CN105387467A - Slag stopping device for chute of feeding trolley and construction method for slag stopping device - Google Patents

Slag stopping device for chute of feeding trolley and construction method for slag stopping device Download PDF

Info

Publication number
CN105387467A
CN105387467A CN201510920242.7A CN201510920242A CN105387467A CN 105387467 A CN105387467 A CN 105387467A CN 201510920242 A CN201510920242 A CN 201510920242A CN 105387467 A CN105387467 A CN 105387467A
Authority
CN
China
Prior art keywords
stay bolt
chute
cylindrical void
base
connecting hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510920242.7A
Other languages
Chinese (zh)
Other versions
CN105387467B (en
Inventor
李雪飞
丁堂文
司景忠
赵彬
秦坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHONGQING SANFENG COVANTA ENVIRONMENTAL INDUSTRY Co Ltd
Original Assignee
CHONGQING SANFENG COVANTA ENVIRONMENTAL INDUSTRY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING SANFENG COVANTA ENVIRONMENTAL INDUSTRY Co Ltd filed Critical CHONGQING SANFENG COVANTA ENVIRONMENTAL INDUSTRY Co Ltd
Priority to CN201510920242.7A priority Critical patent/CN105387467B/en
Publication of CN105387467A publication Critical patent/CN105387467A/en
Application granted granted Critical
Publication of CN105387467B publication Critical patent/CN105387467B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G5/00Incineration of waste; Incinerator constructions; Details, accessories or control therefor
    • F23G5/44Details; Accessories
    • F23G5/442Waste feed arrangements
    • F23G5/444Waste feed arrangements for solid waste

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Manufacture And Refinement Of Metals (AREA)

Abstract

The invention discloses a slag stopping device for a chute of a feeding trolley. The slag stopping device comprises a slag stopping plate and at least two tension brace mechanisms. Each tension brace mechanism comprises a tension brace rod, a bottom seat and a base, wherein the bottom seat and the base are connected with the two ends of the tension brace rod respectively; the bottom seat is fixedly connected with the chute; the base is fixedly connected with the slag stopping plate; the two ends of the tension brace rod are provided with connecting hole buckles; a groove is formed in the bottom seat, and the cross section of the groove is in a U shape; winged edges on the two sides of the groove are symmetrically provided with a set of vertical strip-shaped holes which are identical in shape and size; a transverse strip-shaped hole is formed in the base; the connecting hole buckle at one end of the tension brace rod is connected with the vertical strip-shaped holes through a connection assembly, and the connecting hole buckle at the other end of the tension brace rod is connected with the transverse strip-shaped hole through a bolt. By means of the slag stopping device, the problem that slag overflows from a gap between a baffle at the bottom of the chute and the platform surface of the feeding trolley is solved, the installation precision of the device is further guaranteed, the slag stopping plate can move more freely in the movement process, and the phenomenon that the slag stopping plate gets stuck is avoided; the slag stopping device has the advantages of being simple in structure, easy to implement and high in reliability.

Description

A kind of to trolley chute skimming device and construction method thereof
Technical field
The invention belongs to incinerator field of mechanical technique, be specifically related to a kind of to trolley chute skimming device and construction method thereof.
Background technology
Existing incinerator is have two stay bolt bars in slag trap welded top to trolley chute skimming device, the other end of this two stay bolts bar is connected to Connection Block, this two Connection Block is arranged on on the base of trolley chute steel construction respectively by bolt, because whole skimming device is positioned to the bottom of trolley chute steel construction, its installing space is limited, there are the following problems: one to cause the skimming device of this form, stay bolt bar adopts the mode of welding with slag trap, not only increase on-the-spot welding difficulty, also add the installation of connection angle between slag trap and stay bolt bar, its two, base is connected with Connection Block, the connection space between stay bolt bar and Connection Block is reduced further, thus adds site operation difficulty, reduce efficiency of construction, its three, the installation length of stay bolt bar is fixed, and is unfavorable for on-the-spot adjusting the distance between slag trap and chute feed opening.Therefore, the design of this skimming device is complicated, installs difficulty, and the axiality that two Connection Blocks are installed can not ensure on the same line, and when causing operation, slag trap unbalance stress, easily occur bite phenomenon, and adjustment is also inconvenient.
Summary of the invention
In view of this, the object of the present invention is to provide a kind of to trolley chute skimming device, make slag trap in motion process stressed evenly, there will not be bite phenomenon, and when its intensity does not subtract, have simple for structure, easy for installation, the advantage that reliability is strong.Another object of the present invention is to provide a kind of to the construction method of trolley chute skimming device, for the ease of installing, eliminating alignment error, ensureing normal production run.
For achieving the above object, the present invention is achieved through the following technical solutions:
One provided by the invention, to trolley chute skimming device, comprises the slag trap be located on feed trolley platform face, also comprises at least Liang Tao stay bolt mechanism, follows chute on feed trolley platform face, make horizontal reciprocating movement together for driving slag trap; Described stay bolt mechanism comprises stay bolt bar and the base be connected with stay bolt bar two ends respectively and pedestal, described base and chute affixed, described pedestal and slag trap affixed; Described stay bolt bar two ends are equipped with connecting hole button, described base is provided with the groove that cross section is U-shaped, for holding the connecting hole button of stay bolt bar one end, described groove two flank limit is arranged with respectively a shape, vertical cylindrical void that size is identical, described pedestal is provided with a horizontal cylindrical void; The connecting hole button of described stay bolt bar one end is connected with the vertical cylindrical void on base by coupling assembly, and the connecting hole button of its other end is connected with the horizontal cylindrical void on pedestal by bolt.
Further, described coupling assembly comprises the bearing pin for the vertical cylindrical void of base of connecting and stay bolt bar one end connecting hole button, the two ends of described bearing pin are equipped with connecting thread, and the position, arbitrary hole by the nut screw connection that matches with this connecting thread this bearing pin is located by connecting on vertical cylindrical void, described connecting hole button is rotating to be located on bearing pin.
Further, the internal orifice dimension of described stay bolt bar two ends connecting hole button is equal, and the internal orifice dimension of described vertical cylindrical void and horizontal cylindrical void is equal and be more than or equal to the internal orifice dimension of connecting hole button.
Further, the length of described vertical cylindrical void is 80 ~ 150mm, and the length of described horizontal cylindrical void is 80 ~ 200mm.
Further, on the stay bolt bar of slag trap side, by limit bolt, balancing weight is installed.
Further, the sidewall that described slag trap contacts with slag charge is provided with the flitch that some rows are tilted to lower layout.
Further, between described flitch and slag trap sidewall, the span of angle is 50 ° ~ 80 °.
A kind of construction method of giving trolley chute skimming device of the present invention, specifically implement in accordance with the following steps:
1) prepare: make at least Liang Tao stay bolt mechanism and on feed trolley platform face, make horizontal reciprocating movement for driving slag trap to follow together to chute; This draws pole structure to comprise stay bolt bar and the base be connected with stay bolt bar two ends respectively and pedestal, wherein, is all processed with connecting hole button at stay bolt bar two ends; Base is processed with the groove that cross section is U-shaped, and on this groove two flank limit, offers a shape, vertical cylindrical void that size is identical respectively; Pedestal is processed with a horizontal cylindrical void;
2) install: base is fixed on chute; Pedestal is fixed on slag trap, and the slag trap being provided with pedestal is lain on feed trolley platform face and to be positioned at the below of chute steel structure; Be connected with the vertical cylindrical void on base by coupling assembly by the connecting hole button of stay bolt bar one end, the connecting hole button of its other end is connected with the horizontal cylindrical void on pedestal by bolt;
3) adjusting: by vertically sliding up and down the position of coupling assembly on the vertical cylindrical void of base, adjusting the axiality that all coupling assemblies are installed, and to be horizontally slipped the position of bolt on the horizontal cylindrical void of pedestal by level, adjust the elongation of stay bolt bar;
4) terminate: when meeting installation requirement after slag trap adjustment, tight joint assembly and bolt, complete the construction of skimming device respectively.
Further, described coupling assembly comprises the bearing pin for the vertical cylindrical void of base of connecting and stay bolt bar one end connecting hole button, the two ends of described bearing pin are equipped with connecting thread, and the position, arbitrary hole by the nut screw connection that matches with this connecting thread this bearing pin is located by connecting on vertical cylindrical void, described connecting hole button is rotating to be located on bearing pin.
Further, on the stay bolt bar of slag trap side, by limit bolt, balancing weight is installed.
Advantageous Effects of the present invention is: the present invention not only can solve slag charge from the gap location flooding problems between chute bottom baffle and feed trolley platform face, also by optimizing structure, make to install more effectively simple, improve operating efficiency and shorten the set-up time, simultaneously, also ensure the axiality of installation position, all stay bolt bar two ends, can make slag trap in motion process stressed evenly, run more freely, there will not be bite phenomenon, have simple for structure, the advantage that reliability is high.
Other advantages of the present invention, target and feature will be set forth to a certain extent in the following description, and to a certain extent, based on will be apparent to those skilled in the art to investigating hereafter, or can be instructed from the practice of the present invention.Target of the present invention and other advantages can be realized by description below and obtain.
Accompanying drawing explanation
In order to make the object, technical solutions and advantages of the present invention clearly, below in conjunction with accompanying drawing, the present invention is described in further detail, wherein:
Fig. 1 is the structural representation of skimming device of the present invention;
Fig. 2 is that the A of Fig. 1 is to schematic diagram;
Fig. 3 is the structural representation of stay bolt bar in skimming device of the present invention;
Reference numeral: 1-feed trolley platform face; 2-chute, 21-baffle plate; 3-slag trap; 4-stay bolt bar, 41-connecting hole button, 42-through hole; 5-base, 51-groove, the vertical cylindrical void of 511-; 6-pedestal, the horizontal cylindrical void of 61-; 7-balancing weight; 8-limit bolt; 9-flitch; 10-coupling assembly.
Detailed description of the invention
Below with reference to accompanying drawing, the preferred embodiments of the present invention are described in detail; Should be appreciated that preferred embodiment only in order to the present invention is described, instead of in order to limit the scope of the invention.
As Figure 1-3, one provided by the invention is to trolley chute skimming device, comprise the slag trap 3 be located on feed trolley platform face 1, chute 2 is provided with to trolley, also comprise at least Liang Tao stay bolt mechanism, follow chute 2 for driving slag trap 3 and on feed trolley platform face 1, make horizontal reciprocating movement together; Described stay bolt mechanism comprises stay bolt bar 4 and the base 5 be connected with stay bolt bar 4 two ends respectively and pedestal 6, and described base 5 is affixed with chute 2 steel construction, and described pedestal 6 is affixed with slag trap 3; Described stay bolt bar 4 two ends are equipped with connecting hole button 41, described base 5 is provided with the groove 51 that cross section is U-shaped, for holding the connecting hole button 41 of stay bolt bar 4 one end, described groove 51 liang of flank limits are arranged with respectively a shape, vertical cylindrical void 511 that size is identical, described pedestal 6 is provided with a horizontal cylindrical void 61; The described connecting hole button 41 of stay bolt bar 4 one end is connected by coupling assembly 10 with the vertical cylindrical void 511 on base 5, and the connecting hole button 41 of its other end is connected by bolt (unmarked) with the horizontal cylindrical void 61 on pedestal 6.
Concrete, the quantity of described stay bolt linkage can be determined according to the size of slag trap 3, is designed to two covers in this example.When mounted, first by two bases 5 by welding, to be spirally connected or one or more combinations are fixed in on trolley chute 2 steel construction in riveting, and to offer cross section be thereon U-shaped groove 51, two flank limits of described groove 51 are symmetrically arranged with respectively a shape, vertical cylindrical void 511 that size is identical, then on slag trap 3 along its length on welding or be bolted with two pedestals 6, and offer horizontal cylindrical void 61 thereon, then, respectively two stay bolt bars 4 are connected with corresponding base 5 and pedestal 6, wherein, described stay bolt bar 4 two ends are equipped with connecting hole button 41, the connecting hole button 41 of stay bolt bar 4 one end is mounted interior with the U-shaped groove of base 5 and is connected by coupling assembly 10 with the vertical cylindrical void 511 on it, and the connecting hole button 41 of its other end is connected by bolt (unmarked) with the horizontal cylindrical void 61 on pedestal 6, when adjusting, the vertical height that stay bolt bar 4 installs on base 5 not only can be adjusted by the vertical cylindrical void 511 on base 5, the installation position axiality of two stay bolt bars 4 respectively on its base 5 connected can also be ensured, namely all coupling assemblies 10 are installed on the same line, and can adjust by the horizontal cylindrical void 61 on pedestal 6 the level connection joint position that stay bolt bar 4 installs on pedestal 6, be exactly simply, the spacing between slag trap 3 and chute 2 feed opening can be adjusted by the link position relation of stay bolt bar 4 and vertical cylindrical void 511 and horizontal cylindrical void 61, symbol production requirement is closed to reach, finally distinguish coupling assembly 10 and the bolt at fastening stay bolt bar 4 two ends, complete the installment work of whole stop gauge.The present invention not only can solve slag charge from the gap location flooding problems between chute 2 bottom baffle 22 and feed trolley platform face 1, also by optimizing structure, make to install more effectively simple, improve operating efficiency and shorten the set-up time, simultaneously, also ensure the axiality of installation position, all stay bolt bar 4 two ends, can make slag trap 3 in motion process more freely, stressed more even, there will not be bite phenomenon, have simple for structure, the advantage that reliability is high.
It should be noted that, in various embodiments, described pedestal 6 also can be provided with the groove that the cross section the same with base 5 is U-shaped, can reach the object of above-mentioned connection equally.
In this example, described coupling assembly 10 comprises the bearing pin (unmarked) for the vertical cylindrical void 511 of base 5 of connecting and stay bolt bar 4 one end connecting hole button 41, the two ends of described bearing pin are equipped with connecting thread, and by coordinating the position, arbitrary hole be located by connecting on by this bearing pin on vertical cylindrical void with the nut (unmarked) that this connecting thread matches, described connecting hole button is rotating to be located on bearing pin, the width of described groove 51 is slightly larger than the width of connecting hole button 41, so that stay bolt bar 4 connecting hole button 41 can put into the groove 51 of base 5 smoothly, stay bolt bar 4 can be convenient to relative to bearing pin generation pivot simultaneously, the aperture of described stay bolt bar 4 two ends connecting hole button 41 is equal, the aperture of described vertical cylindrical void 511 and horizontal cylindrical void 61 is equal, and be more than or equal to the aperture of connecting hole button 41, the length of described vertical cylindrical void 511 is 80 ~ 150mm, the length of described horizontal cylindrical void 61 is 80 ~ 200mm, the design of this vertical cylindrical void and horizontal cylindrical void, height fall between adjustable base and pedestal, not only make the gradient of the stay bolt bar connected adjustable between the two, thus the length that change stay bolt bar projects in the horizontal direction, the installation accuracy problem that the fabrication error that can also solve stay bolt mechanism brings with its alignment error, Production requirement can be met with the distance between guaranteeing bottom slag trap and chute.Preferably, the length of vertical cylindrical void is 120mm, and the length of horizontal cylindrical void is 180mm, can meet instructions for use.
Concrete, as as described in the external diameter of bearing pin be φ 20, the aperture of described connecting hole button is slightly larger than φ 20, make matched in clearance between connecting hole button and bearing pin, rotating and the pinned connection of stay bolt bar can be allowed, with the trace that fluctuates regulating slag trap in horizontal movement because the face out-of-flatness of feed trolley platform causes; The aperture of described vertical cylindrical void is φ 21, is convenient to bearing pin and slides up and down in vertical cylindrical void, and not only convenient adjustment, can also ensure the axiality of all coupling assemblies, and namely the difference in height at the bearing pin center of left and right two stay bolt bars is not more than 0.5mm; The aperture of described horizontal cylindrical void is φ 21, stay bolt bar 4 other end connecting hole button 41 is connected by the stud of M20, tighten fixing after slag trap adjustment lateral attitude puts in place, be its lateral attitude adjusted value be that slag trap front end and chute bottom space ensure at 27.5 ± 1mm, namely two ends, slag trap left and right and chute bottom space difference are not more than 0.5mm.
In this example, on the stay bolt bar 4 of slag trap 3 side, by limit bolt 8, balancing weight 7 is installed, stay bolt bar 41 is provided with the through hole 42 matched with limit bolt 8, stay bolt bar 41 pairs of slag traps 3 can be made to apply downward component by increasing balancing weight 7, thus provide a certain amount of downward thrust for slag trap 3, the slag trap 3 and the feed trolley platform face 1 that make are fitted tightr, prevent that stay bolt bar 4 is stressed to be lifted, the object of its limit bolt 8 is to play restriction balancing weight 7 toward being tilted to below to the spacing effect of gliding, this balancing weight weight can be 2 ~ 3kg.
In this example, the sidewall that described slag trap 3 contacts with slag charge is provided with the flitch 9 that some rows are tilted to lower layout, between described flitch 9 and slag trap 3 sidewall, the span of angle is 50 ° ~ 80 °, by being tilted to the flitch 9 of lower layout, the space that the slag charge overflowed from baffle plate 21 can be made to be stored between flitch 9 and slag trap 3 sidewall, after storing a certain amount of slag charge in this space, slag charge can be effectively stoped to continue from baffle plate 21 overflow, can also prevent the gap of slag charge between slag trap 3 and chute 2 outer wall from piling up also upwards discharge further simultaneously, and reduce slag particle to the wearing and tearing of slag trap 3 sidewall.Preferably, described flitch is 3 rows, and between itself and slag trap sidewall, angle is 70 °, can meet service condition.
A kind of construction method of giving trolley chute skimming device of the present invention, specifically implement in accordance with the following steps:
1) prepare: make at least Liang Tao stay bolt mechanism and on feed trolley platform face, make horizontal reciprocating movement together for driving slag trap to follow chute; This stay bolt structure comprises stay bolt bar and the base be connected with stay bolt bar two ends respectively and pedestal, wherein, is all processed with connecting hole button at stay bolt bar two ends; Base is processed with the groove that cross section is U-shaped, and on this groove two flank limit, offers a shape, vertical cylindrical void that size is identical respectively; Pedestal is processed with a horizontal cylindrical void;
2) install: base is welded on chute; Pedestal is welded on slag trap, and the slag trap being provided with pedestal is lain on feed trolley platform face and to be positioned at the below of chute steel structure; Be connected with the vertical cylindrical void on base by coupling assembly by the connecting hole button of stay bolt bar one end, the connecting hole button of its other end is connected with the horizontal cylindrical void on pedestal by bolt; Described coupling assembly comprises bearing pin, the nut that the two ends of described bearing pin are equipped with connecting thread and match with this connecting thread, and described connecting hole button is rotating to be located on bearing pin;
3) adjust: by vertically sliding up and down the position of coupling assembly on the vertical cylindrical void of base, adjust the axiality that all coupling assemblies are installed, make the height of stay bolt bar and base connecting portion in design load, after its vertical position is determined, and by nut screw connection, this bearing pin is tightened in advance the mounting hole site be connected on vertical cylindrical void, then to be horizontally slipped the position of bolt on the horizontal cylindrical void of pedestal by level, adjust the horizontal extension component of stay bolt bar, slag trap front end and chute bottom space is made to ensure in design load, and two ends, slag trap left and right in chute bottom space difference in design load, after its lateral attitude is determined, the mounting hole site on horizontal cylindrical void is tightened in advance by bolt,
4) terminate: when meeting installation requirement after slag trap adjustment, tight joint assembly and bolt, complete the construction of this skimming device respectively.
The construction method of this skimming device has advantage that is quick and easy for installation, high efficient and reliable, and can eliminate the installation accuracy problem that fabrication error and alignment error bring, and ensure that normal production run.
What finally illustrate is, above embodiment is only in order to illustrate technical scheme of the present invention and unrestricted, although with reference to preferred embodiment to invention has been detailed description, those of ordinary skill in the art is to be understood that, can modify to technical scheme of the present invention or equivalent replacement, and not departing from aim and the scope of the technical program, it all should be encompassed in the middle of right of the present invention.

Claims (10)

1. give a trolley chute skimming device, comprise the slag trap be located on feed trolley platform face, it is characterized in that: also comprise at least Liang Tao stay bolt mechanism, follow chute for driving slag trap and on feed trolley platform face, make horizontal reciprocating movement together; Described stay bolt mechanism comprises stay bolt bar and the base be connected with stay bolt bar two ends respectively and pedestal, described base and chute affixed, described pedestal and slag trap affixed; Described stay bolt bar two ends are equipped with connecting hole button, described base is provided with the groove that cross section is U-shaped, for holding the connecting hole button of stay bolt bar one end, described groove two flank limit is arranged with respectively a shape, vertical cylindrical void that size is identical, described pedestal is provided with a horizontal cylindrical void; The connecting hole button of described stay bolt bar one end is connected with the vertical cylindrical void on base by coupling assembly, and the connecting hole button of its other end is connected with the horizontal cylindrical void on pedestal by bolt.
2. according to claim 1 to trolley chute skimming device, it is characterized in that: described coupling assembly comprises the bearing pin for the vertical cylindrical void of base of connecting and stay bolt bar one end connecting hole button, the two ends of described bearing pin are equipped with connecting thread, and the position, arbitrary hole by the nut screw connection that matches with this connecting thread this bearing pin is located by connecting on vertical cylindrical void, this connects, and hole button is rotating to be located on bearing pin.
3. according to claim 1ly give trolley chute skimming device, it is characterized in that: the internal orifice dimension of described stay bolt bar two ends connecting hole button is equal, the internal orifice dimension of described vertical cylindrical void and horizontal cylindrical void is equal and be more than or equal to the internal orifice dimension of connecting hole button.
4. according to claim 1 to trolley chute skimming device, it is characterized in that: the length of described vertical cylindrical void is 80 ~ 150mm, the length of described horizontal cylindrical void is 80 ~ 200mm.
5. according to claim 1 to trolley chute skimming device, it is characterized in that: on the stay bolt bar of slag trap side, by limit bolt, balancing weight is installed.
6. according to claim 1 to trolley chute skimming device, it is characterized in that: the sidewall that described slag trap contacts with slag charge is provided with the flitch that some rows are tilted to lower layout.
7. according to claim 6 to trolley chute skimming device, it is characterized in that: between described flitch and slag trap sidewall, the span of angle is 50 ° ~ 80 °.
8. give a construction method for trolley chute skimming device, it is characterized in that comprising the steps:
1) prepare: make at least Liang Tao stay bolt mechanism and on feed trolley platform face, make horizontal reciprocating movement together for driving slag trap to follow chute; This stay bolt mechanism comprises stay bolt bar and the base be connected with stay bolt bar two ends respectively and pedestal, wherein, is all processed with connecting hole button at stay bolt bar two ends; Base is processed with the groove that cross section is U-shaped, and on this groove two flank limit, offers a shape, vertical cylindrical void that size is identical respectively; Pedestal is processed with a horizontal cylindrical void;
2) install: base is fixed on chute; Pedestal is fixed on slag trap, and the slag trap being provided with pedestal is lain on feed trolley platform face and to be positioned at the below of chute steel construction; Be connected with the vertical cylindrical void on base by coupling assembly by the connecting hole button of stay bolt bar one end, the connecting hole button of its other end is connected with the horizontal cylindrical void on pedestal by bolt;
3) adjusting: by vertically sliding up and down the position of coupling assembly on the vertical cylindrical void of base, adjusting the axiality that all coupling assemblies are installed, and to be horizontally slipped the position of bolt on the horizontal cylindrical void of pedestal by level, adjust the elongation of stay bolt bar;
4) terminate: when meeting installation requirement after slag trap adjustment, tight joint assembly and bolt, complete the construction of skimming device respectively.
9. according to claim 8 to trolley chute skimming device, it is characterized in that: described coupling assembly comprises the bearing pin for the vertical cylindrical void of base of connecting and stay bolt bar one end connecting hole button, the two ends of described bearing pin are equipped with connecting thread, and the position, arbitrary hole by the nut screw connection that matches with this connecting thread this bearing pin is located by connecting on vertical cylindrical void, described connecting hole button is rotating to be located on bearing pin.
10. according to claim 8 to trolley chute skimming device, it is characterized in that: on the stay bolt bar of slag trap side, by limit bolt, balancing weight is installed.
CN201510920242.7A 2015-12-10 2015-12-10 One kind gives trolley chute skimming device and its construction method Active CN105387467B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510920242.7A CN105387467B (en) 2015-12-10 2015-12-10 One kind gives trolley chute skimming device and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510920242.7A CN105387467B (en) 2015-12-10 2015-12-10 One kind gives trolley chute skimming device and its construction method

Publications (2)

Publication Number Publication Date
CN105387467A true CN105387467A (en) 2016-03-09
CN105387467B CN105387467B (en) 2017-07-04

Family

ID=55420040

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510920242.7A Active CN105387467B (en) 2015-12-10 2015-12-10 One kind gives trolley chute skimming device and its construction method

Country Status (1)

Country Link
CN (1) CN105387467B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114955619A (en) * 2021-02-18 2022-08-30 宁波盛世阳光自动化科技有限公司 Adjusting structure and adjusting method of paper feeding table, paper feeding device and creasing machine

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0712316A (en) * 1993-06-23 1995-01-17 Sanyo Electric Co Ltd Combustion device
CN2801793Y (en) * 2005-05-12 2006-08-02 首钢总公司 Morable desulforization reaction device
CN202518783U (en) * 2012-03-23 2012-11-07 成都大宏立机器制造有限公司 Sweeper for belt conveyor
CN202672739U (en) * 2012-07-05 2013-01-16 中联重科股份有限公司 Transition hopper
CN203756226U (en) * 2014-03-07 2014-08-06 鞍钢集团矿业公司 Slag blocking device for ore drawing machine
CN205174387U (en) * 2015-12-10 2016-04-20 重庆三峰卡万塔环境产业有限公司 Feed dolly is pushing off slag device for chute

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0712316A (en) * 1993-06-23 1995-01-17 Sanyo Electric Co Ltd Combustion device
CN2801793Y (en) * 2005-05-12 2006-08-02 首钢总公司 Morable desulforization reaction device
CN202518783U (en) * 2012-03-23 2012-11-07 成都大宏立机器制造有限公司 Sweeper for belt conveyor
CN202672739U (en) * 2012-07-05 2013-01-16 中联重科股份有限公司 Transition hopper
CN203756226U (en) * 2014-03-07 2014-08-06 鞍钢集团矿业公司 Slag blocking device for ore drawing machine
CN205174387U (en) * 2015-12-10 2016-04-20 重庆三峰卡万塔环境产业有限公司 Feed dolly is pushing off slag device for chute

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114955619A (en) * 2021-02-18 2022-08-30 宁波盛世阳光自动化科技有限公司 Adjusting structure and adjusting method of paper feeding table, paper feeding device and creasing machine
CN114955619B (en) * 2021-02-18 2024-05-03 宁波盛世阳光自动化科技有限公司 Adjusting structure and adjusting method of paper feeding table, paper feeding device and creasing machine

Also Published As

Publication number Publication date
CN105387467B (en) 2017-07-04

Similar Documents

Publication Publication Date Title
CN105387467A (en) Slag stopping device for chute of feeding trolley and construction method for slag stopping device
CN205174387U (en) Feed dolly is pushing off slag device for chute
CN105648854A (en) Special regulating device for construction of trench-reserved tracks of tramcars and application method of special regulating device
CN104690548B (en) Aligning device for drawn steel wire of turbine partition plate
CN206020764U (en) A kind of double cables of high voltage substation OPGW draw lower fastener
CN208050576U (en) The fixing device of guide and guard cooling water pipe
CN205174390U (en) Novel pushing off slag for chute of feed dolly device
CN205169867U (en) Feed dolly is pushing off slag device for chute
KR101181493B1 (en) Improved support system
CN104060784B (en) Without column full glass console model handrail base
KR101616012B1 (en) Uphold rod which has an angle control function an Slab Panel for Bridge
US20130101348A1 (en) Adjustable grate frames
CN203867164U (en) Cantilever type scaffold structure with positioning steel pipe
CN209344730U (en) A kind of cable rack
CN105297624B (en) Arch bridge inspection car rail device
CN102703095A (en) Method for quickly installing gas pipeline of coke oven
CN203383457U (en) Board mounting system
CN202532110U (en) Fixing device for foundation bolt of elevated platform
CN220164963U (en) Jacking tool for spindle of screw conveyor
CN218087389U (en) Grit conveyor
CN204854920U (en) Can adjust single section truck scale spacing and weighing platform screw thread board interchangeable on line
CN205745897U (en) Open isolating switch mechanism case device for installing and adjusting
CN104389441B (en) A kind of framework support system
CN104907355B (en) A kind of uncoiling blanking material supporting rack
CN219081055U (en) Precast beam installation protection mechanism

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant