CN105160984A - 开槽明挖法管道施工测量教学模型 - Google Patents

开槽明挖法管道施工测量教学模型 Download PDF

Info

Publication number
CN105160984A
CN105160984A CN201510719250.5A CN201510719250A CN105160984A CN 105160984 A CN105160984 A CN 105160984A CN 201510719250 A CN201510719250 A CN 201510719250A CN 105160984 A CN105160984 A CN 105160984A
Authority
CN
China
Prior art keywords
gradient
stake
jack
center line
transverse slat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510719250.5A
Other languages
English (en)
Other versions
CN105160984B (zh
Inventor
王旭华
孙志红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian University
Original Assignee
Dalian University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian University filed Critical Dalian University
Priority to CN201510719250.5A priority Critical patent/CN105160984B/zh
Publication of CN105160984A publication Critical patent/CN105160984A/zh
Application granted granted Critical
Publication of CN105160984B publication Critical patent/CN105160984B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09BEDUCATIONAL OR DEMONSTRATION APPLIANCES; APPLIANCES FOR TEACHING, OR COMMUNICATING WITH, THE BLIND, DEAF OR MUTE; MODELS; PLANETARIA; GLOBES; MAPS; DIAGRAMS
    • G09B25/00Models for purposes not provided for in G09B23/00, e.g. full-sized devices for demonstration purposes

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Educational Technology (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Instructional Devices (AREA)

Abstract

本发明涉及一种教学辅助工具,尤其涉及一种教学模型;沟槽顶盖板和控制桩面板覆盖在沟槽上,控制桩面板上设置有两个中线控制桩插孔和四个井位控制桩插孔,沟槽顶盖板上设置有两个中线桩插孔,坡度横板跨槽安装于沟槽外壁上,坡度横板上设有中线钉插孔,坡度立板中间具有一个与坡度横板高度相等的U型开口,并通过U型开口安装在坡度横板上,坡度立板侧端设有坡度钉插孔。本发明的有益效果是:通过开槽明挖法管道施工测量教学模型的使用,结合教师的示意讲解,可以使学生生动形象地了解开槽明挖法管道施工测量的基本过程及相关工作,极大地提升教学效果。

Description

开槽明挖法管道施工测量教学模型
技术领域
本发明涉及一种教学辅助工具,尤其涉及一种教学模型。
背景技术
管道施工测量的主要目的是控制管道中线位置和管底设计高程,以确保管道按中线方向和设计坡度敷设。在管道施工测量中,涉及坡度横板、坡度立板、中线钉和坡度钉的设置内容,单纯靠教师的口头讲解,学生无法生动形象地了解开槽明挖法管道施工测量的基本过程及相关工作,如:对中线桩、井位控制桩的设置,槽口放线及开挖过程,坡度板的设置及中线钉的测设。
发明内容
为解决现有技术存在的缺陷,本发明的目的是提供一种开槽明挖法管道施工测量教学模型,通过演示,提高教学效果。
本发明的技术方案是:开槽明挖法管道施工测量教学模型,沟槽顶盖板和控制桩面板覆盖在沟槽上,控制桩面板上设置有两个中线控制桩插孔和四个井位控制桩插孔,沟槽顶盖板上设置有两个中线桩插孔,坡度横板跨槽安装于沟槽外壁上,坡度横板上设有中线钉插孔,坡度立板中间具有一个与坡度横板高度相等的U型开口,并通过U型开口安装在坡度横板上,坡度立板侧端设有坡度钉插孔。
所述中线控制桩插孔、井位控制桩插孔分别与中线桩插孔位于同一直线上,且中线控制桩插孔与中线桩插孔所在直线垂直于井位控制桩插孔与中线桩插孔所在直线。
本发明的有益效果是:通过开槽明挖法管道施工测量教学模型的使用,结合教师的示意讲解,可以使学生生动形象地了解开槽明挖法管道施工测量的基本过程及相关工作,极大地提升教学效果。
附图说明
本发明共有附图5幅。
图1为利用本发明模拟开挖前的俯视图;
图2为本发明设置坡度板后的俯视图;
图3为本发明设置坡度板后的侧视图;
图4为本发明的局部放大图;
图5为本发明设置坡度板后的立体图。
图中附图标记如下:1、沟槽,1.1、沟槽外壁,2、控制桩面板,2.1、中线控制桩插孔,2.2、井位控制桩插孔,3、沟槽顶盖板,3.1、中线桩插孔,4、坡度横板,4.1、中线钉插孔,5、坡度立板,5.1、坡度钉插孔。
具体实施方式
下面结合附图1-5对本发明做进一步说明:
开槽明挖法管道施工测量教学模型,沟槽顶盖板3和控制桩面板2覆盖在沟槽1上,控制桩面板2上设置有两个中线控制桩插孔2.1和四个井位控制桩插孔2.2,沟槽顶盖板3上设置有两个中线桩插孔3.1,坡度横板4跨槽安装于沟槽外壁1.1上,坡度横板4上设有中线钉插孔4.1,坡度立板5中间具有一个与坡度横板4高度相等的U型开口,并通过U型开口安装在坡度横板4上,坡度立板5侧端设有坡度钉插孔5.1。
所述中线控制桩插孔2.1、井位控制桩插孔2.2分别与中线桩插孔3.1位于同一直线上,且中线控制桩插孔2.1与中线桩插孔3.1所在直线垂直于井位控制桩插孔2.2与中线桩插孔3.1所在直线。
沟槽顶盖板3和控制桩面板2覆盖在沟槽1之上,模拟沟槽1开挖前的地面,去除沟槽顶盖板3则表明开始开挖。控制桩面板2上设置有两个中线控制桩插孔2.1和四个井位控制桩插孔2.2,分别用于设置中线控制桩和井位控制桩;沟槽顶盖板3上设置有两个中线桩插孔3.1,用于设置中线桩;沟槽顶盖板3和控制桩面板2之间的边界线即为开挖边界线;坡度横板4跨槽安置于去除顶盖板的沟槽侧壁之上,其上设有一个中线钉插孔4.1,用于设置中线钉,坡度立板5正面中间具有一个与坡度横板4高度相等的U型开口,使坡度立板可以安装在坡度横板上,左侧面具有一个坡度钉插孔,用于设置坡度钉。
将沟槽顶盖板3和控制桩面板2覆盖在沟槽之上,模拟沟槽1开挖前的地面;将小钉***中线桩插孔3.1,模拟中线桩的设置;量取槽口半宽,并指示沟槽顶盖板3和控制桩面板2之间的界线,模拟槽口放线过程;根据模拟的中线桩在控制桩面板2上的两个中线控制桩插孔2.1和四个井位控制桩插孔2.2分别***小钉,模拟中线控制桩和井位控制桩的设置;去除沟槽顶盖板模拟沟槽开挖;将坡度横板跨槽安置于沟槽侧壁之上,使其两端与井位控制桩对齐,将一个模拟的中线控制桩为仪器安置点,另一个模拟的中线控制桩为瞄准目标,示意讲解前述用经纬仪将管道中线投测到坡度横板上的过程,并在坡度横板4的中线钉插孔4.1***小钉,模拟中线钉的设置;将坡度立板5对准中线钉,使其U型开口与坡度横板4对接,示意讲解前述坡度钉的测设过程,并将小钉***坡度钉插孔5.1,完成坡度钉的测设。
以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明技术原理的前提下,还可以做出若干改进和变型,这些改进和变型也应视为本发明的保护范围。

Claims (2)

1.开槽明挖法管道施工测量教学模型,其特征在于,沟槽顶盖板(3)和控制桩面板(2)覆盖在沟槽(1)上,控制桩面板(2)上设置有两个中线控制桩插孔(2.1)和四个井位控制桩插孔(2.2),沟槽顶盖板(3)上设置有两个中线桩插孔(3.1),坡度横板(4)跨槽安装于沟槽外壁(1.1)上,坡度横板(4)上设有中线钉插孔(4.1),坡度立板(5)中间具有一个与坡度横板(4)高度相等的U型开口,并通过U型开口安装在坡度横板(4)上,坡度立板(5)侧端设有坡度钉插孔(5.1)。
2.根据权利要求1所述的开槽明挖法管道施工测量教学模型,其特征在于,所述中线控制桩插孔(2.1)、井位控制桩插孔(2.2)分别与中线桩插孔(3.1)位于同一直线上,且中线控制桩插孔(2.1)与中线桩插孔(3.1)所在直线垂直于井位控制桩插孔(2.2)与中线桩插孔(3.1)所在直线。
CN201510719250.5A 2015-10-29 2015-10-29 开槽明挖法管道施工测量教学模型 Active CN105160984B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510719250.5A CN105160984B (zh) 2015-10-29 2015-10-29 开槽明挖法管道施工测量教学模型

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510719250.5A CN105160984B (zh) 2015-10-29 2015-10-29 开槽明挖法管道施工测量教学模型

Publications (2)

Publication Number Publication Date
CN105160984A true CN105160984A (zh) 2015-12-16
CN105160984B CN105160984B (zh) 2017-09-08

Family

ID=54801819

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510719250.5A Active CN105160984B (zh) 2015-10-29 2015-10-29 开槽明挖法管道施工测量教学模型

Country Status (1)

Country Link
CN (1) CN105160984B (zh)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1085142A2 (de) * 1999-09-20 2001-03-21 Helmut Reiffers Lehre zum ortsfernen Herstellen eines Treppengeländers für eine vorgegebene Treppe
CN101705814A (zh) * 2009-12-03 2010-05-12 中冶集团华冶资源开发有限责任公司 垂直加斜溜井的掘进方向测量方法
KR20110035174A (ko) * 2009-09-30 2011-04-06 주식회사 에스엠이교역 고정밀도의 입체모형 지형도의 제작 방법 및 이에 따른 고정밀도 입체모형 지형도
EP2351884A1 (fr) * 2010-01-08 2011-08-03 Colas Module support de voie ferrée préfabriqué, voie ferrée, section et procédé de montage des voies ferrées
CN103954190A (zh) * 2014-05-12 2014-07-30 济南黄河路桥工程公司 沟槽开挖尺寸检测器
CN104251688A (zh) * 2014-09-25 2014-12-31 陕西华山路桥工程有限公司 顶管工程中利用激光直线定向测量工法
CN205091993U (zh) * 2015-10-29 2016-03-16 大连大学 开槽明挖法管道施工测量教学模型

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1085142A2 (de) * 1999-09-20 2001-03-21 Helmut Reiffers Lehre zum ortsfernen Herstellen eines Treppengeländers für eine vorgegebene Treppe
KR20110035174A (ko) * 2009-09-30 2011-04-06 주식회사 에스엠이교역 고정밀도의 입체모형 지형도의 제작 방법 및 이에 따른 고정밀도 입체모형 지형도
CN101705814A (zh) * 2009-12-03 2010-05-12 中冶集团华冶资源开发有限责任公司 垂直加斜溜井的掘进方向测量方法
EP2351884A1 (fr) * 2010-01-08 2011-08-03 Colas Module support de voie ferrée préfabriqué, voie ferrée, section et procédé de montage des voies ferrées
CN103954190A (zh) * 2014-05-12 2014-07-30 济南黄河路桥工程公司 沟槽开挖尺寸检测器
CN104251688A (zh) * 2014-09-25 2014-12-31 陕西华山路桥工程有限公司 顶管工程中利用激光直线定向测量工法
CN205091993U (zh) * 2015-10-29 2016-03-16 大连大学 开槽明挖法管道施工测量教学模型

Also Published As

Publication number Publication date
CN105160984B (zh) 2017-09-08

Similar Documents

Publication Publication Date Title
CN106950070B (zh) 用于矩形顶管顶进施工全过程模拟的试验装置
CN103837360B (zh) 一种隧道管棚施工法模拟开挖装置及其实施方法
CN106370819B (zh) 一种斜向滑动断层模拟装置及模拟方法
CN103117020A (zh) 盾构隧道动态掘进诱发地层损失及地表沉陷试验装置
CN107130592B (zh) 长螺旋钻和冲击钻双机复合成孔灌注桩施工工法
CN108491620B (zh) 地铁隧道穿越桩基和路基沉降量预测的拟合度检验方法
CN203745218U (zh) 一种隧道管棚施工法模拟开挖装置
CN110512583B (zh) 全透明的可三维调整尺寸的装配式多功能岩土工程模型箱
CN102677672B (zh) 先张法u形预应力混凝土板桩沉桩方法
CN205091993U (zh) 开槽明挖法管道施工测量教学模型
CN103344214B (zh) 一种1.6次抛物线型特大桥墩测量及墩身线形控制方法
CN105887941A (zh) 一种桩基础桩长测算方法
CN104537566B (zh) 一种六边形煤巷表面位移量的预测方法
CN105160984A (zh) 开槽明挖法管道施工测量教学模型
CN107859034B (zh) 大直径桩基漏浆快速处理方法
CN112435527B (zh) 用于模拟断层运动的配合式箱体结构
CN104060598B (zh) 一种竖向布置土压力盒的固定装置
CN103397659B (zh) 超深地下连续墙成槽垂直度控制工艺
CN105372411A (zh) 水泥混凝土坍落度试验插捣深度控制装置
CN207397573U (zh) 模拟crd法隧道施工引起地表变形的实验装置
CN104632080B (zh) 一种三向精确定位相似模拟巷道微型钻机
CN106592654A (zh) 一种钢管桩垂直度监测方法
CN108914997A (zh) 一种加筋挡土墙侧向变形测试装置及工作方法
CN207904918U (zh) 一种钻孔桩用护筒定位架
CN104091516A (zh) 一种地下结构外防内贴法施工教学模型

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant