CN105571106A - Air conditioner frame structure added in balcony of old community and construction method thereof - Google Patents

Air conditioner frame structure added in balcony of old community and construction method thereof Download PDF

Info

Publication number
CN105571106A
CN105571106A CN201610052394.4A CN201610052394A CN105571106A CN 105571106 A CN105571106 A CN 105571106A CN 201610052394 A CN201610052394 A CN 201610052394A CN 105571106 A CN105571106 A CN 105571106A
Authority
CN
China
Prior art keywords
air
bolt
newly
balcony
core pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201610052394.4A
Other languages
Chinese (zh)
Inventor
董有
杨黎明
梁淮南
潘沂华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd
Original Assignee
BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd filed Critical BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201610052394.4A priority Critical patent/CN105571106A/en
Publication of CN105571106A publication Critical patent/CN105571106A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F13/00Details common to, or for air-conditioning, air-humidification, ventilation or use of air currents for screening
    • F24F13/32Supports for air-conditioning, air-humidification or ventilation units
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/18Balustrades; Handrails
    • E04F11/181Balustrades
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/18Balustrades; Handrails
    • E04F11/181Balustrades
    • E04F11/1812Details of anchoring to the wall or floor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/18Balustrades; Handrails
    • E04F11/181Balustrades
    • E04F11/1842Balusters; Grille-type elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses an air conditioner frame structure added in a balcony of an old community and a construction method thereof. The structure comprises a traditional structure, and further comprises a steel core pipe added on the traditional structure, a newly added air conditioner vertical frame and a newly added air conditioner horizontal frame. The structure preferably solves the problem of daily use of air conditioning equipment by old residents based on traditional conditions of the old community, and is short in construction period, simple and convenient for operation, low in production cost and capable of being widely applied to reconstruction of old buildings with the defect.

Description

A kind of balcony place, old community sets up air conditoner support structure and construction method thereof
Technical field
The present invention relates to a kind of old community comprehensive reformation structure and construction method thereof, balcony place, especially a kind of old community sets up air conditoner support structure and construction method thereof, belongs to old community comprehensive reformation technical field.
Background technology
Old community comprehensive reformation is one and pays close attention to the well-being of the people, and facilitates the project supported by commen people of resident family's daily life.Its objective is and facilitate resident family to live, save energy resources, the quality of life of resident family is effectively promoted.Along with growth in the living standard, air-conditioning becomes the necessity of each household substantially.But some old house reckons without resident family's using air-condition equipment when designing, and does not have the position of design arrangement air-conditioning, and near residence outer wall, can not find suitable position placement air-conditioning, can only place outside balcony.For this reason, we have proposed and set up air conditoner support structure at balcony place, old community and solve this problem well, outdoor machine of air-conditioner is made to be fixed on balcony place air conditoner support safely and reliably, the method construction is simple, easy to operate, construct minimum on resident family's daily life impact, be a kind of very practical mode of setting up air conditoner support, there is very large development prospect.
Summary of the invention
Based on the problems referred to above, the present invention proposes balcony place, old community and set up air conditoner support structure and construction method thereof.Mainly not designing air-condition plate to solve old community, the technical problem of air conditoner support can only be set up outside balcony.
Technical scheme of the present invention is as follows:
A kind of balcony place, old community sets up air conditoner support structure, comprise original structure, be also included in the steel core pipe that original structure is set up, newly-increased air-conditioning stand, newly-increased air conditioner water flatrack, wherein, described steel core pipe upper end and former horizontal steel tube are welded to connect, and lower end and former balcony floor are anchored by crab-bolt backing plate; Described newly-increased air-conditioning stand is connected by stay bolt with between steel core pipe; Described newly-increased air conditioner water flatrack is connected by lag bolt with between newly-increased air-conditioning stand; Described outdoor machine of air-conditioner is placed in newly-increased air conditioner water flatrack.
Further, described steel core pipe is of a size of rectangular steel pipe 42mm × 72mm × 4mm.
Further, described newly-increased air-conditioning stand is for being not less than the equal leg angle of L45mm × 4mm.
Further, described anchor hole is arranged in each one of steel core tube section long side direction both sides, and anchor hole is 14mm, the long 120mm of crab-bolt, and diameter is 12mm, rotates and anchors in anchor hole.
Further, described crab-bolt plate thickness is 10mm, long 150mm, wide 100mm.
Above-mentioned balcony place, old community sets up the construction method of air conditoner support, it is characterized in that: adopt following steps:
Step one: according to the installation site of outdoor machine of air-conditioner, removes the insulation guardrail board between original balcony steel core pipe, and timely site clearing;
Step 2: according to design drawing location drilling.Bore anchor hole in former balcony floor relevant position, with oil-free compressed air, floating dust in hole is blown after pore-forming, and prevent in dust or grains of sand access aperture;
Step 3: crab-bolt anchorage part will remove surperficial rusty stain and other dirts, by planting in stud structure glue (joining glue to be used while allocating) hand-hole of configuring, and glue is applied in crab-bolt, simultaneously in slow circumvolve crab-bolt patchhole, discharge hole air, seal with epoxy mortar;
Step 4: after planting bolt adhesive curing, is fastenedly connected by steel core pipe by crab-bolt backing plate and former balcony floor and is corrected, and upper end is to welding burr dirt removal clean by the welding of steel core Guan Yuyuan horizontal steel tube;
Step 5: be fixed on steel core pipe by newly-increased air-conditioning stand stay bolt, is fastened in newly-increased air-conditioning stand by newly-increased air conditioner water flatrack lag bolt;
Step 6: carry out derusting anti-corrosive fire prevention process to all steel beam column, the main portions of easy-to-rust increases coating layer thickness 20-60 μm:
Step 7: basic unit face check and process qualified after, paste and insulation guardrail board be installed.
Beneficial effect:
The most significant advantage of the present invention is to adopt sets up air conditoner support structure outside balcony, the problem of short construction period, simple to operation, the daily life using air-condition equipment that solves former resident family well, less on balcony structure impact itself, cost is low, and the method is safe and reliable.When economic condition is permitted, if this technology is applied, set up air conditoner support structure at balcony place, existing old community and will have significant economic benefit and social benefit.
Accompanying drawing explanation
Fig. 1 is that balcony place sets up the positive elevational schematic view of air conditoner support;
Fig. 2 is that balcony place sets up air conditoner support side elevation schematic diagram;
Fig. 3 is crab-bolt backing plate floor map;
Fig. 4 is newly-increased air conditioner water flatrack and newly-increased air-conditioning stand connection diagram.
In figure, 1: former balcony floor; 2: former horizontal steel tube; 3: crab-bolt backing plate; 4: steel core pipe; 5: newly-increased air-conditioning stand; 6: stay bolt; 7: newly-increased air conditioner water flatrack; 8: lag bolt; 9: outdoor machine of air-conditioner; 10: anchor hole.
Detailed description of the invention
A kind of balcony place, old community sets up air conditoner support structure and construction method thereof, see shown in Fig. 1 to 4, comprise original structure, also be included in the steel core pipe 4 that original structure is set up, newly-increased air-conditioning stand 5, newly-increased air conditioner water flatrack 7, wherein, described steel core pipe 4 upper end and former horizontal steel tube 2 are welded to connect, lower end and former balcony floor 1 are anchored (as shown in Figure 1) by crab-bolt backing plate 3, described newly-increased air-conditioning stand 5 is connected by stay bolt 6 with between steel core pipe 4, described newly-increased air conditioner water flatrack 7 is connected by lag bolt 8 with between newly-increased air-conditioning stand 5, described outdoor machine of air-conditioner 9 is placed in newly-increased air conditioner water flatrack 7, described steel core pipe 4 is of a size of rectangular steel pipe 42mm × 72mm × 4mm, described newly-increased air-conditioning stand 5 is for being not less than the equal leg angle of L45mm × 4mm, described anchor hole 10 is arranged in each one of long side direction both sides, steel core pipe 4 cross section, anchor hole 10 is 14mm, the long 120mm of crab-bolt, diameter is 12mm, rotation anchors in anchor hole 10, described crab-bolt backing plate 3 thickness is 10mm, long 150mm, wide 100mm (as in Figure 2-4).
Above-mentioned balcony place, old community sets up the construction method of air conditoner support, adopts following steps:
Step one: according to the installation site of outdoor machine of air-conditioner 9, removes the insulation guardrail board between original balcony steel core pipe 4, and timely site clearing;
Step 2: according to design drawing location drilling.Bore anchor hole 10 in former balcony floor 1 relevant position, with oil-free compressed air, floating dust in hole is blown after pore-forming, and prevent in dust or grains of sand access aperture;
Step 3: crab-bolt anchorage part will remove surperficial rusty stain and other dirts, by planting in stud structure glue (joining glue to be used while allocating) hand-hole of configuring, and glue is applied in crab-bolt, simultaneously in slow circumvolve crab-bolt patchhole, discharge hole air, seal with epoxy mortar;
Step 4: after planting bolt adhesive curing, is fastenedly connected by steel core pipe 4 by crab-bolt backing plate 3 and former balcony floor 1 and is corrected, and steel core pipe 4 welds with former horizontal steel tube 2 and clean to welding burr dirt removal by upper end;
Step 5: be fixed on steel core pipe 4 by newly-increased air-conditioning stand 5 stay bolt 6, is fastened in newly-increased air-conditioning stand 5 by newly-increased air conditioner water flatrack 7 lag bolt 8;
Step 6: carry out derusting anti-corrosive fire prevention process to all steel beam column, the main portions of easy-to-rust increases coating layer thickness 20-60 μm:
Step 7: basic unit face check and process qualified after, paste and insulation guardrail board be installed.
Be more than a kind of exemplary embodiment of the present invention, specific embodiment of the invention is not limited thereto.

Claims (6)

1. balcony place, an old community sets up air conditoner support structure and construction method thereof, comprise original structure, it is characterized in that: be also included in the steel core pipe (4) that original structure is set up, newly-increased air-conditioning stand (5), newly-increased air conditioner water flatrack (7), described steel core pipe (4) upper end and former horizontal steel tube (2) are welded to connect, lower end and former balcony floor (1) are anchored by crab-bolt backing plate (3), described newly-increased air-conditioning stand (5) is connected by stay bolt (6) with between steel core pipe (4), described newly-increased air conditioner water flatrack (7) is connected by lag bolt (8) with between newly-increased air-conditioning stand (5), described outdoor machine of air-conditioner (9) is placed on newly-increased air conditioner water flatrack (7).
2. balcony place, old community according to claim 1 sets up air conditoner support structure and construction method thereof, it is characterized in that: described steel core pipe (4) is of a size of rectangular steel pipe 42mm × 72mm × 4mm.
3. balcony place, old community according to claim 1 sets up air conditoner support structure and construction method thereof, it is characterized in that: described newly-increased air-conditioning stand (5) is for being not less than the equal leg angle of L45mm × 4mm.
4. balcony place, old community according to claim 1 sets up air conditoner support structure and construction method thereof, it is characterized in that: described anchor hole (10) is arranged in each one of long side direction both sides, steel core pipe (4) cross section, anchor hole (10) is 14mm, the long 120mm of crab-bolt, diameter is 12mm, rotates and anchors in anchor hole (10).
5. balcony place, old community according to claim 1 sets up air conditoner support structure and construction method thereof, it is characterized in that: described crab-bolt backing plate (3) thickness is 10mm, long 150mm, wide 100mm.
6. the balcony place, old community according to claim 1-5 sets up air conditoner support structure and construction method thereof, it is characterized in that: adopt following steps:
Step one: according to the installation site of outdoor machine of air-conditioner (9), removes the insulation guardrail board between original balcony steel core pipe (4), and timely site clearing;
Step 2: according to design drawing location drilling.Bore anchor hole (10) in former balcony floor (1) relevant position, with oil-free compressed air, floating dust in hole is blown after pore-forming, and prevent in dust or grains of sand access aperture;
Step 3: crab-bolt anchorage part will remove surperficial rusty stain and other dirts, by planting in stud structure glue (joining glue to be used while allocating) hand-hole of configuring, and glue is applied in crab-bolt, simultaneously in slow circumvolve crab-bolt patchhole, discharge hole air, seal with epoxy mortar;
Step 4: after planting bolt adhesive curing, steel core pipe (4) is fastenedly connected by crab-bolt backing plate (3) and former balcony floor (1) and is corrected, and steel core pipe (4) welds with former horizontal steel tube (2) and clean to welding burr dirt removal by upper end;
Step 5: will increase air-conditioning stand (5) stay bolt (6) newly and be fixed on steel core pipe (4), will increase air conditioner water flatrack (7) lag bolt (8) newly and be fastened on newly-increased air-conditioning stand (5);
Step 6: carry out derusting anti-corrosive fire prevention process to all steel beam column, the main portions of easy-to-rust increases coating layer thickness 20-60 μm;
Step 7: basic unit face check and process qualified after, paste and insulation guardrail board be installed.
CN201610052394.4A 2016-01-27 2016-01-27 Air conditioner frame structure added in balcony of old community and construction method thereof Withdrawn CN105571106A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610052394.4A CN105571106A (en) 2016-01-27 2016-01-27 Air conditioner frame structure added in balcony of old community and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610052394.4A CN105571106A (en) 2016-01-27 2016-01-27 Air conditioner frame structure added in balcony of old community and construction method thereof

Publications (1)

Publication Number Publication Date
CN105571106A true CN105571106A (en) 2016-05-11

Family

ID=55881531

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610052394.4A Withdrawn CN105571106A (en) 2016-01-27 2016-01-27 Air conditioner frame structure added in balcony of old community and construction method thereof

Country Status (1)

Country Link
CN (1) CN105571106A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0790922A (en) * 1993-09-21 1995-04-04 Sekisui Chem Co Ltd Mounting construction of balcony
JP2000086166A (en) * 1998-09-10 2000-03-28 Watanabe Hitoshi Hanging device for outdoor unit of air conditioner, and installation method thereof
JP2006308243A (en) * 2005-04-28 2006-11-09 Daikin Ind Ltd Wall surface rack for outdoor unit for air conditioner, and installation method of outdoor unit for air conditioner using the same
JP2008185076A (en) * 2007-01-29 2008-08-14 Kfc Ltd Bolt connecting nut and anchor construction method using the same
CN202467187U (en) * 2012-02-21 2012-10-03 北京城乡建设集团有限责任公司 Adjustable tool air-conditioning plate template bracket
JP3189135U (en) * 2013-11-18 2014-02-27 協立技研株式会社 Air conditioner outdoor unit moving device
CN104295109A (en) * 2014-07-24 2015-01-21 北京筑福国际工程技术有限责任公司 Rapid reinforcing structure for home-entry-free balcony of old community and construction method of structure
CN204343442U (en) * 2014-12-12 2015-05-20 苏州规划设计研究院股份有限公司 A kind of prefabricated assembling type reinforced concrete air-condition plate

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0790922A (en) * 1993-09-21 1995-04-04 Sekisui Chem Co Ltd Mounting construction of balcony
JP2000086166A (en) * 1998-09-10 2000-03-28 Watanabe Hitoshi Hanging device for outdoor unit of air conditioner, and installation method thereof
JP2006308243A (en) * 2005-04-28 2006-11-09 Daikin Ind Ltd Wall surface rack for outdoor unit for air conditioner, and installation method of outdoor unit for air conditioner using the same
JP2008185076A (en) * 2007-01-29 2008-08-14 Kfc Ltd Bolt connecting nut and anchor construction method using the same
CN202467187U (en) * 2012-02-21 2012-10-03 北京城乡建设集团有限责任公司 Adjustable tool air-conditioning plate template bracket
JP3189135U (en) * 2013-11-18 2014-02-27 協立技研株式会社 Air conditioner outdoor unit moving device
CN104295109A (en) * 2014-07-24 2015-01-21 北京筑福国际工程技术有限责任公司 Rapid reinforcing structure for home-entry-free balcony of old community and construction method of structure
CN204343442U (en) * 2014-12-12 2015-05-20 苏州规划设计研究院股份有限公司 A kind of prefabricated assembling type reinforced concrete air-condition plate

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
杨志峰;徐伟;胡百根;: "老旧小区住宅楼综合改造技术与管理" *
魏洁;: "外套装配式抗震加固给力老旧小区改造 老楼旧貌换新颜" *

Similar Documents

Publication Publication Date Title
WO2021253808A1 (en) Building technique for low-carbon society in high-technology era
CN107965153B (en) Dry-laid rubble wall seismic strengthening and energy-saving reconstruction integrated method
CN205276769U (en) Light outer wall point is hung heat preservation decorative board combination anchor and is connect system
CN104032840A (en) Prestress assembly type frame joint connecting structure with additionally-arranged steel angles and construction method of prestress assembly type frame joint connecting structure
CN105507539A (en) Light external wall point-hang heat-insulation and decorative plate combined anchoring system and method for constructing same
CN103758358A (en) Steel plate angle iron combined constructional column and anchor adhering steel plate brickwork reinforcing structure and construction method
CN104295109B (en) Do not register one's residence balcony rapid reinforcement structure and construction method thereof in old community
CN101782266B (en) Connection joint for air conditioner board
CN204282709U (en) A kind of diatom decoration panel rock wool combined wall
CN211286074U (en) Self-heat-insulation system for prefabricated light high-strength foam concrete filled wallboard outer wall
CN201614665U (en) Air conditioner mounting plate connecting joint
CN206512866U (en) Concealed installation Fire Hose backing apparatus
CN103104057B (en) Full-glass self-balance glass curtain wall
CN201771070U (en) Externally hung wallboard connection part
CN105571106A (en) Air conditioner frame structure added in balcony of old community and construction method thereof
CN110360668A (en) Increase air-conditioner mounting rack scrap build and construction method at a kind of old house balcony newly
CN204531201U (en) Sensor levels suspended deck structure
CN207277678U (en) The assembled wallboard that batch production multilayer integrates
CN204098519U (en) Do not register one's residence balcony rapid reinforcement structure in old community
CN208633310U (en) A kind of precast facade of embedded solar collector plate
CN205100443U (en) Be used for overlength industry factory building siphon drainage system
CN102926493A (en) Dry hanging wall body node containing self-drilling and connecting built-in buried piece
CN208441288U (en) A kind of connector construction for the connection of prefabricated assembled shear wall
CN202831324U (en) Dry hanging wall panel point containing self-drilling built-in embedded part
CN206396954U (en) A kind of lightgage steel joist composite concrete wallboard

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
CB02 Change of applicant information

Address after: 100043 Shijingshan District, Yang Yang Street, No. 69, No. 1, building an international Park, Fu International

Applicant after: BEIJING ZHUFU INTERNATIONAL ANTI-SEISMIC TECHNOLOGY CO.,LTD.

Address before: 100043 Shijingshan, Yang Yang Street, No. 69, No. 1, building an international Park, Fu International

Applicant before: BEIJING AEIDO ENGINEERING TECHNOLOGY Co.,Ltd.

COR Change of bibliographic data
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20160511

WW01 Invention patent application withdrawn after publication