CN105204793A - Method for applying BIM and 3D printing technology to construction - Google Patents

Method for applying BIM and 3D printing technology to construction Download PDF

Info

Publication number
CN105204793A
CN105204793A CN201510607860.6A CN201510607860A CN105204793A CN 105204793 A CN105204793 A CN 105204793A CN 201510607860 A CN201510607860 A CN 201510607860A CN 105204793 A CN105204793 A CN 105204793A
Authority
CN
China
Prior art keywords
model
construction
rationality
information model
printing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510607860.6A
Other languages
Chinese (zh)
Inventor
汪芦金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201510607860.6A priority Critical patent/CN105204793A/en
Publication of CN105204793A publication Critical patent/CN105204793A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a method for applying a BIM and a 3D printing technology to construction. The method comprises the following steps: 1) establishing a three-dimensional building information model; 2) deriving the three-dimensional building information model in the format of dwf, opening the three-dimensional building information model through Navisworks, using Navisworks software to render the three-dimensional building information model, and examining rationality of spatial arrangement of a building through roaming; 3) after the rationality of the three-dimensional building information model is determined, connecting a 3D printer, and printing a needed model; 4) causing project participators to examine rationality of the printed model and timely feed problems back to model establishing engineers, and causing the professional engineers to adjust the model according to modifications given by a design institute, so that the building use rationality is guaranteed and the problems are obtained at an earlier construction stage. By combining the BIM and the 3D printing technology, the control on a construction process is reinforced, building usability and quality are improved, and the cost is reduced. The communication effect is improved through the method.

Description

A kind of method BIM and 3D printing technique is applied in construction
Technical field
The invention belongs to construction engineering technical field, particularly relate to a kind of method be applied in by BIM and 3D printing technique in construction.
Background technology
Building engineering construction needs to examine the design of project early stage, what designing institute provided is two-dimentional drawing, each specialty is again publish picture separately, project participant may be entirely inconsiderate in early stage, some problem does not have Timeliness coverage, inevitable loss is brought after coming into operation with project in work progress, BIM technology obtained building trade attention in recent years, three-dimensional information model brings great help to project management, but it is also not enough to some extent, project is completed together with personnel by multiple unit, some personnel participating in building may not know hi-tech, some is built workman and was not accepted very high education simultaneously, occur that BIM technology is difficult to popularize at the scene, model virtual in computer and reality is also had still to have certain discrepancy, under these circumstances, BIM and 3D printing technique is combined, in early stage, we can examine BUILDINGS MODELS, print standard jig, great help will be brought to project construction process.
Summary of the invention
The object of the present invention is to provide a kind of method be applied in by BIM and 3D printing technique in construction, to solve the problem proposed in above-mentioned background technology.
For achieving the above object, present invention employs following technical scheme:
BIM and 3D printing technique is applied in the method in construction, comprises the following steps:
1) devising and drawing the blueprint of construction project is converted into three-dimensional building information model with Revit software, after the rationality that expert engineer checks out layout design in three-dimensional information model and wrong part, pipeline is detected with the collision checking function of Revit software, according to the point of impingement checked out, amendment is optimized pipeline and is arranged;
2) three-dimensional building information model is derived with dwf form, open with Navisworks, with Navisworks software renders three-dimensional information model, and check by roaming the rationality that the space of building is arranged;
3), after confirming three-dimensional information model rationality, be connected with 3D printer, the model required for printing;
4) project participant is to the model printed, check its rationality, problem is fed back in time the slip-stick artist that model is set up, the change and adjustment model that expert engineer provides according to designing institute, ensure the rationality that building uses, problem is just resolved in construction early stage.
Preferably, when printing required model in step 3), for model room, basement regional area, water power pipe well, equipment machine room, reinforced bar engineering, form work engineering, masonry project, waterproofing work and heat insulating work, for printing in 1:1 ratio of showing, the model being used to guide construction to each construction teams and groups can ratio print, with easy to use according to actual needs.
Beneficial effect of the present invention is: the present invention is by combining BIM and 3D printing technique, in construction in earlier stage, we find weak point in design in advance by the examination to true model, time update, those being unfamiliar with to the field work person of BIM technology, their nodal analysis method by reducing simultaneously, strengthening the control to working procedure, improve usability and the quality of building, reduce cost, simultaneously by this method, improve communication effectiveness.
Accompanying drawing explanation
Fig. 1 is the process flow diagram BIM and 3D printing technique being applied in the method in construction.
Embodiment
Below in conjunction with embodiment, optimal way of the present invention is described in further detail.
As shown in Figure 1, a kind of method be applied in by BIM and 3D printing technique in construction, comprises the following steps:
1) devising and drawing the blueprint of construction project is converted into three-dimensional building information model with Revit software, after the rationality that expert engineer checks out layout design in three-dimensional information model and wrong part, pipeline is detected with the collision checking function of Revit software, according to the point of impingement checked out, amendment is optimized pipeline and is arranged.
2) three-dimensional building information model is derived with dwf form, open with Navisworks, with Navisworks software renders three-dimensional information model, and check by roaming the rationality that the space of building is arranged.
3) after confirming three-dimensional information model rationality, be connected with 3D printer, model required for printing, for model room, basement regional area, water power pipe well, equipment machine room, reinforced bar engineering, form work engineering, masonry project, waterproofing work and heat insulating work, for printing in 1:1 ratio of showing, the model being used to guide construction to each construction teams and groups can ratio print, with easy to use according to actual needs.
4) project participant is to the model printed, check its rationality, problem is fed back in time the slip-stick artist that model is set up, the change and adjustment model that expert engineer provides according to designing institute, ensure the rationality that building uses, problem is just resolved in construction early stage.
The present invention proposes a kind of method be applied in by BIM and 3D printing technique in construction, utilize BIM technology, three-dimensional information model is set up by devising and drawing the blueprint of designing institute, after pipeline collision detection and expert engineer's examination, model required for printing with 3D printer, the ratio of model is arranged on demand.This model two-dimentional drawing that we use in the past by replacement, in construction in earlier stage, we find weak point in design in advance by the examination to true model, time update, those being unfamiliar with to the field work person of the software that BIM technology adopts, their nodal analysis method by reducing simultaneously, strengthening the control to working procedure, improve usability and the quality of building, reduce cost, simultaneously by this method, improve communication effectiveness.
Above embodiment is only be described the preferred embodiment of the present invention; not scope of the present invention is limited; under not departing from the present invention and designing the prerequisite of spirit; the various distortion that those of ordinary skill in the art make technical scheme of the present invention and improvement, all should fall in protection domain that claims of the present invention determines.

Claims (2)

1. BIM and 3D printing technique is applied in the method in construction, it is characterized in that, comprise the following steps:
1) devising and drawing the blueprint of construction project is converted into three-dimensional building information model with Revit software, after the rationality that expert engineer checks out layout design in three-dimensional information model and wrong part, pipeline is detected with the collision checking function of Revit software, according to the point of impingement checked out, amendment is optimized pipeline and is arranged;
2) three-dimensional building information model is derived with dwf form, open with Navisworks, with Navisworks software renders three-dimensional information model, and check by roaming the rationality that the space of building is arranged;
3), after confirming three-dimensional information model rationality, be connected with 3D printer, the model required for printing;
4) project participant is to the model printed, check its rationality, problem is fed back in time the slip-stick artist that model is set up, the change and adjustment model that expert engineer provides according to designing institute, ensure the rationality that building uses, problem is just resolved in construction early stage.
2. the method BIM and 3D printing technique is applied in construction according to claim 1, it is characterized in that, when printing required model in step 3), for model room, basement regional area, water power pipe well, equipment machine room, reinforced bar engineering, form work engineering, masonry project, waterproofing work and heat insulating work, for printing in 1:1 ratio of showing, the model being used to guide construction to each construction teams and groups can ratio print, with easy to use according to actual needs.
CN201510607860.6A 2015-09-23 2015-09-23 Method for applying BIM and 3D printing technology to construction Pending CN105204793A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510607860.6A CN105204793A (en) 2015-09-23 2015-09-23 Method for applying BIM and 3D printing technology to construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510607860.6A CN105204793A (en) 2015-09-23 2015-09-23 Method for applying BIM and 3D printing technology to construction

Publications (1)

Publication Number Publication Date
CN105204793A true CN105204793A (en) 2015-12-30

Family

ID=54952512

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510607860.6A Pending CN105204793A (en) 2015-09-23 2015-09-23 Method for applying BIM and 3D printing technology to construction

Country Status (1)

Country Link
CN (1) CN105204793A (en)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088598A (en) * 2016-06-12 2016-11-09 中国十七冶集团有限公司 A kind of BIM technology is used to carry out the method led the way of model of constructing
CN106906746A (en) * 2017-02-04 2017-06-30 北京交通大学 A kind of monorail transit 3D printing technique based on BIM
CN106952337A (en) * 2017-03-14 2017-07-14 福州市规划设计研究院 A kind of three-dimensional input output method of city streetscape
CN107065801A (en) * 2017-04-27 2017-08-18 中铁六局集团有限公司 Simulative construction method is automatically assembled using the section of track production line of BIM technology
CN107220464A (en) * 2017-06-28 2017-09-29 中国十七冶集团有限公司 A kind of bridge construction process emulation and risk control method based on BIM
CN107558642A (en) * 2017-08-22 2018-01-09 中国十七冶集团有限公司 A kind of method in the large-scale open stone curtain wall installation based on BIM
CN108182298A (en) * 2016-10-25 2018-06-19 福建省建筑设计研究院有限公司 Virtual and real cross-check system based on BIM
CN108256169A (en) * 2017-12-26 2018-07-06 中国十七冶集团有限公司 A kind of method applied in construction model experience based on BIM and VR technologies
WO2018145510A1 (en) * 2017-02-10 2018-08-16 深圳瑞和建筑装饰股份有限公司 Bim-based construction and decoration method
CN108673900A (en) * 2018-05-22 2018-10-19 中国建筑局(集团)有限公司 Solid model 3D printing forming method
CN108711773A (en) * 2018-06-07 2018-10-26 武汉鑫科信科技有限公司 A kind of design method of buildings integrative wire laying equipment room
CN109461360A (en) * 2018-10-23 2019-03-12 中建八局浙江建设有限公司 Electromechanical pre-buried simulation system and analogy method
CN110044310A (en) * 2019-04-29 2019-07-23 黄山学院 A kind of architectural design device based on BIM
CN110434977A (en) * 2019-08-15 2019-11-12 四川建筑职业技术学院 A kind of production method of the 3D printing assembled architecture based on BIM
CN111753353A (en) * 2020-05-19 2020-10-09 中国一冶集团有限公司 Assembly type residence PC component hoisting simulation system and method based on BIM technology
CN111898186A (en) * 2020-07-22 2020-11-06 四川省第十一建筑有限公司 Application method of BIM technology in template temporary setting
CN112733224A (en) * 2020-12-28 2021-04-30 中铁广州工程局集团有限公司 Simulation pile sinking construction method for dense pile group
CN114266087A (en) * 2021-10-14 2022-04-01 中国建筑第二工程局有限公司 Thin-shell structure formwork system construction method and management system based on BIM technology
CN117874870A (en) * 2023-12-14 2024-04-12 陕西铁路工程职业技术学院 Visual construction method of deformed steel structure based on BIM technology

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103218492A (en) * 2013-04-16 2013-07-24 上海上安机电设计事务所有限公司 BIM (Building Information Model)-based pipe prefabrication method
CN103692651A (en) * 2013-12-06 2014-04-02 中铁建设集团有限公司 BIM (Building Information Modeling) model designing device with 3D input and output functions
US20150248503A1 (en) * 2014-03-01 2015-09-03 Benjamin F. GLUNZ Method and system for creating 3d models from 2d data for building information modeling (bim)

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103218492A (en) * 2013-04-16 2013-07-24 上海上安机电设计事务所有限公司 BIM (Building Information Model)-based pipe prefabrication method
CN103692651A (en) * 2013-12-06 2014-04-02 中铁建设集团有限公司 BIM (Building Information Modeling) model designing device with 3D input and output functions
US20150248503A1 (en) * 2014-03-01 2015-09-03 Benjamin F. GLUNZ Method and system for creating 3d models from 2d data for building information modeling (bim)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李彬等: "BIM技术在项目前期管理工作中的应用", 《价值工程》 *

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088598A (en) * 2016-06-12 2016-11-09 中国十七冶集团有限公司 A kind of BIM technology is used to carry out the method led the way of model of constructing
CN108182298A (en) * 2016-10-25 2018-06-19 福建省建筑设计研究院有限公司 Virtual and real cross-check system based on BIM
CN106906746A (en) * 2017-02-04 2017-06-30 北京交通大学 A kind of monorail transit 3D printing technique based on BIM
WO2018145510A1 (en) * 2017-02-10 2018-08-16 深圳瑞和建筑装饰股份有限公司 Bim-based construction and decoration method
CN106952337A (en) * 2017-03-14 2017-07-14 福州市规划设计研究院 A kind of three-dimensional input output method of city streetscape
CN107065801B (en) * 2017-04-27 2019-06-04 中铁六局集团有限公司 Simulative construction method is automatically assembled using the section of track production line of BIM technology
CN107065801A (en) * 2017-04-27 2017-08-18 中铁六局集团有限公司 Simulative construction method is automatically assembled using the section of track production line of BIM technology
CN107220464A (en) * 2017-06-28 2017-09-29 中国十七冶集团有限公司 A kind of bridge construction process emulation and risk control method based on BIM
CN107558642A (en) * 2017-08-22 2018-01-09 中国十七冶集团有限公司 A kind of method in the large-scale open stone curtain wall installation based on BIM
CN108256169A (en) * 2017-12-26 2018-07-06 中国十七冶集团有限公司 A kind of method applied in construction model experience based on BIM and VR technologies
CN108673900A (en) * 2018-05-22 2018-10-19 中国建筑局(集团)有限公司 Solid model 3D printing forming method
CN108711773A (en) * 2018-06-07 2018-10-26 武汉鑫科信科技有限公司 A kind of design method of buildings integrative wire laying equipment room
CN109461360A (en) * 2018-10-23 2019-03-12 中建八局浙江建设有限公司 Electromechanical pre-buried simulation system and analogy method
CN109461360B (en) * 2018-10-23 2021-04-13 中建八局浙江建设有限公司 Electromechanical pre-buried simulation system and method
CN110044310A (en) * 2019-04-29 2019-07-23 黄山学院 A kind of architectural design device based on BIM
CN110434977A (en) * 2019-08-15 2019-11-12 四川建筑职业技术学院 A kind of production method of the 3D printing assembled architecture based on BIM
CN111753353A (en) * 2020-05-19 2020-10-09 中国一冶集团有限公司 Assembly type residence PC component hoisting simulation system and method based on BIM technology
CN111753353B (en) * 2020-05-19 2024-05-17 中国一冶集团有限公司 BIM technology-based assembled house PC component hoisting simulation system and method
CN111898186A (en) * 2020-07-22 2020-11-06 四川省第十一建筑有限公司 Application method of BIM technology in template temporary setting
CN112733224A (en) * 2020-12-28 2021-04-30 中铁广州工程局集团有限公司 Simulation pile sinking construction method for dense pile group
CN114266087A (en) * 2021-10-14 2022-04-01 中国建筑第二工程局有限公司 Thin-shell structure formwork system construction method and management system based on BIM technology
CN117874870A (en) * 2023-12-14 2024-04-12 陕西铁路工程职业技术学院 Visual construction method of deformed steel structure based on BIM technology

Similar Documents

Publication Publication Date Title
CN105204793A (en) Method for applying BIM and 3D printing technology to construction
CN104156544A (en) Automatic beam and column steel bar joint arranging and constructing simulation method based on BIM technology
US20180113959A1 (en) Cloud-enabled generation of construction metrics and documentation
CN105888248A (en) Construction method of guiding informationization prefabricated member based on BIM (Building Information Modeling)) technology
CN102360535A (en) Three-dimensional visual simulation training system and method
CN107558642A (en) A kind of method in the large-scale open stone curtain wall installation based on BIM
CN209590841U (en) A kind of system integrated based on three-dimensional visualization technique combination internet of things data
CN107299762A (en) A kind of concrete pouring procedure based on BIM
CN105489102A (en) Three-dimensional interactive training exercise system
CN110879905A (en) BIM-based virtual building roof deepening construction method
CN110532653A (en) A kind of building pipeline layout optimization system and classification method based on BIM
CN112347549A (en) BIM technology-based accurate positioning method for prestressed pipeline of continuous railway beam
CN111460566A (en) BIM technology-based architectural engineering structure design information exchange method
CN113761632B (en) BIM-based electromechanical fully-assembled three-dimensional forward design method
CN102541109B (en) Method for manufacturing satellite star surface temperature-control multilayer
CN109145384A (en) A kind of welding equipment three-dimensional process designing system
CN107895065A (en) A kind of plant design method based on 3-D technology
CN108984876A (en) A kind of service sleeve automation modeling method and system based on BIM
CN112765711A (en) BIM modeling method for green building simulation calculation
CN105589989B (en) Process modeling construction method and system
Laudante et al. Design and Digital Manufacturing: an ergonomic approach for Industry 4.0
CN105765468A (en) System-setup assistance apparatus
CN105589978A (en) Three-dimensional process design method based on model
CN104563471A (en) Floor rolling mechanism for construction engineering
CN205844881U (en) Device is controlled based on OPC ring main unit automatic assembly line

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20151230