CN105299444A - Intelligent SF6 (sulfur hexafluoride) gas inflation module for electrical equipment - Google Patents

Intelligent SF6 (sulfur hexafluoride) gas inflation module for electrical equipment Download PDF

Info

Publication number
CN105299444A
CN105299444A CN201510589122.3A CN201510589122A CN105299444A CN 105299444 A CN105299444 A CN 105299444A CN 201510589122 A CN201510589122 A CN 201510589122A CN 105299444 A CN105299444 A CN 105299444A
Authority
CN
China
Prior art keywords
gas
solenoid valve
control valve
pressure value
threshold value
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201510589122.3A
Other languages
Chinese (zh)
Inventor
孙晓凡
罗涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PHOIBOS TECHNOLOGY Co Ltd
Original Assignee
PHOIBOS TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PHOIBOS TECHNOLOGY Co Ltd filed Critical PHOIBOS TECHNOLOGY Co Ltd
Priority to CN201510589122.3A priority Critical patent/CN105299444A/en
Publication of CN105299444A publication Critical patent/CN105299444A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

The invention provides an intelligent SF6 (sulfur hexafluoride) gas inflation module for electrical equipment. The SF6 gas inflation module comprises an SF6 gas tank, a first solenoid valve, a first pressure detector, a first control, a second solenoid valve, a second pressure detector, a second control, a constant temperature heater, a fourway pipe, a vacuum pump, a third control valve and a fourth control valve. When the pressure value of SF6 gas in the SF6 electrical equipment received by the first control is lower than a first preset pressure threshold value, the SF6 electrical equipment is inflated through an gas inflation pipeline; and when the pressure value of SF gas in the SF6 gas tank received by the second control is lower than a second preset pressure threshold value, gas is added into the SF6 gas tank through a gas-adding pipeline; the constant temperature heater is used to perform constant temperature heating during gas inflation; and the second preset pressure threshold value is larger than the first preset pressure threshold value, and the gas inflation pipeline and the gas-adding pipeline are not connected at he same time at any moment. The intelligent SF6 gas inflation module can automatically perform gas inflation on the SF6 electrical equipment.

Description

Electric equipment intelligent SF 6inflator module
Technical field
The present invention relates to SF 6gas charge and discharge technical field, particularly relates to a kind of electric equipment intelligent SF 6inflator module.
Background technique
SF 6(sulphur hexafluoride) gas is a kind of nontoxic, colourless, tasteless, odorless, non-flammable synthetic gas, has the incomparable insulation characterisitic of general electrolyte and arc extinguishing ability, is therefore widely used in SF 6electrical equipment.
At SF 6in the process that electrical equipment uses, work as SF 6sF in electrical equipment 6the force value of gas drops to rating value, needs SF 6electrical equipment is inflated, otherwise can affect SF 6electrical equipment works.The way of prior art is at SF 6electrical equipment arranges pressure gauge, reads manometric force value by human at periodic intervals and judge whether force value drops to rating value.If determine force value to drop to rating value, then by inflating manually.
But most of electric power facility is all that implementation is unattended, so, SF 6when the force value of electrical equipment drops to rating value, cannot learn the very first time, cause and can not inflate in time.And if can not inflate in time, then can cause SF 6electrical equipment non-programmed halt, and then cause power grid accident, there is serious potential safety hazard.
Summary of the invention
The technical problem that the present invention mainly solves is to provide a kind of electric equipment intelligent SF6 inflator module, can automatically to SF 6electrical equipment is inflated.
For solving the problems of the technologies described above, the technological scheme that the present invention adopts is: provide a kind of electric equipment intelligent SF 6inflator module, comprises SF 6gas tank, the first solenoid valve, the first pressure detector, the first controller, the second solenoid valve, the second pressure detector, second controller, constent temperature heater, four-way pipe, vacuum pump, the 3rd control valve and the 4th control valve: described SF 6gas tank is for storing high pressure SF 6gas, described SF 6gas tank connects described 3rd control valve, described 3rd control valve connects the first end of described four-way pipe, described first solenoid valve and described second solenoid valve are connected the second end and the 3rd end of described four-way pipe respectively, 4th end of described four-way pipe connects described vacuum pump by described 4th control valve, and described first solenoid valve is by gas ducting and described SF 6the inflation inlet of electrical equipment connects, and described second solenoid valve connects for accessing external high pressure SF 6the aerating pipeline of gas, described first control valve, the second control valve, the 3rd control valve and the 4th control valve original state are for closing, described first pressure detector is for detecting described SF 6a SF in electrical equipment 6gas pressure value, and by a described SF 6gas pressure value sends to described first controller, described first controller is for receiving a described SF 6gas pressure value, and at a described SF 6when gas pressure value is lower than the first preset pressure threshold value, opens after described 4th control valve and described vacuum pump vacuumize, then close described 4th control valve and open described first solenoid valve and described 3rd solenoid valve, at a described SF 6when gas pressure value is higher than the first preset pressure threshold value, close described first solenoid valve and described 3rd solenoid valve, described second pressure detector is for detecting described SF 6the 2nd SF in gas tank 6gas pressure value, and by described 2nd SF 6gas pressure value sends to described second controller, described second controller is for receiving described 2nd SF 6gas pressure value, and at described 2nd SF 6when gas pressure value is lower than the second preset pressure threshold value, controls described second solenoid valve and connect described aerating pipeline, at described 2nd SF 6when gas pressure value is higher than the second preset pressure threshold value, control aerating pipeline described in described second solenoid valve shuts, described constent temperature heater is installed in the outside of described gas ducting, described constent temperature heater comprises switch power, solid-state relay, heating coil, temperature transducer and temperature regulate chip, described heating coil and described temperature transducer are installed in the outside of described gas ducting, the input end of described switch power connects civil power, the cathode output end of described switch power is connected with the positive pole of described solid-state relay, the cathode output end of described switch power is connected with one end of described heating coil, the negative pole of described solid-state relay is connected with the other end of described heating coil, control end and the described temperature of described solid-state relay regulate the control end of chip to be connected, output terminal and the described temperature of described temperature transducer regulate the input end of chip to be connected, wherein, described second preset pressure threshold value is greater than described first preset pressure threshold value, and connects described SF when described gas ducting and described aerating pipeline are different at any time 6gas tank.
Be different from the situation of prior art, the invention has the beneficial effects as follows: by SF 6electrical equipment carries out SF 6gas pressure value detects, according to SF 6the size of gas pressure value carrys out Controlling solenoid valve to SF 6electrical equipment is inflated, meanwhile, to SF 6gas tank also carries out SF 6gas pressure value detects, according to SF 6the size of gas pressure value carrys out Controlling solenoid valve to SF 6gas tank carries out aerating, makes SF 6gas tank at any time can to SF 6electrical equipment is inflated, thus can automatically to SF 6electrical equipment is inflated, and ensures SF 6electrical equipment normally works.
Accompanying drawing explanation
Fig. 1 is embodiment of the present invention electric equipment intelligent SF 6the structural representation of inflator module.
Fig. 2 is the structural representation of constent temperature heater in Fig. 1.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, be clearly and completely described the technological scheme in the embodiment of the present invention, obviously, described embodiment is only a part of embodiment of the present invention, instead of whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art, not making the every other embodiment obtained under creative work prerequisite, belong to the scope of protection of the invention.
See Fig. 1, be embodiment of the present invention electric equipment intelligent SF 6the structural representation of inflator module.The electric equipment intelligent SF of the present embodiment 6inflator module comprises SF 6gas tank 1, first solenoid valve 2, first pressure detector 3, first controller 4, second solenoid valve 5, second pressure detector 6, second controller 7, constent temperature heater 8, four-way pipe 9, the 3rd control valve 10, the 4th control valve 11 and vacuum pump 12.
SF 6gas tank 1 is for storing high pressure SF 6gas, SF 6gas tank 1 connects the first end that the 3rd control valve the 10, three control valve 10 connects four-way pipe 9, and the first solenoid valve 2 and the second solenoid valve 5 are connected the second end and the 3rd end of four-way pipe 9 respectively, and the 4th end of four-way pipe 9 connects vacuum pump 12 by the 4th control valve 11.
First solenoid valve 2 is by gas ducting 21 and SF 6the inflation inlet of electrical equipment 10 connects.Second solenoid valve 5 connects for accessing external high pressure SF 6the aerating pipeline 51 of gas.First control valve 2, second control valve 5, the 3rd control valve 10 and the 4th control valve 11 original state are for closing.
First pressure detector 3 is for detecting SF 6a SF in electrical equipment 10 6gas pressure value, and by a SF 6gas pressure value sends to the first controller 4.
First controller 4 is for receiving a SF 6gas pressure value, and at a SF 6when gas pressure value is lower than the first preset pressure threshold value, after unlatching the 4th control valve 11 and vacuum pump 12 vacuumize, then closes the 4th control valve 11 and open the first solenoid valve 2 and the 3rd solenoid valve 10, at a SF 6when gas pressure value is higher than the first preset pressure threshold value, close the first solenoid valve 2 and the 3rd solenoid valve 10.Wherein, at SF 6before gas ducting 21 connected by gas tank 1, first process is vacuumized to four-way pipe 9, purification object can be reached.
Second pressure detector 6 is for detecting SF 6the 2nd SF in gas tank 1 6gas pressure value, and by the 2nd SF 6gas pressure value sends to second controller 7.
Second controller 7 is for receiving the 2nd SF 6gas pressure value, and at the 2nd SF 6when gas pressure value is lower than the second preset pressure threshold value, controls the second solenoid valve 5 and connect aerating pipeline 51, at the 2nd SF 6when gas pressure value is higher than the second preset pressure threshold value, controls the second solenoid valve 5 and cut off aerating pipeline 51.
Constent temperature heater 8 is installed in the outside of gas ducting 21, see Fig. 2, is the structural representation of constent temperature heater in Fig. 1.Constent temperature heater 8 comprises switch power 81, solid-state relay 82, heating coil 83, temperature transducer 84 and temperature and regulates chip 85.Heating coil 83 and temperature transducer 84 are installed in the outside of gas ducting 21, the input end of switch power 81 connects civil power, the cathode output end of switch power 81 is connected with the positive pole of solid-state relay 82, the cathode output end of switch power 81 is connected with one end of heating coil 83, the negative pole of solid-state relay 82 is connected with the other end of heating coil 83, control end and the temperature of solid-state relay 82 regulate the control end of chip 85 to be connected, and output terminal and the temperature of temperature transducer 84 regulate the input end of chip 85 to be connected.Temperature regulates chip 85 to send control signal according to the sensing data of temperature transducer 84 to the control end of solid-state relay 82, in order to control conducting and the shutoff of solid-state relay 82, thus controls transfer is to the electric energy of described heating coil 83, realize the heating and temperature control to heating coil 83, be embodied as gas ducting 21 and isoperibol is provided, reduce SF in gas ducting 21 6gas decomposes due to overheating and causes the generation of sulfur-containing compound.
Wherein, the second preset pressure threshold value is greater than the first preset pressure threshold value, and connects SF when gas ducting 21 and aerating pipeline 51 are different at any time 6gas tank 1.
By the way, the electric equipment intelligent SF of the embodiment of the present invention 6inflator module is passed through SF 6electrical equipment carries out SF 6gas pressure value detects, according to SF 6the size of gas pressure value carrys out Controlling solenoid valve to SF 6electrical equipment is inflated, meanwhile, to SF 6gas tank also carries out SF 6gas pressure value detects, according to SF 6the size of gas pressure value carrys out Controlling solenoid valve to SF 6gas tank carries out aerating, makes SF 6gas tank at any time can to SF 6electrical equipment is inflated, thus can automatically to SF 6electrical equipment is inflated, and ensures SF 6electrical equipment normally works, and owing to not needing artificial participation, thus reduces cost of equipment maintenance.
The foregoing is only embodiments of the invention; not thereby the scope of the claims of the present invention is limited; every utilize specification of the present invention and accompanying drawing content to do equivalent structure or equivalent flow process conversion; or be directly or indirectly used in other relevant technical fields, be all in like manner included in scope of patent protection of the present invention.

Claims (1)

1. an electric equipment intelligent SF 6inflator module, is characterized in that, comprises SF 6gas tank, the first solenoid valve, the first pressure detector, the first controller, the second solenoid valve, the second pressure detector, second controller, constent temperature heater, four-way pipe, vacuum pump, the 3rd control valve and the 4th control valve:
Described SF 6gas tank is for storing high pressure SF 6gas, described SF 6gas tank connects described 3rd control valve, described 3rd control valve connects the first end of described four-way pipe, described first solenoid valve and described second solenoid valve are connected the second end and the 3rd end of described four-way pipe respectively, 4th end of described four-way pipe connects described vacuum pump by described 4th control valve, and described first solenoid valve is by gas ducting and described SF 6the inflation inlet of electrical equipment connects, and described second solenoid valve connects for accessing external high pressure SF 6the aerating pipeline of gas, described first control valve, the second control valve, the 3rd control valve and the 4th control valve original state are for closing;
Described first pressure detector is for detecting described SF 6a SF in electrical equipment 6gas pressure value, and by a described SF 6gas pressure value sends to described first controller;
Described first controller is for receiving a described SF 6gas pressure value, and at a described SF 6when gas pressure value is lower than the first preset pressure threshold value, opens after described 4th control valve and described vacuum pump vacuumize, then close described 4th control valve and open described first solenoid valve and described 3rd solenoid valve, at a described SF 6when gas pressure value is higher than the first preset pressure threshold value, close described first solenoid valve and described 3rd solenoid valve;
Described second pressure detector is for detecting described SF 6the 2nd SF in gas tank 6gas pressure value, and by described 2nd SF 6gas pressure value sends to described second controller;
Described second controller is for receiving described 2nd SF 6gas pressure value, and at described 2nd SF 6when gas pressure value is lower than the second preset pressure threshold value, controls described second solenoid valve and connect described aerating pipeline, at described 2nd SF 6when gas pressure value is higher than the second preset pressure threshold value, control aerating pipeline described in described second solenoid valve shuts;
Described constent temperature heater is installed in the outside of described gas ducting, described constent temperature heater comprises switch power, solid-state relay, heating coil, temperature transducer and temperature regulate chip, described heating coil and described temperature transducer are installed in the outside of described gas ducting, the input end of described switch power connects civil power, the cathode output end of described switch power is connected with the positive pole of described solid-state relay, the cathode output end of described switch power is connected with one end of described heating coil, the negative pole of described solid-state relay is connected with the other end of described heating coil, control end and the described temperature of described solid-state relay regulate the control end of chip to be connected, output terminal and the described temperature of described temperature transducer regulate the input end of chip to be connected,
Wherein, described second preset pressure threshold value is greater than described first preset pressure threshold value, and connects described SF when described gas ducting and described aerating pipeline are different at any time 6gas tank.
CN201510589122.3A 2015-09-16 2015-09-16 Intelligent SF6 (sulfur hexafluoride) gas inflation module for electrical equipment Withdrawn CN105299444A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510589122.3A CN105299444A (en) 2015-09-16 2015-09-16 Intelligent SF6 (sulfur hexafluoride) gas inflation module for electrical equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510589122.3A CN105299444A (en) 2015-09-16 2015-09-16 Intelligent SF6 (sulfur hexafluoride) gas inflation module for electrical equipment

Publications (1)

Publication Number Publication Date
CN105299444A true CN105299444A (en) 2016-02-03

Family

ID=55197040

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510589122.3A Withdrawn CN105299444A (en) 2015-09-16 2015-09-16 Intelligent SF6 (sulfur hexafluoride) gas inflation module for electrical equipment

Country Status (1)

Country Link
CN (1) CN105299444A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107943120A (en) * 2017-12-26 2018-04-20 郑州赛奥电子股份有限公司 A kind of on-line automatic density regulating apparatus of SF6
CN109027664A (en) * 2018-07-13 2018-12-18 国网安徽省电力有限公司检修分公司 A kind of online supplementing method for air of SF6 electrical equipment
CN112673206A (en) * 2018-05-30 2021-04-16 气体运输技术公司 Liquefied gas storage device
CN112815228A (en) * 2021-03-30 2021-05-18 国网河南省电力公司平顶山供电公司 SF (sulfur hexafluoride)6Intelligent inflating device of operating equipment
CN114017664A (en) * 2021-11-19 2022-02-08 国网新疆电力有限公司电力科学研究院 Device for preventing low-temperature liquefaction of sulfur hexafluoride gas-filled equipment

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107943120A (en) * 2017-12-26 2018-04-20 郑州赛奥电子股份有限公司 A kind of on-line automatic density regulating apparatus of SF6
CN112673206A (en) * 2018-05-30 2021-04-16 气体运输技术公司 Liquefied gas storage device
CN109027664A (en) * 2018-07-13 2018-12-18 国网安徽省电力有限公司检修分公司 A kind of online supplementing method for air of SF6 electrical equipment
CN112815228A (en) * 2021-03-30 2021-05-18 国网河南省电力公司平顶山供电公司 SF (sulfur hexafluoride)6Intelligent inflating device of operating equipment
CN114017664A (en) * 2021-11-19 2022-02-08 国网新疆电力有限公司电力科学研究院 Device for preventing low-temperature liquefaction of sulfur hexafluoride gas-filled equipment

Similar Documents

Publication Publication Date Title
CN105299444A (en) Intelligent SF6 (sulfur hexafluoride) gas inflation module for electrical equipment
CN207230153U (en) A kind of full-automatic SF6 electrical equipment aerating devices
CN109386731B (en) SF6 gas automatic filling system and filling method of GIS equipment
CN201369283Y (en) Recovering and refilling device for sulfur hexafluoride gas
CN105221926A (en) The SF of electrical equipment 6automatic inflating equipment
CN112815228B (en) SF (sulfur hexafluoride) 6 Intelligent air charging device of operating equipment
CN105202361A (en) Intelligent SF 6 air inflation unit of electrical equipment
CN204240052U (en) SF 6gas inflated, exhaust gas recovery, density meter effect instrument
CN204302440U (en) Can to multiple stage SF 6insulation of electrical installation state and moisture carry out the device of on-line monitoring
CN105202358A (en) SF6 air inflation device of electrical equipment
CN105202360A (en) SF6 air inflation equipment of electrical equipment
CN105299445A (en) Intelligent SF6 inflation device of electric equipment
CN103742782B (en) A kind of electric power charged intelligent making-up air device of SF6 mutual inductor and supplementing method for air thereof
CN203690199U (en) Electric power SF6 breaker live-line intelligent gas supplementing device
CN109027664A (en) A kind of online supplementing method for air of SF6 electrical equipment
CN105221927A (en) SF 6the SF of electrical equipment 6inflator module
CN207865026U (en) The on-line automatic making-up air device of sulfur hexafluoride electrical equipment
CN105202359A (en) SF6 air inflation equipment of electrical equipment
CN203273118U (en) Multi-purpose connector of sulfur hexafluoride gas recovery device
CN105257975A (en) SF6 inflating device of SF6 electrical equipment
CN105156885A (en) SF6 gas charging unit of SF6 electrical device
CN203660401U (en) Oil gas bushing connection gas pipe apparatus for 220 combination electric appliance
CN105156886A (en) Automatic SF6 gas-filling device of electrical apparatus
CN203929524U (en) Steel pipe hydrostatic testing automaton
CN205828265U (en) A kind of drawing-off gas structure of Yellow phosphorus furnace transformator

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20160203

WW01 Invention patent application withdrawn after publication