CN105525569A
CN105525569A CN201410563273.7A CN201410563273A CN105525569A CN 105525569 A CN105525569 A CN 105525569A CN 201410563273 A CN201410563273 A CN 201410563273A CN 105525569 A CN105525569 A CN 105525569A
Authority
CN
China
Prior art keywords
bridge
template
flange plate
wood
seam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410563273.7A
Other languages
Chinese (zh)
Other versions
CN105525569B (en
Inventor
杨明升
毛远富
丁顿斯
周万雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201410563273.7A priority Critical patent/CN105525569B/en
Publication of CN105525569A publication Critical patent/CN105525569A/en
Application granted granted Critical
Publication of CN105525569B publication Critical patent/CN105525569B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

A bridge flange plate wet joint suspended formwork construction method is characterized by comprising the following steps of a, making a plurality of template systems, wherein the template systems are spliced and linked with each other in a length direction of a wet joint; arranging back-arris square timbers at four edges of the bottoms of templates (2) in the template systems; drilling holes at the centers of the back-arris square timbers, transverse to a bridge direction, on the two sides to run through the templates; enabling phi 12mm lifting rods (7) with two threaded ends to penetrate through the holes; b, arranging soft ropes (6) at the two ends of the templates in the bridge direction; c, sleeving phi 40 mm PVC pipes (12) outside the phi 12mm lifting rods (7) within a range of the wet joint; d, binding wet joint reinforcements, pouring concrete and curing the concrete; e, detaching epsilon-type clamping buckles (11) and replacing the epsilon-type clamping buckles with nuts (13); f, tightening the soft ropes (6) on piers and abutments at two ends of a beam plate; and g, enabling the soft ropes (6) at the two ends to cooperate with each other and conveying the templates (2) to one side pier and abutment so as to finish the suspended formwork construction. The invention has the advantages of simple structure, convenient mounting and detaching and low manufacturing cost and does not occupy grounds or water surfaces under bridges.

Description

The bridge flange plate seam that wets hangs mould construction method
Technical field
The present invention relates to a kind of model sheetinstallat and method for dismounting of bridge building operations, specifically, be a kind of bridge flange plate wet seam lifting template construction method.
Background technology
After bridge precast beam plate installation, usual interval 50-80cm between two panels beam flange plate, after this pouring concrete region is wet seam.Current installation and the wet joint template of dismounting mainly contain two kinds of methods, and one is set up at the bottom of scaffold to wet seam under bridge; One is floor manufacture template under bridge, bridge utilizes the equipment hoisting templates such as hoist engine, transfers to ground again during form removal.These two kinds of methods all need to take place under bridge, and need long-time close traffic on traffic main artery, need rent boats and ships at the water surface, construction cost is higher, and unfavorable construction organization affects construction speed.
Therefore known bridge flange plate wet seam construction there is above-mentioned all inconvenience and problem.
Summary of the invention
Object of the present invention, is that propose one only completes the operation of wet seam overall process on bridge floor and pier, does not take the seam that wets of the bridge flange plate in place under bridge and hangs mould construction method.
For achieving the above object, technical solution of the present invention is:
A kind of bridge flange plate seam that wets hangs mould construction method, it is characterized in that comprising the following steps:
A, make some template systems, each template system is connected to mutual split in wet seam length; Bottom template in template system, four limits arrange the back cord lumps of wood, respectively hole through template in the direction across bridge back cord lumps of wood center on two limits, and through the Ф 12mm suspension rod of two head threadings in hole, suspension rod reinforcing bar lower end arranges nut; Tilt template system certain angle, and bridge floor is transferred to bridge flange plate from wet seaming position to be onstructed;
B, template arrange soft rope along bridge to two ends, soft rope length to bridge flange plate two, by soft for template two rope along to bridge flange plate two ends;
C, manage at wet seam scope Ф 12mm suspension rod outer fit Ф 40mmPVC, utilize chevron buckle by Ф 12mm suspension rod and lie across the fastener for connection of wet seam end face with fixed form;
D, colligation are wet seam reinforcing bar, concreting, curing concrete;
E, lay down chevron buckle, change nut, transfer Ф 12mm suspension rod, under nut is stuck in and template makes Ф 12mm suspension rod drop to bridge;
F, on the pier of beam slab two ends, strain soft rope, from PVC hole, gently disclose template, template is come off;
G, the soft rope in two cooperatively interact, and template are delivered to side pier, transfer to bridge floor turnover and use.
The bridge flange plate of the present invention seam that wets is hung mould construction method and can also be further achieved by the following technical measures.
Aforesaid method, wherein said template selects bamboo slab rubber.
Aforesaid method, the wherein said back cord lumps of wood comprise the direction across bridge back cord lumps of wood and along bridge to the back cord lumps of wood.
Aforesaid method, is wherein also included in bottom template and arranges the short lumps of wood to two ends along bridge, and short lumps of wood center is established along bridge to through hole, soft rope from through hole through tying up on the short lumps of wood.
Aforesaid method, the wherein said steel pipe two underlay lumps of wood lying across wet seam end face, steel pipe is 2 one group, in wet seam scope, arrange some groups.
Aforesaid method, numbering is labeled in wherein said soft rope free end end, and the soft rope in same template both sides numbering is consistent, in different templates, soft rope is numbered and do not repeated.
Adopt after technique scheme, the bridge flange plate of the present invention seam that wets is hung mould construction method and is had the following advantages:
1, formwork structure is simple, and mounting or dismounting are convenient, cheap;
2, on bridge floor and pier, complete the operation of wet seam overall process, do not take place under bridge, be beneficial to construction organization, reduce costs;
3, wet seam construction quality is good, reduces engineering cost.
Accompanying drawing explanation
Fig. 1 is the template schematic bottom view of the embodiment of the present invention;
Fig. 2 is that the wet joint template of the embodiment of the present invention installs schematic cross-sectional view;
Fig. 3 is that the wet joint template of the embodiment of the present invention installs schematic longitudinal section;
Fig. 4 is that the form removable of the embodiment of the present invention is hung and sent schematic diagram.
In figure: Bridge 1 beam flange plate, 2 templates, the 3 direction across bridge back cord lumps of wood, 4 along bridge to the back cord lumps of wood, the 5 short lumps of wood, 6 soft ropes, 7 suspension rods, 8 nuts, 9 lumps of wood, 10 steel pipes, 11 chevron buckles, 12PVC manage, 13 nuts, 14 bridge piers.
Detailed description of the invention
Below in conjunction with embodiment and accompanying drawing thereof, the present invention is illustrated further.
Embodiment 1
The bridge flange plate of the present invention seam that wets hangs mould construction method, it is characterized in that comprising the following steps:
A, make some template systems, each template system is connected to mutual split in wet seam length, and described template 2 selects bamboo slab rubber.
Now refer to Fig. 1, Fig. 1 is the template schematic bottom view of the embodiment of the present invention.As shown in the figure, bottom the template 2 in described template system, four limits arrange the back cord lumps of wood, respectively hole through template in the direction across bridge back cord lumps of wood center on two limits, and through the Ф 12mm suspension rod 7 of two head threadings in hole, suspension rod reinforcing bar lower end arranges nut 8; Tilt template system certain angle, and bridge floor is transferred to bridge flange plate 1 from wet seaming position to be onstructed; The described back cord lumps of wood comprise the direction across bridge back cord lumps of wood 3 and along bridge to the back cord lumps of wood 4.Also bottom template, fixedly mount the short lumps of wood 5 along bridge to two ends, short lumps of wood center is established along bridge to through hole, soft rope 6 from through hole through tying up on the short lumps of wood 5.
Fig. 2 is that the wet joint template of the embodiment of the present invention installs schematic cross-sectional view, and Fig. 3 is that the wet joint template of the embodiment of the present invention installs schematic longitudinal section.
B, template arrange soft rope 6 along bridge to two ends, soft rope length to bridge flange plate two, by soft for template two rope 6 along to bridge flange plate two ends; Numbering is labeled in described soft rope 6 free end end, and same template both sides soft rope numbering is consistent, and in different templates, soft rope numbering does not repeat.
C, at the outer fit Ф 40mmPVC pipe 12 of wet seam scope Ф 12mm suspension rod 7, chevron buckle 11 is utilized to be connected with fixed form by Ф 12mm suspension rod 7 with the steel pipe 10 lying across wet seam end face; The described steel pipe 10 two underlay lumps of wood 9 lying across wet seam end face, steel pipe 10 is 2 one group, in wet seam scope, arrange 3 groups.
D, colligation are wet seam reinforcing bar, concreting, curing concrete.
E, lay down chevron buckle 11, change nut 13, transfer Ф 12mm suspension rod 7, under nut 13 is stuck in and template 2 makes Ф 12mm suspension rod 7 drop to bridge.
F, on the pier of beam slab two ends, strain soft rope 6, from PVC hole 12, gently disclose template, template is come off.
G, the soft rope 6 in two cooperatively interact, and template 2 is delivered to side pier, transfer to bridge floor turnover and use.
The present invention has substantive distinguishing features and significant technological progress, and bridge flange plate of the present invention wets, and to hang mould construction method structure simple for seam, and mounting or dismounting are convenient, cheap.Bridge floor and pier complete the operation of wet seam overall process, does not take place under bridge, be beneficial to construction organization, reduce costs.
Above embodiment is used for illustrative purposes only, but not limitation of the present invention, person skilled in the relevant technique, without departing from the spirit and scope of the present invention, can also make various conversion or change.Therefore, all equivalent technical schemes also should belong to category of the present invention, should be limited by each claim.

Claims (6)

1. the bridge flange plate seam that wets hangs a mould construction method, it is characterized in that comprising the following steps:
A, make some template systems, each template system is connected to mutual split in wet seam length; Four limits, template (2) bottom in template system arrange the back cord lumps of wood, and respectively hole through template in the direction across bridge back cord lumps of wood center on two limits, through the Ф 12mm suspension rod (7) of two head threadings in hole, suspension rod reinforcing bar lower end arranges nut (8); Tilt template system certain angle, and bridge floor is transferred to bridge flange plate (1) bottom from wet seaming position to be onstructed;
B, template arrange soft rope (6) along bridge to two ends, soft rope length to bridge flange plate two, by soft for template two rope (6) along to bridge flange plate two ends;
C, manage (12) at wet seam scope Ф 12mm suspension rod (7) outer fit Ф 40mmPVC, utilize chevron buckle (11) to be connected with fixed form by Ф 12mm suspension rod (7) with the steel pipe (10) lying across wet seam end face;
D, colligation are wet seam reinforcing bar, concreting, curing concrete;
E, lay down chevron buckle (11), change nut (13), transfer Ф 12mm suspension rod (7), under nut (13) is stuck in and template (2) makes Ф 12mm suspension rod (7) drop to bridge;
F, on the pier of beam slab two ends, strain soft rope (6), from PVC hole (12), gently disclose template, template is come off;
G, the soft rope in two (6) cooperatively interact, and template (2) is delivered to side pier, transfer to bridge floor turnover and use.
2. the bridge flange plate as claimed in claim 1 seam that wets hangs mould construction method, and it is characterized in that, described template (2) selects bamboo slab rubber.
3. the bridge flange plate as claimed in claim 1 seam that wets hangs mould construction method, it is characterized in that, the described back cord lumps of wood comprise the direction across bridge back cord lumps of wood (3) and along bridge to the back cord lumps of wood (4).
4. the bridge flange plate as claimed in claim 1 seam that wets hangs mould construction method, it is characterized in that, also be included in bottom template and arrange the short lumps of wood (5) to two ends along bridge, short lumps of wood center is established along bridge to through hole, soft rope (6) from through hole through tying up on the short lumps of wood (5).
5. the bridge flange plate as claimed in claim 1 seam that wets hangs mould construction method, it is characterized in that, described in lie across steel pipe (10) two underlay lumps of wood (9) of wet seam end face, steel pipe (10) is 2 one group, in wet seam scope, arrange some groups.
6. the bridge flange plate as claimed in claim 1 seam that wets hangs mould construction method, it is characterized in that, numbering is labeled in described soft rope (6) free end end, and the soft rope numbering in same template both sides unanimously, in different templates, number and do not repeat by soft rope.
CN201410563273.7A 2014-10-22 2014-10-22 Bridge flange plate wet joint suspended formwork construction method Active CN105525569B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410563273.7A CN105525569B (en) 2014-10-22 2014-10-22 Bridge flange plate wet joint suspended formwork construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410563273.7A CN105525569B (en) 2014-10-22 2014-10-22 Bridge flange plate wet joint suspended formwork construction method

Publications (2)

Publication Number Publication Date
CN105525569A true CN105525569A (en) 2016-04-27
CN105525569B CN105525569B (en) 2017-04-19

Family

ID=55768064

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410563273.7A Active CN105525569B (en) 2014-10-22 2014-10-22 Bridge flange plate wet joint suspended formwork construction method

Country Status (1)

Country Link
CN (1) CN105525569B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108951424A (en) * 2018-07-09 2018-12-07 中国五冶集团有限公司 The formwork support structure and construction method that bridge suspension type pours
CN110396932A (en) * 2019-07-24 2019-11-01 中交一公局集团有限公司 A kind of wet joint template peace of bridge jointing formula tears circulator and its construction method open
CN111502258A (en) * 2020-04-15 2020-08-07 广西建工集团第五建筑工程有限责任公司 Superimposed sheet pours mould split subassembly with seam hoist and mount
CN111996921A (en) * 2020-09-07 2020-11-27 中冶建工集团有限公司 Construction method for hanging formwork at building joint
CN112240004A (en) * 2020-10-28 2021-01-19 中国十九冶集团有限公司 Wet joint reinforcing steel bar installation device and installation method
CN113668403A (en) * 2021-08-31 2021-11-19 上海市基础工程集团有限公司 Movable mold hanging device for wet joint of cast-in-place main beam and construction method
CN114277686A (en) * 2021-12-21 2022-04-05 中铁二十五局集团第二工程有限公司 Construction process of large-span steel plate combination beam
CN114717959A (en) * 2022-04-14 2022-07-08 中交第四公路工程局有限公司 Heat storage and heat preservation maintenance device for bridge wet joint concrete
CN114753253A (en) * 2022-03-08 2022-07-15 武汉市市政建设集团有限公司 Prefabricated beam bridge wet joint mold flying device and construction method
CN114775447A (en) * 2022-05-26 2022-07-22 中国十七冶集团有限公司 Manufacturing and construction method of wet joint template of high pier stud bridge

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3865660B2 (en) * 2002-06-24 2007-01-10 大成建設株式会社 Cement-based mixed material curing device and method of using the same
CN101705748A (en) * 2009-11-19 2010-05-12 张永忠 Formwork for placing concrete on slope surface
CN202849944U (en) * 2012-08-20 2013-04-03 中建七局第一建筑有限公司 Suspension type post-cast strip template
CN203188121U (en) * 2013-03-01 2013-09-11 浙江省交通工程建设集团有限公司 Cast-in-place bridge floor suspending mold of half-through or through arch bridge
CN103306205A (en) * 2013-06-09 2013-09-18 中国十七冶集团有限公司 Construction method of longitudinal wet joint formwork of prefabricated T beam or box beam
CN103758045A (en) * 2014-02-20 2014-04-30 中铁十局集团第三建设有限公司 Box girder wet joint formwork construction method under space limitation condition
CN203768803U (en) * 2014-04-10 2014-08-13 中核华泰建设有限公司 Bridge wet joint formwork lifting device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3865660B2 (en) * 2002-06-24 2007-01-10 大成建設株式会社 Cement-based mixed material curing device and method of using the same
CN101705748A (en) * 2009-11-19 2010-05-12 张永忠 Formwork for placing concrete on slope surface
CN202849944U (en) * 2012-08-20 2013-04-03 中建七局第一建筑有限公司 Suspension type post-cast strip template
CN203188121U (en) * 2013-03-01 2013-09-11 浙江省交通工程建设集团有限公司 Cast-in-place bridge floor suspending mold of half-through or through arch bridge
CN103306205A (en) * 2013-06-09 2013-09-18 中国十七冶集团有限公司 Construction method of longitudinal wet joint formwork of prefabricated T beam or box beam
CN103758045A (en) * 2014-02-20 2014-04-30 中铁十局集团第三建设有限公司 Box girder wet joint formwork construction method under space limitation condition
CN203768803U (en) * 2014-04-10 2014-08-13 中核华泰建设有限公司 Bridge wet joint formwork lifting device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
庄乾国: "上跨铁路干线架梁施工技术", 《铁道建筑技术》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108951424A (en) * 2018-07-09 2018-12-07 中国五冶集团有限公司 The formwork support structure and construction method that bridge suspension type pours
CN110396932A (en) * 2019-07-24 2019-11-01 中交一公局集团有限公司 A kind of wet joint template peace of bridge jointing formula tears circulator and its construction method open
CN111502258A (en) * 2020-04-15 2020-08-07 广西建工集团第五建筑工程有限责任公司 Superimposed sheet pours mould split subassembly with seam hoist and mount
CN111996921A (en) * 2020-09-07 2020-11-27 中冶建工集团有限公司 Construction method for hanging formwork at building joint
CN112240004A (en) * 2020-10-28 2021-01-19 中国十九冶集团有限公司 Wet joint reinforcing steel bar installation device and installation method
CN112240004B (en) * 2020-10-28 2022-02-15 中国十九冶集团有限公司 Wet joint reinforcing steel bar installation device and installation method
CN113668403A (en) * 2021-08-31 2021-11-19 上海市基础工程集团有限公司 Movable mold hanging device for wet joint of cast-in-place main beam and construction method
CN114277686A (en) * 2021-12-21 2022-04-05 中铁二十五局集团第二工程有限公司 Construction process of large-span steel plate combination beam
CN114753253A (en) * 2022-03-08 2022-07-15 武汉市市政建设集团有限公司 Prefabricated beam bridge wet joint mold flying device and construction method
CN114717959A (en) * 2022-04-14 2022-07-08 中交第四公路工程局有限公司 Heat storage and heat preservation maintenance device for bridge wet joint concrete
CN114775447A (en) * 2022-05-26 2022-07-22 中国十七冶集团有限公司 Manufacturing and construction method of wet joint template of high pier stud bridge

Also Published As

Publication number Publication date
CN105525569B (en) 2017-04-19

Similar Documents

Publication Publication Date Title
CN105525569B (en) Bridge flange plate wet joint suspended formwork construction method
CN203768811U (en) Embedded steel anchor beam combined pylon anchoring structure
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN103161126A (en) Road bridge variable section hollow high pier slip-form construction method
CN205025086U (en) Strength nature skeleton concrete beam construction suspend template in midair
CN106638304A (en) UHPC-common-concrete-lamination composite bridge-deck-slab construction and constructing method thereof
CN103410320B (en) The tower silo flexibility platform bitubular connects sliding construction method
CN105178603A (en) EPS polyphenyl dismantling-exempt template concrete building cover plate construction technology method
CN104947719A (en) Basement roof post-cast strip hanging support formwork structure and post-cast strip construction method thereof
CN101781878A (en) Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof
CN206956565U (en) A kind of steel box girder bridge hogging moment area pre-stress system
CN106337361A (en) Separated fiber reinforced plastic (FRP)-concrete-steel composite girder bridge structure and construction method thereof
CN102661019A (en) Heat preservation and decoration integrated construction method for outer wall of building
CN111074795A (en) Construction method for pouring continuous beam in cantilever mode spanning existing railway
CN103510466B (en) Wet joint construction method of T-shaped beam bridge floor system
CN210597029U (en) Template suspension device for wet joint of bridge
CN108571166A (en) A kind of deformation joint formwork construction method
CN105019357B (en) The installation method of abnormity prefabricated bridge on a kind of arch bridge uncovered lattice girder steel
CN205036070U (en) Device is set up in complete pre -buried installation of cantilever frame roof beam side
CN213173317U (en) Be used for T roof beam wet seam construction equipment of encorbelmenting
CN210658035U (en) Draw to one side and hang knot supporting structure
CN206769199U (en) After wear formula post stretching vertical prestressing cast-in-place concrete rod structure
CN102535339A (en) Bracket for thin-wall hollow high-pier cantilever perfusing continuous beam and constructing method thereof
CN103469736B (en) Template supporting device of diaphragm plate of T-shaped bridge surface and template supporting and removing method
CN106284097B (en) The installation method that pier K is supportted on a kind of tubular arch bridge arch

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant