CN105240036B - The horizontal massif method for tunnel construction handled to pre-reinforcement - Google Patents

The horizontal massif method for tunnel construction handled to pre-reinforcement Download PDF

Info

Publication number
CN105240036B
CN105240036B CN201510682672.XA CN201510682672A CN105240036B CN 105240036 B CN105240036 B CN 105240036B CN 201510682672 A CN201510682672 A CN 201510682672A CN 105240036 B CN105240036 B CN 105240036B
Authority
CN
China
Prior art keywords
massif
horizontal
tunnel
rock
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510682672.XA
Other languages
Chinese (zh)
Other versions
CN105240036A (en
Inventor
杨庆国
何琳
韩勇
王家林
陈世民
陈燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Jiaotong University
Original Assignee
Chongqing Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Jiaotong University filed Critical Chongqing Jiaotong University
Priority to CN201510682672.XA priority Critical patent/CN105240036B/en
Publication of CN105240036A publication Critical patent/CN105240036A/en
Application granted granted Critical
Publication of CN105240036B publication Critical patent/CN105240036B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a kind of horizontal massif method for tunnel construction handled to pre-reinforcement,Before boring tunnels excavate,By carrying out overall time level to reinforcement and strengthening to massif more than tunnel contour cable architecture to the method that massif is driven piles,Cement concrete in stake holes is penetrated into the gap in Rock And Soil,With the high-strength support frame for combining to form massif rock-soil layer of stanchion structure,Change the stress of massif rock-soil layer,Improve the stability of massif rock-soil layer,Compression strength and shearing strength,And then improve the stability of country rock after tunnel excavation,Effectively prevent rock,Soil layer collapses,And can avoids the occurrence of surface subsidence phenomenon,When ensureing tunnel piercing,The vault soil body does not produce slump and is smoothed out so as to ensureing construction and construction safety,Effect firm for a long time can be reached,Soft stratum and the constructing tunnel of big cross section span all adapt to,Do not limited by geographical environment,Design,Construction method is simple,Settle at one go,Greatly improve project progress.

Description

The horizontal massif method for tunnel construction handled to pre-reinforcement
Technical field
The present invention relates to constructing tunnel, the more particularly to horizontal massif method for tunnel construction handled to pre-reinforcement.
Background technology
After tunnel excavation, moderate finite deformation occurs for country rock, bad stability, the sedimentation of earth's surface, Jin Erhui can be caused when serious Bring serious ground structures breakoff phenomenon, in tunnel excavation, front geotechnical stability is most important, is related to engineering construction Safety, in order to ensure the stability of tunnel excavation, take certain pre-reinforcement measure to be very important.In the prior art, With more pre-reinforcement measure it is slip casting, ductule, front bolt anchorage measure etc. in tunnel excavation.
Ductule is a kind of shed ding support pre-reinforcement measure, and typically face is played by reinforcing the country rock of face Stablizing effect, but the pipe diameter of ductule and arrangement have considerable influence, and rock mass in tunnel knot to the stress in conduit Structure is bigger on the influence of ductule structure, and especially in soft stratum and the tunnel of big cross section span, the design of ductule is straight Connecing influences its using effect.Do not serve in chiltern country rock is controlled much, while the length of ductule is to ground settlement Influence greatly, ductule only combines with the preliminary bracing of tunnel surrounding could form certain support system, and then play Its consolidation effect, it is necessary to assure the lap of splice of ductule is consistent with the length that face overlaps.
The measure of slip casting pre-reinforcement has unique advantage in the pre-reinforcement of face, can effectively improve the country rock ginseng of face Number, changes its stressing conditions, so as to reach certain surrounding rock stability purpose.However, it can easily caused by there is construction wrong The problem of wall for grouting ftractures, in turn results in spillage phenomenon, has both influenceed the efficiency of construction and quality of slip casting, had influence on slip casting pre-add again Gu measure function and the performance of effect.
Positive suspension roof support, it is that anchor pole is squeezed into earth's surface rock mass, utilizes the support of its body of rod, the special tectonic on head and afterbody Class is closely linked with country rock, suspention, combination beam effect is produced, so as to reach the purpose of supporting.But positive suspension roof support Measure can not close country rock, can not prevent weathering, and the length of time one may result in the peeling of fissure rock between anchor pole.
The content of the invention
It is an object of the invention to provide a kind of horizontal massif method for tunnel construction handled to pre-reinforcement, tunnel excavation Before, horizontal direction integral reinforcing reinforcement first is carried out to massif more than tunnel contour cable architecture, improves the stabilization of massif rock-soil layer Property, compression strength and shearing strength, and then improve the stability of country rock after tunnel excavation, when ensureing tunnel piercing, vault ground Body does not produce slump and is smoothed out so as to ensureing construction and construction safety, and is not limited by geographical environment, and construction method is simple, Effect firm for a long time can be reached.
The horizontal massif method for tunnel construction handled to pre-reinforcement of the present invention, before set of tunneling construction section, in tunnel Road excavation contour line above Rock And Soil level carries out pre-reinforcement processing to reach firm tunneling construction section rock to cast-in-situ bored pile The purpose of the soil body;
Further, massif above tunnel piercing section face and adjacent side massif are locally excavated, then carried out respectively laterally Horizontal drilling bored concrete pile and vertical equity bored pile construction;
Further, massif above tunnel piercing face and adjacent side massif are locally excavated, first carried out horizontal and vertical Pile driving construction is irrigated after horizontal drilling again;
Further, the bored concrete pile is distributed in one or more layers vertically along massif;
Further, using tremie in stake holes continuous stratification concrete perfusion;
Further, the bored concrete pile section is square or circular configuration.
Beneficial effects of the present invention:The horizontal massif method for tunnel construction handled to pre-reinforcement of the present invention, tunnel excavation Before, mended by carrying out overall time level to massif more than tunnel contour cable architecture to the method that massif is driven piles to reinforcing By force, the cement concrete in stake holes is penetrated into the gap in Rock And Soil, and stanchion structure is high-strength combines to form massif rock-soil layer Support frame, change the stress of massif rock-soil layer, it is strong to improve the self-stability of massif rock-soil layer, compression strength and shearing resistance Degree, and then the stability of country rock after tunnel excavation is improved, effectively prevent rock-soil layer from collapsing, and can avoids the occurrence of surface subsidence and showed As when ensureing tunnel piercing, the vault soil body does not produce slump and is smoothed out so as to ensureing construction and construction safety, can reach long-term The constructing tunnel of firm effect, soft stratum and big cross section span all adapts to, and is not limited by geographical environment, designs, constructs Method is simple, settles at one go, greatly improves project progress.
Brief description of the drawings
The invention will be further described with reference to the accompanying drawings and examples:
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the horizontal profile top view that bored concrete pile is distributed in massif rock-soil layer.
Embodiment
Fig. 1 is the structural representation of the present invention;Fig. 2 is that the horizontal profile that bored concrete pile is distributed in massif rock-soil layer is overlooked Figure.
The horizontal massif method for tunnel construction handled to pre-reinforcement of the present embodiment, of the invention is horizontal to pre-reinforcement processing Massif method for tunnel construction, before set of tunneling construction, filled to drilling more than 3 rock-soil layer of tunnel excavation contour line 1 is horizontal Note stake 2 carries out pre-reinforcement processing to reach the purpose of the firm soil body;Cement concrete is permeable to the gap of massif rock-soil layer 1 In, the support frame of massif rock-soil layer 1 is collectively forming with bored concrete pile 2, being formed has some strength and overall compound rock-soil layer 1, Self-stability, compression strength and the shearing strength of massif rock-soil layer 1 are improved, eliminates its inhomogeneous deformation, and then improve tunnel excavation The stability of country rock afterwards, effectively prevent rock-soil layer 1 from collapsing, and can avoids the occurrence of surface subsidence phenomenon, when ensureing tunnel piercing, pick Enter face Rock And Soil not producing slump and be smoothed out so as to ensureing construction and construction safety.In the present embodiment, further, the perfusion Stake is horizontal to the fixed tie bar structure for presenting support Rock And Soil of overlap joint.
In the present embodiment, the horizontal tie bar structure for presenting support Rock And Soil after fixed to overlap joint in length and breadth of the bored concrete pile 2; " horizontal to connection in length and breadth " refers to that bored concrete pile 2 forms the attachment structure of ladder-shaped in the horizontal direction, for upper support rock-soil layer 1, avoid collapsing.
In the present embodiment, massif above tunnel piercing face and adjacent side massif are locally excavated, then successively carried out laterally Horizontal drilling bored concrete pile 2 and vertical equity cast-in-situ bored pile 2 are constructed;Retain at the top of massif, by massif above tunnel piercing face and Adjacent side massif excavates a part of construction space reserved to massif horizontal drilling vertically, can be first in the top in tunnel piercing face Massif after massif progress horizontal drilling bored concrete pile 2 again in adjacent side carries out horizontal drilling bored concrete pile 2 and constructed, also can be first in tunnel After the massif of the adjacent side of road development end carries out the construction of horizontal drilling bored concrete pile 2, then massif carries out water above tunnel piercing face Flat drill hole pouring pile 2 is constructed.In order to ensure effective connection that bored concrete pile 2 is horizontal and vertical, detecting devices can be used to carry out accurate Post is irrigated after carrying out drilling construction again after positioning.
In the present embodiment, massif above tunnel piercing face and adjacent side massif are locally excavated, first carried out laterally and vertical To horizontal drilling after be irrigated stake 2 again and construct;Massif and adjacent side massif local vertical excavate above tunnel piercing face The construction space to massif horizontal drilling is reserved, first massif and the massif of adjacent side are bored by rig above development end Behind good hole, then construction is irrigated, being so advantageous to bored concrete pile 2, vertically and horizontally directly contraposition is integrally connected shaping, reduces other Auxiliary para connects the use of equipment.
In the present embodiment, the bored concrete pile 2 is along massif vertically in one or more layers distribution;According to specific geology feelings Condition, also can be using two layers or more than two layers in level side using one layer of bored concrete pile being connected with each other in the horizontal direction 2 The bored concrete pile 2 being connected with each other upwards, suitably selected with specific reference to the stability of rock-soil layer 1.
In the present embodiment, using tremie in stake holes continuous stratification concrete perfusion;Hole inner concrete can be ensured The density of filling, it is ensured that the intensity of every perfusion post is consistent, and then ensures the uniformity of stress deformation, improves bored concrete pile 2 Compression strength, and then improve the stability of rock-soil layer 1.
In the present embodiment, the perfusion column section is square or circular configuration;Before drilling construction spuds in, drill bit point position with Cloth hole point is not more than 1 ° away from being more or less the same in 2cm, drilling rod degree;, should be strictly by figure positioning, and there is reinspection to make in work progress Degree.Axis stake is distinguished with stake position stake application color, must not be obscured.Before starting borehole, have with the annulus of centring ring reinforcement fabrication Scale cross puts borehole line, it is necessary to pile center's point calibration template position, and is responsible for by special messenger.Centring ring center line and design Misalignment of axe cannot be greater than 20 millimeters.During borehole, center line should be hung with line pendant at any time, it is found that deviation is excessive and entangle immediately Partially.It is required that each branch dado template will messenger wire once (be defined by the crossed circular of top center).Answer uniform ring-type excavate into Chi, it is advisable every time with 100 millimeters to surrounding drilling depth, the wall that collapses excessively is caused to prevent local excavation.After pore-forming, it should check immediately Check and accept, follow subsequent processing closely, hang steel reinforcement cage, casting concrete, avoid hole overlong time of drying in the air, cause unnecessary collapse hole, it is special In the case of being not rainy season or having infiltration, pore-forming must not be stayed overnight.
Finally illustrate, the above embodiments are merely illustrative of the technical solutions of the present invention and it is unrestricted, although with reference to compared with The present invention is described in detail good embodiment, it will be understood by those within the art that, can be to the skill of the present invention Art scheme is modified or equivalent substitution, and without departing from the objective and scope of technical solution of the present invention, it all should cover at this Among the right of invention.

Claims (6)

  1. A kind of 1. horizontal massif method for tunnel construction handled to pre-reinforcement, it is characterised in that:Before set of tunneling construction section, Pre-reinforcement processing is carried out in tunnel excavation contour line above rock-soil layer level to cast-in-situ bored pile to reach firm tunneling construction to break The purpose of face Rock And Soil, the bored concrete pile include vertical equity stake and transverse horizontal stake, vertical equity stake and transverse horizontal stake water Put down the tie bar structure for presenting support Rock And Soil after fixed to overlap joint in length and breadth.
  2. 2. the horizontal massif method for tunnel construction handled to pre-reinforcement according to claim 1, it is characterised in that:By tunnel Massif and adjacent side massif locally excavate above excavated section, then carry out transverse horizontal cast-in-situ bored pile and vertical equity respectively Bored pile construction.
  3. 3. the horizontal massif method for tunnel construction handled to pre-reinforcement according to claim 2, it is characterised in that:By tunnel Massif or adjacent side massif locally excavate above excavated section, are irrigated again after first carrying out horizontal and vertical horizontal drilling Pile driving construction.
  4. 4. the horizontal massif method for tunnel construction handled to pre-reinforcement according to Claims 2 or 3, it is characterised in that:Institute Bored concrete pile is stated along massif vertically in one or more layers distribution.
  5. 5. the horizontal massif method for tunnel construction handled to pre-reinforcement according to claim 4, it is characterised in that:Using mixed Coagulate native conduit continuous stratification concrete perfusion in stake holes.
  6. 6. the horizontal massif method for tunnel construction handled to pre-reinforcement according to claim 5, it is characterised in that:The filling Stake section is noted as square or circular configuration.
CN201510682672.XA 2015-10-20 2015-10-20 The horizontal massif method for tunnel construction handled to pre-reinforcement Expired - Fee Related CN105240036B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510682672.XA CN105240036B (en) 2015-10-20 2015-10-20 The horizontal massif method for tunnel construction handled to pre-reinforcement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510682672.XA CN105240036B (en) 2015-10-20 2015-10-20 The horizontal massif method for tunnel construction handled to pre-reinforcement

Publications (2)

Publication Number Publication Date
CN105240036A CN105240036A (en) 2016-01-13
CN105240036B true CN105240036B (en) 2017-11-17

Family

ID=55037827

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510682672.XA Expired - Fee Related CN105240036B (en) 2015-10-20 2015-10-20 The horizontal massif method for tunnel construction handled to pre-reinforcement

Country Status (1)

Country Link
CN (1) CN105240036B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107605504A (en) * 2017-11-03 2018-01-19 中交公局第三工程有限公司 Cliff position double-hole tunnel port structure and method for tunnel construction

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101215838A (en) * 2007-12-28 2008-07-09 浙江环宇建设集团有限公司 Construction technique for foundation ditch on top of underground railway tunnel in soft soil area
CN202866817U (en) * 2012-09-04 2013-04-10 中铁十二局集团有限公司 Tunnel ruggedized construction of full face dry silty-fine sand layer
CN103306687A (en) * 2012-10-31 2013-09-18 王卓 Construction method for deformation control via horizontal whirling jet grouting of long cantilever in soft-rock tunnel
CN103967504A (en) * 2014-05-21 2014-08-06 中国能源建设集团广东省电力设计研究院 Supporting structure of tunnel opening of power plant circulating water system and construction method
CN104500100A (en) * 2014-12-15 2015-04-08 中铁第四勘察设计院集团有限公司 Advanced support structure for oversized variable-section tunnel
CN104533434A (en) * 2014-12-28 2015-04-22 上海隧道工程股份有限公司 Construction method of rectangular ultra-shallow covered soil tunnel

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101215838A (en) * 2007-12-28 2008-07-09 浙江环宇建设集团有限公司 Construction technique for foundation ditch on top of underground railway tunnel in soft soil area
CN202866817U (en) * 2012-09-04 2013-04-10 中铁十二局集团有限公司 Tunnel ruggedized construction of full face dry silty-fine sand layer
CN103306687A (en) * 2012-10-31 2013-09-18 王卓 Construction method for deformation control via horizontal whirling jet grouting of long cantilever in soft-rock tunnel
CN103967504A (en) * 2014-05-21 2014-08-06 中国能源建设集团广东省电力设计研究院 Supporting structure of tunnel opening of power plant circulating water system and construction method
CN104500100A (en) * 2014-12-15 2015-04-08 中铁第四勘察设计院集团有限公司 Advanced support structure for oversized variable-section tunnel
CN104533434A (en) * 2014-12-28 2015-04-22 上海隧道工程股份有限公司 Construction method of rectangular ultra-shallow covered soil tunnel

Also Published As

Publication number Publication date
CN105240036A (en) 2016-01-13

Similar Documents

Publication Publication Date Title
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN102606162B (en) Quick construction method for weak surrounding rock shallowly-buried easily-collapsed area of tunnel
CN104405399B (en) One kind passes through drift sand stratum tunnel excavation support body engineering method
CN110017144B (en) Loess tunnel three-step construction method considering substrate reinforcement treatment
CN106930321B (en) The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole
CN109208637A (en) Increase the construction method of open-cut station newly on the basis of existing tunnel
CN104818991A (en) Construction method of residual slope wash tunnel with shallow cover and unsymmetrical pressure
CN102155234B (en) Excavation construction method for unsymmetrical small-space tunnel
CN106121661A (en) A kind of tunnel trunk is by loess separating surface water rich strata construction method
CN104790978A (en) Small-clear-distance grade separation tunnel annular guide pit construction method
CN108252719B (en) Plastic flow modeling shape red clay layer construction method is worn under a kind of urban shallow tunnel
CN108915736A (en) The water damage control method of digging laneway under the strong weak cementing water-bearing layer of rich water
CN102943466A (en) Construction method for miniature steel pipe concrete pile to penetrate through roadbed layer for reinforcing soft foundation construction
CN107023300A (en) A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
CN103775093A (en) Construction method for right-angle skew tunnel-entering cover arch of unsymmetrical-loaded and shallow-buried tunnel
CN206174963U (en) Cross shallow undercut tunnel supporting construction of burying of ground fissure crushed zone
CN103898916A (en) Mini-pile combined support structure and construction method thereof
CN109930609A (en) A kind of campshed composite supporting construction and its construction method for upper-soft lower-hard ground
CN108843341A (en) A kind of the cut-and-cover tunnel structure and its construction method of mixture of piles and concrete wall formula
CN114278310B (en) Construction method of micro steel pipe pile lattice beam at shallow buried section of tunnel
CN106812150A (en) A kind of mountain area steep slope region Road Bridge Pile Foundation construction method
CN108374672B (en) A method of reinforcing Deep Mine soft coal level roadway surrounding rock
CN115539048A (en) Construction method for shallow-buried bias tunnel portal
CN216342131U (en) Shield tunnel invades limit stake and handles reinforced structure
CN205152983U (en) Stratum pre -reinforcing of underground space construction handles structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171117

Termination date: 20191020