CN105298507B - A kind of underground pipe gallery construction method of top open cut bottom tunneler construction - Google Patents

A kind of underground pipe gallery construction method of top open cut bottom tunneler construction Download PDF

Info

Publication number
CN105298507B
CN105298507B CN201510790394.XA CN201510790394A CN105298507B CN 105298507 B CN105298507 B CN 105298507B CN 201510790394 A CN201510790394 A CN 201510790394A CN 105298507 B CN105298507 B CN 105298507B
Authority
CN
China
Prior art keywords
shield
construction
tube coupling
cut
piping lane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510790394.XA
Other languages
Chinese (zh)
Other versions
CN105298507A (en
Inventor
李建斌
于少辉
李洋
王全胜
张新伟
程绍磊
范磊
孙恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Engineering Equipment Group Co Ltd CREG
Original Assignee
China Railway Engineering Equipment Group Co Ltd CREG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Engineering Equipment Group Co Ltd CREG filed Critical China Railway Engineering Equipment Group Co Ltd CREG
Priority to CN201510790394.XA priority Critical patent/CN105298507B/en
Publication of CN105298507A publication Critical patent/CN105298507A/en
Application granted granted Critical
Publication of CN105298507B publication Critical patent/CN105298507B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The present invention provides a kind of underground pipe gallery construction method of top open cut bottom tunneler construction, carries out as steps described below:(1) construction launching shaft and received well;(2) the construction piping lane section part soil body;(3) piping lane top earthing uses excavator open-cut;(4) Pipe rack uses the tube coupling of prefabricated reinforced concrete, lifting appliance on ground is hung into assembled position, when tube coupling deviates from shield tail after installing, and packing material is synchronously backfilled in tube coupling sidepiece and bottom, deviate from after shield tail, backfilling of earthwork is carried out at the top of tube coupling;(5) rectangular shield is tunneled to received well along piping lane designed lines, hangs out Suporting structure, completes structure and backfill construction, and construction terminates.The present invention by the way of cut and cover method is combined, solves the city integrated problem that piping lane open-cut floor space is big, speed of application is slow using shield method, with more preferable adaptability, has cut and cover method concurrently with low cost with the safe and efficient advantage of shield method.

Description

A kind of underground pipe gallery construction method of top open cut bottom tunneler construction
Technical field
The invention belongs to city underground engineering technical field of construction, and in particular to a kind of top open cut bottom tunneler construction Underground pipe gallery construction method.
Background technology
Urban Underground pipe gallery is new city municipal administration infrastructure, be construction of modern important symbol it One.It to modern city environment, reduce urban road and repeat to excavate, play good demonstration and impetus.Build underground Pipe gallery can meet realize city intensivization development, spatial synthesis utilize the need for, expand urban development space, build up efficiently Operation, the city support system of ecological low-carbon;Space under effective intensive utilization road, economizes the land resource.
The construction of current pipe gallery mainly has:Cut and cover method and no-dig technique method.Cut and cover method large area is excavated, destruction ring Border, influences big to ground installations such as traffic, buildings, the interference nearby residents normal work life such as noise, dust, earth excavation Backfill occupies large number of ground space, and dewatering operation is needed in the case where level of ground water is shallower, foundation ditch is needed when buried depth is larger again Supporting, mechanization of building operation degree is low, inefficient, and in particular cases construction cost is higher, but its construction is to technology, equipment and people Member requires low, has cost advantage in spacious outskirts of a town or newly built city district construction;No-dig technique engineering method is using circular or shield rectangular top Tube apparatus does not destroy ground surface environment in underground boring construction, small to ground disturbance, to traffic above-ground, building etc. almost without shadow Ring, many merits such as construction site is small, efficiency is high, but its construction cost is higher, is unfavorable for stratum stability contorting when earthing is excessively shallow.
The content of the invention
There is provided a kind of top open cut bottom tunneler construction for above-mentioned the deficiencies in the prior art for the purpose of the present invention Underground pipe gallery construction method, its adaptability is stronger, with low cost and safe and efficient.
The technical proposal of the invention is realized in this way:A kind of underground pipe gallery construction of top open cut bottom tunneler construction Method, is carried out as steps described below:(1) construction launching shaft and received well, make shield be completed in the two vertical shafts Originate and receive;(2) using the open type rectangular shield construction piping lane section part soil body, rectangular shield is dug along piping lane designed lines Enter, the thrust laid and provided on tube coupling forward is provided by oil cylinder, slagged tap using belt, shield is arranged at shield tail both sides and bottom Shield, prevents dregs entrance around;(3) piping lane top earthing uses excavator open-cut;(4) Pipe rack is using precast reinforced Concrete tube coupling, is hung into assembled position, tube coupling is installed by the lifting appliance at rectangular shield rear aperture on ground When deviating from shield tail after finishing, after tube coupling sidepiece and bottom synchronously backfill packing material, abjection shield tail, the earthwork is carried out at the top of tube coupling Backfill;(5) rectangular shield is tunneled to received well along piping lane designed lines, hangs out Suporting structure, is completed structure and backfill construction, is applied Work terminates.
It is preferred that, the present invention is as follows:(1) pipe gallery construction bottom is excavated using rectangular shield, and top uses open cut; (2) tube coupling uses prefabricated reinforced concrete tube coupling;(3) after the completion of tube coupling is assembled, top is backfilled with dregs;(4) rectangular shield Shield is arranged at shield tail both sides and bottom, and top is opened wide, for hanging in installation for tube coupling;(5) there is earth-retaining in shield both sides above shield shell Above plate, breast boards insertion shield and in the soil body of front, the gib of open-cut is used as.
Further preferably, the present invention is as follows:(1) rectangular shield size is according to pipe gallery size design, it is ensured that tube coupling is suitable It is sharp assembled;(2) soil body is excavated by the cutter laid on rectangle cutterhead;(3) there is complete dreg removing system;(4) at the top of shield tail Open wide, be available for tube coupling to hang in assembly;(5) shield back and front set breast boards, are top open cut operation and tube coupling peace Dress provides gib;(6) shield machine provides jacking force jacking construction forward by acting on the hydraulic jack on tube coupling.
The present invention solves the city integrated problem that piping lane open-cut floor space is big, speed of application is slow.With existing skill Art is compared, and this method mechanization degree is high, speed of application is fast, underground pipe gallery construction can be completed in narrow and small place, with tradition Method, which is compared, can also substantially reduce ambient influnence and construction risk, and with good economy.The present invention using shield method with The mode that cut and cover method is combined, solves the city integrated problem that piping lane open-cut floor space is big, speed of application is slow, has More preferable adaptability, has that cut and cover method is with low cost and the advantage of shield method rapidly and efficiently concurrently, and with more preferable adaptability.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is the accompanying drawing used required in technology description to be briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, can be with Other accompanying drawings are obtained according to these accompanying drawings.
Fig. 1 excavates view for present invention distribution.
Fig. 2 is construction process schematic diagram.
Wherein:1. drag-out slag car, 2. backhoes, 3. backfills, 4. haulage trucks, 5. cranes, 6. carrying walls, 7. reaction frames, 8. back-grouting, 9. tube couplings, 10. dreg removing systems, 11. shield tails, 12. cutterheads, 13. breast boards, 14. starting wells, 15. received wells.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not paid Embodiment, belongs to the scope of protection of the invention.
As illustrated in fig. 1 and 2, a kind of underground pipe gallery construction method of top open cut bottom tunneler construction, is according to following What step was carried out:
(1) construction launching shaft 14 and received well 15, make shield complete the beginning in two vertical shafts of starting well and received well Hair and reception;
(2) using the open type rectangular shield construction piping lane section part soil body, according to geological condition can be set cutterhead 12 or Person uses other cutting ways, and rectangular shield is tunneled along piping lane designed lines, is acted on by oil cylinder and has laid offer on tube coupling Thrust forward, is slagged tap using belt, and dregs is discharged by dreg removing system 10, drag-out slag car 1, and shield is arranged at the both sides of shield tail 11 and bottom Shield, prevents dregs entrance around;
(3) piping lane top earthing uses excavator open-cut;
(4) Pipe rack use prefabricated reinforced concrete tube coupling 9, by rectangular shield rear aperture on ground Lifting appliance is hung into assembled position, when tube coupling deviates from shield tail after installing, in tube coupling sidepiece and bottom synchronously backfill filling After material, abjection shield tail, backfilling of earthwork is carried out at the top of tube coupling, backfill 3 is filled by backfill backhoe 2, haulage truck 4.
(5) rectangular shield is tunneled to received well along piping lane designed lines, hangs out Suporting structure, completes structure and backfill is applied Work, construction terminates.
Wherein the side wall of starting well 14 is that reaction frame 7 is provided with carrying wall 6, starting well 6, and the both sides of cutterhead 12 are provided with breast boards 13。
In the present invention, the excavation size of the rectangular shield is consistent with piping lane Section Design size;Shield tail both sides and bottom There is shield, top is opened wide, for hanging in installation for tube coupling;There are breast boards, breast boards insertion shield above shield shell in shield both sides In the soil body of front, the gib of open-cut is used as.
In the present invention, piping lane section is excavated using open type rectangular shield;Piping lane top earthing uses open-cut;Tube coupling Shield tail is put into from shield rear upper open hanger by lifting appliance and completes assembled;Shield is by acting on the jack on tube coupling Propulsive force forward is provided.
The technological principle of the present invention:
1. digging process stratum is stable:Shield-tunneling construction keeps in a basic balance by cutterhead thrust and the face soil body;Open cut Construction keeps soil at both sides basicly stable by shield breast boards.
2. the back-grouting 8 of tube coupling 9 ensures that stratum is stable:Installed in open type shield machine shield tail after tube coupling, in tube coupling Testing of Grouting Material Behind Segments is used to carry out once grouting with the gap of the shield tail of shield machine;The shield tail produced along with the driving of shield machine Gap (equivalent to shield side plate, the thickness of bottom plate), progress secondary grouting synchronous with driving.
The sequence of construction of the present invention is as follows:Construct and originate vertical shaft and received well → driving → pipe is started by starting well shield Corridor section shield tunneling, top soil body open cut → tube coupling installation → backfilling of earthwork → shield, which continues to tunnel, completes subsequent cycle → pick Enter to complete arrival and receive → complete whole section of piping lane construction.
Compared with prior art, the present invention also tool has the advantage that:
1) cut and cover method economy and shield method security are had concurrently, while a wide range of interference of the cut and cover method to environment is avoided, When buried depth is larger, it is to avoid pattern foundation pit supporting structure, speed of application is faster;
2) tight turn radius construction can be carried out;
3) can be in the neighbouring construction adjacent to buildings such as houses;
4) it can be constructed under the complex geological conditions such as soft stratum, water-bearing layer, earth layer of solitary stone;
5) noise, vibration are small;
6) construction width range is small, and dregs is few, environmentally friendly;
7) piping lane ground can be handled;
8) device extension is good, can be applied to complete mechanical boring construction after extension simultaneously.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention God is with principle, and any modification, equivalent substitution and improvements made etc. should be included in the scope of the protection.

Claims (2)

1. a kind of underground pipe gallery construction method of top open cut bottom tunneler construction, it is characterised in that be to enter as steps described below Capable:
(1) construction launching shaft and received well, make shield complete to originate and receive in the two vertical shafts;
(2) using the open type rectangular shield construction piping lane section part soil body, rectangular shield is tunneled along piping lane designed lines, passed through Oil cylinder acts on the thrust laid and provided on tube coupling forward, is slagged tap using belt, and shield is arranged at shield tail both sides and bottom, prevents week Enclose dregs entrance;
(3) piping lane top earthing uses excavator open-cut;
(4) Pipe rack uses the tube coupling of prefabricated reinforced concrete, passes through the lifting at rectangular shield rear aperture on ground Equipment is hung into assembled position, when tube coupling deviates from shield tail after installing, and packing material is synchronously backfilled in tube coupling sidepiece and bottom, Deviate from after shield tail, backfilling of earthwork is carried out at the top of tube coupling;
(5) rectangular shield is tunneled to received well along piping lane designed lines, hangs out Suporting structure, is completed structure and backfill construction, is applied Work terminates;
Above-mentioned steps (1) ~(5)Middle pipe gallery construction bottom is excavated using rectangular shield, and top uses open cut;Tube coupling is used Prefabricated reinforced concrete tube coupling;After the completion of tube coupling is assembled, top is backfilled with dregs;The shield tail both sides of rectangular shield and bottom have Shield, top is opened wide, for hanging in installation for tube coupling;Have above shield shell in shield both sides in breast boards, breast boards insertion shield In side and the front soil body, the gib of open-cut is used as.
2. the underground pipe gallery construction method of top open cut bottom tunneler construction according to claim 1, it is characterised in that: (1) rectangular shield size is according to pipe gallery size design, it is ensured that tube coupling is smoothly assembled;(2) by laying on rectangle cutterhead Cutter excavates the soil body;(3) there is complete dreg removing system;(4) opened wide at the top of shield tail, be available for tube coupling to hang in assembly;(5) shield machine Body and front set breast boards, are that top open cut operation and tube coupling are installed and provide gib;(6) shield machine passes through effect Hydraulic jack on tube coupling provides jacking force jacking construction forward.
CN201510790394.XA 2015-11-17 2015-11-17 A kind of underground pipe gallery construction method of top open cut bottom tunneler construction Active CN105298507B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510790394.XA CN105298507B (en) 2015-11-17 2015-11-17 A kind of underground pipe gallery construction method of top open cut bottom tunneler construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510790394.XA CN105298507B (en) 2015-11-17 2015-11-17 A kind of underground pipe gallery construction method of top open cut bottom tunneler construction

Publications (2)

Publication Number Publication Date
CN105298507A CN105298507A (en) 2016-02-03
CN105298507B true CN105298507B (en) 2017-09-12

Family

ID=55196236

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510790394.XA Active CN105298507B (en) 2015-11-17 2015-11-17 A kind of underground pipe gallery construction method of top open cut bottom tunneler construction

Country Status (1)

Country Link
CN (1) CN105298507B (en)

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049532B (en) * 2016-07-25 2018-03-30 中铁工程装备集团有限公司 A kind of pipe gallery open-cut branch blocking means and its construction method
CN106088149B (en) * 2016-08-05 2017-08-25 中交第二航务工程局有限公司 A kind of mechanization rapid constructing method of precast splice type underground gallery
CN106869165A (en) * 2017-02-20 2017-06-20 曾庆如 City integrated prefabricated piping lane open cut formula is from construction of prevention work method and self-propelled laydown machine
CN107268681A (en) * 2017-08-09 2017-10-20 中国铁建重工集团有限公司 Piping lane apparatus for work
CN107762519B (en) * 2017-11-03 2020-03-31 上海市城市建设设计研究总院(集团)有限公司 Pipe jacking enclosing construction method for end transverse channel of subway station
CN109555126A (en) * 2017-12-28 2019-04-02 中建科技有限公司深圳分公司 Foundation pit method for digging
CN109555154B (en) * 2017-12-28 2020-12-22 中建科技有限公司深圳分公司 Open excavation construction method for comprehensive pipe gallery
CN108661666B (en) * 2018-05-02 2020-02-18 中亿丰隧道工程股份有限公司 Assembling method of rectangular half pipe section shield pipe section and special equipment thereof
CN109024668B (en) * 2018-06-07 2021-09-14 北京市轨道交通设计研究院有限公司 Construction method of multilayer subway station
CN109610503A (en) * 2018-06-14 2019-04-12 中煤建工集团有限公司 A kind of prefabricated piping lane installation method
CN109812272B (en) * 2019-01-30 2020-12-11 浙江汉领建设有限公司 Construction method of shield pipe gallery
CN111852487A (en) * 2020-06-09 2020-10-30 中铁工程装备集团有限公司 Stratum instability prevention type tunneling device and construction method thereof
CN112343614B (en) * 2020-11-03 2022-08-30 中能(厦门)智慧科技有限公司 U-shaped shield tunneling machine-based overlapped-spliced comprehensive pipe gallery construction method
CN112727466A (en) * 2021-01-29 2021-04-30 绍兴市柯桥区轨道交通集团有限公司 Construction method for support-free prefabricated assembled type shield tunnel air shaft structure
CN114960620A (en) * 2021-02-26 2022-08-30 中能(厦门)智慧科技有限公司 Construction method of underground continuous hollow wall
CN113737854A (en) * 2021-09-24 2021-12-03 中国建筑第七工程局有限公司 Underground pipe gallery construction method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4309219B2 (en) * 2003-09-30 2009-08-05 大成建設株式会社 Tunnel construction method
CN102995660B (en) * 2012-12-21 2015-07-22 张双里 Multifunctional arched combined prestress underground pipe gallery for cisty and preparation process thereof
CN103174131A (en) * 2013-02-07 2013-06-26 北京建工集团有限责任公司 Underground engineering guiding-cavity-excavating small-diameter pile construction complete equipment system
CN103953354B (en) * 2014-04-28 2016-10-05 北京市三一重机有限公司 Opened type shield machine
CN204401650U (en) * 2014-12-08 2015-06-17 张楸长 Square longitudinally connection prestressed assembly formula underground pipe gallery
CN105019475B (en) * 2015-08-06 2018-05-04 湖北宇辉新型建筑材料有限公司 Fabricated assembly overall concrete pipe gallery and construction

Also Published As

Publication number Publication date
CN105298507A (en) 2016-02-03

Similar Documents

Publication Publication Date Title
CN105298507B (en) A kind of underground pipe gallery construction method of top open cut bottom tunneler construction
CN102644466B (en) Joist arching method for constructing ultra-shallow buried large-span underground excavated subway station in rocky stratum
CN106049532B (en) A kind of pipe gallery open-cut branch blocking means and its construction method
CN103726495B (en) Coastal waters deep foundation pit supporting structure and construction method thereof
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN103590406A (en) Construction method for synchronously excavating ultra-large type deep foundation pits in partitioned mode
CN104131565B (en) A kind of against making the construction method that the earthwork is just made to excavate
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN102704957A (en) Shed-frame method for shallowly burying large-sized underground structure construction
CN103485790A (en) Shallow tunneling method for pipe-proof-supporting structure combined system
CN104674827A (en) Novel totally-closed water stopping system for water-rich stratum foundation pit and construction method of novel totally-closed water stopping system
WO2021088349A1 (en) Method for excavating tunnel shaft
CN103775110A (en) Underground excavation construction method for multilayer underground space of soft soil area
CN103410152B (en) A kind of construction method for long and narrow deep foundation pit earthwork digging
CN101793023A (en) Foundation pit construction method
CN107514262A (en) The construction method of shield piping lane
CN108677926A (en) Coercion underground continuous wall and its construction method
JP4132442B2 (en) Tunnel construction method
CN108677925A (en) Half coercion underground continuous wall structure and its construction method
CN204825923U (en) Relay formula underground structure
CN208441084U (en) Coercion underground continuous wall
CN106640155A (en) Large-span underground space structure and construction method thereof
CN203613544U (en) Envelop enclosure for deep foundation pit partition simultaneous excavation
CN209760299U (en) light and shade of avoiding house to tear open and move is dug and is combined subway station structure
CN208441083U (en) Half coercion underground continuous wall structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant