CN105631079B CN201410697814.5A CN201410697814A CN105631079B CN 105631079 B CN105631079 B CN 105631079B CN 201410697814 A CN201410697814 A CN 201410697814A CN 105631079 B CN105631079 B CN 105631079B
Authority
CN
China
Prior art keywords
process flow
technique
production
information
executive plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410697814.5A
Other languages
Chinese (zh)
Other versions
CN105631079A (en
Inventor
姚亚仙
黄建中
张晓煜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Institute of Automation of CAS
Original Assignee
Shenyang Institute of Automation of CAS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Institute of Automation of CAS filed Critical Shenyang Institute of Automation of CAS
Priority to CN201410697814.5A priority Critical patent/CN105631079B/en
Publication of CN105631079A publication Critical patent/CN105631079A/en
Application granted granted Critical
Publication of CN105631079B publication Critical patent/CN105631079B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Abstract

The present invention relates to a kind of configurable segmented production task scheduling methods.Its step are as follows: if process flow 1) is divided into associated stem portion according to factory's actual process process first.2) virtual connection pool is established between each sub- technique, establishes the input and output content of connection pool, completes the information transmitting of the superior and the subordinate's technique.3) every sub- technique establishes model, the input/output argument of establishing model according to specific process flow.4) parameter of assigning plans is inputted at first line technique according to given format.5) observation output is as a result, obtain the design parameter value of executive plan and each executive plan in its process flow.6) according to actual needs, adjusting parameter optimizes executive plan.The present invention is applied in the manufacturing execution system software of industry spot, inputs parameter and process flow according to different assigning plans and carries out controllable type generation to executive plan.

Description

A kind of configurable segmented production task scheduling method
Technical field
The present invention relates to computer application technologies, are especially applied in the manufacturing execution system of industry spot, root According to different process feature generate executive plan and can according to input parameter regulation executive plan a kind of configurable segmented Production task scheduling method.
Background technique
In manufacturing execution system software, the generation of executive plan will have a direct impact on production efficiency, the output time of product Deng in the industry of part, since production process is various, production technology is complicated, and common executive plan generation method causes production to be imitated Rate is low, heavy then delivery can not be timely completed by assigning plans, and causes economic loss.In order to improve the production efficiency, a root is provided It models and can be very important according to the method for parameter regulation executive plan according to process characteristic.
Summary of the invention
Aiming at the defects existing in the prior art, the present invention provides a kind of be based on according to process characteristic modeling simultaneously It can be according to the configurable segmented production task scheduling method of parameter regulation executive plan.
Present invention technical solution used for the above purpose is: a kind of configurable segmented production task scheduling Method, comprising the following steps:
Process flow is divided into associated several sub- techniques according to factory's actual process process, and by every sub- technique It implements in production, forms production module;
Virtual connection pool is established between each production module, establishes the input and output content of connection pool, completes the superior and the subordinate The information of technique is transmitted;
Each production module establishes model, the input and output ginseng of establishing model according to its corresponding specific process flow Number;
Parameter of assigning plans is inputted at first line technique according to given format, obtains executive plan and each executes meter Draw the design parameter value in its process flow;
According to actual needs, adjusting parameter optimizes executive plan.
For every sub- technique for generating the stage product, in entire process flow is interim product in product And need the data input of the stage product into information system, then the sub- technique for generating the stage product is partitioned into Come.
Virtual connection pool is established between each sub- technique, specifically:
The operation result of upper production module is entered into database;
Giffler&Thompson algorithm is called to carry out operation, and record product title, coding, quantity information to connection pool The middle finished product information as current block;
The finished product information of current block is converted into the input raw material information of next module: the finished product in connection pool Title and encode constant, quantity divided by batch size, make there are in other database table by the new finished product information of generation For the input raw material information of next module.
Every sub- technique establishes model according to specific process flow, and model includes following information: process name, should The process for including under process, the material which generates, station corresponding with process.
The present invention has the following advantages and beneficial effects:
1) this method has wide applicability.Due to the difference between industry, even each producer inside of the same trade Production technology is also not quite similar, the executive plan generation method or applicability is narrow or enforceability is low that regular software provides. This method is modeled according to different productive prospecting piecemeals, so that this method has extensive industrial applicability.
2) accuracy of this method and adjustability are very high.Process provides the flexibilities that two parameters are used to control plan With the real-time of production status.Once Plan rescheduling, this method can generate new executive plan quickly, so that planning to have very high Feasibility and accuracy.It can guarantee that system really reflects entire process flow with machine state state modulator production status Production status.
Detailed description of the invention
Fig. 1 is executive plan product process figure.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and embodiments.
According to industry characteristic, entire technique is split as several associated sub- process modelings, this little process modeling It can be flexible manufacturing model by naturalization.The present invention has gone out a set of calculate based on Giffler& according to flexible manufacturing model development The operation method of Thompson algorithm.
[basic conception]
Assign plans: according to production task demand, manufacturer can produce by certain type product is assigned in month or week The production plan of quantity out.
Executive plan: for assigning plans, factory will formulate process time and the processing sequence of each workpiece, every machine The workpieces processing time and sequence.
Process: the order of entire production process Zhong Ge workshop section converted products.
Technique: the entire production process of certain type product is processed.
One, it is illustrated first to according to process characteristic modeling.
1, under normal conditions, if the production of a product can pass through arterial highway production process, process be single machine, have Process be pipeline system production.The processing method of heat treatment etc. is also different with the mode of common process.The raw material of certain processes Batch size is also different with other processes.So the first step of modeling is according to production method, processing method, reproduced goods processing side The process of close technology mode is classified as a production module by the sequencing of process by the features such as formula, batch.It is our in this way The technique of one product is abstracted as several production modules by method;
2, virtual link pond is established, the operation result that module is produced according to upper one is generated to the finished product of the module in pond Information, including material are processed on which platform machine, beginning process time on this machine.System built-in algorithm by the information from Turn changes the input raw material information of next module into, and the finished product information of last production module is the defeated of next production module Enter raw material information.
3, system provides different executive plan schemes.Difference between scheme is by the number of iterations of different algorithms It determines.The number of iterations is more, and executive plan is arranged closer, but operation time is longer.The number of iterations is less, and operation is got over Fastly, but obtained executive plan result may be more not as good as the number of iterations.Enable client's selector according to the actual situation in this way Close the scheme of oneself productive prospecting.
Two, the realization of method can be adjusted after generation executive plan according to parameter
In order to guarantee the real-time and adjustability of system, which generates system and introduces two parameters, and one is The weight parameter assigned plans, the other is the operating parameter of production equipment.
The weight parameter assigned plans is divided into three grades, 1 be it is non-emergent, if production order delivery date is later, can set It is set to the weight.2 be common order, which is default value.It is rush order greater than 3, the more big then urgency level of numerical value is higher. Parameter typing when raw material information inputs.In process of production, if order adjusts, the adjustable parameter value, Then system regenerates new executive plan for Instructing manufacture.Production efficiency can be improved, in case equipment is by non-emergent Business Occupation time and emergency task drag the phase.
The operating parameter of production equipment is used to control the operation of everyday devices.If equipment damage or ordinary maintenance, can To adjust equipment operating parameter.It can accurately be made a plan according to production status in this way, ensure that the accuracy of executive plan And flexibility.
As shown in Figure 1, one embodiment of the present of invention are as follows:
1, production module is established, and by process characteristic difference entire production procedure is split into according to produced on-site situation several A production module.
2, information needed is modeled in the typing of data input interface.Such as producing modules A includes M platform machine, and machine m can be processed The type { e1, e2 ... en } and processing duration { t1, t2 ... tn } of part;The machining set and sequence that part n needs.
3, system establishes virtual link pond between adjacent production module automatically, includes the production of upper one production module in pond Finished product information and the input raw material information for being automatically converted into next module;
4, it will assign plans and split into raw material information, and the typing before first production module;
5, system can automatically record according to built-in algorithm and generate the product information in each connection pool and the last one Produce the finished product information that module generates.
6, it is assigned plans according to order adjustment, keeps the accuracy of executive plan.It is set according to the adjustment of the state parameter of equipment Standby state guarantees the real-time of the production process of system reflection.

Claims (3)

1. a kind of configurable segmented production task scheduling method, which comprises the following steps:
Process flow is divided into associated several sub- techniques according to factory's actual process process, and every sub- technique is implemented Onto production, production module is formed;
Virtual connection pool is established between each production module, establishes the input and output content of connection pool, completes the superior and the subordinate's technique Information transmitting;
Each production module establishes model, the input/output argument of establishing model according to its corresponding specific process flow;
Parameter of assigning plans is inputted at first line technique according to given format, obtains executive plan and each executive plan exists Design parameter value in its process flow;
According to actual needs, adjusting parameter optimizes executive plan;
Virtual connection pool is established between each production module, specifically:
The operation result of upper production module is entered into database;
Giffler&Thompson algorithm is called to carry out operation, and record product title, coding, quantity information is made into connection pool For the finished product information of current block;
The finished product information of current block is converted into the input raw material information of next module: the name of the finished product in connection pool Claim and encode constant, quantity is divided by batch size, and the new finished product information of generation is there are in other database table, as under The input raw material information of a module.
2. a kind of configurable segmented production task scheduling method according to claim 1, which is characterized in that described Process flow is divided into associated several sub- techniques according to factory's actual process process are as follows: by the data input of interim product Into information system, the sub- technique for generating the stage product is split;The stage product is entire process flow In in product, the sub- technique is used for generation phase product.
3. a kind of configurable segmented production task scheduling method according to claim 1, which is characterized in that described every A production module establishes model according to its corresponding specific process flow, and model includes following information: process flow title, should The process for including under process flow, the material which generates, station corresponding with process.
CN201410697814.5A 2014-11-27 2014-11-27 A kind of configurable segmented production task scheduling method Expired - Fee Related CN105631079B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410697814.5A CN105631079B (en) 2014-11-27 2014-11-27 A kind of configurable segmented production task scheduling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410697814.5A CN105631079B (en) 2014-11-27 2014-11-27 A kind of configurable segmented production task scheduling method

Publications (2)

Publication Number Publication Date
CN105631079A CN105631079A (en) 2016-06-01
CN105631079B true CN105631079B (en) 2019-03-12

Family

ID=56046010

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410697814.5A Expired - Fee Related CN105631079B (en) 2014-11-27 2014-11-27 A kind of configurable segmented production task scheduling method

Country Status (1)

Country Link
CN (1) CN105631079B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109146125A (en) * 2018-07-02 2019-01-04 中化能源科技有限公司 A kind of oil product processing benefit measuring method, system and visualization system, method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1622528A (en) * 2003-11-26 2005-06-01 国际商业机器公司 Efficient connection pool management system and method
CN101079121A (en) * 2006-05-24 2007-11-28 宝山钢铁股份有限公司 Metallurgical industry integrative plan scheduling system and method
CN102034167A (en) * 2010-12-27 2011-04-27 用友软件股份有限公司 Method and device for making production task
CN102663963A (en) * 2012-06-06 2012-09-12 上海爱捷斯敏软件开发有限公司 Manufacturing precision marking system of trademark-based subdividing process section, and use method of manufacturing precision marking system
CN102722785A (en) * 2012-05-29 2012-10-10 安徽金缆信息技术有限公司 Workshop operation management method, system and server
CN103377076A (en) * 2012-04-28 2013-10-30 国际商业机器公司 Method and system for adjusting task execution plans during operation
CN103941674A (en) * 2014-03-27 2014-07-23 上海华力微电子有限公司 Method for designing multi-channel controlling technological processes

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1622528A (en) * 2003-11-26 2005-06-01 国际商业机器公司 Efficient connection pool management system and method
CN101079121A (en) * 2006-05-24 2007-11-28 宝山钢铁股份有限公司 Metallurgical industry integrative plan scheduling system and method
CN102034167A (en) * 2010-12-27 2011-04-27 用友软件股份有限公司 Method and device for making production task
CN103377076A (en) * 2012-04-28 2013-10-30 国际商业机器公司 Method and system for adjusting task execution plans during operation
CN102722785A (en) * 2012-05-29 2012-10-10 安徽金缆信息技术有限公司 Workshop operation management method, system and server
CN102663963A (en) * 2012-06-06 2012-09-12 上海爱捷斯敏软件开发有限公司 Manufacturing precision marking system of trademark-based subdividing process section, and use method of manufacturing precision marking system
CN103941674A (en) * 2014-03-27 2014-07-23 上海华力微电子有限公司 Method for designing multi-channel controlling technological processes

Also Published As

Publication number Publication date
CN105631079A (en) 2016-06-01

Similar Documents

Publication Publication Date Title
CN102411333B (en) Fast numerical control machining process system for complex parts of airplane
Zhang et al. Application framework of digital twin-driven product smart manufacturing system: A case study of aeroengine blade manufacturing
CN107832497A (en) A kind of intelligent workshop fast custom design method and system
CN103824136A (en) MES (Manufacturing Execution System) dynamic workshop scheduling and manufacturing execution system
CN107861478A (en) A kind of parallel control method in intelligent workshop and system
Wang An overview of function block enabled adaptive process planning for machining
CN108053047A (en) Cloud resources of production scheduling methods, devices and systems
CN111353690B (en) Block chain enabled production scheduling edge calculation method
TW202111618A (en) Production scheduling system and method
CN103454974A (en) Intelligent numerical control programming method driven by complex component process scheme
CN109583761A (en) A kind of Production-Plan and scheduling system of forged steel process
CN103823455A (en) Workshop scheduling simulation method based on equipment failure scheduling model
CN106951621B (en) A kind of simulation optimization method carrying Plan rescheduling for ship
US7228196B2 (en) Computer-aided manufacturing system and method for sheet-metal punching
CN114971407A (en) Automatic scheduling control method and system for maintenance plan
CN103902757A (en) System and method for rapid creation and interaction of three-dimensional model
CN105631079B (en) A kind of configurable segmented production task scheduling method
Kuric et al. Computer aided process planning in machinery industry
CN106909992B (en) Split charging production method and device of multi-variety small-batch mixed flow assembly line
CN104123611A (en) Production management system for sand casting enterprise
Tantik et al. Industrie 4.0: Using cyber-physical systems for value-stream based production evaluation
CN105739476A (en) Product control method and product control device with configurable workshop processes and technology
CN107113189A (en) For calculating to support cascade model PREDICTIVE CONTROL(MPC)The apparatus and method for acting on behalf of the limit
CN106033217B (en) Dispatching system and work dispatching method
CN103914042B (en) Intelligent plant and its flexibly direct writing unit, flexible intelligent equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190312

Termination date: 20211127

CF01 Termination of patent right due to non-payment of annual fee