CN105672133B - A kind of construction method for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton - Google Patents

A kind of construction method for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton Download PDF

Info

Publication number
CN105672133B
CN105672133B CN201610052926.4A CN201610052926A CN105672133B CN 105672133 B CN105672133 B CN 105672133B CN 201610052926 A CN201610052926 A CN 201610052926A CN 105672133 B CN105672133 B CN 105672133B
Authority
CN
China
Prior art keywords
bank
bridge
steel pipe
bridge skeleton
end bay
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610052926.4A
Other languages
Chinese (zh)
Other versions
CN105672133A (en
Inventor
李豪
闫川川
廖云昭
邓晓峰
周永峰
徐亮
黄冰
陈伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Guangzhou Engineering Group Co Ltd CRECGZ
CRECGZ No 2 Engineering Co Ltd
Original Assignee
China Railway Port and Channel Engineering Group Co Ltd
Second Engineering Co Ltd of China Railway Port and Channel Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Port and Channel Engineering Group Co Ltd, Second Engineering Co Ltd of China Railway Port and Channel Engineering Group Co Ltd filed Critical China Railway Port and Channel Engineering Group Co Ltd
Priority to CN201610052926.4A priority Critical patent/CN105672133B/en
Publication of CN105672133A publication Critical patent/CN105672133A/en
Application granted granted Critical
Publication of CN105672133B publication Critical patent/CN105672133B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of construction method for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton, comprise the following steps:Set up in the side slope in eastern bank river valley and hanging pulley has been set on hoisting platform, tensioning track cable, track cable, risen and hauling rope and hoisting rope are set on hanging pulley;Prefabricated boom segments;Symmetrical to set up eastern bank, the bridge skeleton end bay of west bank, when the bridge skeleton end bay for bank of playing the host is inserted into the boom segments directly over hoisting platform, pause sets up the bridge skeleton end bay of eastern bank, and the bridge skeleton end bay of west bank continues to be inserted into span centre, and wait is closed up;The remaining boom segments of eastern bank bridge skeleton end bay are put as corresponding lifting position, remaining boom segments are lifted by playing hanging pulley, and set up successively until closing up.The present invention saves the time, has economically saved the cost for setting up levelling bench and passage by symmetrically combining asymmetric boom segments erection method on the duration, the problem that pier sets up difficulty is solved in difficulty of construction.

Description

A kind of construction method for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton
Technical field
The present invention is used for technical field of bridge construction, and more particularly to one kind takes asymmetric lifting to set up steel pipe stiffness bridge The construction method of beam framework.
Background technology
Chinese arch bridge construction history is long, in ancient times using stone arch bridge as main bridge type, today after industrial fast development, adopts Also developed rapidly with the arch bridge of different materials, different systems.In long-span arch bridge, when in reinforced concrete arch bridge When steel pipe stiff skeleton is set up using cable crane air transport, Inclined cable-stayed erection by protrusion, hanging method is generally Symmetrical erection method, both section correspondence was set up section by section for small mileage, big mileage steel pipe stiff skeleton, treated all cantilever stiff skeleton sections Installation, waits closure section to install.Erection order is typically symmetrically set up from skewback two ends to span centre, until all segmental erections Complete, then wait and closing up in good time.
Existing symmetrical erection method, is only applicable to Arch Bridge Construction of the hoisting platform in span centre position.Using symmetrical erection Method, need to set up hoisting platform, and ensure that skeleton transport routes are unimpeded at span centre position.Because Arch Bridge Construction is largely In the location across mountain valley or river valley, general span centre position is all the center in mountain valley or river valley, and putting up platform difficulty is big, no Only time-consuming, fund input is also huge.
The content of the invention
To solve the above problems, the present invention provides a kind of construction for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton Method, it saves the time on the duration, the cost for setting up levelling bench and passage has economically been saved, in difficulty of construction Solve the problem that pier sets up difficulty.
The technical solution adopted for the present invention to solve the technical problems is:One kind takes asymmetric lifting to set up steel pipe stiffness The construction method of bridge skeleton, comprises the following steps:
S10. hoisting platform is set up in the side slope in eastern bank river valley, hoisting platform is located at below bridge skeleton to be set up, And extended from the highway of eastern bank to river valley center, the tensioning load-bearing between eastern bank and west bank in the top of bridge skeleton to be set up Hanging pulley has been set on rope, track cable, has risen and hauling rope and hoisting rope is set on hanging pulley;
S20. boom segments are transported to lifting by the boom segments of prefabricated sliceable shaping bridge skeleton by the highway of eastern bank On platform;
S30. boom segments are lifted by playing hanging pulley, it is symmetrical to set up eastern bank, the bridge skeleton end bay of west bank, bank of playing the host When bridge skeleton end bay is inserted into the boom segments directly over hoisting platform, pause sets up the bridge skeleton end bay of eastern bank, west bank Bridge skeleton end bay continue to be inserted into span centre, wait is closed up;
S40. the remaining boom segments of eastern bank bridge skeleton end bay are put as corresponding lifting position, the lifting position In the river valley immediately below respective cantilevered segmental erection position on bridge skeleton end bay, remaining hang is lifted by playing hanging pulley Arm joint section, and set up successively until closing up.
The improvement of technical solution of the present invention is further used as, the eastern bank, the bridge skeleton end bay of west bank include 20 Boom segments, the 13rd boom segments of the bridge skeleton end bay of eastern bank are located at the surface of the hoisting platform.
It is further used as in the improvement of technical solution of the present invention, step S40, boom segments is put as corresponding lifting position When putting, the river course bottom in river valley is first flattened, then deposits in boom segments in river course by steel pipe base.
The improvement of technical solution of the present invention is further used as, hoisting platform includes some people being located in eastern bank River Valley Slope Work caisson, the steel pipe column being located at the top of each artificial digging pile, the distribution beam being located at the top of the steel pipe column and it is located at institute The Bailey beam at the top of distribution beam is stated, the platform docked with the highway of eastern bank, the top of Bailey beam are formed on the top of the Bailey beam Lay prefabricated bridge.
The improvement of technical solution of the present invention is further used as, the steel pipe intercolumniation is provided with connection.
The improvement of technical solution of the present invention is further used as, the bottom of the prefabricated bridge, which is provided with, blocks the Bailey beam Limiting plate, the top edge of the prefabricated bridge is provided with railing.
The improvement of technical solution of the present invention is further used as, the position that the hoisting platform is docked with highway is provided with concrete base Plinth, the concrete basis has the step of overlap joint Bailey beam end.
Beneficial effects of the present invention:The present invention, which passes through, symmetrically combines asymmetric boom segments erection method, it is to avoid The putting up platform of span centre position, saves the time on the duration, economically saved the cost for setting up levelling bench and passage, The problem that pier sets up difficulty is solved in difficulty of construction.The success of the asymmetric construction method for hanging of steel pipe stiff skeleton is opened Hair, does not guarantee the quality still and completes the erection of stiff skeleton as scheduled, and has saved substantial amounts of work on overlay amount, saves work Phase and cost;The method for the asymmetric lifting construction that steel pipe stiff skeleton is taken, greatly reduces cable crane, pre-splicing field, fortune Defeated passage, hoisting platform etc. face greatly the quantities of facility.Take full advantage of in equipment, practical application, shorten the duration about 6 Month, add up cost-effective about 45,000,000 yuan.
Brief description of the drawings
The invention will be further described below in conjunction with the accompanying drawings:
Fig. 1 is structural representation after bridge skeleton integral erection of the present invention;
Fig. 2 is hoisting platform setting structure schematic diagram of the present invention;
Fig. 3 is hoisting platform side view of the present invention;
Fig. 4 is sectional view at A-A in Fig. 3.
Embodiment
Referring to figs. 1 to Fig. 4, that show the concrete structure of the preferred embodiments of the invention.It will be detailed below this Invent the design feature of each element, and be with shown in Fig. 1 if being described to during direction (upper and lower, left and right, before and after) Structure is that reference is described, but the actual use direction of the present invention is not limited thereto.
The purpose of the present invention is with a varied topography at the construction field (site), does not possess and sets up the situation of hoisting platform in span centre position Under, it is advanced to plan, pier is changed into land platform.According to topographic features, taken in the side slope in Dong An highways side and river valley If hoisting platform(The corresponding Section 13 section of skeleton), but lifting space is restricted, bank of playing the host is remained after being inserted into 13 sections Remaining section can not vertical lifting, so be inserted into behind 13 sections use asymmetric erection method.
The asymmetric construction method for lifting erection steel pipe stiffness bridge skeleton is taken the invention provides a kind of, including it is following Step:
S10. hoisting platform 1 is set up in the side slope in eastern bank river valley, hoisting platform 1 is located under bridge skeleton 2 to be set up Side, and extended from the highway 3 of eastern bank to river valley center, in top tensioning between eastern bank and west bank of bridge skeleton 2 to be set up Hanging pulley 5 has been set on track cable 4, track cable 4, has risen and hauling rope 6 and hoisting rope 7 is set on hanging pulley 5;
S20. boom segments 8 of prefabricated sliceable shaping bridge skeleton 2, the eastern bank, west bank bridge skeleton end bay it is equal Including 20 boom segments 8, whole bridge skeleton 2 amounts to 40 boom segments 8 for needing to lift, and boom segments 8 are passed through into east The highway 3 of bank is transported on hoisting platform 1;
S30. boom segments 8 are lifted by playing hanging pulley 5, it is symmetrical to set up eastern bank, the bridge skeleton end bay of west bank(1-13 hangs Arm joint section), the bridge skeleton end bay of bank of playing the host is inserted into the boom segments 8 directly over hoisting platform 1(13rd boom segments)When, Pause sets up the bridge skeleton end bay of eastern bank, and the bridge skeleton end bay of west bank continues to be inserted into span centre, and wait is closed up;
S40. by the eastern remaining boom segments 8 of bank bridge skeleton end bay(14-20 boom segments)Put as corresponding lifting Position, the lifting position is located in the river valley on bridge skeleton end bay immediately below respective cantilevered segmental erection position, will hang When arm joint section 8 is put as corresponding lifting position, the river course bottom in river valley is first flattened, boom segments are then passed through into steel pipe base Deposit in river course, lift remaining boom segments by playing hanging pulley 5, and set up successively until closing up.
Wherein, hoisting platform 1 includes being located in eastern bank River Valley Slope some artificial digging piles 11, be located at it is each described artificial The steel pipe column 12 at the top of caisson 11, the distribution beam 13 for being located at the top of steel pipe column 12 and it is located at the top of distribution beam 13 Provided with connection it is 15 between Bailey beam 14, the steel pipe column 12, increases overall structure stability.The top of the Bailey beam 14 is formed The platform docked with the highway 3 of eastern bank, the position that the hoisting platform 1 is docked with highway 3 is provided with concrete basis 16, the concrete basis 16 have the step of overlap joint Bailey beam 14 end.The top laying prefabricated bridge 17 of Bailey beam 14.The prefabricated bridge 17 Bottom be provided with and block the limiting plate 18 of the Bailey beam 14, the top edge of the prefabricated bridge 17 is provided with railing 19.
The present invention, which passes through, symmetrically combines asymmetric boom segments erection method, it is to avoid the platform in span centre position is taken If saving the time on the duration, the cost for setting up levelling bench and passage is economically saved, has been solved in difficulty of construction Pier sets up the problem of difficulty.The successful exploitation of the asymmetric construction method for hanging of steel pipe stiff skeleton, is not protected still as scheduled Matter completes the erection of stiff skeleton, and has saved substantial amounts of work on overlay amount, saves duration and cost;Steel pipe strength The method for the asymmetric lifting construction that property skeleton is taken, greatly reduces cable crane, pre-splicing field, transport channel, hoisting platform Deng the big quantities for facing facility.Take full advantage of in equipment, practical application, shorten the duration about 6 months, add up it is cost-effective about 45000000 yuan.
Certainly, the invention is not limited to above-mentioned embodiment, and those skilled in the art are without prejudice to originally Equivalent variations or replacement can be also made on the premise of spirit, these equivalent modifications or replacement are all contained in the application right It is required that in limited range.

Claims (7)

1. a kind of construction method for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton, it is characterised in that including following step Suddenly:
S10. hoisting platform is set up in the side slope in eastern bank river valley, hoisting platform is located at below bridge skeleton to be set up, and by The highway of eastern bank to river valley center extend, in the top of bridge skeleton to be set up between eastern bank and west bank tensioning track cable, hold Hanging pulley has been set on weight rope, has risen and hauling rope and hoisting rope is set on hanging pulley;
S20. boom segments are transported to hoisting platform by the boom segments of prefabricated sliceable shaping bridge skeleton by the highway of eastern bank On;
S30. boom segments are lifted by playing hanging pulley, it is symmetrical to set up eastern bank, the bridge skeleton end bay of west bank, the bridge for bank of playing the host When skeleton end bay is inserted into the boom segments directly over hoisting platform, pause sets up the bridge skeleton end bay of eastern bank, the bridge of west bank Beam framework end bay continues to be inserted into span centre, and wait is closed up;
S40. the remaining boom segments of eastern bank bridge skeleton end bay are put as corresponding lifting position, the lifting position is located at In river valley on bridge skeleton end bay immediately below respective cantilevered segmental erection position, remaining cantilever section is lifted by playing hanging pulley Section, and set up successively until closing up.
2. the construction method according to claim 1 for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton, its feature It is:The eastern bank, the bridge skeleton end bay of west bank include 20 boom segments, and the 13rd of the bridge skeleton end bay of eastern bank hangs Arm joint section is located at the surface of the hoisting platform.
3. the construction method according to claim 1 for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton, its feature It is:In step S40, when boom segments are put as corresponding lifting position, the river course bottom in river valley is first flattened, then will be outstanding Arm joint section is deposited in river course by steel pipe base.
4. the construction method according to claim 1 for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton, its feature It is:Some artificial digging piles that hoisting platform includes being located in eastern bank River Valley Slope, it is located at the top of each artificial digging pile Steel pipe column, the distribution beam being located at the top of the steel pipe column and the Bailey beam being located at the top of the distribution beam, the Bailey beam The platform docked with the highway of eastern bank, the top laying prefabricated bridge of Bailey beam are formed on top.
5. the construction method according to claim 4 for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton, its feature It is:The steel pipe intercolumniation is provided with connection system.
6. the construction method according to claim 4 for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton, its feature It is:The bottom of the prefabricated bridge is provided with the limiting plate for blocking the Bailey beam, the top edge of the prefabricated bridge Provided with railing.
7. the construction method according to claim 4 for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton, its feature It is:The position that the hoisting platform is docked with highway has the platform of overlap joint Bailey beam end provided with concrete basis, the concrete basis Rank.
CN201610052926.4A 2016-01-26 2016-01-26 A kind of construction method for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton Active CN105672133B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610052926.4A CN105672133B (en) 2016-01-26 2016-01-26 A kind of construction method for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610052926.4A CN105672133B (en) 2016-01-26 2016-01-26 A kind of construction method for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton

Publications (2)

Publication Number Publication Date
CN105672133A CN105672133A (en) 2016-06-15
CN105672133B true CN105672133B (en) 2017-10-24

Family

ID=56303161

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610052926.4A Active CN105672133B (en) 2016-01-26 2016-01-26 A kind of construction method for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton

Country Status (1)

Country Link
CN (1) CN105672133B (en)

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10183999A (en) * 1996-12-25 1998-07-14 Okabe Co Ltd Method of building movable form for arched concrete body
CN101705661B (en) * 2009-11-27 2011-11-09 中铁港航局集团第二工程有限公司 Method for constructing bridge over ravine
CN202090286U (en) * 2011-01-30 2011-12-28 中交三航局第三工程有限公司 Traction system suitable for self-anchored type double cable plane suspension bridge
CN103882798B (en) * 2014-04-03 2016-09-07 四川省交通运输厅公路规划勘察设计研究院 The reinforced concrete arch bridge of the powerful skeleton of a kind of concrete filled steel tube and construction method thereof
CN104278637B (en) * 2014-09-23 2016-04-06 中铁大桥局集团第一工程有限公司 A kind of main rope of suspension bridge strand is without the cableway erection method in cat road
CN204282189U (en) * 2014-12-01 2015-04-22 中铁二十局集团第一工程有限公司 A kind of long-span steel pipe arch bridge assembling construction structure

Also Published As

Publication number Publication date
CN105672133A (en) 2016-06-15

Similar Documents

Publication Publication Date Title
CN104612058B (en) A kind of construction method of buckstay flexible arch bridge
CN104294748B (en) A kind of hybrid beam cable-stayed bridge adapter section structure and construction method thereof
CN106638259B (en) The superstructure and its assembling and construction method of prefabricated uncovered beam type combined steel plate beam bridge
CN104294747A (en) Double-tower hybrid beam cable-stayed bridge system and construction method thereof
CN106939553B (en) A kind of Steel Bridge Deck and steel box arch rib installation method
CN102943440A (en) Method for constructing bridges
Siwowski et al. Horizontal rotation via floatation as an accelerated bridge construction for long-span footbridge erection: Case study
CN107245953A (en) The bent device and crossed construction method of a kind of multilayer bridge structure
CN206887771U (en) A kind of small across footpath plate-beam construction platform structure
CN101122115B (en) Construction method for tower crane shift
CN105672133B (en) A kind of construction method for taking asymmetric lifting to set up steel pipe stiffness bridge skeleton
CN205329550U (en) Suspension bridge catwalk system
Russell et al. Prefabricated bridge elements and systems in Japan and Europe
CN110424243A (en) A kind of Long span Tied-Arch Bridge Main Bridge jack-up system and jack-up construction method
CN113668399B (en) Construction method of half-through tied steel box arch bridge
CN204401462U (en) For the support of pier prestressed cap beam with extra length Construction Supporting System in water
Tang Segmental bridges in chongqing, China
CN207452663U (en) A kind of base-supporting steel pipe concrete tie-rod arch structure
CN112523097A (en) Large-span bridge gantry crane and construction method thereof
CN205474797U (en) Hold formula beam element and half through bridge girder construction among prefabricated ultra high performance concrete
CN206467549U (en) The superstructure of prefabricated uncovered beam type combined steel plate beam bridge
CN104404884B (en) For the support of pier prestressed cap beam with extra length Construction Supporting System in water
CN217758292U (en) Transition bridge between tunnels under gully landform
CN106958200B (en) A kind of small across footpath plate-beam construction platform structure and its application method
Sun et al. Key techniques for the construction of a special-shaped space single-tower cable-stayed bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20180130

Address after: Nansha District Nansha street Guangzhou city Guangdong province 510032 Port Street No. 1 Port Avenue South of Hong Kong Air China court office building No. 1 room 2502

Co-patentee after: The Second Co., Ltd. of China Railway Port Channel Engineering Group

Patentee after: China Railway Guangzhou Engineering Bureau Group Co Ltd

Address before: 510660 Guangzhou Science City, Guangdong Xiang Shan Road, No. 11

Co-patentee before: The Second Co., Ltd. of China Railway Port Channel Engineering Group

Patentee before: China Railway Port and Channel Engineering Group Co., Ltd.

TR01 Transfer of patent right
CP01 Change in the name or title of a patent holder

Address after: 510032 Room 2502, Office Complex Building No. 1, Nansha Street, Nansha District, Guangzhou City, Guangdong Province

Co-patentee after: China Railway Guangzhou Engineering Bureau Group Second Engineering Co., Ltd.

Patentee after: China Railway Guangzhou Engineering Bureau Group Co Ltd

Address before: 510032 Room 2502, Office Complex Building No. 1, Nansha Street, Nansha District, Guangzhou City, Guangdong Province

Co-patentee before: The Second Co., Ltd. of China Railway Port Channel Engineering Group

Patentee before: China Railway Guangzhou Engineering Bureau Group Co Ltd

CP01 Change in the name or title of a patent holder