CN105293304A - Tower crane with counterweight blocks capable of being quickly mounted or demounted - Google Patents

Tower crane with counterweight blocks capable of being quickly mounted or demounted Download PDF

Info

Publication number
CN105293304A
CN105293304A CN201510829590.3A CN201510829590A CN105293304A CN 105293304 A CN105293304 A CN 105293304A CN 201510829590 A CN201510829590 A CN 201510829590A CN 105293304 A CN105293304 A CN 105293304A
Authority
CN
China
Prior art keywords
counterweight
clump weight
slideway
tower crane
arm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510829590.3A
Other languages
Chinese (zh)
Other versions
CN105293304B (en
Inventor
郑冬冬
王克军
许常敏
郑杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHANGJIAGANG ZHONGLIAN CONSTRUCTION MACHINERY Co.,Ltd.
Original Assignee
ZHENHAI CONSTRUCTION GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHENHAI CONSTRUCTION GROUP Co Ltd filed Critical ZHENHAI CONSTRUCTION GROUP Co Ltd
Priority to CN201510829590.3A priority Critical patent/CN105293304B/en
Publication of CN105293304A publication Critical patent/CN105293304A/en
Application granted granted Critical
Publication of CN105293304B publication Critical patent/CN105293304B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

The invention discloses a tower crane with counterweight blocks capable of being quickly mounted or demounted, and relates to construction engineering machinery. A jib and a balance arm are arranged on a rotating platform table, and are at opposite positions; a counterweight lifting device is arranged at the inner top of a jacking sleeve frame, and can move up and down in standard joints; a counterweight slideway matched with the counterweight lifting device is arranged on the balance arm; a fixing device for fixing the counterweight blocks, and an air bag device for protecting the counterweight blocks are also arranged on the balance arm; the air bag device comprises an air bag which is arranged at the lower part of the top end of the balance arm and can be repeatedly inflated. Compared with the prior art, the tower crane disclosed by the invention has the advantages that the counterweight blocks can be quickly mounted or demounted, and the counterweight blocks can be quickly demounted when a typhoon approaches or under other states with strong wind so as to keep the barycentre of the tower body stable; the tower crane disclosed by the invention solves the problems that because conventional counterweight blocks need to be mounted by a crane, the mounting efficiency and the mounting speed are low; further, according to the tower crane disclosed by the invention, when the counterweight blocks drop off accidentally, the counterweight blocks can be wrapped, so that the phenomenon that after the counterweight blocks are crashed into pieces, the block pieces splash and hurt people is avoided.

Description

A kind of can the tower crane of fast assembling-disassembling clump weight
Technical field
The present invention relates to a kind of constructional engineering machinery, especially relate to a kind of building ground tower crane.
Background technology
Tower crane is called for short tower machine, also known as tower crane, originates from West Europe.It is exactly the rotary crane that swing arm is contained in towering tower body top.Tower crane working space is large, is mainly used in the installation of vertical and horizontal feed and the building element of material in housing construction.Be made up of metal construction, operating mechanism and electric system three part.Metal construction comprises tower body, swing arm and base etc.Operating mechanism hoists, luffing, revolution and walking four part.Electric system comprises electrical motor, controller, electric power distribution cabinet, connection line, signal and illumination equipment etc.Along with the progress of engineering technology, the floor of present building is more and more higher, make required tower crane also more and more higher, but too high tower crane has the problem of poor stability, especially at southeastern coast During Typhoon, often there is tower crane and hung in typhoon sky the event created greater casualties.In addition, tower crane all needs to install clump weight, and clump weight is all hang on tower crane with other loop wheel machines mostly, and installing/dismounting bothers, and makes tower crane to realize fast-assembling.
Summary of the invention
The present invention is directed to deficiency of the prior art, provide a kind of can the tower crane of fast assembling-disassembling clump weight, the present invention Fast Installation can dismantle clump weight, under typhoon or other strong wind states, can pull down rapidly clump weight keep tower body steadily of centre of gravity, also solving clump weight in the past needs crane to install, and installation effectiveness is low, slow-footed problem, further, the present invention can also wrap clump weight when clump weight surprisingly drops, the problem preventing from clump weight from breaking rear splashing into pieces hurting sb.'s feelings.
In order to solve the problems of the technologies described above, the present invention is solved by following technical proposals: a kind of can the tower crane of fast assembling-disassembling clump weight, comprise pedestal, tower body, jacking stock, rotating table, crane arm, equilibrium arm and clump weight, described tower body is built by several standard knots, described jacking stock can move on described standard knot, described rotating table is arranged on described jacking cover top of the trellis, described crane arm and described equilibrium arm are arranged on described rotating table, described crane arm is relative with described equilibrium arm position, in described jacking stock, top is provided with counterweight jacking system, described counterweight jacking system can move up and down in described standard knot inside, described equilibrium arm is provided with the counterweight slideway matched with described counterweight jacking system, described equilibrium arm is also provided with the anchor fitting of fixing described clump weight and the airbag apparatus of the described clump weight of protection, described airbag apparatus comprise be arranged on bottom, described equilibrium arm top can the air bag of repeated inflation, described air bag is the cuboid of opening upwards, fast connection interface is provided with between described air bag and described equilibrium arm.
In technique scheme, preferably, described counterweight jacking system comprises lifter, described lifter is provided with some stay cords, described stay cord is provided with counterweight fixed way, described counterweight fixed way is provided with fixed way slideway, and described fixed way slideway slides is provided with several clump weight fixed mounts, described counterweight slideway is provided with the alignment device matched with described fixed way slideway.
In technique scheme, preferably, described alignment device electric rotation shaft, described electric rotation shaft is provided with connecting panel, described connecting panel is provided with the connection slideway coordinated with described fixed way slideway and described counterweight slideway, described connecting panel is also provided with several electric expansion limited posts, described fixed way is provided with the spacing hole matched with described electric expansion limited post.
In technique scheme, preferably, described spacing hole is tapered, inwardly reduces gradually from opening part.
In technique scheme, preferably, described clump weight fixed mount is provided with protection framework, drive motor and electronic locked piece.
In technique scheme, preferably, described protection framework biside plate is respectively arranged with inside fixed lobe, described clump weight is provided with the fixed groove matched with described fixed lobe.
In technique scheme, preferably, several supporting linkages are provided with between described counterweight slideway and described equilibrium arm.
Existing clump weight is all lifted by crane, the installation of one piece one piece is needed during lifting, not only installation effectiveness is low, time is long, also dismounting operation cannot be carried out when bad environments, once projection strong wind, clump weight cannot unload the crank being very easy to cause tower crane, jeopardizes production and construction safety.The present invention is then the installation that counterweight jacking system by being arranged on tower crane inside carries out clump weight, without the need to external force, and not by the impact of weather, as long as tower crane can carry out work, just can carry out the dismounting of clump weight.Its cardinal principle utilizes standard knot inner space to form transport channel, in this passage, carry out the rise of clump weight and put down, then after clump weight rises to top, moved to the end of equilibrium arm by the counterweight slideway on equilibrium arm, be fixed finally by the anchor fitting on equilibrium arm.Consistent when principle and installation when clump weight unloads, first removed by anchor fitting fixing, then slide onto on counterweight jacking system, be finally down to ground.In order to reach this effect, counterweight jacking system of the present invention comprises lifter, lifter is provided with some stay cords, stay cord is provided with counterweight fixed way, counterweight fixed way is provided with fixed way slideway, fixed way slideway is provided with clump weight fixed mount.Clump weight is put on clump weight fixed mount, and the fixed way slideway on counterweight fixed way can be aimed at through with counterweight slideway, completed the rise and fall of clump weight by lifter, completes clump weight again move on equilibrium arm by counterweight slideway and fixed way slideway.Again because counterweight jacking system once can transport multiple clump weight or single clump weight, make tower crane in use can increase or reduce breeding fast, also avoid and need now again to replace all clump weight problems.Equilibrium arm is also provided with airbag apparatus, airbag apparatus wraps clump weight, once occur that contingency makes clump weight drop, airbag apparatus drops at next block of effect of clump weight gravity, and the fragment that can prevent the cracked splashing of clump weight from rising when dropping to ground is hurted sb.'s feelings thing.
Compared with prior art, the invention has the beneficial effects as follows: the present invention Fast Installation can dismantle clump weight, under typhoon or other strong wind states, clump weight can be pulled down rapidly keep tower body steadily of centre of gravity, also solving clump weight in the past needs crane to install, installation effectiveness is low, slow-footed problem, further, the present invention can also wrap clump weight when clump weight surprisingly drops, the problem preventing from clump weight from breaking rear splashing into pieces hurting sb.'s feelings.
Accompanying drawing explanation
Fig. 1 is front schematic view of the present invention.
Fig. 2 is contraction state schematic diagram of the present invention.
Fig. 3 is contraction process schematic diagram of the present invention.
Fig. 4 is using state schematic diagram of the present invention.
Fig. 5 is connecting panel schematic diagram of the present invention.
Fig. 6 is clump weight fixed mount side schematic view of the present invention.
Fig. 7 is clump weight fixed mount front schematic view of the present invention.
Fig. 8 is standard knot schematic diagram of the present invention.
Fig. 9 is that Fig. 4-A of the present invention locates partial enlarged drawing schematic diagram.
Figure 10 is that Fig. 4-B of the present invention locates partial enlarged drawing schematic diagram.
Detailed description of the invention
Below in conjunction with accompanying drawing and detailed description of the invention, the present invention is described in further detail.
As shown in Figures 1 to 10, a kind of can the tower crane of fast assembling-disassembling clump weight, comprise pedestal 1, tower body 2, jacking stock 3, rotating table 6, tower top 7, crane arm 5, equilibrium arm 4 and clump weight 11, described tower body 2 is built by several standard knots 21, described jacking stock 3 can move on described standard knot 21, described rotating table 6 is arranged on described jacking stock 3 top, and described tower top 7 is arranged on described rotating table 6.
Described rotating table 6 is respectively arranged with lifting rotating shaft 63 and balance rotating shaft 61, crane arm 5 rotates and is arranged in lifting rotating shaft 63, equilibrium arm 4 rotates and is arranged in balance rotating shaft 61, described crane arm 5 is relative with described equilibrium arm 4 position, described crane arm 5 is provided with several first electric expansion fixed links 64, described rotating table 6 is provided with the first hold down groove matched with described first electric expansion fixed link 64, described equilibrium arm 4 is provided with several second electric expansion fixed links 63, described rotating table 6 is provided with the second hold down groove matched with described second electric expansion fixed link 63, described crane arm 5 and top, described equilibrium arm 4 top are respectively arranged with first Guyed Towers 55 and second Guyed Towers 48, described tower top 7 is provided with first tubing sections device 73 and second tubing sections device 71, be connected by first rope 74 between described first Guyed Towers 55 with described first tubing sections device 73, 72 are connected by second rope between described second Guyed Towers 48 with described second tubing sections device 71, described first rope 74 and described second rope 72 are all that some steel ropes twist into.Described equilibrium arm 4 top is rotated and is provided with electronic drag hook 46, and described electronic drag hook 46 can hang over the junction between two standard knots 21.Described crane arm 5 top is provided with the cambered way 53 be connected with described lifting slideway 51, has occluding device 54 between described lifting slideway 51 and described cambered way 53.Described crane arm 5 and described equilibrium arm 4 top end are respectively arranged with first cable lifter 56 and second cable lifter 47, described pedestal 1 are provided with the fixed hook 13 coordinated with described first cable lifter 56 and described second cable lifter 47.
In described jacking stock 3, top is provided with counterweight jacking system 8, described counterweight jacking system 8 can move up and down in described standard knot 21 inside, described equilibrium arm 4 is provided with the counterweight slideway 41 matched with described counterweight jacking system 8, between described counterweight slideway 41 and described equilibrium arm 4, is provided with several supporting linkages 42.Described counterweight jacking system 8 comprises lifter 81, described lifter 81 is provided with some stay cords 82, described stay cord 82 is provided with counterweight fixed way 83, described counterweight fixed way 83 is provided with fixed way slideway 84, described fixed way slideway 84 slides and is provided with several clump weight fixed mounts 85, described clump weight fixed mount 85 is provided with protection framework 853, drive motor 851 and electronic locked piece 852.Described protection framework 853 biside plate is respectively arranged with inside fixed lobe 854, described clump weight 11 is provided with the fixed groove matched with described fixed lobe 854.Described counterweight slideway 41 is provided with the alignment device 43 matched with described fixed way slideway 84.Described alignment device 43 comprises electric rotation shaft 431, described electric rotation shaft 431 is provided with connecting panel 432, described connecting panel 432 is provided with the connection slideway 433 coordinated with described fixed way slideway 84 and described counterweight slideway 41, described connecting panel 432 is also provided with several electric expansion limited posts 434, described fixed way 83 is provided with the spacing hole 86 matched with described electric expansion limited post 434.Described spacing hole 86 is tapered, inwardly reduces gradually from opening part.
Described equilibrium arm 4 is also provided with the anchor fitting 44 of fixing described clump weight 11 and the airbag apparatus 45 of the described clump weight 11 of protection, described anchor fitting 44 comprises electric turnover frame 441, described electric turnover frame 441 is provided with telescopic cylinder 442, described telescopic cylinder 442 is provided with fixed dam 443.Described airbag apparatus 45 comprise be arranged on bottom, described equilibrium arm 4451 top can the air bag of repeated inflation, described air bag 451 is the cuboid of opening upwards, is provided with fast connection interface 452 between described air bag 451 and described equilibrium arm 4.Described jacking stock 3 is provided with several electronic coilers 32, described electronic coiler 32 comprises fixing hawser 33, described pedestal 1 is provided with the hook 12 matched with described fixing hawser 33.
Tower crane of the present invention can before inclement weather arrives rapid removal clump weight 11 and pack up crane arm 5 and equilibrium arm 4, change tower crane center of gravity and wind surface by this measure, to reduce the probability that tower crane topples under strong wind weather.After weather improves, can reinstall again clump weight 11 and expansion crane arm 5 and equilibrium arm 4 fast allows tower crane devote oneself to work at once.Its cardinal principle first by counterweight jacking system 8, clump weight 11 is unloaded down to pedestal 1.First need to unclamp fixed dam 443 by being pressed on clump weight 11 by anchor fitting 44, then receive fixed dam 443 by electric turnover frame 441 and telescopic cylinder 442 and allow whole anchor fitting 44 away from counterweight slideway 41, not affecting the slippage of clump weight fixed mount 85.Then rotational alignment device 43 allows connection slideway 433 on standard apparatus 43 and counterweight slideway 41 UNICOM.Move up and down counterweight fixed way 83 by lifter 81, allow counterweight fixed way 83 roughly align with connecting panel 432, the electric expansion limited post 434 on its relief connecting panel 432 stretches out, and is inserted in the spacing hole 86 on counterweight fixed way 83.Because spacing hole 86 is tapered and inwardly reduce gradually from opening part, electric expansion limited post 434 can be allowed to extend in spacing hole 86 when counterweight fixed way 83 has certain deviation with connecting panel 432, and electric expansion limited post 434 can allow counterweight fixed way 83 and connecting panel 432 complete matching after stretching into completely, now connect slideway 433, counterweight slideway 41 is communicated with the fixed way slideway 8 on counterweight fixed way 83, the drive motor 851 on clump weight fixed mount 85 is allowed to start, automatic sliding is on counterweight fixed way 83, after on all clump weight fixed mounts 85 all slippage to counterweight fixed way 83, start electronic locked piece 852 on clump weight fixed mount 85, prevent clump weight fixed mount 85 from sliding at fixed way slideway 8.Finally by lifter 81, counterweight fixed way 83 is moved on on pedestal 1.
After clump weight 11 moves on to pedestal 1, first rope 74 between tensioning first Guyed Towers 55 with first tubing sections device 73 and the second rope between second Guyed Towers 48 with second tubing sections device 71 are connected 72, then allow crane arm 5, device of fixedly making between equilibrium arm 4 with rotating table 6 be separated, both unclamp first electric expansion fixed link 64 and second electric expansion fixed link 63.Subsequently turn lower crane arm 5 and equilibrium arm 4 slowly at first tubing sections device 73 and putting in rope action of second tubing sections device 71.Before crane arm 5 and equilibrium arm 4 rotate, need the air bag 451 be arranged on equilibrium arm 4 to be exitted and bends to regain alignment device 43; Unclamp the occluding device 54 on crane arm 5 between lifting slideway 51 and cambered way 53, allow lifting slideway 51 and cambered way 53 UNICOM, facilitate suspender 52 to move on cambered way 53.The first cable lifter 56 being arranged on crane arm 5 and equilibrium arm 4 top end and second cable lifter 47 can be allowed after crane arm 5 and equilibrium arm 4 have rotated to fall connecting rope, and rope is tied up on the fixed hook 13 on pedestal 1, can prevent crane arm 5 and equilibrium arm 4 in inclement weather from can swing with the wind like this and have an accident.The junction between two standard knots 21 can also be hung over if necessary by the electronic drag hook 46 on equilibrium arm 4, equilibrium arm 4 is better fixed.
Only need during installation to carry out reverse operating, both first by first tubing sections device 73 and second tubing sections device 71 crane arm 5 and equilibrium arm 4 pull-up again, then by first electric expansion fixed link 64 and second electric expansion fixed link 63 allow crane arm 5 and equilibrium arm 4 fixing with rotating table 6.After fixedly completing, both clump weight fixed mount 85 can be risen again, by connection slideway 433 and counterweight slideway 41, clump weight fixed mount 85 be moved to equilibrium arm 4 top.After clump weight fixed mount 85 moves to equilibrium arm 4 top, prop up clump weight fixed mount 85 by the fixed dam 443 on anchor fitting 44, keep the stable of clump weight fixed mount 85.Because clump weight fixed mount 85 can install single clump weight 11 additional, so operationally installing additional and dismantling of clump weight 11 can be carried out at any time, keep the force balance that crane arm 5 is different between equilibrium arm 4.Air bag 451 has two kinds of modes when reclaiming, and one is direct venting, then follows equilibrium arm 4 and folds together, and another kind is directly put down by fast connection interface 452.Air bag 451 is if there is to topple and clump weight 11 drops situation in effect of the present invention, air bag 451 can be allowed to wrap up clump weight 11, although air bag 451 cannot stop dropping of clump weight 11, but air bag 451 can stop clump weight 11 to break the particle of rear splashing into pieces, prevent these particles from splashing and hurt sb.'s feelings and damage machine.The present invention simultaneously is also provided with limit guide groove 31 on jacking stock 3, limit guide groove 31 can auxiliary criteria joint 21 installation, the sliver 22 matched with limit guide groove 31 is provided with at standard knot 21 top, be provided with bottom standard knot 21 match with described sliver 22 agree with groove 23, limit guide groove 31 opening is exit skirt, when standard knot 21 installs additional in jacking stock 3, sliver 22 can be allowed to move along limit guide groove 31, easier aligning, after aiming at guide groove 31 also with agree with groove 23 and agree with, expediently the standard knot 21 of upper/lower positions is aimed at and is agreed with, have and utilize the fixing of next step standard knot 21.

Claims (7)

1. one kind can the tower crane of fast assembling-disassembling clump weight, comprise pedestal (1), tower body (2), jacking stock (3), rotating table (6), crane arm (5), equilibrium arm (4) and clump weight (11), described tower body (2) is built by several standard knots (21), described jacking stock (3) can be upper mobile at described standard knot (21), described rotating table (6) is arranged on described jacking stock (3) top, it is characterized by, described crane arm (5) and described equilibrium arm (4) are arranged on described rotating table (6), described crane arm (5) is relative with described equilibrium arm (4) position, in described jacking stock (3), top is provided with counterweight jacking system (8), described counterweight jacking system (8) can move up and down in described standard knot (21) inside, described equilibrium arm (4) is provided with the counterweight slideway (41) matched with described counterweight jacking system (8), described equilibrium arm (4) is also provided with the anchor fitting (44) of fixing described clump weight (11) and the airbag apparatus (45) of the described clump weight of protection (11), described airbag apparatus (45) comprise be arranged on described equilibrium arm (4) bottom, top can the air bag (451) of repeated inflation, the cuboid that described air bag (451) is opening upwards, fast connection interface (452) is provided with between described air bag (451) and described equilibrium arm (4).
2. according to claim 1 a kind of can the tower crane of fast assembling-disassembling clump weight, it is characterized by, described counterweight jacking system (8) comprises lifter (81), described lifter (81) is provided with some stay cords (82), described stay cord (82) is provided with counterweight fixed way (83), described counterweight fixed way (83) is provided with fixed way slideway (84), the upper slip of described fixed way slideway (84) is provided with several clump weight fixed mounts (85), described counterweight slideway (41) is provided with the alignment device (43) matched with described fixed way slideway (84).
3. according to claim 2 a kind of can the tower crane of fast assembling-disassembling clump weight, it is characterized by, described alignment device (43) comprises electric rotation shaft (431), described electric rotation shaft (431) is provided with connecting panel (432), described connecting panel (432) is provided with the connection slideway () 433 coordinated with described fixed way slideway (84) and described counterweight slideway (41), described connecting panel (432) is also provided with several electric expansion limited posts (434), described fixed way (83) is provided with the spacing hole (86) matched with described electric expansion limited post (434).
4. according to claim 3 a kind of can the tower crane of fast assembling-disassembling clump weight, it is characterized by, described spacing hole (86) is tapered, inwardly reduces gradually from opening part.
5. according to claim 2 a kind of can the tower crane of fast assembling-disassembling clump weight, it is characterized by, described clump weight fixed mount (85) is provided with protection framework (853), drive motor (851) and electronic locked piece (852).
6. according to claim 5 a kind of can the tower crane of fast assembling-disassembling clump weight, it is characterized by, described protection framework (853) biside plate is respectively arranged with inside fixed lobe (854), described clump weight (11) is provided with the fixed groove matched with described fixed lobe (854).
7. according to claim 1 a kind of can the tower crane of fast assembling-disassembling clump weight, it is characterized by, between described counterweight slideway (41) and described equilibrium arm (4), be provided with several supporting linkages (42).
CN201510829590.3A 2015-11-25 2015-11-25 It is a kind of can be with the tower crane of fast assembling-disassembling balancing weight Active CN105293304B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510829590.3A CN105293304B (en) 2015-11-25 2015-11-25 It is a kind of can be with the tower crane of fast assembling-disassembling balancing weight

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510829590.3A CN105293304B (en) 2015-11-25 2015-11-25 It is a kind of can be with the tower crane of fast assembling-disassembling balancing weight

Publications (2)

Publication Number Publication Date
CN105293304A true CN105293304A (en) 2016-02-03
CN105293304B CN105293304B (en) 2017-09-19

Family

ID=55191260

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510829590.3A Active CN105293304B (en) 2015-11-25 2015-11-25 It is a kind of can be with the tower crane of fast assembling-disassembling balancing weight

Country Status (1)

Country Link
CN (1) CN105293304B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106629405A (en) * 2016-12-13 2017-05-10 泰山石膏(江阴)有限公司 Wind weakening device of large-sized plasterboard crane
CN107244610A (en) * 2016-12-13 2017-10-13 江苏博阳智慧电气股份有限公司 A kind of security monitoring system of hoister
CN112239160A (en) * 2020-11-04 2021-01-19 常德市荣程机械有限公司 Node connection structure of tower machine forearm

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4567990A (en) * 1983-08-16 1986-02-04 Bellio Stephen L Self-balancing crane
CN2793032Y (en) * 2005-03-17 2006-07-05 辽宁工程技术大学 Adjustable counterweight tower shaped crane
CN203513191U (en) * 2013-10-28 2014-04-02 安徽德摩新能源叉车股份有限公司 Forklift with anti-collision structure
CN203998711U (en) * 2014-08-25 2014-12-10 中铁十一局集团有限公司 Civil engineering tower crane

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4567990A (en) * 1983-08-16 1986-02-04 Bellio Stephen L Self-balancing crane
CN2793032Y (en) * 2005-03-17 2006-07-05 辽宁工程技术大学 Adjustable counterweight tower shaped crane
CN203513191U (en) * 2013-10-28 2014-04-02 安徽德摩新能源叉车股份有限公司 Forklift with anti-collision structure
CN203998711U (en) * 2014-08-25 2014-12-10 中铁十一局集团有限公司 Civil engineering tower crane

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106629405A (en) * 2016-12-13 2017-05-10 泰山石膏(江阴)有限公司 Wind weakening device of large-sized plasterboard crane
CN107244610A (en) * 2016-12-13 2017-10-13 江苏博阳智慧电气股份有限公司 A kind of security monitoring system of hoister
CN106629405B (en) * 2016-12-13 2018-04-24 泰山石膏(江阴)有限公司 A kind of large-scale weak wind apparatus of plasterboard crane
CN112239160A (en) * 2020-11-04 2021-01-19 常德市荣程机械有限公司 Node connection structure of tower machine forearm
CN112239160B (en) * 2020-11-04 2023-08-04 常德市荣程机械有限公司 Node connection structure of tower machine forearm

Also Published As

Publication number Publication date
CN105293304B (en) 2017-09-19

Similar Documents

Publication Publication Date Title
CN105271024A (en) Tower crane with wind-proof structure
CN203924874U (en) Attaching pole is from lifting appliance
CN107473102A (en) A kind of miniature crawler belt derrick car of substation equipment maintenance and repair
CN207348429U (en) The rotating platform built for tower
CN103863955B (en) From introduction system and have this tower machine from introduction system
CN105293304A (en) Tower crane with counterweight blocks capable of being quickly mounted or demounted
CN105293301A (en) Windproof tower crane
CN103663189A (en) Swing arm tower crane installation method
CN109025234A (en) A kind of building high-altitude vacantly construct with can level, vertically the track crane ship that walk
CN105293299A (en) Windproof tower crane for building
CN105293302A (en) Tower crane with wind resistance function
CN105293311A (en) Tower crane having windproof function
CN105293300A (en) Tower crane capable of quickly disassembling and assembling counterweight block
CN105293312A (en) Tower crane
CN105293321A (en) Tower crane
CN105293316A (en) Windproof tower crane
CN208071214U (en) A kind of material lifting device of automatic discharging
CN105293303A (en) Windproof tower crane for construction
CN106379217B (en) A kind of electric pole maintenance climbing anti-fall device
CN108657968A (en) One kind prevents steel cable from falling off telescopic crane
CN105293310A (en) Tower crane with waterproof structure
CN105155506B (en) Dynamic compaction machine and dynamic compaction method
CN213326443U (en) Quick unloading platform
CN113955636A (en) Hoisting equipment for assembly type building construction
CN107601301A (en) A kind of steel reinforcement cage lifting device and hoisting method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20191023

Address after: 314511 room 1-402, building 647, Shiji Avenue, Chongfu Town, Tongxiang City, Jiaxing City, Zhejiang Province

Patentee after: Jiaxing Juteng Information Technology Co., Ltd.

Address before: 315202 West Village, Jiulong Town, Zhenhai District, Zhejiang, Ningbo

Patentee before: ZHENHAI CONSTRUCTION GROUP CO., LTD.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210525

Address after: 215611 Changyin Sha Zhujiang Road, Zhangjiagang City, Suzhou City, Jiangsu Province

Patentee after: ZHANGJIAGANG ZHONGLIAN CONSTRUCTION MACHINERY Co.,Ltd.

Address before: Room 1-402, building 647, Century Avenue, Chongfu Town, Tongxiang City, Jiaxing City, Zhejiang Province

Patentee before: Jiaxing Juteng Information Technology Co.,Ltd.

TR01 Transfer of patent right