CN105442855B - A kind of high-precision buried equipment, method of large scale embedded board - Google Patents

A kind of high-precision buried equipment, method of large scale embedded board Download PDF

Info

Publication number
CN105442855B
CN105442855B CN201511011212.0A CN201511011212A CN105442855B CN 105442855 B CN105442855 B CN 105442855B CN 201511011212 A CN201511011212 A CN 201511011212A CN 105442855 B CN105442855 B CN 105442855B
Authority
CN
China
Prior art keywords
embedded board
equipment
steel bar
long steel
bar end
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201511011212.0A
Other languages
Chinese (zh)
Other versions
CN105442855A (en
Inventor
所明义
刘金平
刘欢
杨灵武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201511011212.0A priority Critical patent/CN105442855B/en
Publication of CN105442855A publication Critical patent/CN105442855A/en
Application granted granted Critical
Publication of CN105442855B publication Critical patent/CN105442855B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention provides a kind of high-precision buried equipment, method of large scale embedded board.According to sequence of construction, including have the following steps:Site inspection underlying basis bar-mat reinforcement is distributed, long steel bar end is welded in embedded board bottom relevant position, then track, track girder and equipment bay are assembled by design requirement, it is required that embedded board and the seamless and spot welding of equipment bay close contact are firm, using driving a vehicle equipment integral hoisting to installation site, absolute altitude is looked for by code requirement levelling capturing, takes auxiliary part to fix equipment, the long steel bar end in embedded board bottom and reinforcement foundation net are welded, is finally poured with High Strength Non-shrinking Filling Material.The present invention is simple to operate, practical, can greatly improve centering operating efficiency, conscientiously ensure installation accuracy, effectively reduce cost, when solving conventional construction technique and pouring, reinforcing bar carrying is big yielding, and connection machinery vibrates and basic rising-heat contracting-cold influences on buried plate precision.

Description

A kind of high-precision buried equipment, method of large scale embedded board
Technical field
The present invention relates to large scale equipment installation Technology field, and in particular to a kind of large scale embedded board is embedded in high precision Method.
Background technology
Pickling flat line step rate walking support system includes track, track girder, equipment bay.In installation process, rail Do not allow to set adjusting pad between road and track girder, track girder and equipment bay, equipment bay and embedded board, directly once pacify Dress is in place, requires high to embedded board embedding precision.Conventional method is first by embedded board by designed elevation and centrally disposed, anchoring piece It is welded and fixed with reinforcement foundation, then primary concreting, big yielding, the concreting machinery in casting process of the method reinforcing bar carrying Vibrate easy movement, basic rising-heat contracting-cold easily waits and all buried plate can be had an impact so that embedded board be unable to reach design accuracy will Ask, many difficulties are caused to equipment installation.
Built-in fitting is to stay to set component in concrete structure, is mainly made up of steel plate and anchor rib.Main function is connection Structural elements or non-structural element, it is divided into force bearing embedded part and two kinds of built-in fitting of construction, wherein force bearing embedded part is primarily subjected to lotus Carry.Under normal circumstances, built-in fitting can be the dowel for being embedded in inside concrete, can also be the exposed anchor in concrete surface Plate.It is the important component for ensureing engineering structure in any operating mode stability inferior, in civil engineering when built-in fitting connects as structure In engineering construction, it is necessary to the technical essential for catching built-in fitting to construct, quality control efforts, especially large scale embedded board are carried out, Embedding precision is higher, and difficulty is bigger.
The content of the invention
The technical problems to be solved by the invention are to be directed to above-mentioned deficiency, there is provided one kind solves traditional handicraft once Property pouring reinforcement carrying it is big yielding;Concreting machinery vibrates caused vibration displacement in casting process;Basic rising-heat contracting-cold production The problems such as lively displacement, ensure the high-precision buried equipment, method of large scale embedded board of embedded board installation accuracy.
The technical solution adopted for the present invention to solve the technical problems is:
A kind of high-precision buried equipment, method of large scale embedded board, it is characterised in that according to sequence of construction, include following step Suddenly:
Site inspection underlying basis bar-mat reinforcement is distributed, and long steel bar end is welded in embedded board bottom relevant position, then by rail Road, track girder and equipment bay are assembled by design requirement, it is desirable to which embedded board is in close contact seamless and spot welding with equipment bay Firmly, using driving a vehicle equipment integral hoisting to installation site, absolute altitude is looked for by code requirement levelling capturing, takes auxiliary part will Equipment is fixed, and the welding long steel bar end in embedded board bottom and reinforcement foundation net, is finally poured with High Strength Non-shrinking Filling Material.
Specific workflow is:
(1)It wouldn't pour the concrete of 300mm regions below embedded board is reserved, according to reinforcement foundation net distribution situation, Weld long steel bar end in embedded board bottom relevant position;
(2)Track, track girder and equipment bay are assembled by drawing, and by embedded board and equipment bay spot welding;
(3)By embedded board and equipment integral installation in design attitude, and by drawing by equipment centering;
(4)The long steel bar end in embedded board bottom and reinforcement foundation net firm welding, finally poured with High Strength Non-shrinking Filling Material Build remaining 300mm regions;
(5)After embedded board is buried well, when pouring, it should be noted that protection embedded board;The vibrating head of concrete construction is pre- Buried plate side should extend vibrating time, ensure that the concrete on embedded board periphery is closely knit, avoid producing spillage and hollowing phenomenon, influence embedded board Quality.
The present invention principle be:
According to equipment feature and construction condition, research tilts installation site overweight equipment hoisting technology, sets two Extended type hanging axis extends equipment suspension centre, realizes that the vertical stress of two-shipper plate hook beam lifts in workshop.Field condition effectively is utilized, is dropped Low difficulty of construction, save construction cost.
The beneficial effect comprise that:
By large scale embedded board burying technology, after equipment installation is in place, one-piece casting is carried out.Solves conventional construction When technique pours, reinforcing bar carrying is big yielding, and connection machinery vibrates and basic rising-heat contracting-cold influences on buried plate precision.Operation letter It is single, it is practical.Centering operating efficiency can be greatly improved, ensures installation accuracy conscientiously, effectively reduces cost.
Brief description of the drawings
Fig. 1 is the structural representation of the embodiment of the present invention
In figure:1- embedded boards;2- equipment bays;3- track girders;4- tracks;5- rail pressing plates;6- connecting bolts;The long steel of 7- Muscle head;8- reinforcement foundation nets.
Embodiment
With reference to embodiment, the present invention is further illustrated:
The high-precision buried equipment, method of large scale embedded board as shown in Figure 1, according to sequence of construction, including has the following steps:
Embedded board 300mm regions concrete below 1, which are reserved, to be poured, according to the distribution situation of reinforcement foundation net 8, pre- Weld long steel bar end 7 in the bottom relevant position of buried plate 1;
Track 4, track girder 3, rail pressing plate 5 are fixed by the installation of connecting bolt 6, and press drawing with equipment bay 2 It is required that assemble, and by embedded board 1 and the spot welding of equipment bay 2;
By embedded board 1 and equipment integral installation in design attitude, and by drawing by equipment centering;
The long steel bar end 7 in the bottom of embedded board 1 and the firm welding of reinforcement foundation net 8, finally poured with High Strength Non-shrinking Filling Material Build remaining 300mm regions;
After embedded board 1 is buried well, when pouring, it should be noted that protection embedded board 1;The vibrating head of concrete construction is pre-buried The side of plate 1 should extend vibrating time, ensure that the concrete on the periphery of embedded board 1 is closely knit, avoid producing spillage and hollowing phenomenon, influence embedded board 1 mass.
The embodiment of the present invention after equipment installation is in place, carries out one-piece casting by large scale embedded board burying technology.Solution When conventional construction technique of having determined pours, reinforcing bar carrying is big yielding, and connection machinery vibrates and basic rising-heat contracting-cold is to buried plate essence Degree influences.It is simple to operate, it is practical.Centering operating efficiency can be greatly improved, ensure installation accuracy conscientiously, effectively reduce into This.
The right model described above for being only the Application Example of the present invention, the present invention can not being limited with this certainly Enclose, therefore the equivalence changes made according to scope of the present invention patent, still belong to protection scope of the present invention.

Claims (1)

1. a kind of high-precision buried equipment, method of large scale embedded board, it is characterised in that according to sequence of construction, including have the following steps:
Site inspection underlying basis bar-mat reinforcement is distributed, and long steel bar end is welded in embedded board bottom relevant position, then by track, rail Road beam is assembled with equipment bay by design requirement, it is desirable to and embedded board and the seamless and spot welding of equipment bay close contact are firm, Using driving a vehicle equipment integral hoisting to installation site, absolute altitude is looked for by code requirement levelling capturing, takes auxiliary part by equipment It is fixed, the welding long steel bar end in embedded board bottom and reinforcement foundation net, finally poured with High Strength Non-shrinking Filling Material;
Specific workflow is:
(1)The concrete of 300mm regions below embedded board, which is reserved, to be poured, according to reinforcement foundation net distribution situation, pre-buried Weld long steel bar end in plate bottom relevant position;
(2)Track, track girder and equipment bay are assembled by drawing, and by embedded board and equipment bay spot welding;
(3)By embedded board and equipment integral installation in design attitude, and by drawing by equipment centering;
(4)The long steel bar end in embedded board bottom and reinforcement foundation net firm welding, finally poured with High Strength Non-shrinking Filling Material surplus Remaining 300mm regions;
(5)After embedded board is buried well, when pouring, it should be noted that protection embedded board;The vibrating head of concrete construction is in embedded board Side should extend vibrating time, ensure that the concrete on embedded board periphery is closely knit, avoid producing spillage and hollowing phenomenon, influence embedded board matter Amount.
CN201511011212.0A 2015-12-30 2015-12-30 A kind of high-precision buried equipment, method of large scale embedded board Active CN105442855B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201511011212.0A CN105442855B (en) 2015-12-30 2015-12-30 A kind of high-precision buried equipment, method of large scale embedded board

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201511011212.0A CN105442855B (en) 2015-12-30 2015-12-30 A kind of high-precision buried equipment, method of large scale embedded board

Publications (2)

Publication Number Publication Date
CN105442855A CN105442855A (en) 2016-03-30
CN105442855B true CN105442855B (en) 2018-03-09

Family

ID=55553445

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201511011212.0A Active CN105442855B (en) 2015-12-30 2015-12-30 A kind of high-precision buried equipment, method of large scale embedded board

Country Status (1)

Country Link
CN (1) CN105442855B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107131761B (en) * 2017-05-03 2019-04-26 中国二十冶集团有限公司 Tilting equipment installation method
CN115246052A (en) * 2021-12-16 2022-10-28 李俊 Simplified ore crusher feed opening light rail welding method
CN115055857A (en) * 2022-06-30 2022-09-16 重庆中环建设有限公司 Method for embedding rail of cement mineral aggregate blanking bin

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1060913A (en) * 1996-08-14 1998-03-03 Sumitomo Metal Ind Ltd Installation method for machine equipment
CN101307605A (en) * 2008-06-06 2008-11-19 中冶天工上海十三冶建设有限公司 High precision apparatus foundation mounting method
CN102134879A (en) * 2011-01-12 2011-07-27 陕西建工集团第六建筑工程有限公司 Embedding accuracy control construction method for embedded part of overlong equipment foundation platform
CN103276747A (en) * 2013-06-26 2013-09-04 陕西建工集团第十一建筑工程有限公司 One-time high-accuracy pre-burying construction method for large equipment base guide rails
CN103352476A (en) * 2013-07-22 2013-10-16 陕西建工集团第十一建筑工程有限公司 Large-scale bolt high-precision pre-burying construction method
CN103388343A (en) * 2013-07-31 2013-11-13 天津二十冶建设有限公司 Super-long and large horizontal embedded part reverse construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1060913A (en) * 1996-08-14 1998-03-03 Sumitomo Metal Ind Ltd Installation method for machine equipment
CN101307605A (en) * 2008-06-06 2008-11-19 中冶天工上海十三冶建设有限公司 High precision apparatus foundation mounting method
CN102134879A (en) * 2011-01-12 2011-07-27 陕西建工集团第六建筑工程有限公司 Embedding accuracy control construction method for embedded part of overlong equipment foundation platform
CN103276747A (en) * 2013-06-26 2013-09-04 陕西建工集团第十一建筑工程有限公司 One-time high-accuracy pre-burying construction method for large equipment base guide rails
CN103352476A (en) * 2013-07-22 2013-10-16 陕西建工集团第十一建筑工程有限公司 Large-scale bolt high-precision pre-burying construction method
CN103388343A (en) * 2013-07-31 2013-11-13 天津二十冶建设有限公司 Super-long and large horizontal embedded part reverse construction method

Also Published As

Publication number Publication date
CN105442855A (en) 2016-03-30

Similar Documents

Publication Publication Date Title
CN104746422B (en) A kind of hollow pier stud delay-pour joint structure of bridge prefabrication and construction method
CN104294753B (en) A kind of hollow pier stud syndeton of bridge prefabrication and construction
CN107268424B (en) Can fast leveling precast assembly bridge pier structure and its construction method
CN109853381B (en) Transitional structure for preventing bridge head from jumping and construction method thereof
CN105442855B (en) A kind of high-precision buried equipment, method of large scale embedded board
CN211036679U (en) Socket joint connection structure of prefabricated pier stud of assembled bridge and cushion cap
CN102021889A (en) Bridge erection method
CN108035594A (en) The prefabricated decompression cone construction method of concrete silo structure
CN104088291A (en) Annular wedge combined concrete precast block tower crane foundation
CN110847010B (en) Construction and construction method suitable for large-span abutment rigid frame bridge
CN204097864U (en) A kind of bridge prefabrication hollow pier stud delay-pour joint structure
CN209194353U (en) It is a kind of to ride integral type bracket suitable for the construction of Bridge High-pier 0# block
CN104929047A (en) V-shaped pier outer support construction method
CN105752864B (en) Derrick crane adheres to node and its construction method
CN108643429B (en) But height-adjusting's assembled coincide floor
CN101839063B (en) Movable steel base for constructing prefabricated beam and standard joint thereof
CN210768051U (en) Be applied to prefabricated assembled isolation bearing of shear wall structure
CN201671063U (en) Movable steel base for construction precast beams and standard knot thereof
CN203891060U (en) Permanent steel pipe column positioning system of major structure of cover and excavation top-down station
CN204174527U (en) The hollow pier stud syndeton of a kind of bridge prefabrication
CN206784159U (en) A kind of bridge girder anti-seismic bearing
CN102535496A (en) Expanded pier structure and forming method thereof
CN102644379A (en) Temporary supporting system of steel column base and construction method of temporary supporting system
CN214883824U (en) Pre-leveling tower foundation
CN102251536B (en) Vertical positioning connecting structure of base frame of tower mast type mechanical equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant