CN105422624B - Debugging method for oil clearance of motor bearing - Google Patents

Debugging method for oil clearance of motor bearing Download PDF

Info

Publication number
CN105422624B
CN105422624B CN201510741009.2A CN201510741009A CN105422624B CN 105422624 B CN105422624 B CN 105422624B CN 201510741009 A CN201510741009 A CN 201510741009A CN 105422624 B CN105422624 B CN 105422624B
Authority
CN
China
Prior art keywords
bearing
value
pressure oil
shift value
oil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510741009.2A
Other languages
Chinese (zh)
Other versions
CN105422624A (en
Inventor
刘海云
赵继武
王松涛
潘彪
王文忠
詹美珠
张宏杰
高文华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shougang Jingtang United Iron and Steel Co Ltd
Original Assignee
Shougang Jingtang United Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shougang Jingtang United Iron and Steel Co Ltd filed Critical Shougang Jingtang United Iron and Steel Co Ltd
Priority to CN201510741009.2A priority Critical patent/CN105422624B/en
Publication of CN105422624A publication Critical patent/CN105422624A/en
Application granted granted Critical
Publication of CN105422624B publication Critical patent/CN105422624B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16CSHAFTS; FLEXIBLE SHAFTS; ELEMENTS OR CRANKSHAFT MECHANISMS; ROTARY BODIES OTHER THAN GEARING ELEMENTS; BEARINGS
    • F16C32/00Bearings not otherwise provided for
    • F16C32/06Bearings not otherwise provided for with moving member supported by a fluid cushion formed, at least to a large extent, otherwise than by movement of the shaft, e.g. hydrostatic air-cushion bearings
    • F16C32/0662Details of hydrostatic bearings independent of fluid supply or direction of load
    • F16C32/067Details of hydrostatic bearings independent of fluid supply or direction of load of bearings adjustable for aligning, positioning, wear or play
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16CSHAFTS; FLEXIBLE SHAFTS; ELEMENTS OR CRANKSHAFT MECHANISMS; ROTARY BODIES OTHER THAN GEARING ELEMENTS; BEARINGS
    • F16C32/00Bearings not otherwise provided for
    • F16C32/06Bearings not otherwise provided for with moving member supported by a fluid cushion formed, at least to a large extent, otherwise than by movement of the shaft, e.g. hydrostatic air-cushion bearings
    • F16C32/0629Bearings not otherwise provided for with moving member supported by a fluid cushion formed, at least to a large extent, otherwise than by movement of the shaft, e.g. hydrostatic air-cushion bearings supported by a liquid cushion, e.g. oil cushion
    • F16C32/064Bearings not otherwise provided for with moving member supported by a fluid cushion formed, at least to a large extent, otherwise than by movement of the shaft, e.g. hydrostatic air-cushion bearings supported by a liquid cushion, e.g. oil cushion the liquid being supplied under pressure
    • F16C32/0644Details of devices to control the supply of liquids to the bearings
    • F16C32/0648Details of devices to control the supply of liquids to the bearings by sensors or pressure-responsive control devices in or near the bearings
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02KDYNAMO-ELECTRIC MACHINES
    • H02K5/00Casings; Enclosures; Supports
    • H02K5/04Casings or enclosures characterised by the shape, form or construction thereof
    • H02K5/16Means for supporting bearings, e.g. insulating supports or means for fitting bearings in the bearing-shields

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Power Engineering (AREA)
  • Sliding-Contact Bearings (AREA)
  • Motor Or Generator Frames (AREA)
  • Manufacture Of Motors, Generators (AREA)

Abstract

The invention relates to the field of static pressure sliding bearings, and discloses a method for debugging an oil clearance of a motor bearing, which aims to solve the technical problem that the value of the oil clearance of the bearing debugged in the prior art is not accurate enough.

Description

A kind of adjustment method of the oil clearance of bearing for electric machine
Technical field
The present invention relates to static-pressure sliding bearing field, more particularly to a kind of adjustment method of the oil clearance of bearing for electric machine.
Background technology
In the maintenance work of the roughing main motor of large-scale thin plate continuous hot-rolling mill, it is often necessary to debug each axle of roughing main motor The extreme pressure lubricant oil clearance held.Generally, the measurement of the oil clearance is to start axle near antero posterior axis bearing by measuring high-pressure oil pump The difference of face height change is realized.The adjustment method of such roughing main motor sliding bearing oil clearance of prior art typically has It is following two:
First method is to maintain motor and is in the simple adjustment method of connecting shaft state with transmission connecting shaft.
Second method is to separate the roughing main motor and transmission connecting shaft dismounting, then individually carries out roughing main motor The debugging of high-tension lubrication oil clearance, again transmission connecting shaft is recovered to install after the completion of debugging efforts.
Prior art above two method common ground is only to place a dial gauge near each bearing block at axial plane.
Above-mentioned first method, regard roughing motor shaft as a preferable rigid body, do not consider motor shaft by various Pressure influence and produce the bending on microcosmic, thus when carrying out motor bearings high-tension lubrication oil clearance debugging efforts, it is assumed that bearing The height change of axial plane is equal with the change of corresponding shaft bearing high pressure oil clearance near seat, so only placing one near each bearing block Individual dial gauge.Its advantage is simple to operate, is easily realized, but its shortcoming is as follows, and motor shaft is being kept and transmission connecting shaft connecting shaft shape During state, by the transmission connecting shaft is under different conditions and caused different pressures are influenceed, motor shaft is formed on microcosmic Elastic bending, the number range of motor bearings oil clearance is decimillimeter level, and the influence of above-mentioned motor bending shaft is just in this order of magnitude model Within enclosing, therefore, the lubricant oil gap measured by the method will produce very important error.
Above-mentioned second method is to separate main motor and transmission connecting shaft dismounting, is then individually carrying out main motor bearing Extreme pressure lubricant oil clearance is debugged, and recovers to install again after the completion of debugging efforts.But for such large-scale roughing mill, transmission connecting shaft Length is more than 10 meters, and weight is at 55 tons or so, and the workload that it is dismounted is very big, and time-consuming, efficiency is low, typically stopping in short-term Machine periodical repair can not be realized.And the monomer of motor bearings oil clearance debugs, connecting shaft different from actual working state during motor connecting shaft Motor shaft stressing conditions change afterwards, equally also result in bearing oil clearance tune-up data inaccuracy.
Therefore, technical problem not accurate enough when measuring the bearing oil clearance value debugged in the prior art be present.
The content of the invention
The invention provides a kind of adjustment method of the oil clearance of bearing for electric machine, to solve present in prior art to institute Not accurate enough technical problem during the bearing oil clearance value measurement of debugging.
The embodiment of the present invention provides a kind of adjustment method of the oil clearance of bearing for electric machine, and the motor includes being used to export turning The motor shaft of square, close external load for supporting the motor shaft an end fore bearing and for supporting the electricity The rear bearing of another end of the remote external load of arbor, the motor shaft is close to an end of the external load Portion is connected to an end of transmission connecting shaft, and another end of the transmission connecting shaft is connected with the external load, described Transmission connecting shaft is rotated by spindle support member supports, and the lower bearing of the fore bearing is provided with for the motor shaft to be jacked up Fore bearing pressure oil jacks hole, and the rear bearing pressure oil overhold that the rear bearing is provided with for the motor shaft to be jacked up rises hole, It is rotatably connected at the top of the transmission connecting shaft support member with the transmission connecting shaft, and the support force of the support member is pre- first If can adjust in scope, pressure oil is controlled jacks hole and the rear bearing pressure oil overhold liter from the fore bearing pressure oil respectively Hole is sprayed so that the motor shaft to be jacked up, and methods described includes:
S1:The support pressure for keeping the transmission connecting shaft support member is zero and stops the motor bearings pressure oil It is supplied to the fore bearing pressure oil jacking hole and the rear bearing pressure oil overhold rises hole;
S2:It is located in the motor shaft at the fore bearing and fore bearing is set respectively along the bearing block both sides in shaft extension direction Seat front height measuring instrument and front-end bearing pedestal posterior height measuring instrument, and in the motor shaft on front side of the rear bearing block Height-gauge is set;
S3:The support pressure is adjusted to pressure corresponding when the external load works;
S4:Record the first front-end bearing pedestal front height shift value, the institute that the front-end bearing pedestal front height measuring instrument measures State the first front-end bearing pedestal posterior height shift value and rear bearing block front side height that front-end bearing pedestal posterior height measuring instrument measures The first rear bearing block front height shift value that degree measuring instrument measures;
S5:Open the fore bearing pressure oil jacking hole and the rear bearing pressure oil overhold rises the pressure oil supply in hole;
S6:Record the second front-end bearing pedestal front height shift value, the institute of the front-end bearing pedestal front height measuring instrument measurement State high on front side of the second front-end bearing pedestal posterior height shift value and the rear bearing block of front-end bearing pedestal posterior height measuring instrument measurement Spend the second rear bearing block front height shift value of measuring instrument measurement;
S7:Based on the first front-end bearing pedestal front height shift value, the first front-end bearing pedestal posterior height shift value, The first rear bearing block front height shift value, the second front-end bearing pedestal front height shift value, second fore bearing Seat posterior height shift value, the second rear bearing block front height shift value obtain the value of oil clearance to calculate;
S8:If the value of the oil clearance in the second preset range, will be fed separately to the fore bearing pressure oil overhold The pressure for rising the pressure oil in hole and the rear bearing pressure oil overhold liter hole uses as a result;If the value of the oil clearance is not pre- Determine in scope, be then fed separately to the fore bearing pressure oil jacking hole and the rear bearing according to the value of the oil clearance to adjust The pressure of the pressure oil in pressure oil jacking hole, and step S6-S8 is performed again, until the value of the oil clearance is default described second In the range of.
Alternatively, it is described based on high on rear side of the first front-end bearing pedestal front height shift value, first front-end bearing pedestal Spend shift value, the first rear bearing block front height shift value, the second front-end bearing pedestal front height shift value, described the Two front-end bearing pedestal posterior height shift values, the second rear bearing block front height shift value obtain the oil clearance to calculate Value, it is specially:
The first front-end bearing pedestal front height shift value is designated as haB51, by the first front-end bearing pedestal posterior height position Shifting value is designated as haB52, the first rear bearing block front height shift value is designated as haB3, will be high on front side of second front-end bearing pedestal Degree shift value is designated as hbB51, the second front-end bearing pedestal posterior height shift value is designated as haB52, before second rear bearing block Side height displacement value is designated as hbB3
gB5=hbB5-haB5, wherein, hbB5=(hbB52+hbB51)/2, haB5=(haB52+haB51)/2, gB5For the motor The oil clearance value of front-end bearing pedestal;
gB3=hbB3-haB3, wherein gB3For the oil clearance value of the rear bearing block of the motor.
Alternatively, the value according to the oil clearance is fed separately to the fore bearing pressure oil jacking hole and institute to adjust The pressure that rear bearing pressure oil overhold rises the pressure oil in hole is stated, is specifically included:
When corresponding shaft bearing oil clearance value is less than the minimum value of second preset range, the pressure piping of big corresponding shaft bearing is opened Choke valve;
When corresponding shaft bearing oil clearance value is more than the maximum of second preset range, the pressure piping of corresponding shaft bearing is turned down Choke valve.
Alternatively, second preset range is:0.07mm is between 0.15mm.
One or more technical scheme in the embodiment of the present invention, at least has the following technical effect that or advantage:
1st, the adjustment method of the oil clearance of bearing for electric machine provided in an embodiment of the present invention need not be by motor and drive shaft system Split, it becomes possible to detect the bearing oil clearance value of motor, avoid because by motor and after being split with drive shaft system again Cause the inaccurate technical problem of bearing oil clearance value after assembling, so as to reach the more accurate skill of bearing oil clearance value detected Art effect, also, save workload and the time of dismounting motor and drive shaft system;
2nd, a measuring instrument is respectively placed in the front-end bearing pedestal front and rear sides axial plane of motor, is so directed to the same part of bearing Multiple sampled values can be obtained, and then can further improve the precision of the oil clearance value of detected bearing.
Brief description of the drawings
Fig. 1 is the flow chart of the adjustment method of the oil clearance of bearing for electric machine provided in an embodiment of the present invention;
Fig. 2 is the schematic diagram of the drive shaft system of motor provided in an embodiment of the present invention;
Fig. 3 is the structure chart of bearing provided in an embodiment of the present invention;
Fig. 4 a be bearing oil clearance of the embodiment of the present invention adjustment method in spindle support when being zero, spindle gravity causes motor Curved schematic diagram on axle;
Fig. 4 b are that spindle top lift overcomes when connecing support in the adjustment method of bearing oil clearance of the embodiment of the present invention normally to jack Gravity causes curved schematic diagram under motor shaft.
Embodiment
The invention provides a kind of adjustment method of the oil clearance of bearing for electric machine, to solve present in prior art to institute Not accurate enough technical problem during the bearing oil clearance value measurement of debugging.
Technical scheme in the embodiment of the present application is the above-mentioned technical problem of solution, and general thought is as follows:
A kind of adjustment method of the oil clearance of bearing for electric machine is provided, motor includes the motor shaft for output torque, used In the fore bearing of end of the close external load of support motor shaft and remote external load for supporting motor shaft The rear bearing of another end, motor shaft are connected to an end of transmission connecting shaft close to an end of external load, transmission Another end of spindle is connected with external load, and transmission connecting shaft is rotated by spindle support member supports, the lower axle of fore bearing Watt it is provided with the fore bearing pressure oil for motor shaft to be jacked up and jacks hole, after rear bearing is provided with for motor shaft to be jacked up Bearing pressure oil overhold rises hole, is rotatably connected at the top of transmission connecting shaft support member with transmission connecting shaft, and the support force of support member exists It can adjust in first preset range, pressure oil is controlled rises hole and rear bearing pressure oil overhold liter hole from preceding bearing pressure oil overhold respectively Spray so that motor shaft to be jacked up, this method includes:S1:The support pressure of transmission connecting shaft support member is kept to be zero and make motor Bearing pressure oil stops being supplied to fore bearing pressure oil jacking hole and rear bearing pressure oil overhold rises hole;S2:Before motor shaft is located at The bearing block both sides along shaft extension direction at bearing set high on rear side of front-end bearing pedestal front height measuring instrument and front-end bearing pedestal respectively Measuring instrument is spent, and height-gauge is set on front side of rear bearing block in motor shaft;S3:Support pressure is adjusted to external load Corresponding pressure during work;S4:The first front-end bearing pedestal front height position that record front-end bearing pedestal front height measuring instrument measures The the first front-end bearing pedestal posterior height shift value and rear bearing block front height that shifting value, front-end bearing pedestal posterior height measuring instrument measure The first rear bearing block front height shift value that measuring instrument measures;S5:Open fore bearing pressure oil jacking hole and rear bearing pressure Oil overhold rises the pressure oil supply in hole;S6:Record the second front-end bearing pedestal front height of front-end bearing pedestal front height measuring instrument measurement Shift value, the second front-end bearing pedestal posterior height shift value of front-end bearing pedestal posterior height measuring instrument measurement and rear bearing block front side are high Spend the second rear bearing block front height shift value of measuring instrument measurement;S7:Based on the first front-end bearing pedestal front height shift value, One front-end bearing pedestal posterior height shift value, the first rear bearing block front height shift value, the second front-end bearing pedestal front height displacement Value, the second front-end bearing pedestal posterior height shift value, the second rear bearing block front height shift value come calculate obtain oil clearance value; S8:If the value of oil clearance in the second preset range, will be fed separately to fore bearing pressure oil jacking hole and rear bearing pressure The pressure that oil overhold rises the pressure oil in hole uses as a result;If the value of oil clearance is not within the predefined range, the value according to oil clearance To adjust the pressure for the pressure oil for being fed separately to fore bearing pressure oil jacking hole and rear bearing pressure oil overhold liter hole, and hold again Row step S6-S8, until the value of oil clearance is in the second preset range.
As can be seen that the adjustment method of the oil clearance of bearing for electric machine provided in an embodiment of the present invention need not be by motor with passing Moving axis system is split, it becomes possible to detect the bearing oil clearance value of motor, avoid because by motor with being torn open with drive shaft system Cause the inaccurate technical problem of bearing oil clearance value after being assembled again after point, it is more accurate so as to reach the bearing oil clearance value detected True technique effect, also, save workload and the time of dismounting motor and drive shaft system;
Meanwhile a measuring instrument is respectively placed in the front-end bearing pedestal front and rear sides axial plane of motor, so for the same of bearing Part can obtain multiple sampled values, and then can further improve the precision of the oil clearance value of detected bearing.
In order to be better understood from above-mentioned technical proposal, below by accompanying drawing and specific embodiment to technical solution of the present invention It is described in detail, it should be understood that the specific features in the embodiment of the present invention and embodiment are to the detailed of technical solution of the present invention Thin explanation, rather than the restriction to technical solution of the present invention, in the case where not conflicting, the embodiment of the present invention and embodiment In technical characteristic can be mutually combined.
The embodiment of the present invention provides a kind of adjustment method of the oil clearance of bearing for electric machine, and motor is included for output torque Motor shaft, close external load for supporting motor shaft an end fore bearing and for support motor shaft away from outer The rear bearing of another end of load is connect, motor shaft is connected to an end of transmission connecting shaft close to an end of external load Portion, another end of transmission connecting shaft are connected with external load, and transmission connecting shaft is rotated by spindle support member supports, fore bearing Lower bearing be provided with and jack hole for the fore bearing pressure oil that jacks up motor shaft, rear bearing is provided with for by motor shaft top The rear bearing pressure oil overhold risen rises hole, is rotatably connected at the top of transmission connecting shaft support member with transmission connecting shaft, specifically, this fulcrum There is a rolling bearing at place, and spindle support member is propped up in bearing outer ring, and the support force of support member can in the first preset range Regulation, pressure oil, which is controlled to rise hole and rear bearing pressure oil overhold from preceding bearing pressure oil overhold respectively and rise hole, to be sprayed with by motor shaft top Rise, refer to Fig. 1, this method includes:
S1:The support pressure for keeping transmission connecting shaft support member is zero and motor bearings pressure oil is stopped before being supplied to Bearing pressure oil overhold rises hole and rear bearing pressure oil overhold rises hole;
S2:Set respectively in the bearing block both sides along shaft extension direction that motor shaft is located at fore bearing high on front side of front-end bearing pedestal Measuring instrument and front-end bearing pedestal posterior height measuring instrument are spent, and height-gauge is set on front side of rear bearing block in motor shaft;
S3:The support pressure of support member is adjusted to pressure corresponding when external load works;
S4:The first front-end bearing pedestal front height shift value, the fore bearing that record front-end bearing pedestal front height measuring instrument measures The the first front-end bearing pedestal posterior height shift value and rear bearing block front height measuring instrument that seat posterior height measuring instrument measures measure The first rear bearing block front height shift value;
S5:Open fore bearing pressure oil jacking hole and rear bearing pressure oil overhold rises the pressure oil supply in hole;
S6:Record the second front-end bearing pedestal front height shift value, the fore bearing of front-end bearing pedestal front height measuring instrument measurement Second front-end bearing pedestal posterior height shift value of seat posterior height measuring instrument measurement and the measurement of rear bearing block front height measuring instrument The second rear bearing block front height shift value;
S7:Based on the first front-end bearing pedestal front height shift value, the first front-end bearing pedestal posterior height shift value, the first rear axle Bearing front height shift value, the second front-end bearing pedestal front height shift value, the second front-end bearing pedestal posterior height shift value, second Rear bearing block front height shift value obtains the value of oil clearance to calculate;
S8:If the value of oil clearance in the second preset range, will be fed separately to fore bearing pressure oil jacking hole with after The pressure that bearing pressure oil overhold rises the pressure oil in hole uses as a result;If the value of oil clearance is not within the predefined range, foundation The value of oil clearance is fed separately to the pressure for the pressure oil that fore bearing pressure oil jacks hole and rear bearing pressure oil overhold liter hole to adjust, And step S6-S8 is performed again, until the value of oil clearance is in the second preset range.
As further preferred embodiment, bearing oil clearance refers to the high pressure of motor sliding bearing in motor transmission shaft system Lubricant oil gap.
Please continue to refer to Fig. 2, Fig. 2 is the schematic diagram of the drive shaft system of motor provided in an embodiment of the present invention, such as Fig. 2 institutes Show, the drive shaft system includes:Machine shaft 20a, the transmission connecting shaft 20b for being connected to machine shaft 20a, it is supported in transmission connecting shaft 20b transmission connecting shaft support meanss 20c, the operation roll of mill 20d for being connected to transmission connecting shaft 20b;The forward and backward bearing shell 20e of motor, It is respectively arranged at machine shaft 20a both ends;
Wherein, upper transmission connecting shaft support meanss 20c, underdrive knot axle support meanss 21d are equivalent to the support of pressure adjustable Hydraulic cylinder, the supporting cylinder provide holding power can be adjusted zero between maximum holding power, using steel mill electric machine as Example, when the supporting cylinder external load works corresponding pressure refer to motor by motor shaft drive transmission connecting shaft and then The situation of roll steel rolling is driven, has defined hydraulic oil lift-up pressure generally for supporting cylinder for specific milling train, It is not limited in the present embodiment, is defined by the needs for meeting actual conditions;It is remote before drive shaft system is close to roughing load side After load side is;The bearing of motor is, for example,:Spherical aligning watt sliding bearing.
Fig. 3 is refer to, Fig. 3 is the structure chart of bearing provided in an embodiment of the present invention, and bearing is as shown in figure 3, include again:
Machine shaft 30;
High pressure oil clearance 31a between bearing shell 31 before motor, with machine shaft 30 be present, have aligning seat on bearing shell 31 before motor 31b;
High-pressure oil pipe and regulating valve 32, bearing shell 31 before motor is connected to, with machine shaft 30 in high pressure oil clearance 31a positions phase Connect;
High pressure oil clearance 33a between electric motor back shaft watt 33, with machine shaft 30 be present, have aligning seat on electric motor back shaft watt 33 33b;
High-pressure oil pipe and regulating valve 34, are connected to electric motor back shaft watt 33, connect with machine shaft 30 in high pressure oil clearance position.
In addition, the bearing shell of motor sliding bearing is designed as spherical aligning watt, it is exactly to adapt to roughing electricity that aligning watt, which sets purpose, Distortion of the machine drive shaft system in different conditions.
Fig. 1, Fig. 2 and Fig. 3 are please also refer to, for motor fore bearing, inventor has found in debugging process is measured Following phenomenon:1. when motor bearings pressure oil stop being supplied to fore bearing pressure oil jacking hole and after bearing pressure oil overhold rise hole In the state of, when the support pressure of support member is worked by acyclic homologically trioial to external load during corresponding pressure, before the motor Dial gauge measures height " rise " change on front side of bearing block, and dial gauge measures height " reduction " on rear side of the motor front-end bearing pedestal Change;2. the fore bearing pressure oil jacking hole is opened on the basis of above-mentioned " 1. " and the rear bearing pressure oil overhold rises hole Pressure oil supplies, and now dial gauge measures on rear side of dial gauge and the motor front-end bearing pedestal on front side of the motor front-end bearing pedestal Highly " rise " changes, but " rise " value that dial gauge measures on front side of the motor front-end bearing pedestal is more than the motor front-end bearing pedestal " rise " value that rear side dial gauge measures." 1. " phenomenon shows bearing using motor fore bearing aligning bearing shell as fulcrum, bearing both sides Axial plane height has certain change under different conditions because motor shaft elastic bending deflection be present, while shows under " 1. " state, Above-mentioned spindle support force does not make to produce gap between the axle of fore bearing and lower axle tiling;What is more important phenomenon " 2. " table It is bright, the change of the high pressure oil pressure of bearing is supplied, also the degree of bending shaft is had an impact, " 2. " phenomenon shows, described in unlatching After fore bearing pressure oil jacks the pressure oil supply in hole and the rear bearing pressure oil overhold liter hole, in the front side of front-end bearing pedestal with after Obtained oil clearance value is measured at side two to have differences, and larger error can be caused by using any as oil clearance value.Cause This, it is necessary to set front-end bearing pedestal front height measurement table B51 and front-end bearing pedestal posterior height respectively at the front-end bearing pedestal of motor Measurement table B52, and the reading by measuring B51 and B52 average it is difference right to reduce the degree of crook of motor bearings Influence caused by the bearing oil clearance value detected.
Above-mentioned phenomenon is interpretable as follows:Spindle support is different with the state of operation roll of mill, and the degree of crook of motor shaft is not Together;The pressure of hydraulic oil is different, and the degree of crook of axle is also different.As shown in fig. 4 a, the supporting cylinder pressure of spindle support is When zero, spindle gravity is applied to motor shaft end, makes machine shaft that upper curved trend be presented, and as shown in Figure 4 b, spindle support hydraulic pressure During normal pressure of the cylinder to the work of upper external load, machine shaft by rotor self gravitation influenceed and in now curved trend. In S1, specifically, that is, the support pressure for keeping the supporting cylinder 20c of transmission connecting shaft is zero, and makes motor bearings pressure Oil stops being supplied to fore bearing pressure oil jacking hole and rear bearing pressure oil overhold rises hole.
In S2, specifically, i.e., front-end bearing pedestal front height is set to measure respectively in the front-end bearing pedestal both sides of motor shaft Instrument B51 and front-end bearing pedestal posterior height measurement B52, and height-gauge is set on front side of rear bearing block in motor shaft B3;In specific implementation process, height-gauge displacement measuring equipment such as can be dial gauge, amesdial or scale will The main body of dial gauge, amesdial etc., which is fixed on, needs the position that sets, and by the detection thimble and motor of dial gauge, amesdial etc. The axial plane contact of axle, is just repeated no more herein.
In S3, specifically, i.e., supporting cylinder 20c support pressure is adjusted to corresponding when external load works Pressure, can be that motor drives transmission connecting shaft to be carried and then hydraulic cylinder when driving roll steel rolling by motor shaft in the present embodiment The support pressure of confession, is just repeated no more herein.
In S4, specifically, namely the first front-end bearing pedestal front side that record front-end bearing pedestal front height measurement table measures Height displacement value haB51, the first front-end bearing pedestal posterior height shift value h for measuring of front-end bearing pedestal posterior height measurement tableaB52With it is rear The first rear bearing block front height shift value h that bearing block front height measurement table measuresaB3
In S5, specifically, will being also used for control, bearing pressure oil overhold rises hole and rear bearing pressure oil overhold liter forward The ball valve of hole fuel feeding is opened, and the pressure oil supply in hole is risen so as to open fore bearing pressure oil jacking hole and rear bearing pressure oil overhold.
In S6, specifically, namely on front side of the second front-end bearing pedestal of record front-end bearing pedestal front height measurement table measurement Height displacement value hbB51, front-end bearing pedestal posterior height measurement table measurement the second front-end bearing pedestal posterior height shift value haB52With it is rear Second rear bearing block front height shift value h of bearing block front height measurement table measurementbB3
In S7, specifically, the oil clearance value at two bearings can be calculated by equation below:
gB5=hbB5-haB5, wherein, hbB5=(hbB52+hbB51)/2, haB5=(haB52+haB51)/2, gB5For the front axle of motor The oil clearance value of bearing;
gB3=hbB3-haB3, wherein gB3For the oil clearance value of the rear bearing block of motor.
In S8, specifically, if calculating obtained g in S7B3And gB5In the second preset range, then it can incite somebody to action The pressure for being fed separately to the pressure oil in fore bearing pressure oil jacking hole and rear bearing pressure oil overhold liter hole uses as a result; In practical application, motor bearings oil clearance value is generally 0.04mm between 0.2mm, and in the present embodiment, the second preset range can Think that 0.07mm between 0.15mm, to eliminate caused error in engineering practice, further reduces the risk of error band.
In specific implementation process, if calculating obtained g in S7B3And gB5Not in the second preset range, corresponding When bearing oil clearance value is less than the minimum value of the second preset range, the choke valve of the pressure piping of big corresponding shaft bearing is driven, or right When answering the bearing oil clearance value to be more than the maximum of the second preset range, the choke valve of the pressure piping of corresponding shaft bearing is turned down, and again Perform S6-S8 so that calculate obtained gB3And gB5In the second preset range, ensure the normal need of production, herein just not Repeat again.
Certainly, it is necessary to which explanation, in the present embodiment, the adjustment method for describing the oil clearance of bearing for electric machine are directed to one The process that platform motor is adjusted, by the introduction of the present embodiment, in actual applications, the technical staff belonging to this area can According to actual conditions, set and close for the bearing number of the respective power transmission shaft of multiple electric motors or the multichannel power transmission shaft of a motor The elevation carrection table of suitable number, so as to accurately measure the oil clearance value at each bearing, to meet the needs of actual conditions, herein Just repeat no more.
One or more technical scheme in the embodiment of the present invention, at least has the following technical effect that or advantage:
1st, the adjustment method of the oil clearance of bearing for electric machine provided in an embodiment of the present invention need not be by motor and drive shaft system Split, it becomes possible to detect the bearing oil clearance value of motor, avoid because by motor and after being split with drive shaft system again Cause the inaccurate technical problem of bearing oil clearance value after assembling, so as to reach the more accurate skill of bearing oil clearance value detected Art effect, also, save workload and the time of dismounting motor and drive shaft system;
2nd, a measuring instrument is respectively placed in the front-end bearing pedestal front and rear sides axial plane of motor, is so directed to the same part of bearing Multiple sampled values can be obtained, and then can further improve the precision of the oil clearance value of detected bearing.
Although preferred embodiments of the present invention have been described, but those skilled in the art once know basic creation Property concept, then can make other change and modification to these embodiments.So appended claims be intended to be construed to include it is excellent Select embodiment and fall into having altered and changing for the scope of the invention.
Obviously, those skilled in the art can carry out various changes and modification without departing from this hair to the present invention
Bright spirit and scope.So, if the present invention these modifications and variations belong to the claims in the present invention and its Within the scope of equivalent technologies, then the present invention is also intended to comprising including these changes and modification.

Claims (4)

1. a kind of adjustment method of the oil clearance of bearing for electric machine, the motor includes the motor shaft for output torque, for propping up Support the fore bearing of an end of the close external load of the motor shaft and for supporting the remote described outer of the motor shaft The rear bearing of another end of load is connect, the motor shaft is connected to transmission connecting shaft close to an end of the external load An end, another end of the transmission connecting shaft is connected with the external load, and the transmission connecting shaft is by spindle branch Support part part support rotating, the lower bearing of the fore bearing are provided with the fore bearing pressure oil jacking for the motor shaft to be jacked up Hole, the rear bearing pressure oil overhold that the rear bearing is provided with for the motor shaft to be jacked up rise hole, the transmission connecting shaft support Component top is rotatably connected with the transmission connecting shaft, and the support force of the support member can adjust in the first preset range, Pressure oil is controlled jacks hole and the rear bearing pressure oil overhold liter hole ejection with by described in from the fore bearing pressure oil respectively Motor shaft jacks up, it is characterised in that methods described includes:
S1:The support pressure for keeping the transmission connecting shaft support member is zero and the motor bearings pressure oil is stopped supply Hole is jacked to the fore bearing pressure oil and the rear bearing pressure oil overhold rises hole;
S2:Before front-end bearing pedestal is set respectively in the bearing block both sides along shaft extension direction that the motor shaft is located at the fore bearing Side height-gauge and front-end bearing pedestal posterior height measuring instrument, and set in the motor shaft on front side of the rear bearing block Height-gauge;
S3:The support pressure of the support member is adjusted to pressure corresponding when the external load works;
S4:Record the first front-end bearing pedestal front height shift value that the front-end bearing pedestal front height measuring instrument measures, it is described before The the first front-end bearing pedestal posterior height shift value and the rear bearing block front height that bearing block posterior height measuring instrument measures are surveyed The first rear bearing block front height shift value that amount instrument measures;
S5:Open the fore bearing pressure oil jacking hole and the rear bearing pressure oil overhold rises the pressure oil supply in hole;
S6:Record front-end bearing pedestal front height measuring instrument measurement the second front-end bearing pedestal front height shift value, it is described before Second front-end bearing pedestal posterior height shift value of bearing block posterior height measuring instrument measurement and the rear bearing block front height are surveyed Measure the second rear bearing block front height shift value of instrument measurement;
S7:Based on the first front-end bearing pedestal front height shift value, the first front-end bearing pedestal posterior height shift value, described After first rear bearing block front height shift value, the second front-end bearing pedestal front height shift value, second front-end bearing pedestal Side height displacement value, the second rear bearing block front height shift value come calculate obtain oil clearance value;
S8:If the value of the oil clearance in the second preset range, will be fed separately to the fore bearing pressure oil jacking hole The pressure for the pressure oil for rising hole with the rear bearing pressure oil overhold uses as a result;If the value of the oil clearance is not in predetermined model In enclosing, then the fore bearing pressure oil jacking hole and the rear bearing pressure are fed separately to according to the value of the oil clearance to adjust Oil overhold rises the pressure of the pressure oil in hole, and performs step S6-S8 again, until the value of the oil clearance is in second preset range It is interior.
2. adjustment method as claimed in claim 1, it is characterised in that described to be based on the first front-end bearing pedestal front height position Before shifting value, the first front-end bearing pedestal posterior height shift value, the first rear bearing block front height shift value, described second Bearing block front height shift value, the second front-end bearing pedestal posterior height shift value, the second rear bearing block front height Shift value obtains the value of the oil clearance to calculate, and is specially:
The first front-end bearing pedestal front height shift value is designated as haB51, by the first front-end bearing pedestal posterior height shift value It is designated as haB52, the first rear bearing block front height shift value is designated as haB3, by the second front-end bearing pedestal front height position Shifting value is designated as hbB51, the second front-end bearing pedestal posterior height shift value is designated as haB52, will be high on front side of second rear bearing block Degree shift value is designated as hbB3
gB5=hbB5-haB5, wherein, hbB5=(hbB52+hbB51)/2, haB5=(haB52+haB51)/2, gB5For the front axle of the motor The oil clearance value of bearing;
gB3=hbB3-haB3, wherein gB3For the oil clearance value of the rear bearing block of the motor.
3. adjustment method as claimed in claim 1, it is characterised in that the value according to the oil clearance is supplied respectively to adjust The pressure of the pressure oil in hole and the rear bearing pressure oil overhold liter hole is jacked to the fore bearing pressure oil, is specifically included:
When corresponding shaft bearing oil clearance value is less than the minimum value of second preset range, the section of the pressure piping of big corresponding shaft bearing is opened Flow valve;
When corresponding shaft bearing oil clearance value is more than the maximum of second preset range, the section of the pressure piping of corresponding shaft bearing is turned down Flow valve.
4. adjustment method as claimed in claim 1, it is characterised in that second preset range is:0.07mm to 0.15mm Between.
CN201510741009.2A 2015-11-02 2015-11-02 Debugging method for oil clearance of motor bearing Active CN105422624B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510741009.2A CN105422624B (en) 2015-11-02 2015-11-02 Debugging method for oil clearance of motor bearing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510741009.2A CN105422624B (en) 2015-11-02 2015-11-02 Debugging method for oil clearance of motor bearing

Publications (2)

Publication Number Publication Date
CN105422624A CN105422624A (en) 2016-03-23
CN105422624B true CN105422624B (en) 2017-11-28

Family

ID=55501077

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510741009.2A Active CN105422624B (en) 2015-11-02 2015-11-02 Debugging method for oil clearance of motor bearing

Country Status (1)

Country Link
CN (1) CN105422624B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1186381A (en) * 1966-03-28 1970-04-02 Cie Electro Mechanique Rotary Electric Machines
DE1775375A1 (en) * 1968-08-03 1972-04-06 Hamburger Flugzeugbau Gmbh Suspension for a hydraulic cylinder
ES400891A1 (en) * 1971-03-18 1975-01-16 Siemens Ag Improvements in devices for the accommodation of electromotorically powered shafts. (Machine-translation by Google Translate, not legally binding)
CN2076182U (en) * 1990-10-12 1991-05-01 北京海淀东方自动化轧钢设备研究所 Hydraulic superimposing speed controllerd
CN1342528A (en) * 2001-10-24 2002-04-03 方崇实 Rolling mill for wire rod material and tandem mill set
CN101323095A (en) * 2008-06-27 2008-12-17 中信重工机械股份有限公司 Design of pure static pressure sliding shoe structure for fixed end and free end in tube mill supporting device
CN202768510U (en) * 2012-08-30 2013-03-06 首钢京唐钢铁联合有限责任公司 Working roll connecting shaft balance hydraulic loop of roughing mill
CN103499582A (en) * 2013-09-27 2014-01-08 首钢京唐钢铁联合有限责任公司 Thrust pad inspection method for damping thrust bearing
CN204554327U (en) * 2015-04-08 2015-08-12 首钢京唐钢铁联合有限责任公司 Oil return device of roller bearing

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5423041Y2 (en) * 1972-06-13 1979-08-09
US6120004A (en) * 1998-06-16 2000-09-19 Korea Institute Of Machinery And Materials Variable capillary apparatus for hydrostatic bearing and motion error compensating method using same

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1186381A (en) * 1966-03-28 1970-04-02 Cie Electro Mechanique Rotary Electric Machines
DE1775375A1 (en) * 1968-08-03 1972-04-06 Hamburger Flugzeugbau Gmbh Suspension for a hydraulic cylinder
ES400891A1 (en) * 1971-03-18 1975-01-16 Siemens Ag Improvements in devices for the accommodation of electromotorically powered shafts. (Machine-translation by Google Translate, not legally binding)
CN2076182U (en) * 1990-10-12 1991-05-01 北京海淀东方自动化轧钢设备研究所 Hydraulic superimposing speed controllerd
CN1342528A (en) * 2001-10-24 2002-04-03 方崇实 Rolling mill for wire rod material and tandem mill set
CN101323095A (en) * 2008-06-27 2008-12-17 中信重工机械股份有限公司 Design of pure static pressure sliding shoe structure for fixed end and free end in tube mill supporting device
CN202768510U (en) * 2012-08-30 2013-03-06 首钢京唐钢铁联合有限责任公司 Working roll connecting shaft balance hydraulic loop of roughing mill
CN103499582A (en) * 2013-09-27 2014-01-08 首钢京唐钢铁联合有限责任公司 Thrust pad inspection method for damping thrust bearing
CN204554327U (en) * 2015-04-08 2015-08-12 首钢京唐钢铁联合有限责任公司 Oil return device of roller bearing

Also Published As

Publication number Publication date
CN105422624A (en) 2016-03-23

Similar Documents

Publication Publication Date Title
CN101407247A (en) Shipping shafting centering and main unit load measuring methods
CN102997885B (en) Gap detection device of large slewing bearing
CN103148818B (en) A kind of high accuracy gyroscope motor bearing loading method
CN112595513B (en) Integrated bearing test bench
CN103344495B (en) Rigid bearing plate center pit method servocontrol deep rock-mass deformation test unit and method thereof
CN104596759A (en) Electric spindle reliability test bed with hydraulic-type energy recovery function
CN103673813A (en) Cargo oil pump and turbine mounting and aligning method
CN102359848A (en) Water turbine rotating wheel three-fulcrum weighing static balance device and static balance technology thereof
CN108519185A (en) A kind of shafting load measuring based on mechanical meaurement
CN104374572A (en) Large-scale forklift portal idler wheel bearing unit service life test system and method
CN204422189U (en) There is the electro spindle reliability test bench of fluid pressure type energy regenerating
CN104048634A (en) Online automatic detecting machine for bearing outer ring rail and detecting method thereof
CN105422624B (en) Debugging method for oil clearance of motor bearing
CN208333826U (en) A kind of static submissive system safety testing device of industrial robot
CN202317872U (en) Double compensation device for ram motion and inclination of CNC (computerized numerical control) floor-type boring and milling machine
CN107063185A (en) A kind of experimental provision for measuring Large Machine Body low dip
CN207730134U (en) A kind of piston rod Linearity surveying coalignment
CN201841489U (en) Crankshaft flywheel positioning device
CN106052765A (en) Dynamic shield tunneling machine hobbing cutter detection apparatus
CN106799558B (en) Labyrinth ring field repair processing technology under a kind of runner
CN203385556U (en) Host engine base horizontal alignment adjusting pad of marine diesel engine
CN111238810B (en) Motorized spindle reliability test device based on synchronous hydraulic cylinder driving loading
CN204128826U (en) A kind of large-scale fork truck door frame idler wheel bearing unit service life experiment system
CN104634490B (en) Triaxial adjustable composite dynamometer loading and driving device
CN105620658A (en) Method for installing middle bearing of ship shaft system by using airbag

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant