trigger erecting equipment and mainly contain drive unit, head, tail and equipment box, after civil engineering completes, line setting by drawing, based on 5 tons of stable cars, in conjunction with 3 tons of chain blocks, all devices lifting is put in place, then install according to drawing, when medial launder is installed, install successively by the sequence number (SN) outside medial launder, when chain assembles, by vertical for chain link cup soldering opening upwards, flat boxing interface is to chain medullary ray, upwards, plane is downward for shack boss.
CN201610223689.3A 2016-04-12 2016-04-12 Installation process for electric coal wharf screening system Pending CN105672667A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610223689.3A CN105672667A (en) 2016-04-12 2016-04-12 Installation process for electric coal wharf screening system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610223689.3A CN105672667A (en) 2016-04-12 2016-04-12 Installation process for electric coal wharf screening system

Publications (1)

Publication Number Publication Date
CN105672667A true CN105672667A (en) 2016-06-15

Family

ID=56310235

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610223689.3A Pending CN105672667A (en) 2016-04-12 2016-04-12 Installation process for electric coal wharf screening system

Country Status (1)

Country Link
CN (1) CN105672667A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0975849A (en) * 1995-09-12 1997-03-25 Ishikawajima Transport Mach Co Ltd Rotary screening apparatus
US6581780B1 (en) * 2001-01-16 2003-06-24 Ai Enterprises, Inc. Automatic gradation unit
JP2004000847A (en) * 2002-05-31 2004-01-08 Fukuyama Juki Kk Vibration feeding and sifting apparatus
CN102400558A (en) * 2010-09-13 2012-04-04 五冶集团上海有限公司 Method for mounting process steel platform steel columns in project of mounting benzene hydrogenation steel structure
CN102465601A (en) * 2010-11-17 2012-05-23 五冶集团上海有限公司 Method for installing main body frame steel structure of benzene hydrogenation project
CN204234337U (en) * 2014-11-21 2015-04-01 湖北三宁化工股份有限公司 A kind of moulded coal screening closed conveying re-use device
CN104624470A (en) * 2015-02-04 2015-05-20 中交一航局安装工程有限公司 Lump coal sieving device
CN104624471A (en) * 2015-02-04 2015-05-20 中交一航局安装工程有限公司 Lump coal sieving process

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0975849A (en) * 1995-09-12 1997-03-25 Ishikawajima Transport Mach Co Ltd Rotary screening apparatus
US6581780B1 (en) * 2001-01-16 2003-06-24 Ai Enterprises, Inc. Automatic gradation unit
JP2004000847A (en) * 2002-05-31 2004-01-08 Fukuyama Juki Kk Vibration feeding and sifting apparatus
CN102400558A (en) * 2010-09-13 2012-04-04 五冶集团上海有限公司 Method for mounting process steel platform steel columns in project of mounting benzene hydrogenation steel structure
CN102465601A (en) * 2010-11-17 2012-05-23 五冶集团上海有限公司 Method for installing main body frame steel structure of benzene hydrogenation project
CN204234337U (en) * 2014-11-21 2015-04-01 湖北三宁化工股份有限公司 A kind of moulded coal screening closed conveying re-use device
CN104624470A (en) * 2015-02-04 2015-05-20 中交一航局安装工程有限公司 Lump coal sieving device
CN104624471A (en) * 2015-02-04 2015-05-20 中交一航局安装工程有限公司 Lump coal sieving process

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
牛小惠: "港口块煤筛分工艺及设备选型", 《中国港湾建设》 *

Similar Documents

Publication Publication Date Title
CN106836498B (en) Hoisting construction method for steel truss of grand stand roof of super-large span stadium
CN105839919B (en) Sectional hoisting construction method for large-span ultrahigh-section steel frame
CN106087752B (en) Multispan cable-carried arch bridge construction method
CN106193618B (en) A kind of aerial steel structure truss construction of Long span
CN103883129B (en) A kind of steel structural roof beam installation method
CN105152032A (en) Installing method for bridge crane in enclosed environment workshop
CN101858163B (en) Method for installing flare tower frame in bulk
CN104831844B (en) The unidirectional double rope inverted cone-shaped cable curtain wall construction methods of arc
CN107476597A (en) Integral roof synchronization of jacking up method
CN105018115B (en) Dry quenching primary deduster fragment hoisting method
CN107720575B (en) A kind of towing type construction method for hanging of tower crane support system
CN114215170A (en) Method for lifting super-altitude giant hanging multi-layer connected structure
CN115467421A (en) Hoisting construction method for complex large-span steel roof
CN108842954A (en) Installation and construction method of huge different-section honeycomb beam structure system of wing-shaped roof
CN113789712B (en) Longitudinal beam and arch rib forming control method of steel arch bridge
CN103523665B (en) A kind of transport device and method of high pedestal jib crane
CN104692261A (en) Symmetrical dismounting construction method for attachment device of tower crane
CN106120573B (en) Multispan cable-carried arch bridge self-balancing button over strait hangs construction method
CN109763431A (en) A kind of bridge tower hydraulic climbing formwork is without pulling rod formwork construction method
CN105672667A (en) Installation process for electric coal wharf screening system
CN102587676B (en) Method for mounting internal girder structure of nuclear island at nuclear power station
CN107419902A (en) The method of steel-structure factory building crane girder construction roofing
CN113789713B (en) Longitudinal beam and arch rib forming control method of steel arch bridge
CN115030064A (en) Construction method for rebuilding and moving beam of high-speed rail elevated station
CN107217912A (en) It is a kind of to be used for the superelevation physical isolation construction method of neighbouring high ferro Business Line construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160615