Prior art keywords
coil
level
nut
order
horn mouth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410571698.2A
Other languages
Chinese (zh)
Other versions
CN105583278B (en
Inventor
张文忠
安立辉
贾春莉
何铁军
英升琪
白景彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Academy of Launch Vehicle Technology CALT
Capital Aerospace Machinery Co Ltd
Original Assignee
China Academy of Launch Vehicle Technology CALT
Capital Aerospace Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Academy of Launch Vehicle Technology CALT, Capital Aerospace Machinery Co Ltd filed Critical China Academy of Launch Vehicle Technology CALT
Priority to CN201410571698.2A priority Critical patent/CN105583278B/en
Publication of CN105583278A publication Critical patent/CN105583278A/en
Application granted granted Critical
Publication of CN105583278B publication Critical patent/CN105583278B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Shaping Metal By Deep-Drawing, Or The Like (AREA)

Abstract

The invention relates to a method for forming a horn-mouth-shaped flanged hole part on a top cap of a carrier rocket storage tank. The method is characterized by comprising the steps of (1) carrying out deep drawing forming on a part; (2) machining a pre-manufactured hole, specifically, drawing a circle at the center of the pretreated part, machining the pre-manufactured hole in the position of the circle, and obtaining a pre-manufactured hole part; (3) estimating a deformation region, comparing the shape of the horn-mouth-shaped flanged hole part to be obtained and the shape of the pre-manufactured hole part, dividing the region to be deformed into a plurality of sub-regions, and carrying out multiple stages of coil winding on a coil support according to the areas of the sub-regions; and (4) carrying out forming process, specifically, carrying out coil fixation stage by stage and magnetic impulse forming. The method has the beneficial effects that product development can be completed within a short period of time without a complex die, and accordingly the product development cost is reduced.

Description

Horn mouth flanging bore manufacturing process on carrier rocket tank top cover
Technical field
The present invention relates to carrier rocket manufacturing technology field, be specifically related at the bottom of carrier rocket tank case on loudspeakerMouth flanging bore part forming method.
Background technology
Carrier rocket tank comprises oxidant and fuel tank, all adopts aluminium alloy manufacture. On at the bottom of caseThere is a kind of flanging bore to be toroidal. General this flanging bore adopts large hydraulic press and large mold conventionallyProcessing.
But the processing method of this routine has following shortcoming:
(1) conventional method process complexity, the design cycle is long, the manufacturing cycle is long;
(2), there is the risk of reprocessing or scrapping in conventional method process complexity;
(3) rely on conventional method to process this part and cannot ensure the carrier rocket lead time;
Therefore, urgently at the bottom of a kind of new carrier rocket tank case on horn mouth flanging bore forming technology, with gramTake the defect of prior art.
Summary of the invention
The technical problem that will solve of the present invention is to provide one and uses simple mould to exist based on magnetic pulse technologyIn the very short time, complete the manufacturing process of horn mouth flanging bore part at the bottom of carrier rocket tank case.
In order to solve the problems of the technologies described above, technical scheme of the present invention is, at the bottom of a kind of carrier rocket tank caseUpper horn mouth flanging bore part forming method, specifically comprises the following steps:
Step 1, part drawing are shaped
Adopt large hydraulic press, by large-scale Drawing Die, original part carried out to drawing and form pretreatment part,Described pretreatment part is disk-like structure, and its outer surface is elliposoidal or spherical;
Step 2, processing pre-manufactured hole
Circle is drawn at the center of described pretreatment part, processes pre-manufactured hole in described round position, thereby obtainsPre-manufactured hole part;
Step 3, estimation deformed region
The horn mouth flanging bore part that contrast will be obtained and the shape of described pre-manufactured hole part, described in obtainingThe region that pre-manufactured hole part need to be out of shape, and the described region that needs distortion is divided into several regions, pointSafety pin carries out some grades of coil windings on coil brace to the area in these several regions;
Step 4, forming technology
From the first order, the coil brace that winds coil is positioned on backing plate, secondly by described pre-Drilling part is placed on coil brace, again mould is placed on part, finally uses screw bolt and nutMould, part and lower bolster are fixed together from top to bottom;
The two ends of described first order coil are connected with the output of magnetic field impulse equipment, after shaping, pineOpen bolt, nut, take apart a die, take out one-level formation of parts;
After this, rear one-level is on the basis of previous stage forming part, according to the technique mistake same with previous stageCheng Jinhang next stage forming technology; The formation of parts that afterbody obtains is for the horn mouth that will obtain turns overLateral opening part.
In described step 3, some grades of coil windings are three grades of coil windings, and described step 4 comprises followingStep:
4.1 first order are shaped
First the coil brace that winds first order coil is placed on backing plate, secondly part is placed onOn coil brace, again mould is placed on part, finally with screw bolt and nut by mould, part andLower bolster is fixed together from top to bottom;
The two ends of described first order coil are connected with the output of magnetic field impulse equipment, after shaping, pineOpen bolt, nut, take apart a die, take out one-level formation of parts;
4.2 second level are shaped
First the coil brace that winds second level coil is placed on backing plate, secondly the first order is shapedPart after treatment is placed on coil brace, again mould is placed on part, finally use bolt andNut is fixed together mould, part and lower bolster from top to bottom;
The two ends of described second level coil are connected with the output of magnetic field impulse equipment, after shaping, pineOpen bolt, nut, take apart a die, take out secondary formation of parts;
4.3 third level are shaped
First the coil brace that winds tertiary coil is placed on backing plate, secondly step 7 is quenchedAfter part be placed on coil brace, again mould is placed on part, finally use screw bolt and nutMould, part and lower bolster are fixed together from top to bottom;
The two ends of described tertiary coil are connected with the output of magnetic field impulse equipment, after shaping, pineOpen bolt, nut, take apart a die, take out the horn mouth flanging bore part that will obtain.
Described three grades of coil windings are that first order coil winding, second level coil winding, tertiary coil twineAround;
Described first order coil winding adopts copper bar or the cable of 10~30 squares, the number of turn 15~20 itBetween;
Described second level coil winding adopts copper bar or the cable of 10~30 squares, the number of turn 12~16 itBetween;
Described tertiary coil is wound around the copper bar or the cable that adopt 10~30 squares, the number of turn 8~12 it.
Beneficial effect of the present invention: without adopting complicated die, complete at short notice product development, fallLow production development cost.
Brief description of the drawings
Fig. 1 is the part schematic diagram before the shaping of horn mouth flanging bore on carrier rocket tank top cover of the present invention;
Fig. 2 is first order shaping in horn mouth flanging bore forming process on carrier rocket tank top cover of the present inventionDevice schematic diagram;
Fig. 3 is second level shaping in horn mouth flanging bore forming process on carrier rocket tank top cover of the present inventionDevice schematic diagram;
Fig. 4 be at the bottom of carrier rocket tank case of the present invention in horn mouth flanging bore forming process the third level be shapedDevice schematic diagram.
Detailed description of the invention
Below in conjunction with embodiment, the present invention is described further.
Horn mouth flanging bore part forming method at the bottom of a kind of carrier rocket tank of the present invention case, adopts magnetic arteries and veinsRushing the scope of horn mouth flanging bore at the bottom of technology shaping carrier rocket tank case isWall thickness2~10mm, material is aluminium alloy; Specifically comprise the following steps:
Step 1, part drawing are shaped
At the bottom of tank case, part as shown in Figure 1. Adopt large hydraulic press, by large-scale Drawing Die to original partCarry out drawing and form pretreatment part, described pretreatment part shape, according to layout design, is generally plate-likeStructure, and its outer surface is elliposoidal or spherical;
Step 2, processing pre-manufactured hole
According to drawing requirement, at described pretreatment Central of the parts place, taking diameter asDrawCircle, adopts the instruments such as electric drill, sweep-saw, file, emery cloth to process pre-manufactured hole in described round position;
Step 3, estimation deformed region
According to part shape, protruding hole dimension, estimate that every grade of described part need to carry out the region of deformation processing.
According to estimated deformed region, be divided into 3 steps, and just respectively for this trizonalAmass and on coil brace, carry out three grades of coil windings; Be specially first order coil winding, second level coil twinesBe wound around around, tertiary coil;
Described first order coil winding adopts copper bar or the cable of 10~30 squares, the number of turn 15~20 itBetween;
Described second level coil winding adopts copper bar or the cable of 10~30 squares, the number of turn 12~16 itBetween;
Described tertiary coil is wound around the copper bar or the cable that adopt 10~30 squares, the number of turn 8~12 it.Step 4, forming technology
4.1 first order are shaped
As shown in Figure 2, erection sequence be coil below, part is in centre, mould in the above; FirstThe coil brace that winds first order coil is placed on backing plate, secondly part is placed on to coil braceUpper, again mould is placed on part, finally with screw bolt and nut by mould, part and lower bolster fromUpper and under be fixed together;
The two ends of described first order coil are connected with the output of magnetic field impulse equipment, turn on the power switch,Set discharge energy, start automatic inflatable eletric button, after shaping, unclamp bolt, nut, unloadMould, takes out part;
4.2 second level are shaped
As shown in Figure 3, erection sequence be coil below, part is in centre, mould in the above; FirstThe coil brace that winds second level coil is placed on backing plate, secondly the first order is shaped after treatmentPart is placed on coil brace, again mould is placed on part, finally with screw bolt and nut by mouldTool, part and lower bolster are fixed together from top to bottom;
The two ends of described second level coil are connected with the output of magnetic field impulse equipment, turn on the power switch,Set discharge energy, start automatic inflatable eletric button, after shaping, unclamp bolt, nut, unloadMould, takes out part;
4.3 third level are shaped
As shown in Figure 4, erection sequence be coil below, part is in centre, mould in the above; FirstThe coil brace that winds tertiary coil is placed on backing plate to the part after secondly step 7 being quenchedBe placed on coil brace, again mould be placed on part, finally with screw bolt and nut by mould,Part and lower bolster are fixed together from top to bottom;
The two ends of described tertiary coil are connected with the output of magnetic field impulse equipment, turn on the power switch,Set discharge energy, start automatic inflatable eletric button, after shaping, unclamp bolt, nut, unloadMould, takes out part.

Claims (3)

1. at the bottom of carrier rocket tank case, a horn mouth flanging bore part forming method, is characterized in that: toolBody comprises the following steps:
Step 1, part drawing are shaped
Adopt large hydraulic press, by large-scale Drawing Die, original part is carried out to drawing and form pretreatment part, instituteStating pretreatment part is disk-like structure, and its outer surface is elliposoidal or spherical;
Step 2, processing pre-manufactured hole
Circle is drawn at the center of described pretreatment part, processes pre-manufactured hole in described round position, thereby obtains pre-Drilling part;
Step 3, estimation deformed region
The horn mouth flanging bore part that contrast will be obtained and the shape of described pre-manufactured hole part, obtain described pre-The region that drilling part need to be out of shape, and the described region that needs distortion is divided into several regions, point safety pinThe area in these several regions is carried out on coil brace to some grades of coil windings;
Step 4, forming technology
From the first order, the coil brace that winds coil is positioned on backing plate, secondly by described prefabricatedHole part is placed on coil brace, again mould is placed on part, finally with screw bolt and nut by mouldTool, part and lower bolster are fixed together from top to bottom;
The two ends of described first order coil are connected with the output of magnetic field impulse equipment, after shaping, unclampBolt, nut, take apart a die, and takes out one-level formation of parts;
After this, rear one-level is on the basis of previous stage forming part, according to the technical process same with previous stageCarry out next stage forming technology; The horn mouth flanging bore for obtaining of formation of parts that afterbody obtainsPart.
2. according to horn mouth flanging bore part forming side at the bottom of carrier rocket tank case claimed in claim 1Method, is characterized in that: in described step 3, some grades of coil windings are three grades of coil windings, described stepFour comprise the following steps:
4.1 first order are shaped
First the coil brace that winds first order coil is placed on backing plate, secondly part is placed onlineOn coil support, again mould is placed on part, finally with screw bolt and nut by mould, part and underlayPlate is fixed together from top to bottom;
The two ends of described first order coil are connected with the output of magnetic field impulse equipment, after shaping, unclampBolt, nut, take apart a die, and takes out one-level formation of parts;
4.2 second level are shaped
First the coil brace that winds second level coil is placed on backing plate, secondly by first order shaping placePart after reason is placed on coil brace, again mould is placed on part, finally uses screw bolt and nutMould, part and lower bolster are fixed together from top to bottom;
The two ends of described second level coil are connected with the output of magnetic field impulse equipment, after shaping, unclampBolt, nut, take apart a die, and takes out secondary formation of parts;
4.3 third level are shaped
First the coil brace that winds tertiary coil is placed on backing plate, after secondly step 7 being quenchedPart be placed on coil brace, again mould is placed on part, finally with screw bolt and nut by mouldTool, part and lower bolster are fixed together from top to bottom;
The two ends of described tertiary coil are connected with the output of magnetic field impulse equipment, after shaping, unclampBolt, nut, take apart a die, and takes out the horn mouth flanging bore part that will obtain.
3. according to horn mouth flanging bore part forming side at the bottom of carrier rocket tank case claimed in claim 2Method, is characterized in that: described three grades of coil windings are first order coil winding, second level coil winding,Three grades of coil windings;
Described first order coil winding adopts copper bar or the cable of 10~30 squares, and the number of turn is between 15~20;
Described second level coil winding adopts copper bar or the cable of 10~30 squares, and the number of turn is between 12~16;
Described tertiary coil is wound around the copper bar or the cable that adopt 10~30 squares, the number of turn 8~12 it.
CN201410571698.2A 2014-10-23 2014-10-23 Horn mouth flanging bore manufacturing process on carrier rocket tank top cover Active CN105583278B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410571698.2A CN105583278B (en) 2014-10-23 2014-10-23 Horn mouth flanging bore manufacturing process on carrier rocket tank top cover

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410571698.2A CN105583278B (en) 2014-10-23 2014-10-23 Horn mouth flanging bore manufacturing process on carrier rocket tank top cover

Publications (2)

Publication Number Publication Date
CN105583278A true CN105583278A (en) 2016-05-18
CN105583278B CN105583278B (en) 2018-02-13

Family

ID=55923393

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410571698.2A Active CN105583278B (en) 2014-10-23 2014-10-23 Horn mouth flanging bore manufacturing process on carrier rocket tank top cover

Country Status (1)

Country Link
CN (1) CN105583278B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106270104A (en) * 2016-09-07 2017-01-04 哈尔滨工业大学 A kind of magnetic field impulse hole flanging formation method of housing component
CN106964684A (en) * 2017-03-31 2017-07-21 华中科技大学 A kind of complex multi-step local plastic electromagnetic forming method suitable for sheet material workpiece
CN107116128A (en) * 2017-06-05 2017-09-01 三峡大学 The plate electromagnetism hemmer and method of a kind of axial-radial electromagnetic force timesharing loading
CN107138589A (en) * 2017-06-19 2017-09-08 中南大学 A kind of sheet material hole flanging building mortion and manufacturing process
CN107138591A (en) * 2017-06-19 2017-09-08 中南大学 A kind of electromagnetic forming device and manufacturing process of cylindrical member fillet
CN107138588A (en) * 2017-06-09 2017-09-08 华中科技大学 A kind of band pre-manufactured hole tubing electromagnetism side flanging device and method
CN107952860A (en) * 2017-11-03 2018-04-24 首都航天机械公司 It is a kind of to prevent the fracture of magnetic field impulse projecting apertures fillet and thinned method
CN108405699A (en) * 2018-04-02 2018-08-17 三峡大学 A kind of the plate electromagnetism hemmer and method of vertical repulsive force-radial direction suction timesharing load
CN109590373A (en) * 2018-11-16 2019-04-09 首都航天机械有限公司 Carrier rocket tank sinker thin-wall stainless steel cone-shaped component integral forming method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1380364A1 (en) * 2002-07-09 2004-01-14 Kabushiki Kaisha Kobe Seiko Sho Method for electromagnetically forming metallic member and metallic member formed by electromagnetic forming
DE102007053361A1 (en) * 2007-11-06 2009-05-07 Volkswagen Ag Method for shaping electromagnetic work pieces, involves use of flat coil to generate shaping force
CN103586325A (en) * 2013-11-05 2014-02-19 华中科技大学 Electromagnetic forming method for deeply punched member
CN103861930A (en) * 2014-04-01 2014-06-18 哈尔滨工业大学 Device and method for forming small-diameter flanging holes in aluminum alloy plate through magnetic pulses

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1380364A1 (en) * 2002-07-09 2004-01-14 Kabushiki Kaisha Kobe Seiko Sho Method for electromagnetically forming metallic member and metallic member formed by electromagnetic forming
DE102007053361A1 (en) * 2007-11-06 2009-05-07 Volkswagen Ag Method for shaping electromagnetic work pieces, involves use of flat coil to generate shaping force
CN103586325A (en) * 2013-11-05 2014-02-19 华中科技大学 Electromagnetic forming method for deeply punched member
CN103861930A (en) * 2014-04-01 2014-06-18 哈尔滨工业大学 Device and method for forming small-diameter flanging holes in aluminum alloy plate through magnetic pulses

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
卢兆勇: "箱底翻边孔磁脉冲成形技术的研究", 《万方数据库 工程硕士学位论文》 *
张文忠等: "基于磁脉冲技术的铝合金板材圆孔翻边工艺研究", 《航天制造技术》 *
黄亮等: "大型复杂型面铝合金翻边件电磁成形", 《机械工程学报》 *

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106270104A (en) * 2016-09-07 2017-01-04 哈尔滨工业大学 A kind of magnetic field impulse hole flanging formation method of housing component
CN106270104B (en) * 2016-09-07 2019-09-17 哈尔滨工业大学 A kind of magnetic field impulse hole flanging formation method of housing component
CN106964684A (en) * 2017-03-31 2017-07-21 华中科技大学 A kind of complex multi-step local plastic electromagnetic forming method suitable for sheet material workpiece
CN106964684B (en) * 2017-03-31 2019-05-31 华中科技大学 A kind of complex multi-step local plastic electromagnetic forming method suitable for sheet material workpiece
CN107116128B (en) * 2017-06-05 2019-09-24 三峡大学 A kind of the plate electromagnetism hemmer and method of axial direction-radial electromagnetic force timesharing load
CN107116128A (en) * 2017-06-05 2017-09-01 三峡大学 The plate electromagnetism hemmer and method of a kind of axial-radial electromagnetic force timesharing loading
CN107138588A (en) * 2017-06-09 2017-09-08 华中科技大学 A kind of band pre-manufactured hole tubing electromagnetism side flanging device and method
CN107138588B (en) * 2017-06-09 2018-08-21 华中科技大学 A kind of band pre-manufactured hole tubing electromagnetism side flanging device and method
CN107138589A (en) * 2017-06-19 2017-09-08 中南大学 A kind of sheet material hole flanging building mortion and manufacturing process
CN107138591A (en) * 2017-06-19 2017-09-08 中南大学 A kind of electromagnetic forming device and manufacturing process of cylindrical member fillet
CN107138589B (en) * 2017-06-19 2021-04-23 中南大学 Plate hole flanging forming device and forming method
CN107138591B (en) * 2017-06-19 2020-01-10 中南大学 Electromagnetic forming device and method for cylindrical part fillet
CN107952860A (en) * 2017-11-03 2018-04-24 首都航天机械公司 It is a kind of to prevent the fracture of magnetic field impulse projecting apertures fillet and thinned method
CN108405699A (en) * 2018-04-02 2018-08-17 三峡大学 A kind of the plate electromagnetism hemmer and method of vertical repulsive force-radial direction suction timesharing load
CN109590373A (en) * 2018-11-16 2019-04-09 首都航天机械有限公司 Carrier rocket tank sinker thin-wall stainless steel cone-shaped component integral forming method

Also Published As

Publication number Publication date
CN105583278B (en) 2018-02-13

Similar Documents

Publication Publication Date Title
CN105583278A (en) Method for forming horn-mouth-shaped flanged hole in top cap of carrier rocket storage tank
CN103658297B (en) The progressive drawing forming method of electromagnetic pulse assisted and device
CN102974689B (en) The processing technology of external teeth serrated lock washer and frock
CN107138589B (en) Plate hole flanging forming device and forming method
CN106270104A (en) A kind of magnetic field impulse hole flanging formation method of housing component
CN105312380A (en) Device and method for forming flange holes in large storage box
CN110899451A (en) Method and device for forming flange hole in integral box bottom of carrier rocket storage box
CN103084534A (en) Manufacturing method of cone-cylinder shaped forged piece of nuclear power evaporator transition cone
CN106424502A (en) Upsetting method and device for sheet-metal part with cylinder wall being thicker than flange
CN103212948A (en) Planet carrier flange forge piece forging process
CN203253753U (en) Cold extrusion device
CN103545694A (en) Planar all-plastic commutator processing method
CN203678888U (en) Metal wire drawing machine
CN203330293U (en) Material stripping structure of compound die
CN205816510U (en) A kind of automatic position-changing decompressor based on Malta's runner
CN105964780B (en) Fire extinguisher tank drawing process and its equipment
CN204771364U (en) Full -automatic kludge of drawing die
CN103212949B (en) A kind of oblate flange forging technique of full fiber
CN105081080A (en) Flanging forming mold
CN211479856U (en) Flat copper wire vertical winding die for high-power reactor
CN216614747U (en) High-dimensional-precision nanocrystalline magnetic core heat treatment forming device
CN204616237U (en) A kind of middle frame structure
CN103831593A (en) Forming method of air-conditioner blower-fan end ring
CN212121539U (en) Blank making equipment
CN202591386U (en) Cup-shaped workpiece flanging mould with steps

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant