CN105200878A - Roadbed and inspection well differential settlement control construction method - Google Patents

Roadbed and inspection well differential settlement control construction method Download PDF

Info

Publication number
CN105200878A
CN105200878A CN201510554128.7A CN201510554128A CN105200878A CN 105200878 A CN105200878 A CN 105200878A CN 201510554128 A CN201510554128 A CN 201510554128A CN 105200878 A CN105200878 A CN 105200878A
Authority
CN
China
Prior art keywords
roadbed
manhole
construction method
settlement control
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510554128.7A
Other languages
Chinese (zh)
Inventor
陈志诚
彭丽华
曾邦国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huzhou Haocheng Environmental Engineering Co Ltd
Original Assignee
Huzhou Haocheng Environmental Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huzhou Haocheng Environmental Engineering Co Ltd filed Critical Huzhou Haocheng Environmental Engineering Co Ltd
Priority to CN201510554128.7A priority Critical patent/CN105200878A/en
Publication of CN105200878A publication Critical patent/CN105200878A/en
Pending legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention relates to a roadbed and inspection well differential settlement control construction method, and belongs to the technical field of road construction. The roadbed and inspection well differential settlement control construction method comprises the following steps of (1) roadbed filling: digging slopes into ladder shapes, and carrying out layered filling and dense grinding according to the varieties of soil; (2) pipe channel construction: setting one water collecting well, digging a pipe channel to designed elevation, stably placing pipelines, and performing a pipeline leakproofness closed water test for once after the construction of a section of pipeline is completed every time; (3) inspection well construction: tamping a foundation soil layer of the inspection well by adopting a pounder, and then carrying out foundation construction of a cushion layer and reinforced concrete; (4) backfilling: backfilling the pipeline channel by adopting medium-coarse sand, and compacting in layers; backfilling the periphery of the inspection well by adopting aggregate and dust or sand; (5) roadbed top surface construction: densely grinding by adopting a vibrating type road roller of which the weight is more than 12t until the surface has no obvious wheelmarks. According to the roadbed and inspection well differential settlement control construction method disclosed by the invention, the roadbed is compact, the roadbed is stably matched with the pipelines and the inspection well, and the inspection well is not easy to collapse.

Description

A kind of roadbed and manhole difference settlement control construction method
Technical field
The present invention relates to technical field of road construction, be specifically related to a kind of roadbed and manhole difference settlement control construction method.
Background technology
In urban road, manhole periphery sinks and breakage, cause road surface " rotten eyelet " phenomenon, it is a kind of common common quality defect, cause jumping car during vehicle normal pass, cause surface course sinking, be full of cracks, breakage further, crib and superelevation of highway surface value excessive, main cause is different parts Subgrade Compaction, draining, filler moisture content, also have in addition manhole based process, well room (cylinder) are built by laying bricks or stones, the detailed treatment at the position such as borehole wall periphery backfill.
Summary of the invention
Object of the present invention is to solve the problem, and provides a kind of roadbed sturdy, coordinates stable with pipeline and manhole, and the not givey construction method of manhole.
The technical scheme that the present invention solves the problem is as follows:
A kind of roadbed and manhole difference settlement control construction method, comprise the steps:
1. roadbed filling: side slope is scraped out the stepped of convenient overlap joint, every grade of shoulder height 0.7-1.3m, then according to the kind placement in layers of the soil that will fill, layer-by-layer rolling is closely knit;
2. pipe groove construction: be not more than a well segment limit in trench length and arrange place's collecting well, to discharge groove ponding, pipe trench groove digs to design altitude, pipeline is laid firmly, often complete one section of pipeline construction, make a pipeline leakproofness closed-water test, finding leaks fills up in time;
3. manhole construction: first manhole foundation bed is adopted hammer ram compacting before construction, then carry out bed course and reinforced concrete foundation construction;
4. backfill: adopt medium coarse sand backfill pipeline groove, by the bottom of pipe, thoracic cavity, the different parts back-filling in layers of pipe top, compaction in layers; Adopt sandstone dirt or system sand to backfill manhole periphery, build rising by laying bricks or stones with the borehole wall during backfill, successively by the tamping of manhole outer ring, filler virtual resurfacing thickness is not more than 20 ㎝, within the scope of the 60-80cm of manhole outer ring, adopts small vibrating to grind or frog rammer compacting;
5. roadbed end face construction: carry out king-pile recovery to road, uniform filling is filled up smooth along manhole week, adopts more than 12t vibrating roller grinding compacting, should carry out piecemeal, roll to surface without obvious wheelmark when rolling from roadside to road.
Preferred as technique scheme, step 1. in every grade of shoulder height be 1m, bench floor slopes inwardly.
Preferred as technique scheme, step 1. in every layer of native filling-up thickness be less than 40cm, be less than 30cm after compacting, roadbed filling compaction plane both sides are 50cm wider than design width respectively.
Preferred as technique scheme, step 1. in, fill in scope when having pipe works, soil layer filled height should higher than pipeline highest point at least 50cm, and through more than 12 tons heavy road roller grinding compactings.
Preferred as technique scheme, step 2. in, polyethylene pipe pipe heelpiece sand before laying should adopt plate vibration machine to flatten compacting, and pipeline avris backfills medium coarse sand in time with stable pipeline.
Preferred as technique scheme, step 4. in, the jolt ramming of small vibrating machine is adopted to medium coarse sand, and sprays water on a small quantity in vibration processes, make medium coarse sand packing course in conjunction with closely knit.
Preferred as technique scheme, step 5. in, packing material size is not more than 10cm.
Preferred as technique scheme, step 5. in, road roller does not collide borehole wall extruding walling crib, road roller construction less than position, make separate arrangements small vibrating rolling compaction machine or frog rammer, coordinate the synchronous compacting of roadbed.
Preferred as technique scheme, step 1. before also comprise road repetition measurement step.
Preferred as technique scheme, road repetition measurement step comprises traverse testing survey, check survey of centre line, bench mark repetition measurement.
Traverse testing survey: according to design data, conscientiously carries out traverse testing survey work, adopting through checking the infrared range-measurement system meeting corresponding precision edited, answering traverse station to encrypt if desired, can mutual intervisibility to ensure implementing consecutive points in overall process at road.Certainty of measurement is except being designed with particular/special requirement, and angle is closed poor (" entirely) requirement of ± 16 √ n (n is measuring point number) and relative closing error ± 1/10000 of coordinate should be met.After repetition measurement wire, must with the traverse closure of adjacent construction section.
Check survey of centre line: first should check comprehensively and recover centre mark, route major control stake, as intersection point, turning point, the rising of circular curve and easement curve, settled point.The deviation of center line of road position should control within 5 ㎜: during employing DJ2 level instrument, angle at least surveys a survey time; During employing DJ6 level instrument, angle at least surveyed for two survey time; The common steel ruler of distance comes and goes survey one survey time, or electromagnetic distance measuring instrument can one way measure.
Bench mark repetition measurement: check the bench mark checked Construction unit and pay, and determine bench mark as far as possible with state closed.Construction measurement of the level between adjacent 2 years vertical control points, should adopt contact level measuring method.Urban road temporary bench mark should close with design bench mark repetition measurement, and it allows closing error through street, major trunk roads are ± 12 √ L ㎜, and branch road is ± 20 √ L ㎜.Bench mark spacing is not more than 1 ㎞ temporary bench mark and should adopts 200 ~ 300m arrange one in urban district.
In sum, the present invention has following beneficial effect:
1. a kind of roadbed of the present invention and manhole difference settlement control construction method roadbed are in a down-to-earth manner, coordinate stable with pipeline and manhole;
2. a kind of roadbed of the present invention and manhole difference settlement control construction method manhole not easily subside.
Accompanying drawing explanation
Fig. 1 is rendzinas subgrade construction process chart described in embodiment 1 and embodiment 2;
Fig. 2 is rendzinas subgrade construction process chart described in embodiment 3 and embodiment 4.
Detailed description of the invention
Be clearly and completely described to the technical scheme in the embodiment of the present invention below, obviously, described embodiment is only the present invention's part embodiment, instead of whole embodiments.Embodiment in the present invention, those of ordinary skill in the art, not doing other embodiments all obtained under creative work prerequisite, belong to the scope of protection of the invention.
Below in conjunction with accompanying drawing, with embodiment, the present invention is described in detail.
Embodiment 1: a kind of roadbed and manhole difference settlement control construction method, comprise the steps:
1. roadbed filling: side slope is scraped out the stepped of convenient overlap joint, every grade of shoulder height 1m, bench floor slopes inwardly, and then according to the kind placement in layers of the soil that will fill, layer-by-layer rolling is closely knit;
2. pipe groove construction: be not more than a well segment limit in trench length and arrange place's collecting well, to discharge groove ponding, pipe trench groove digs to design altitude, pipeline is laid firmly, often complete one section of pipeline construction, make a pipeline leakproofness closed-water test, finding leaks fills up in time;
3. manhole construction: first manhole foundation bed is adopted hammer ram compacting before construction, then carry out bed course and reinforced concrete foundation construction;
4. backfill: adopt medium coarse sand backfill pipeline groove, by the bottom of pipe, thoracic cavity, the different parts back-filling in layers of pipe top, compaction in layers; Adopt sandstone dirt or system sand to backfill manhole periphery, build rising by laying bricks or stones with the borehole wall during backfill, successively by the tamping of manhole outer ring, filler virtual resurfacing thickness is not more than 20 ㎝, within the scope of the 60-80cm of manhole outer ring, adopts small vibrating to grind or frog rammer compacting;
5. roadbed end face construction: king-pile recovery is carried out to road, uniform filling is filled up smooth along manhole week, and packing material size is not more than 10cm, adopts more than 12t vibrating roller grinding compacting, should carry out piecemeal to road from roadside when rolling, roll to surface without obvious wheelmark.
Embodiment 2: a kind of roadbed and manhole difference settlement control construction method, comprise the steps:
1. roadbed filling: side slope is scraped out the stepped of convenient overlap joint, every grade of shoulder height 0.7m, bench floor slopes inwardly, then according to the kind placement in layers of the soil that will fill, layer-by-layer rolling is closely knit, every layer of native filling-up thickness is less than 40cm, is less than 30cm after compacting, and roadbed filling compaction plane both sides are 50cm wider than design width respectively;
2. pipe groove construction: be not more than a well segment limit in trench length and arrange place's collecting well, to discharge groove ponding, pipe trench groove digs to design altitude, pipeline is laid firmly, often complete one section of pipeline construction, make a pipeline leakproofness closed-water test, finding leaks fills up in time;
3. manhole construction: first manhole foundation bed is adopted hammer ram compacting before construction, then carry out bed course and reinforced concrete foundation construction;
4. backfill: adopt medium coarse sand backfill pipeline groove, by the bottom of pipe, thoracic cavity, the different parts back-filling in layers of pipe top, compaction in layers, adopts the jolt ramming of small vibrating machine to medium coarse sand, and sprays water on a small quantity in vibration processes, make medium coarse sand packing course in conjunction with closely knit; Adopt sandstone dirt or system sand to backfill manhole periphery, build rising by laying bricks or stones with the borehole wall during backfill, successively by the tamping of manhole outer ring, filler virtual resurfacing thickness is not more than 20 ㎝, within the scope of the 60-80cm of manhole outer ring, adopts small vibrating to grind or frog rammer compacting;
5. roadbed end face construction: king-pile recovery is carried out to road, uniform filling is filled up smooth along manhole week, and packing material size is not more than 10cm, adopts more than 12t vibrating roller grinding compacting, should carry out piecemeal to road from roadside when rolling, roll to surface without obvious wheelmark.
Embodiment 3: a kind of roadbed and manhole difference settlement control construction method, first carry out repetition measurement to road, comprise traverse testing survey, check survey of centre line and bench mark repetition measurement, the Specific construction after retest-ok comprises the steps:
1. roadbed filling: side slope is scraped out the stepped of convenient overlap joint, every grade of shoulder height 1.3m, then according to the kind placement in layers of the soil that will fill, layer-by-layer rolling is closely knit, every layer of native filling-up thickness is less than 40cm, be less than 30cm after compacting, roadbed filling compaction plane both sides are 50cm wider than design width respectively;
2. pipe groove construction: be not more than a well segment limit in trench length and arrange place's collecting well, to discharge groove ponding, pipe trench groove digs to design altitude, pipeline is laid firmly, often complete one section of pipeline construction, make a pipeline leakproofness closed-water test, finding leaks fills up in time;
3. manhole construction: first manhole foundation bed is adopted hammer ram compacting before construction, then carry out bed course and reinforced concrete foundation construction;
4. backfill: adopt medium coarse sand backfill pipeline groove, by the bottom of pipe, thoracic cavity, the different parts back-filling in layers of pipe top, compaction in layers; Adopt sandstone dirt or system sand to backfill manhole periphery, build rising by laying bricks or stones with the borehole wall during backfill, successively by the tamping of manhole outer ring, filler virtual resurfacing thickness is not more than 20 ㎝, within the scope of the 60-80cm of manhole outer ring, adopts small vibrating to grind or frog rammer compacting;
5. roadbed end face construction: king-pile recovery is carried out to road, uniform filling is filled up smooth along manhole week, packing material size is not more than 10cm, adopt more than 12t vibrating roller grinding compacting, should carry out piecemeal to road from roadside when rolling, roll to surface without obvious wheelmark, road roller does not collide borehole wall extruding walling crib, road roller construction less than position, make separate arrangements small vibrating rolling compaction machine or frog rammer, coordinate roadbed synchronous compacting.
Embodiment 4: a kind of roadbed and manhole difference settlement control construction method, first carry out repetition measurement to road, comprise traverse testing survey, check survey of centre line and bench mark repetition measurement, the Specific construction after retest-ok comprises the steps:
1. roadbed filling: side slope is scraped out the stepped of convenient overlap joint, every grade of shoulder height 0.9m, then according to the kind placement in layers of the soil that will fill, layer-by-layer rolling is closely knit, fill in scope when having pipe works, soil layer filled height should higher than pipeline highest point at least 50cm, and through more than 12 tons heavy road roller grinding compactings;
2. pipe groove construction: be not more than a well segment limit in trench length and one place's collecting well is set, to discharge groove ponding, pipe trench groove digs to design altitude, pipeline is laid firmly, polyethylene pipe pipe heelpiece sand before laying should adopt plate vibration machine to flatten compacting, and pipeline avris backfills medium coarse sand in time with stable pipeline, often completes one section of pipeline construction, make a pipeline leakproofness closed-water test, finding leaks fills up in time;
3. manhole construction: first manhole foundation bed is adopted hammer ram compacting before construction, then carry out bed course and reinforced concrete foundation construction;
4. backfill: adopt medium coarse sand backfill pipeline groove, by the bottom of pipe, thoracic cavity, the different parts back-filling in layers of pipe top, compaction in layers, adopts the jolt ramming of small vibrating machine to medium coarse sand, and sprays water on a small quantity in vibration processes, make medium coarse sand packing course in conjunction with closely knit; Adopt sandstone dirt or system sand to backfill manhole periphery, build rising by laying bricks or stones with the borehole wall during backfill, successively by the tamping of manhole outer ring, filler virtual resurfacing thickness is not more than 20 ㎝, within the scope of the 60-80cm of manhole outer ring, adopts small vibrating to grind or frog rammer compacting;
5. roadbed end face construction: king-pile recovery is carried out to road, uniform filling is filled up smooth along manhole week, packing material size is not more than 10cm, adopt more than 12t vibrating roller grinding compacting, should carry out piecemeal to road from roadside when rolling, roll to surface without obvious wheelmark, road roller does not collide borehole wall extruding walling crib, road roller construction less than position, make separate arrangements small vibrating rolling compaction machine or frog rammer, coordinate roadbed synchronous compacting.

Claims (10)

1. roadbed and a manhole difference settlement control construction method, is characterized in that: comprise the steps:
Roadbed filling: side slope is scraped out the stepped of convenient overlap joint, every grade of shoulder height 0.7-1.3m, then according to the kind placement in layers of the soil that will fill, layer-by-layer rolling is closely knit;
Pipe groove construction: be not more than a well segment limit in trench length and arrange place's collecting well, to discharge groove ponding, pipe trench groove digs to design altitude, pipeline is laid firmly, often complete one section of pipeline construction, make a pipeline leakproofness closed-water test, finding leaks fills up in time;
Manhole is constructed: first manhole foundation bed is adopted hammer ram compacting before construction, then carries out bed course and reinforced concrete foundation construction;
Backfill: adopt medium coarse sand backfill pipeline groove, by the bottom of pipe, thoracic cavity, the different parts back-filling in layers of pipe top, compaction in layers; Adopt sandstone dirt or system sand to backfill manhole periphery, build rising by laying bricks or stones with the borehole wall during backfill, successively by the tamping of manhole outer ring, filler virtual resurfacing thickness is not more than 20 ㎝, within the scope of the 60-80cm of manhole outer ring, adopts small vibrating to grind or frog rammer compacting;
Roadbed end face is constructed: carry out king-pile recovery to road, uniform filling is filled up smooth along manhole week, adopts more than 12t vibrating roller grinding compacting, should carry out piecemeal, roll to surface without obvious wheelmark when rolling from roadside to road.
2. a kind of roadbed according to claim 1 and manhole difference settlement control construction method, is characterized in that: step 1. in every grade of shoulder height be 1m, bench floor slopes inwardly.
3. a kind of roadbed according to claim 1 and manhole difference settlement control construction method, is characterized in that: step 1. in every layer of native filling-up thickness be less than 40cm, be less than 30cm after compacting, roadbed filling compaction plane both sides are 50cm wider than design width respectively.
4. a kind of roadbed according to claim 1 and manhole difference settlement control construction method, it is characterized in that: step 1. in, fill in scope when having pipe works, soil layer filled height should higher than pipeline highest point at least 50cm, and through more than 12 tons heavy road roller grinding compactings.
5. a kind of roadbed according to claim 1 and manhole difference settlement control construction method, it is characterized in that: step 2. in, polyethylene pipe pipe heelpiece sand before laying should adopt plate vibration machine to flatten compacting, and pipeline avris backfills medium coarse sand in time with stable pipeline.
6. a kind of roadbed according to claim 1 and manhole difference settlement control construction method, is characterized in that: step 4. in, the jolt ramming of small vibrating machine is adopted to medium coarse sand, and sprays water on a small quantity in vibration processes, make medium coarse sand packing course in conjunction with closely knit.
7. a kind of roadbed according to claim 1 and manhole difference settlement control construction method, is characterized in that: step 5. in, packing material size is not more than 10cm.
8. a kind of roadbed according to claim 1 and manhole difference settlement control construction method, it is characterized in that: step 5. in, road roller do not collide the borehole wall extruding walling crib, road roller construction less than position, to make separate arrangements small vibrating rolling compaction machine or frog rammer, coordinate the synchronous compacting of roadbed.
9. a kind of roadbed according to claim 1 and manhole difference settlement control construction method, is characterized in that: 1. step also comprises road repetition measurement step before.
10. a kind of roadbed according to claim 9 and manhole difference settlement control construction method, is characterized in that: road repetition measurement step comprises traverse testing survey, check survey of centre line, bench mark repetition measurement.
CN201510554128.7A 2015-09-02 2015-09-02 Roadbed and inspection well differential settlement control construction method Pending CN105200878A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510554128.7A CN105200878A (en) 2015-09-02 2015-09-02 Roadbed and inspection well differential settlement control construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510554128.7A CN105200878A (en) 2015-09-02 2015-09-02 Roadbed and inspection well differential settlement control construction method

Publications (1)

Publication Number Publication Date
CN105200878A true CN105200878A (en) 2015-12-30

Family

ID=54948812

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510554128.7A Pending CN105200878A (en) 2015-09-02 2015-09-02 Roadbed and inspection well differential settlement control construction method

Country Status (1)

Country Link
CN (1) CN105200878A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107165251A (en) * 2017-07-03 2017-09-15 杭州木兰园林绿化工程有限公司 A kind of construction method of drainage system
CN107178020A (en) * 2017-05-24 2017-09-19 浙江明通建设工程有限公司 A kind of road drainage construction method
CN107245994A (en) * 2017-06-27 2017-10-13 中铁第四勘察设计院集团有限公司 It is a kind of based on pre-judging method of the deep foundation pit precipitation to high ferro roadbed safety effects
CN110685203A (en) * 2019-09-19 2020-01-14 杭州南岳建设工程有限公司 Method for ensuring compactness of periphery of gully of inspection well

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4793729A (en) * 1985-09-16 1988-12-27 Bosich Joseph F Process of making material for and constructing a road
JPH11117207A (en) * 1997-10-16 1999-04-27 Daikure Co Ltd Fitting structure of drainage channel for draining pavement and catch basin
CN101718101A (en) * 2009-11-19 2010-06-02 济南城建工程公司 Concrete integral pouring construction method and device for road inspection well
CN102644295A (en) * 2012-04-28 2012-08-22 江苏阳湖建设项目管理有限公司 Construction method for preventing peripheral and local sedimentation of road surface inspection well

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4793729A (en) * 1985-09-16 1988-12-27 Bosich Joseph F Process of making material for and constructing a road
JPH11117207A (en) * 1997-10-16 1999-04-27 Daikure Co Ltd Fitting structure of drainage channel for draining pavement and catch basin
CN101718101A (en) * 2009-11-19 2010-06-02 济南城建工程公司 Concrete integral pouring construction method and device for road inspection well
CN102644295A (en) * 2012-04-28 2012-08-22 江苏阳湖建设项目管理有限公司 Construction method for preventing peripheral and local sedimentation of road surface inspection well

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
徐金光: "浅谈道路排水检查井施工质量通病产生的原因及防治方法", 《给水排水》 *
李永永: "关于城市道路检查井施工方案的探析", 《科学之友》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107178020A (en) * 2017-05-24 2017-09-19 浙江明通建设工程有限公司 A kind of road drainage construction method
CN107245994A (en) * 2017-06-27 2017-10-13 中铁第四勘察设计院集团有限公司 It is a kind of based on pre-judging method of the deep foundation pit precipitation to high ferro roadbed safety effects
CN107245994B (en) * 2017-06-27 2019-07-09 中铁第四勘察设计院集团有限公司 It is a kind of based on deep foundation pit precipitation to the pre-judging method of high-speed rail roadbed safety effects
CN107165251A (en) * 2017-07-03 2017-09-15 杭州木兰园林绿化工程有限公司 A kind of construction method of drainage system
CN110685203A (en) * 2019-09-19 2020-01-14 杭州南岳建设工程有限公司 Method for ensuring compactness of periphery of gully of inspection well

Similar Documents

Publication Publication Date Title
CN104358188A (en) Filling construction method for collapsible loess subgrade
CN103912001B (en) Roadbed backfilling of pipe canal soil " layering splicing processes " construction method
CN111893827A (en) Construction process of urban trunk road
CN111706362A (en) Karst cave treatment method for tunnel construction
CN107761495A (en) A kind of pre-buried expanding bag compensation subgrade settlement construction method
CN106930319A (en) A kind of high slope framed revetment and its construction method
CN102747662A (en) Construction method for sand-filling subgrade
CN105200878A (en) Roadbed and inspection well differential settlement control construction method
CN110080051B (en) Geotextile bag bridge type embankment structure and construction method thereof
CN107119520A (en) The soft base combined type of coastal tidal, which is changed, fills out structure and Treatment Methods
CN101311418A (en) Exchange filling method for deep-foundation pit and large area equipment foundation
CN108978385A (en) A kind of roadbed construction method on the road Tong Cun
CN103161109A (en) Method for subgrade filling of peat soil subgrade by sea sand
CN112211053A (en) Construction method for widening roadbed
CN113235341A (en) Construction method for adding high-speed railway subgrade to existing high-speed railway in parallel
CN114232649B (en) Construction method for filling earthwork of ballastless track roadbed
CN102383346A (en) Construction interference-free railroad bed settlement test device and test method thereof
CN203908552U (en) Surface subsidence leveling measuring and monitoring device
CN108252176A (en) A kind of pavement engineering construction method equipped with inspection shaft
CN110230272A (en) A kind of pipe culvert construction method
CN206800092U (en) The soft base combined type of coastal tidal, which is changed, fills out structure and Roadbed by offshore soft clay
CN107700513A (en) A kind of anti-excavation construction method of pile cover
CN109082961B (en) Road construction method with steep slope
CN110820719A (en) Vacuum preloading dynamic compaction electroosmosis method for conductive plastic drainage plate
CN106978770A (en) A kind of cheuch phase weak soil combined type, which is changed, fills out structure and Treatment Methods

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20151230

RJ01 Rejection of invention patent application after publication