CN105447631A - Subway engineering tri-network intelligent control system and method thereof - Google Patents

Subway engineering tri-network intelligent control system and method thereof Download PDF

Info

Publication number
CN105447631A
CN105447631A CN201510783248.4A CN201510783248A CN105447631A CN 105447631 A CN105447631 A CN 105447631A CN 201510783248 A CN201510783248 A CN 201510783248A CN 105447631 A CN105447631 A CN 105447631A
Authority
CN
China
Prior art keywords
module
project
management
user
engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510783248.4A
Other languages
Chinese (zh)
Inventor
谌中平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUZHOU WORLD WAYEASY INTELLIGENT TECHNOLOGY Co Ltd
Original Assignee
SUZHOU WORLD WAYEASY INTELLIGENT TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUZHOU WORLD WAYEASY INTELLIGENT TECHNOLOGY Co Ltd filed Critical SUZHOU WORLD WAYEASY INTELLIGENT TECHNOLOGY Co Ltd
Priority to CN201510783248.4A priority Critical patent/CN105447631A/en
Publication of CN105447631A publication Critical patent/CN105447631A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • G06Q10/06375Prediction of business process outcome or impact based on a proposed change

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Educational Administration (AREA)
  • Operations Research (AREA)
  • Development Economics (AREA)
  • Marketing (AREA)
  • Game Theory and Decision Science (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a subway engineering tri-network intelligent control system and method thereof. The subway engineering tri-network intelligent control system includes a system function module, a project management module, a work module, a system management module, a report management module, and a video monitoring module. The project management module acquires the project management authority data via the system management module, the work module acquires the work module authority and user information data via the system function module, the system management module acquires the system management authority data and authority group data via the system function module, the report management module acquires the report authority data via the system function module, and the video monitoring module acquires the video monitoring data and data authority via the system function module. The system is used to provide accurate and timely information for decision-making levels and to promote management normalization and standardization, and facilities the implementation of the project management business norms of the management units.

Description

Subway engineering three nets intelligent managing and control system and method thereof
Technical field
The present invention relates to a kind of subway engineering three and net intelligent managing and control system and method thereof.
Background technology
At present, Metro Construction project has the features such as investment is large, the construction period is long, unit of taking part in building is many.To carry out comprehensively these engineering projects, effectively manage and control, reach and speed up the work, reduce construction costs, improve construction quality, guarantee safety construction, thus the strategic objective of Making high quality engineering, theory and the method for advanced project management must be adopted, utilize the means such as computer technology, network technology, infotech, set up an information integerated, resource sharing, powerful subway three net intelligent managing and control system, engineering construction project holistic management level and monitoring capacity could be improved like this.
Summary of the invention
The object of the invention is the deficiency overcoming prior art existence, provide a kind of subway engineering three to net intelligent managing and control system and method thereof.
Object of the present invention is achieved through the following technical solutions:
Subway engineering three nets intelligent managing and control system, feature is: comprise system function module, project management module, operational module, system management module, statement management module and video monitoring module, described system function module, for role-security management service, identity authentication service, SMS notification service, instant message service, event management service, data processing service, assembly and interface service;
Described project management module, for the overall process to project, omnibearing management, project enters system by project Registration Module, as the management starting point of project, carries out project information, stage, bid, contract, earth clearance management work to around project;
Described operational module, there is provided to user act on behalf matters prompting, notice bulletin information display, internal communication IM (InstantMessaging, instant messaging, real-time communication) message, outside inform by short message, the data query of routine work is provided, business reports and audit function;
Described system management module, provides and arranges the management of authority, unit, user;
Described statement management module, based on the electronic spreadsheet service of system function module, the each bore data of project of needs are extracted from project management module, various form is provided, comprises engineering Report Server Management, safety in production form, change in the work statistical report form, construction investment plan, legal affairs form;
Described video monitoring module, by the assembly, interface and the integrated functionality that provide in system function module, access video monitoring data, real-time viewing building site video, there is provided real-time video monitoring to priority project, risk node, check building-site situation whenever and wherever possible, playback history image.
Further, above-mentioned subway engineering three nets intelligent managing and control system, wherein, described project management module obtains project management permissions data by system function module, described operational module obtains operational module authority, user profile data by system function module, described system management module obtains system management permissions data and bundle of permissions data by system function module, described statement management module obtains form permissions data by system function module, and described video monitoring module obtains video monitoring data and data permission by system function module.
Further, above-mentioned subway engineering three nets intelligent managing and control system, wherein, described system function module comprises role-security administration module, authentication module, SMS notification module, instant message IM module, event manager module and data processing module, described role-security administration module, for leading subscriber table, authority list;
According to retrieval, comparing result, described authentication module, for the retrieval to subscriber's meter, contrast, to judge whether current login user is validated user and provides system service;
Described SMS notification module, for providing short message sending to user;
Described instant message IM module, allows to send mail, message by system between user, provides the real-time interaction between user;
Described event manager module, for monitoring and the scheduling of resource of event;
Described data processing module, for the write of data, amendment, inquiry.
Further, above-mentioned subway engineering three nets intelligent managing and control system, wherein, described project management module comprises project Registration Module, project control administration module, project earth clearance administration module, project contract management module and project examination and bid module, described project Registration Module, for the registration of project, so that project enters system, as the starting point of management;
Described project control administration module, the target advance of establishment project, generates Gantt chart, project key node and tracking, project cost control, project integration, project security management;
Described project earth clearance administration module, for management and the removing management of taking over the land for use, comprises expropriation of land administration module and removing management;
Described project contract management module, for managing the contract of project, and provides contract statistical form and working unit credit appraisal situation;
Described project examination and bid module, for examining and bidding management the stage of project, comprise project stage approval module and bidding management module.
Further, above-mentioned subway engineering three nets intelligent managing and control system, wherein, described operational module comprises todo list administration module notice bulletin module and routine work module, described todo list administration module, for carrying out statistics collection to active user's Pending tasks, and carry out todo list prompting in homepage;
Described notice bulletin module, allows user to arrange notice bulletin content, and Information issued is carried out information display to homepage;
Described routine work module, for the routine work content catering service of user, comprise message processing module, enquiry module and report module to a higher authorities for approval, message processing module based on instant message IM module for providing real-time interactive between user, enquiry module provides the data query service of system for user, and reporting module to a higher authorities for approval is that the business processing of user carries out reporting and examining.
Again further, above-mentioned subway engineering three nets intelligent managing and control system, wherein, described system management module comprises grouping priority assignation module, user arranges module and unit arranges module, grouping priority assignation module, based role authority management module, for user provides visual grouping priority assignation, grouping rights management is by actual business requirement, the rights of using of each module are divided into groups, form different authority combinations, then in user management module, the user specified is distributed in authority combination, thus realize the flexible management of user and authority, each user can have multiple groups, the union of multiple groups of authorities is exactly the authority that respective user has,
User arranges module, based role authority management module, the essential information of leading subscriber, authority, affiliated unit's information;
Unit arranges module, carries out information setting to management unit and unit of taking part in building, comprises management unit and arranges module and unit of taking part in building arranges module.
Again further, above-mentioned subway engineering three nets intelligent managing and control system, wherein, described statement management module comprises engineering statement management module, safety in production Reports module, change in the work statistical report form module, construction investment schedule module and legal affairs Reports module, described engineering statement management module, provides engineering form;
Safety in production Reports module, arranges engineering safety accident statistics bulletin, engineering safety accident statistics monthly magazine and scheme and summary;
Change in the work statistical report form module, lists design alteration Report List, and provide search, newly-increased, lack report project query, derive form, locking, unlock, return, submit to, make a report on, edit and delete;
Construction investment schedule module, lists year, season, Monthly Investment Plan tabular table in the works for construction investment, and provide search, newly-increased, lack report project query, derive form, locking, unlock, return, submit to, make a report on, edit and delete;
Legal affairs Reports module, arranges monthly contract statistical form, material items statistical form and case statistical form.
Subway engineering three of the present invention nets intelligent management-control method, comprises the following steps:
Steps A, parameters;
Step B, typing project information, include project in management;
Step C, according to inventory model, by project data import system, generate inventory;
Step D, actual development situation according to engineering, by the engineering staff of different rights, by the actual development data inputting of engineering, and generate engineering actual metered inventory;
Step e, according to priority assignation, the metering inventory of project examination personnel to typing carries out review operations;
Step F, list of engineering according to final review, synthetic time series form, and demonstrated by the figure of image.
The substantive distinguishing features that technical solution of the present invention is outstanding and significant progress are mainly reflected in:
Subway engineering three net intelligent managing and control system for providing analysis decision accurately necessary for decision-making level information timely, promote management standardization, standardization, be conducive to the engineering management business norms carrying out management unit.Engineering construction project data realize flattening and centralized management, and engineering construction project data acquisition is directly changed and facilitation, and data are directly inputted by project parties, stepwise disposal, promote the validity of management data, authenticity and promptness.Degree of depth excavation is carried out to data various in project management, generates various form flexibly, assist and carry out analysis and prediction.Improve the transparency of project management and the confidentiality of data.Be convenient to the business cooperation of engineering construction project, promote and link up efficiency, reduce and link up cost, realize effective accumulation of project management experience and data.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, technical solution of the present invention is described further:
Fig. 1: the configuration diagram of present system;
Fig. 2: the configuration diagram of system function module;
Fig. 3: the configuration diagram of project management module;
Fig. 4: the configuration diagram of operational module;
Fig. 5: the configuration diagram of system management module;
Fig. 6: the configuration diagram of statement management module.
Embodiment
As shown in Figure 1, subway engineering three nets intelligent managing and control system, comprise system function module 1, project management module 2, operational module 3, system management module 4, statement management module 5 and video monitoring module 6, system function module 1, for role-security management service, identity authentication service, SMS notification service, instant message service, event management service, data processing service, assembly and interface service;
Project management module 2, for the overall process to project, omnibearing management, project enters system by project Registration Module, as the management starting point of project, carries out project information, stage, bid, contract, earth clearance management work to around project;
Operational module 3, provides and acts on behalf the prompting of matters, information display, the IM message of internal communication, the outside inform by short message of notice bulletin to user, provide the data query of routine work, business reports and audit function;
System management module 4, provides and arranges the management of authority, unit, user;
Statement management module 5, based on the electronic spreadsheet service of system function module, from project management module, extract each bore data of project of needs, various form is provided, comprise engineering Report Server Management, safety in production form, change in the work statistical report form, construction investment plan, legal affairs form;
Video monitoring module 6, by the assembly, interface and the integrated functionality that provide in system function module, access video monitoring data, real-time viewing building site video, there is provided real-time video monitoring to priority project, risk node, check building-site situation whenever and wherever possible, playback history image.
Project management module 2 obtains project management permissions data by system function module 1, operational module 3 obtains operational module authority, user profile data by system function module 1, system management module 4 obtains system management permissions data and bundle of permissions data by system function module 1, statement management module 5 obtains form permissions data by system function module 1, and video monitoring module 6 obtains video monitoring data and data permission by system function module 1.
As shown in Figure 2, system function module 1 comprises role-security administration module 101, authentication module 102, SMS notification module 103, instant message IM module 104, event manager module 105 and data processing module 106, described role-security administration module 101, for leading subscriber table, authority list;
According to retrieval, comparing result, authentication module 102, for the retrieval to subscriber's meter, contrast, to judge whether current login user is validated user and provides system service;
SMS notification module 103, for providing short message sending to user;
Instant message IM module 104, allows to send mail, message by system between user, provides the real-time interaction between user;
Event manager module 105, for monitoring and the scheduling of resource of event;
Data processing module 106, for the write of data, amendment, inquiry.
As shown in Figure 3, project management module 2 comprises project Registration Module 201, project control administration module 202, project earth clearance administration module 203, project contract management module 204 and project examination and bid module 205, described project Registration Module 201, for the registration of project, so that project enters system, as the starting point of management;
Project control administration module 202, the target advance of establishment project, generates Gantt chart, project key node and tracking, project cost control, project integration, project security management;
Project earth clearance administration module 203, for management and the removing management of taking over the land for use, comprises expropriation of land administration module 206 and removing management 207;
Project contract management module 204, for managing the contract of project, and provides contract statistical form and working unit credit appraisal situation;
Project examination and bid module 205, for examining and bidding management the stage of project, comprise project stage approval module 208 and bidding management module 209.
As shown in Figure 4, operational module 3 comprises todo list administration module 301 and notifies bulletin module 302 and routine work module 303, described todo list administration module 301, for carrying out statistics collection to active user's Pending tasks, and carries out todo list prompting in homepage;
Notice bulletin module 302, allows user to arrange notice bulletin content, and Information issued is carried out information display to homepage;
Routine work module 303, for the routine work content catering service of user, comprise message processing module 304, enquiry module 305 and report module 306 to a higher authorities for approval, message processing module 304 based on instant message IM module for providing real-time interactive between user, enquiry module 305 provides the data query service of system for user, and reporting module 306 to a higher authorities for approval is that the business processing of user carries out reporting and examining.
As shown in Figure 5, system management module 4 comprises grouping priority assignation module 401, user arranges module 402 and unit arranges module 403, grouping priority assignation module 401, based role authority management module, for user provides visual grouping priority assignation, grouping rights management is by actual business requirement, the rights of using of each module are divided into groups, form different authority combinations, then in user management module, the user specified is distributed in authority combination, thus realize the flexible management of user and authority, each user can have multiple groups, the union of multiple groups of authorities is exactly the authority that respective user has,
User arranges module 402, based role authority management module, the essential information of leading subscriber, authority, affiliated unit's information;
Unit arranges module 403, carries out information setting to management unit and unit of taking part in building, comprises management unit and arranges module 404 and unit of taking part in building arranges module 405.
As shown in Figure 6, statement management module 5 comprises engineering statement management module 501, safety in production Reports module 502, change in the work statistical report form module 503, construction investment schedule module 504 and legal affairs Reports module 505, described engineering statement management module 501, provides engineering form;
Safety in production Reports module 502, arranges engineering safety accident statistics bulletin, engineering safety accident statistics monthly magazine and scheme and summary;
Change in the work statistical report form module 503, lists design alteration Report List, and provide search, newly-increased, lack report project query, derive form, locking, unlock, return, submit to, make a report on, edit and delete;
Construction investment schedule module 504, lists year, season, Monthly Investment Plan tabular table in the works for construction investment, and provide search, newly-increased, lack report project query, derive form, locking, unlock, return, submit to, make a report on, edit and delete;
Legal affairs Reports module 505, arranges monthly contract statistical form, material items statistical form and case statistical form.
Subway engineering three of the present invention nets intelligent management-control method, comprises the following steps:
Steps A, parameters;
Step B, typing project information, include project in management;
Step C, according to inventory model, by project data import system, generate inventory;
Step D, actual development situation according to engineering, by the engineering staff of different rights, by the actual development data inputting of engineering, and generate engineering actual metered inventory;
Step e, according to priority assignation, the metering inventory of project examination personnel to typing carries out review operations;
Step F, list of engineering according to final review, synthetic time series form, and demonstrated by the figure of image.
Subway engineering three net intelligent managing and control system for providing analysis decision accurately necessary for decision-making level information timely, adopt B/S framework, use MicrosoftVisualStudio2005 and MicrosoftSQLServer2005 database, utilize new frame and Rich Client Technology, comprise the technology such as online Word, Excel document editor.Powerful, greatly improve Consumer's Experience.
This system can promote management work regulation and standardization, is conducive to the engineering management business norms carrying out management unit.Engineering construction project data realize flattening and centralized management, and engineering construction project data acquisition is directly changed and facilitation, and data are directly inputted by project parties, stepwise disposal, promote the validity of management data, authenticity and promptness.Degree of depth excavation is carried out to data various in project management, generates various form flexibly, assist and carry out analysis and prediction.Improve the transparency of project management and the confidentiality of data.Be convenient to the business cooperation of engineering construction project, promote and link up efficiency, reduce and link up cost.Realize effective accumulation of project management experience and data, change the extensive management pattern of project construction.
It is to be understood that: the above is only the preferred embodiment of the present invention; for those skilled in the art; under the premise without departing from the principles of the invention, can also make some improvements and modifications, these improvements and modifications also should be considered as protection scope of the present invention.

Claims (8)

1. subway engineering three nets intelligent managing and control system, it is characterized in that: comprise system function module (1), project management module (2), operational module (3), system management module (4), statement management module (5) and video monitoring module (6), described system function module (1), for role-security management, authentication, SMS notification, instant message, incident management, data processing, assembly and interface service;
Described project management module (2), for the overall process to project, omnibearing management, project enters system by project Registration Module, as the management starting point of project, to carrying out project information, stage, bid, contract, earth clearance management around project;
Described operational module (3), provides and acts on behalf the prompting of matters, information display, the IM message of internal communication, the outside inform by short message of notice bulletin to user, reports for the data query of routine work, business and audits;
Described system management module (4), provides and arranges the management of authority, unit, user;
Described statement management module (5), based on the electronic spreadsheet service of system function module, the each bore data of project of needs are extracted from project management module, various form is provided, comprises engineering Report Server Management, safety in production form, change in the work statistical report form, construction investment plan, legal affairs form;
Described video monitoring module (6), by the assembly, interface and the integrated functionality that provide in system function module, access video monitoring data, real-time viewing building site video, real-time video monitoring is provided to priority project, risk node, check building-site situation whenever and wherever possible, playback history image.
2. subway engineering three according to claim 1 nets intelligent managing and control system, it is characterized in that: described project management module (2) obtains project management permissions data by system function module (1), described operational module (3) obtains operational module authority by system function module (1), user profile data, described system management module (4) obtains system management permissions data and bundle of permissions data by system function module (1), described statement management module (5) obtains form permissions data by system function module (1), described video monitoring module (6) obtains video monitoring data and data permission by system function module (1).
3. subway engineering three according to claim 1 nets intelligent managing and control system, it is characterized in that: described system function module (1) comprises role-security administration module (101), authentication module (102), SMS notification module (103), instant message IM module (104), event manager module (105) and data processing module (106), described role-security administration module (101), for leading subscriber table, authority list;
According to retrieval, comparing result, described authentication module (102), for the retrieval to subscriber's meter, contrast, to judge whether current login user is validated user and provides system service;
Described SMS notification module (103), for providing short message sending to user;
Described instant message IM module (104), allows to send mail, message by system between user, provides the real-time interaction between user;
Described event manager module (105), for monitoring and the scheduling of resource of event;
Described data processing module (106), for the write of data, amendment, inquiry.
4. subway engineering three according to claim 1 nets intelligent managing and control system, it is characterized in that: described project management module (2) comprises project Registration Module (201), project control administration module (202), project earth clearance administration module (203), project contract management module (204) and project examination and bid module (205), described project Registration Module (201), for the registration of project, so that project enters system, as the starting point of management;
Described project control administration module (202), the target advance of establishment project, generates Gantt chart, project key node and tracking, project cost control, project integration, project security management;
Described project earth clearance administration module (203), for management and the removing management of taking over the land for use, comprises expropriation of land administration module (206) and removing management module (207);
Described project contract management module (204), for managing the contract of project, and provides contract statistical form and working unit credit appraisal situation;
Described project examination and bid module (205), for examining and bidding management the stage of project, comprise project stage approval module (208) and bidding management module (209).
5. subway engineering three according to claim 1 nets intelligent managing and control system, it is characterized in that: described operational module (3) comprises todo list administration module (301) notice bulletin module (302) and routine work module (303), described todo list administration module (301), for carrying out statistics collection to active user's Pending tasks, and carry out todo list prompting in homepage;
Described notice bulletin module (302), allows user to arrange notice bulletin content, and Information issued is carried out information display to homepage;
Described routine work module (303), for the routine work content catering service of user, comprise message processing module (304), enquiry module (305) and report module (306) to a higher authorities for approval, message processing module (304) based on instant message IM module for providing real-time interactive between user, enquiry module (305) provides the data query service of system for user, reports the business processing that module (306) is user to a higher authorities for approval and carries out reporting and examining.
6. subway engineering three according to claim 1 nets intelligent managing and control system, it is characterized in that: described system management module (4) comprises grouping priority assignation module (401), user arranges module (402) and unit arranges module (403), grouping priority assignation module (401), based role authority management module, for user provides visual grouping priority assignation, grouping rights management is by actual business requirement, the rights of using of each module are divided into groups, form different authority combinations, then in user management module, the user specified is distributed in authority combination, thus realize the flexible management of user and authority, each user can have multiple groups, the union of multiple groups of authorities is exactly the authority that respective user has,
User arranges module (402), based role authority management module, the essential information of leading subscriber, authority, affiliated unit's information;
Unit arranges module (403), carries out information setting to management unit and unit of taking part in building, comprises management unit and arranges module (404) and unit of taking part in building arranges module (405).
7. subway engineering three according to claim 1 nets intelligent managing and control system, it is characterized in that: described statement management module (5) comprises engineering statement management module (501), safety in production Reports module (502), change in the work statistical report form module (503), construction investment schedule module (504) and legal affairs Reports module (505), described engineering statement management module (501), provides engineering form;
Safety in production Reports module (502), arranges engineering safety accident statistics bulletin, engineering safety accident statistics monthly magazine and scheme and summary;
Change in the work statistical report form module (503), lists design alteration Report List, and provide search, newly-increased, lack report project query, derive form, locking, unlock, return, submit to, make a report on, edit and delete;
Construction investment schedule module (504), list year, season, Monthly Investment Plan tabular table in the works for construction investment, and provide search, newly-increased, lack report project query, derive form, locking, unlock, return, submit to, make a report on, edit and delete;
Legal affairs Reports module (505), arranges monthly contract statistical form, material items statistical form and case statistical form.
8. system described in claim 1 realizes subway engineering three and nets intelligent management-control method, it is characterized in that: comprise the following steps:
Steps A, parameters;
Step B, typing project information, include project in management;
Step C, according to inventory model, by project data import system, generate inventory;
Step D, actual development situation according to engineering, by the engineering staff of different rights, by the actual development data inputting of engineering, and generate engineering actual metered inventory;
Step e, according to priority assignation, the metering inventory of project examination personnel to typing carries out review operations;
Step F, list of engineering according to final review, synthetic time series form, and demonstrated by the figure of image.
CN201510783248.4A 2015-11-16 2015-11-16 Subway engineering tri-network intelligent control system and method thereof Pending CN105447631A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510783248.4A CN105447631A (en) 2015-11-16 2015-11-16 Subway engineering tri-network intelligent control system and method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510783248.4A CN105447631A (en) 2015-11-16 2015-11-16 Subway engineering tri-network intelligent control system and method thereof

Publications (1)

Publication Number Publication Date
CN105447631A true CN105447631A (en) 2016-03-30

Family

ID=55557779

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510783248.4A Pending CN105447631A (en) 2015-11-16 2015-11-16 Subway engineering tri-network intelligent control system and method thereof

Country Status (1)

Country Link
CN (1) CN105447631A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106547892A (en) * 2016-11-01 2017-03-29 山东浪潮云服务信息科技有限公司 A kind of data resource management platform gathered based on internet data
CN106682839A (en) * 2016-12-30 2017-05-17 天津市测绘院 Showing method and device for construction item management information
CN106779509A (en) * 2017-03-21 2017-05-31 武汉微诚科技股份有限公司 A kind of visual workflow automotive engine system
CN107016530A (en) * 2017-04-24 2017-08-04 广西民族师范学院 A kind of Venture projects intelligent management system
CN110516926A (en) * 2019-08-08 2019-11-29 浙江大学城市学院 A kind of data processing cloud platform system based on subway protection automatic monitoring
CN113344540A (en) * 2021-06-22 2021-09-03 上海外高桥造船有限公司 Project cooperative control system and method, electronic device and storage medium

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101504741A (en) * 2009-02-18 2009-08-12 路桥集团国际建设股份有限公司 Intelligent metering management system and method for construction engineering
US20110126111A1 (en) * 2009-11-20 2011-05-26 Jasvir Singh Gill Method And Apparatus For Risk Visualization and Remediation
CN104463439A (en) * 2014-11-21 2015-03-25 王新明 Highway engineering project managing system and method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101504741A (en) * 2009-02-18 2009-08-12 路桥集团国际建设股份有限公司 Intelligent metering management system and method for construction engineering
US20110126111A1 (en) * 2009-11-20 2011-05-26 Jasvir Singh Gill Method And Apparatus For Risk Visualization and Remediation
CN104463439A (en) * 2014-11-21 2015-03-25 王新明 Highway engineering project managing system and method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
胡荣明等: "远程城市地铁施工测量管理模式的研究", 《西北大学学报(自然科学版)》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106547892A (en) * 2016-11-01 2017-03-29 山东浪潮云服务信息科技有限公司 A kind of data resource management platform gathered based on internet data
CN106682839A (en) * 2016-12-30 2017-05-17 天津市测绘院 Showing method and device for construction item management information
CN106779509A (en) * 2017-03-21 2017-05-31 武汉微诚科技股份有限公司 A kind of visual workflow automotive engine system
CN107016530A (en) * 2017-04-24 2017-08-04 广西民族师范学院 A kind of Venture projects intelligent management system
CN110516926A (en) * 2019-08-08 2019-11-29 浙江大学城市学院 A kind of data processing cloud platform system based on subway protection automatic monitoring
CN113344540A (en) * 2021-06-22 2021-09-03 上海外高桥造船有限公司 Project cooperative control system and method, electronic device and storage medium

Similar Documents

Publication Publication Date Title
CN105447631A (en) Subway engineering tri-network intelligent control system and method thereof
CN105243518A (en) Municipal engineering measurement management system and method thereof
CN108009758B (en) BIM-based intelligent management method for field construction materials
CN110765337A (en) Service providing method based on internet big data
CN203165006U (en) Engineering project management system
CN105260857A (en) Intelligent management system and method thereof for rural migrant workers
CN107977795A (en) A kind of government procurement manages transaction system
CN107766579A (en) The design method of master data management system based on XBRL standards
CN105184642A (en) Comprehensive tax administration platform
CN108960456A (en) Private clound secure, integral operation platform
CN104376430A (en) Hidden risk management system based on cloud service platform and implementing method of hidden risk management system
CN104463439A (en) Highway engineering project managing system and method
CN106875155A (en) A kind of chain of command
Qing et al. Quality risk management model for railway construction projects
CN104200325A (en) Management system and method of enterprise technology center
CN104572615A (en) Method and system for on-line case investigation processing
CN107730430A (en) Production, teaching & research public service system based on big data
CN103258261A (en) Production management system and production management method based on RFID technology
CN104408587A (en) Government project management information system
CN110647567B (en) Power failure plan auxiliary decision system based on end data fusion
CN102663645A (en) Integrated management system of investment bank and realization method thereof
CN112988865B (en) Industrial Internet service management system
CN108154340A (en) Prefabricated component informationization management system based on BIM cloud platforms
CN107437133A (en) A kind of property centralized management platform
CN105225051A (en) Project management system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160330

RJ01 Rejection of invention patent application after publication