CN105275207A - Up-down cyclic alternating construction method for external vertical face of high-rise building - Google Patents

Up-down cyclic alternating construction method for external vertical face of high-rise building Download PDF

Info

Publication number
CN105275207A
CN105275207A CN201510071027.4A CN201510071027A CN105275207A CN 105275207 A CN105275207 A CN 105275207A CN 201510071027 A CN201510071027 A CN 201510071027A CN 105275207 A CN105275207 A CN 105275207A
Authority
CN
China
Prior art keywords
construction
lifting platform
integrated form
layer
vertical face
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510071027.4A
Other languages
Chinese (zh)
Inventor
王加鑫
杨广海
赵桌
王电
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau Third Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau Third Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau Third Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau Third Construction Engineering Co Ltd
Priority to CN201510071027.4A priority Critical patent/CN105275207A/en
Publication of CN105275207A publication Critical patent/CN105275207A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses an up-down cyclic alternating construction method for the external vertical face of a high-rise building. The method comprises two steps. The first step comprises constructing the structure of the main body of a building from the bottom to the top layer by layer and preliminarily constructing standpipes, rails and window frames at the outside by an integrated construction elevating platform. The second step comprises finally finishing the outer wall along with fall of the integrated construction elevating platform after the top of the structure of the main body is closed, coating the external vertical face, and constructing glasses on sills, and glasses on rails. According to the up-down cyclic alternating construction method, various operations on the external vertical face can be constructed in advance, a partial of finishing work of the external vertical face can be constructed from the bottom to the top layer by layer along with the structure of the main body, various operations are alternated, the work efficiency is high and the construction progress is quick. The integrated construction elevating platform is used for constructing the external vertical face, the protection is closed, the high altitude construction is safe, the construction place is neat and beautiful, and the cladding material is green and environmentally friendly.

Description

A kind of highrise building alien invasion circulates interspersed construction method up and down
Technical field
the present invention relates to a kind of highrise building alien invasion to circulate up and down interspersed construction method, belong to architectural engineering construction technique field.
Background technology
the construction of traditional architecture alien invasion utilizes scaffold to construct from top to bottom after main structure construction completes.Traditional architecture alien invasion construction method operating efficiency is low, construction speed cannot improve further, and because the protection airtight of alien invasion is undesirable, work high above the ground exists potential safety hazard.
Summary of the invention
the object of the invention is to, provide a kind of highrise building alien invasion to circulate up and down interspersed construction method.Enable the various operation of alien invasion effectively intert circulation construction, thus improve construction speed, guarantee high-altitude alien invasion job execution safety, reduce construction cost.
technical scheme of the present invention:
a kind of highrise building alien invasion circulates interspersed construction method up and down, and the method is constructed in two steps: the first step is the preliminary construction completing alien invasion standpipe, railing, window frame integrated form construction lifting platform successively completes major structure of construction construction from bottom to top while; Second step is after agent structure binds, and the decline along with integrated form construction lifting platform is carried out exterior wall again and finally fitted up; Realize the construction of alien invasion coating, windowsill glass, railing glass.
in preceding method, when successively completing major structure of construction construction from bottom to top, integrated form construction lifting platform covers 5 floors; When construction lifting platform declines, integrated form construction lifting platform covers 4 floors, and integrated form construction lifting platform declines two floors at every turn.
in preceding method, cover in floor at integrated form construction lifting platform, the construction manpower of facade is divided into different construction group, adopt interspersed form of construction work or flow system to construct.
compared with prior art, various for alien invasion operation is inserted construction by the present invention in advance, and alien invasion part fitting-out work is first followed agent structure from bottom to top and successively constructed, and each operation interts that operating efficiency is high, construction speed is fast.Utilize integrated form construction lifting platform to carry out protection airtight, the work high above the ground construction safety of alien invasion, and construction plant is neat and artistic, cladding environmental protection.
Detailed description of the invention
below in conjunction with construction process table and embodiment, the present invention is described in further detail, but not as any limitation of the invention.
a kind of highrise building alien invasion circulates interspersed construction method up and down, and the method is constructed in two steps: the first step is the preliminary construction completing alien invasion standpipe, railing, window frame integrated form construction lifting platform successively completes major structure of construction construction from bottom to top while; Second step is after agent structure binds, and the decline along with integrated form construction lifting platform is carried out exterior wall again and finally fitted up; Realize the construction of alien invasion coating, windowsill glass, railing glass.When successively completing major structure of construction construction from bottom to top, integrated form construction lifting platform covers 5 floors; When construction lifting platform declines, integrated form construction lifting platform covers 4 floors, and integrated form construction lifting platform declines two floors at every turn.Cover in floor at integrated form construction lifting platform, the construction manpower of facade is divided into different construction group, adopt interspersed form of construction work or flow system to construct.
Embodiment
this example illustrates construction method of the present invention for building 30 storey building.This example adopts integrated form construction lifting platform to construct, in uphill process, integrated form construction lifting platform once covers 5 floors, constructor is divided into 5 groups by the number of floor levels that can cover according to integrated form construction lifting platform, is responsible for main structure construction for first group.Second group of some leftover problem be responsible for when processing structure construction.As some spillages of polishing during structure construction, the work such as the screw hole left over after repairing some strippings.Be responsible for for 3rd group window frame being installed and scraping first pass Tired.The 4th group of standpipe being responsible for installing on guardrail and exterior wall also scrapes second time Tired.Be responsible for brushing exterior wall base paint for 5th group.Specific construction flow process is as shown in table 1;
table 1: construction process table when integrated form construction lifting platform climbs from the bottom to top
when the structure construction that first group completes the 1st layer is transferred to the 2nd layer, second group can carry out the 1st layer carry out polish spillage, repair hole construction.When the structure construction that first group completes the 2nd layer is transferred to the 3rd layer, second group can enter the construction that the 2nd layer is carried out polishing spillage, repairing hole, and the 3rd group can enter the 1st layer of construction of carrying out installing window frame and scraping slubbing putty.When the structure construction that first group completes the 3rd layer is transferred to the 4th layer, second group can enter the construction that the 3rd layer is carried out polishing spillage, repairing hole, 3rd group can enter the 2nd layer and carry out installing window frame and scraping the construction of slubbing putty, and the 4th group can enter the 1st layer and carry out installing guardrail and standpipe and scrape the construction of second putty.When the structure construction that first group completes the 4th layer is transferred to the 5th layer, second group can enter the construction that the 4th layer is carried out polishing spillage, repairing hole, 3rd group can enter the 3rd layer of construction of carrying out installing window frame and scraping slubbing putty, 4th group can enter the 2nd layer of construction of carrying out installing guardrail and standpipe and scraping second putty, and the 5th group can enter the 1st layer of brushing exterior wall base paint.After completing the structure construction of the 5th layer when first group, other respectively group also substantially complete respective construction, now utilize time half a day to be climbed by whole integrated form construction lifting platform one deck.Then each group enters last layer and carries out respective construction, forms continuous productive process until agent structure binds.
above-mentioned work progress also can be constructed in the following manner, when carrying out 1 ~ 4 layer of construction, traditional scaffold can be adopted to construct, when needs proceed to the 5th layer of construction, remove scaffold, integrated form construction lifting platform is installed, first group enters the 5th layer and carries out structure construction, second group enters the 4th layer and carries out polishing spillage, repair the construction of hole, 3rd group enters the 3rd layer of construction of carrying out installing window frame and scraping slubbing putty, 4th group enters the 2nd layer of construction of carrying out installing guardrail and standpipe and scraping second putty, 5th group enters the 1st layer of brushing exterior wall base paint.Time half a day is utilized to be climbed by whole integrated form construction lifting platform one deck after all completing respective construction when each group.Then each group enters last layer and carries out respective construction, forms continuous productive process until agent structure binds.
said process is the construction process of integrated form construction lifting platform when climbing.This process integration formula construction lifting platform once covers 5 floors, 5 work planes can be provided to carry out the construction of each procedure respectively, be independent of each other between each operation, the every 5 days one decks that climb, the each operation of one deck of often climbing rises a work plane, forms continuous productive process, circulates until top out with this.
table 2 is integrated form construction lifting platform construction process tables when from top to bottom declining.
in integrated form construction lifting platform decline process, integrated form construction lifting platform covers 4 floors, each two floors that decline.According to need of work, constructor is divided into two groups, is responsible for glass and shutter that window and guardrail are installed, is responsible for exterior wall paint coating application for second group for first group.First first group enter the 30th layer respectively and the 29th layer carry out the glass of window and guardrail and the installation of shutter.Be transferred to the 28th layer after completing the glass of window and guardrail and the installation of shutter when first group and the 27th layer construct, simultaneously second group enter the 30th layer and the 29th layer carry out exterior wall paint coating application.After two groups are finished the work respectively, integrated form construction lifting platform declines two-layer, first group enter the 26th layer and the 25th layer construct, second group enter 28 layers and the 27th layer construct, until integrated form construction lifting platform drops to the 1st layer, first group of backed off after random of first finishing the work, then second group of backed off after random of finishing the work.Finally remove integrated form construction lifting platform.
in sum, method of the present invention is under the cooperation of integrated form construction lifting platform " rising ", and the preliminary finishing of exterior wall, with agent structure successively synchronous construction from bottom to top, realizes alien invasion standpipe, railing, window frame etc. and inserts construction first.After agent structure binds, successively " decline " along with integrated form construction lifting platform is carried out exterior wall and is finally fitted up, and realizes the interspersed construction of the secondaries such as alien invasion coating, windowsill glass, railing glass.Various procedure carries out cross construction in integrated form construction lifting platform coverage, and along with integrated form construction lifting platform rise or decline carry out repetition, sequential production.Integrated form construction lifting platform uphill process covers 5 floors, and each operation of alien invasion carries out cross construction in its coverage, until agent structure binds.Integrated form construction lifting platform decline process covers 4 floors, is often two-layerly divided into one group of operation to construct, and the construction of windowsill glass, railing glass, shutter is one group of operation, and exterior wall is repaired, coating is one group of operation.Each operation effectively can be connected and keep continuity of constructing.

Claims (3)

1. highrise building alien invasion circulates an interspersed construction method up and down, it is characterized in that: the method is constructed in two steps: the first step is the preliminary construction completing alien invasion standpipe, railing, window frame integrated form construction lifting platform successively completes major structure of construction construction from bottom to top while; Second step is after agent structure binds, and the decline along with integrated form construction lifting platform is carried out exterior wall again and finally fitted up; Realize the construction of alien invasion coating, windowsill glass, railing glass.
2. highrise building alien invasion circulates interspersed construction method up and down according to claim 1, it is characterized in that: when successively completing major structure of construction construction from bottom to top, integrated form construction lifting platform covers 5 floors; When construction lifting platform declines, integrated form construction lifting platform covers 4 floors, and integrated form construction lifting platform declines two floors at every turn.
3. highrise building alien invasion circulates interspersed construction method up and down according to claim 2, it is characterized in that: cover in floor at integrated form construction lifting platform, the construction manpower of facade is divided into different construction group, adopts interspersed form of construction work or flow system to construct.
CN201510071027.4A 2015-02-11 2015-02-11 Up-down cyclic alternating construction method for external vertical face of high-rise building Pending CN105275207A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510071027.4A CN105275207A (en) 2015-02-11 2015-02-11 Up-down cyclic alternating construction method for external vertical face of high-rise building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510071027.4A CN105275207A (en) 2015-02-11 2015-02-11 Up-down cyclic alternating construction method for external vertical face of high-rise building

Publications (1)

Publication Number Publication Date
CN105275207A true CN105275207A (en) 2016-01-27

Family

ID=55144957

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510071027.4A Pending CN105275207A (en) 2015-02-11 2015-02-11 Up-down cyclic alternating construction method for external vertical face of high-rise building

Country Status (1)

Country Link
CN (1) CN105275207A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106285001A (en) * 2016-08-31 2017-01-04 中天建设集团有限公司天津分公司 A kind of little area segmentation quickly intersects flowing water construction method
CN107237496A (en) * 2017-07-13 2017-10-10 广东骏峰建筑科技有限公司 A kind of high-rise building construction process
CN108086714A (en) * 2017-12-20 2018-05-29 佛山市万科置业有限公司 Complete cast-in-place exterior wall high residential building kitchen and bath interts construction and puies forward efficacious prescriptions method
CN108104257A (en) * 2017-12-20 2018-06-01 佛山市万科置业有限公司 The complete cast-in-place exterior wall high residential building hall interts construction and puies forward efficacious prescriptions method
CN108104278A (en) * 2017-12-20 2018-06-01 佛山市万科置业有限公司 Complete cast-in-place exterior wall high residential building main body interts construction after binding and puies forward efficacious prescriptions method entirely
CN108104472A (en) * 2017-12-20 2018-06-01 佛山市万科置业有限公司 Intert construction outside complete cast-in-place exterior wall high residential building room and put forward efficacious prescriptions method
CN109488030A (en) * 2018-11-07 2019-03-19 中建三局第建设工程有限责任公司 Quick interspersed construction method for frame structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000282691A (en) * 1999-03-30 2000-10-10 Sumitomo Heavy Ind Ltd Construction method for mounting member on inner wall of high-rise, tower structure, and scaffold device
US20120023840A1 (en) * 2009-04-10 2012-02-02 Bin Yuan Main Work Construction Method for Reinforced Concrete Building and Building Construction Machine
CN103243912A (en) * 2013-05-09 2013-08-14 中化二建集团有限公司 Multilayer no-board frame structure constructing method
CN103741939A (en) * 2013-12-25 2014-04-23 山东省建筑科学研究院 Climbing type building construction operating platform on outer portion of building and installing method
CN203755637U (en) * 2014-03-19 2014-08-06 中国葛洲坝集团股份有限公司 High-altitude double-rail-beam bottom movable type hanging operating platform
CN104100090A (en) * 2014-07-17 2014-10-15 成都市第四建筑工程公司 High-altitude comprehensive construction method of big-cantilever steel truss structure
CN104131703A (en) * 2014-05-16 2014-11-05 中国建筑第四工程局有限公司 Method for constructing core tube wall through self-climbing formwork and adopted self-climbing formwork

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000282691A (en) * 1999-03-30 2000-10-10 Sumitomo Heavy Ind Ltd Construction method for mounting member on inner wall of high-rise, tower structure, and scaffold device
US20120023840A1 (en) * 2009-04-10 2012-02-02 Bin Yuan Main Work Construction Method for Reinforced Concrete Building and Building Construction Machine
CN103243912A (en) * 2013-05-09 2013-08-14 中化二建集团有限公司 Multilayer no-board frame structure constructing method
CN103741939A (en) * 2013-12-25 2014-04-23 山东省建筑科学研究院 Climbing type building construction operating platform on outer portion of building and installing method
CN203755637U (en) * 2014-03-19 2014-08-06 中国葛洲坝集团股份有限公司 High-altitude double-rail-beam bottom movable type hanging operating platform
CN104131703A (en) * 2014-05-16 2014-11-05 中国建筑第四工程局有限公司 Method for constructing core tube wall through self-climbing formwork and adopted self-climbing formwork
CN104100090A (en) * 2014-07-17 2014-10-15 成都市第四建筑工程公司 High-altitude comprehensive construction method of big-cantilever steel truss structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
周王丽、高冬: "导座式爬升式脚手架技术总结", 《城市建设理论研究(电子版)》 *
赵勇: "爬架施工技术在高层建筑工程中的应用", 《建筑工程技术与设计》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106285001A (en) * 2016-08-31 2017-01-04 中天建设集团有限公司天津分公司 A kind of little area segmentation quickly intersects flowing water construction method
CN106285001B (en) * 2016-08-31 2019-04-16 中天建设集团有限公司 A kind of facet integration segment quickly intersects flowing water construction method
CN107237496A (en) * 2017-07-13 2017-10-10 广东骏峰建筑科技有限公司 A kind of high-rise building construction process
CN108086714A (en) * 2017-12-20 2018-05-29 佛山市万科置业有限公司 Complete cast-in-place exterior wall high residential building kitchen and bath interts construction and puies forward efficacious prescriptions method
CN108104257A (en) * 2017-12-20 2018-06-01 佛山市万科置业有限公司 The complete cast-in-place exterior wall high residential building hall interts construction and puies forward efficacious prescriptions method
CN108104278A (en) * 2017-12-20 2018-06-01 佛山市万科置业有限公司 Complete cast-in-place exterior wall high residential building main body interts construction after binding and puies forward efficacious prescriptions method entirely
CN108104472A (en) * 2017-12-20 2018-06-01 佛山市万科置业有限公司 Intert construction outside complete cast-in-place exterior wall high residential building room and put forward efficacious prescriptions method
CN109488030A (en) * 2018-11-07 2019-03-19 中建三局第建设工程有限责任公司 Quick interspersed construction method for frame structure

Similar Documents

Publication Publication Date Title
CN105275207A (en) Up-down cyclic alternating construction method for external vertical face of high-rise building
CN101832015B (en) Construction process for outer wall metal fluorocarbon coating
CN109680795A (en) A kind of quick assembled type building system and method
CN207268043U (en) A kind of fabricated construction stair
CN108005321A (en) A kind of method that exterior wall bulk finish coat adds stone-like coating layer
CN108177731A (en) A kind of method of construction of tanker manifold platforms
CN108952157A (en) Aluminum alloy mould plate and climbing frame share the construction of screw hole
CN209308189U (en) A kind of building board splice cracking-proof structure
CN202990446U (en) Overhang frame structure
CN207658895U (en) Working at height glass hanging equipment
CN203647250U (en) Track type window cleaning machine for complex inner court curtain wall
CN204212443U (en) A kind of external wall stop water
CN104856618A (en) Flight type overhead work multi-purpose machine
CN103669867B (en) Building body and outer decoration construction discrepancy in elevation adjustable double-layer operating platform and installation method
CN204266404U (en) A kind of outer-wall crack-resisting anti-leakage structure
CN107237496A (en) A kind of high-rise building construction process
CN103883123A (en) Method for simultaneous construction on upper main concrete and lower internal and external decoration and cantilever rack
CN103720427B (en) A kind of complicated Neiting curtain wall rail mounted window cleaning equipment
CN101592006A (en) A kind of window impaired method in construction that prevents
KR101219466B1 (en) Method for constructing framework and outer window simultaneously
CN114687556A (en) Northern constructional engineering alternate construction method and device
CN210622286U (en) Assembled construction is with instrumentization stair of going up people
CN211473274U (en) Efficient cement wall surface latex paint smearing device
CN107902524A (en) Working at height glass hanging equipment
CN218061366U (en) Building external climbing type building construction operation platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160127

RJ01 Rejection of invention patent application after publication