CN105257300B - 一种隧道超欠挖控制方法及钻孔检测杆 - Google Patents
一种隧道超欠挖控制方法及钻孔检测杆 Download PDFInfo
- Publication number
- CN105257300B CN105257300B CN201510761272.8A CN201510761272A CN105257300B CN 105257300 B CN105257300 B CN 105257300B CN 201510761272 A CN201510761272 A CN 201510761272A CN 105257300 B CN105257300 B CN 105257300B
- Authority
- CN
- China
- Prior art keywords
- detection bar
- drilling
- underbreak
- detection
- control
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Geophysics And Detection Of Objects (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本发明公开了一种隧道超欠挖控制方法及钻孔检测杆,方法为:采用钻机适配装置将显示检测杆安装于钻机上;逐一在需检测钻孔中安装钻孔检测杆,钻孔检测杆末端安装反光膜片;用手持终端无线读取每个钻孔角度信息,用全站仪测试钻孔检测杆末端膜片坐标;动态调整***设计参数;采用全站仪进行***断面扫描,扫描数据无线同步至手持终端,断面扫描数据上传至隧道超欠挖控制检测信息化***;所述钻孔检测杆包括传感器模块:由三轴磁阻传感器和三轴加速度传感器组成;A/D转换模块:将传感器模块检测的钻孔角度原始信息转换为数字信号;以及滤波模块、控制模块和无线模块。本发明对隧道超欠挖进行过程控制和结果评价,最终隧道超欠挖调整在可控范围。
Description
技术领域
本发明涉及隧道开挖领域,特别涉及一种隧道超欠挖控制方法及在此控制方法中使用的钻孔检测杆。
背景技术
开挖是隧道施工中的关建工序。超挖过多,不仅因出渣量和衬砌量增多而提高工程造价,而且由于局部超挖会产生应力集中,影响围岩稳定性。欠挖则直接影响衬砌厚度,处理起来费时费力。超欠挖在钻爆法施工中虽然不可避免,但可以通过一定措施,将超欠挖值控制在较小水平,降低对施工成本、施工进度和隧道安全的影响。
超欠挖的影响因素分为钻孔精度、***技术、施工组织管理、测量画线、地质条件变化和其它因素,经过对实际开挖循环***效果统计,钻孔精度对超欠挖影响最大。钻孔精度对超欠挖的影响主要是周边炮孔的外插角、开口误差(径向)和***孔深。
目前对超欠挖的检测多集中在效果检测上,且效果检测数据为人工处理,不能直接进入信息化平台自动处理,不利于效果监督和评判,缺少对过程中的检测控制,不能形成有效的过程+效果的综合评判以及动态调整***设计的能力。
发明内容
本发明所要解决的技术问题是提供一种隧道超欠挖控制方法及钻孔检测杆,针对钻孔精度进行辅助控制、测试成孔精度,对隧道超欠挖进行过程控制、结果评价和辅助***方案调整,以实现控制超欠挖的目的。
为解决上述技术问题,本发明采用的技术方案是:
一种隧道超欠挖控制方法,包括过程检测控制及效果检测:
过程检测控制
步骤1:采用钻机适配装置,将显示检测杆安装于钻机上,确保显示检测杆与钻机轴线平行,从而显示钻机的姿态信息;步骤2:钻孔完成后,逐一在需检测钻孔中安装钻孔检测杆,钻孔检测杆末端安装反光膜片;步骤3:钻孔检测杆安装完毕后,用手持终端(包括手机、平板电脑等智能终端)无线读取每个钻孔角度信息,同时用全站仪测试钻孔检测杆末端膜片坐标并同步无线传输至手持终端,两组数据组合形成钻孔角度和位置检测值;步骤4:将钻孔角度和位置检测值无线上传至隧道超欠挖检测信息化***,信息化***结合隧道***设计信息化***研究成果及检测的实际钻孔角度和位置,动态调整***设计参数;
效果检测
步骤5:***后,采用全站仪进行***断面扫描,扫描数据无线同步至手持终端,完成断面扫描后数据上传至隧道超欠挖控制检测信息化***,与设计断面进行比对,形成超欠挖效果数据,指导修正下一次***设计参数,以及形成超欠挖控制效果评价数据库;
步骤6:重复步骤1至步骤5,直至控制隧道超欠挖在可控范围之内。
一种在隧道超欠挖控制中使用的钻孔检测杆,包括:
传感器模块:由三轴磁阻传感器和三轴加速度传感器组成,用于获取钻孔角度原始信息;
A/D转换模块:将传感器模块检测的钻孔角度原始信息转换为数字信号;
滤波模块:接收A/D转换模块的数字信号,通过有效滤波算法得到去噪后的钻孔角度原始信息;
控制模块:包括磁场强度运算和偏转角运算,通过对滤波模块的钻孔角度原始信息进行运算,得到钻孔检测杆所检测的钻孔角度;
无线模块:将钻孔角度发送至手持终端。
进一步的,在控制模块中,还设置有硬铁软铁补偿单元,用于修正偏转角。
进一步的,还设置有显示模块,用于实时显示钻孔角度。
与现有技术相比,本发明针对钻孔精度进行辅助控制、测试成孔精度,对隧道超欠挖进行过程控制、结果评价和辅助***方案调整,将隧道超欠挖控制在一定的范围之内。
附图说明
图1是本发明隧道超欠挖控制方法工作流程示意图。
图2是本发明中钻孔检测杆外部结构示意图。
图3是本发明中钻孔检测杆结构示意图。
图4是本发明中钻孔检测杆工作流程示意图。
图2中:1-外胀式定位环;2-电池仓;3-控制板;4-传感器;5-定位锁;6-天线。
具体实施方式
下面结合附图和具体实施方式对本发明作进一步详细的说明。本发明的目的是要提高钻孔精度、采集钻孔信息及***后断面超欠挖数据,数据集中于信息化平台处理,形成远端+现场手持的网络控制***,有利于降低超欠挖水平,减小对施工成本、施工进度和隧道安全的影响。
本发明提供的一种隧道超欠挖控制方法,包括过程检测控制(步骤1到步骤4)及效果检测(步骤5):
步骤1:采用钻机适配装置,将显示检测杆安装于钻机上,确保显示检测杆与钻机轴线平行,从而显示钻机的姿态信息;步骤2:钻孔完成后,逐一在需检测钻孔中安装钻孔检测杆,钻孔检测杆末端安装反光膜片;步骤3:钻孔检测杆安装完毕后,用手持终端(包括手机、平板电脑等智能终端)无线读取每个钻孔角度信息,同时用全站仪测试钻孔检测杆末端膜片坐标并同步无线传输至手持终端,两组数据组合形成钻孔角度和位置检测值;步骤4:将钻孔角度和位置检测值无线上传至隧道超欠挖检测信息化***,信息化***结合隧道***设计信息化***研究成果及检测的实际钻孔角度和位置,动态调整***设计参数;
步骤5:***后,采用全站仪进行***断面扫描,扫描数据无线同步至手持终端,完成断面扫描后数据上传至隧道超欠挖控制检测信息化***,与设计断面进行比对,形成超欠挖效果数据,指导修正下一次***设计参数,以及形成超欠挖控制效果评价数据库;
步骤6:重复步骤1至步骤5,直至控制隧道超欠挖在可控范围之内。
根据超欠挖过程控制及效果控制检测设备及相应数据分析方法,结合隧道施工实际情况,建立在此工作模式下的预警体系及标准。形成一套适合于B/S、C/S工作模式的超欠挖控制检测信息化***,实现超欠挖信息的网络化传输、分析及预警管理。
本发明还提供了一种在隧道超欠挖控制中使用的钻孔检测杆,包括:
传感器模块:由三轴磁阻传感器和三轴加速度传感器组成,用于获取钻孔角度原始信息;A/D转换模块:将传感器模块检测的钻孔角度原始信息转换为数字信号;滤波模块:接收A/D转换模块的数字信号,通过有效滤波算法得到去噪后的钻孔角度原始信息;控制模块:包括磁场强度运算和偏转角运算,通过对滤波模块的钻孔角度原始信息进行运算,得到钻孔检测杆所检测的钻孔角度;无线模块:将钻孔角度发送至手持终端。
另外,为了使本钻孔检测杆所检测的钻孔角度更加准确,在钻孔检测杆控制模块中,还设置有硬铁软铁补偿单元,用于修正偏转角。还可设置显示模块,实时显示钻孔角度,通过钻机适配装置安装于凿岩机上,工人根据显示数据调整凿岩机外插角以满足设计要求。
表1 隧道超欠挖钻孔检测杆精度表
本发明的钻孔检测杆采用三轴加速度计、三轴磁阻传感器组合,结合动力学及有效滤波算法,对钻孔角度进行测试。钻孔检测杆设计外胀式定位环,方便在钻孔中固定与取出;末端设计全站仪反射膜片,用全站仪测量钻孔开口位置,蓝牙传送至手持终端;检测杆完成钻孔偏转角及俯仰角测试传送至手持终端;手持终端结合全站仪测量开口位置及检测杆角度数据,计算出钻孔开口及外插角,上传至信息化平台,对比***设计信息,提出预警及辅助动态设计修正。
Claims (1)
1.一种隧道超欠挖控制方法,其特征在于,包括过程检测控制及效果检测:
过程检测控制
步骤1:采用钻机适配装置将显示检测杆安装于钻机上,从而显示钻机的姿态信息;
步骤2:钻孔完成后,逐一在需检测钻孔中安装钻孔检测杆,钻孔检测杆末端安装反光膜片;
步骤3:钻孔检测杆安装完毕后,用手持终端无线读取每个钻孔角度信息,同时用全站仪测试钻孔检测杆末端膜片坐标并同步无线传输至手持终端,两组数据组合形成钻孔角度和位置检测值;
步骤4:将钻孔角度和位置检测值无线上传至隧道超欠挖检测信息化***,信息化***结合隧道***设计信息化***研究成果及检测的实际钻孔角度和位置,动态调整***设计参数;
效果检测
步骤5:***后,采用全站仪进行***断面扫描,扫描数据无线同步至手持终端,完成断面扫描后数据上传至隧道超欠挖控制检测信息化***,与设计断面进行比对,形成超欠挖效果数据,指导修正下一次***设计参数,以及形成超欠挖控制效果评价数据库;
步骤6:重复步骤1至步骤5,直至控制隧道超欠挖在可控范围之内。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510761272.8A CN105257300B (zh) | 2015-11-10 | 2015-11-10 | 一种隧道超欠挖控制方法及钻孔检测杆 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510761272.8A CN105257300B (zh) | 2015-11-10 | 2015-11-10 | 一种隧道超欠挖控制方法及钻孔检测杆 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105257300A CN105257300A (zh) | 2016-01-20 |
CN105257300B true CN105257300B (zh) | 2017-08-01 |
Family
ID=55097190
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510761272.8A Active CN105257300B (zh) | 2015-11-10 | 2015-11-10 | 一种隧道超欠挖控制方法及钻孔检测杆 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105257300B (zh) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106121632A (zh) * | 2016-10-12 | 2016-11-16 | 贵州新联***工程集团有限公司 | 一种用于测量炮孔倾角的装置及测量方法 |
CN112392486B (zh) * | 2020-11-16 | 2022-11-01 | 中国铁建重工集团股份有限公司 | 一种处理隧道欠挖的施工方法 |
CN114623954A (zh) * | 2020-12-10 | 2022-06-14 | 中国石油天然气集团有限公司 | 用于检测油气管道应力的内检测装置及设备 |
CN113266364B (zh) * | 2021-05-29 | 2022-10-04 | 贵州铁建工程质量检测咨询有限公司 | 一种隧道施工监控量测与超欠挖测量控制方法 |
CN113407915A (zh) * | 2021-05-31 | 2021-09-17 | 中国电建集团华东勘测设计研究院有限公司 | 一种优化围岩***参数的app***及其使用方法 |
CN114352300B (zh) * | 2021-12-07 | 2024-02-02 | 江苏徐工工程机械研究院有限公司 | 一种数字化钻爆开挖***和开挖方法 |
CN114352290B (zh) * | 2022-01-06 | 2023-09-12 | 徐工汉云技术股份有限公司 | 一种隧道施工引导方法、平台、***及作业方法 |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1948707A (zh) * | 2006-11-20 | 2007-04-18 | 北京航空航天大学 | 基于磁阻和倾角传感器的捷联式钻孔测斜仪 |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201397207Y (zh) * | 2009-04-30 | 2010-02-03 | 中国矿业大学 | 煤岩体地应力连续测试装置 |
CN102748008B (zh) * | 2012-07-18 | 2014-11-12 | 武汉岩海工程技术有限公司 | 可实现钻孔三维成像的检测装置及其方法 |
CN202903161U (zh) * | 2012-10-10 | 2013-04-24 | 山东科技大学 | 矿用钻孔微位移测量仪 |
CN202882893U (zh) * | 2012-10-23 | 2013-04-17 | 淮南润成科技股份有限公司 | 矿用钻孔深度监测装置 |
CN205117332U (zh) * | 2015-11-10 | 2016-03-30 | 中铁西南科学研究院有限公司 | 一种钻孔检测杆 |
-
2015
- 2015-11-10 CN CN201510761272.8A patent/CN105257300B/zh active Active
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1948707A (zh) * | 2006-11-20 | 2007-04-18 | 北京航空航天大学 | 基于磁阻和倾角传感器的捷联式钻孔测斜仪 |
Also Published As
Publication number | Publication date |
---|---|
CN105257300A (zh) | 2016-01-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105257300B (zh) | 一种隧道超欠挖控制方法及钻孔检测杆 | |
CN108930539B (zh) | 一种基于bim隧道超欠挖控制的方法 | |
CN104390537B (zh) | 一种基于***振动测试的边坡预裂***开挖损伤控制方法 | |
CN108868805B (zh) | 基于统计分析与XGboost结合的盾构纠偏方法 | |
CN110515117B (zh) | 一种基于桩锤激震和决策树模型的地下溶洞探测方法 | |
CN207007177U (zh) | 一种凿岩台车快速定位自动测量*** | |
CN101419277A (zh) | 一种利用声波对矿山地下采掘点进行监测的***与方法 | |
CN110927785A (zh) | 一种矿区水力压裂裂缝微地震监测应用方法 | |
CN103790582A (zh) | 地应力测量设备及方法 | |
CN104931353B (zh) | 煤柱塑性区测试方法和测试装置 | |
CN101482621A (zh) | 一种滑坡体滑动姿态加速度监测方法 | |
CN110644973A (zh) | 一种钻孔角度测定仪及其测定方法 | |
CN107421519A (zh) | 一种涵洞顶进纠偏的监控测量方法 | |
CN111734397B (zh) | 一种近钻头磁场成像定位测量仪及工作方法 | |
CN107702638B (zh) | 围岩开挖变形全过程监测***及使用方法 | |
CN106032750B (zh) | 一种基于钻探能谱的地质编录仪 | |
CN104060983B (zh) | 有线地磁随钻导向仪及测量方法 | |
CN205477594U (zh) | 一种随钻测斜仪 | |
CN107036495A (zh) | 单叶双曲面掏心扩孔岩塞***方法 | |
CN205117332U (zh) | 一种钻孔检测杆 | |
CN114370897B (zh) | 一种暗挖隧道***震动监测装置及方法 | |
CN105758509A (zh) | 一种露天矿山岩体声速的现场测量方法 | |
CN106869904B (zh) | 一种利用钻机运行参数原位实时确定岩体损伤状态的方法 | |
CN206174952U (zh) | 一种钻孔测斜装置 | |
CN101806591A (zh) | 一种滑坡体三维位移监测方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |