CN105133655B - Construction method of well lid of road surface inspection well and auxiliary installation device - Google Patents
Construction method of well lid of road surface inspection well and auxiliary installation device Download PDFInfo
- Publication number
- CN105133655B CN105133655B CN201510550285.0A CN201510550285A CN105133655B CN 105133655 B CN105133655 B CN 105133655B CN 201510550285 A CN201510550285 A CN 201510550285A CN 105133655 B CN105133655 B CN 105133655B
- Authority
- CN
- China
- Prior art keywords
- well
- road surface
- concrete
- inspection shaft
- well lid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The invention discloses a construction method of a well lid of a road surface inspection well. The construction method overcomes the defects that in the prior art, time for installation work of a well lid base is long, and the consistency of construction quality cannot be guaranteed. The construction method of the well lid of the road surface inspection well comprises the following steps that A, a concrete well ring and a well lid base are integrally prefabricated; B, a well ring foundation pit is dug; C, a well mouth supporting inner formwork is mounted in the well mouth of the inspection well; D, the space between the well mouth supporting inner formwork and the well ring foundation pit is filled with concrete; E, the concrete well ring and the well lid base are hoisted integrally; F, the well ring foundation pit and the prefabricated concrete well ring are filled with concrete, and the concrete is compacted; G, the well mouth supporting inner formwork and a hoisting and leveling device are taken out; and H, an asphalt concrete pavement layer between the well ring and the road surface is laid. The invention further provides an auxiliary installation device. The auxiliary installation device comprises the well mouth supporting inner formwork and the hoisting and leveling device. According to the construction method of the well lid of the road surface inspection well and the auxiliary installation device, construction is simple, work time is short, the dimensional precision of well lid installation is high, and the construction method and the auxiliary installation device are suitable for well lid installation.
Description
Technical field
The present invention relates to the construction of municipal inspection shaft, the more particularly, to a kind of well lid construction method of road surface inspection shaft and auxiliary
Erecting device.
Background technology
For many years, the inspection shaft well lid of various pipelines is installed is all the weak link of municipal road construction, and town road is examined
The construction quality looking into well well lid directly influences the flatness on road surface, road-ability, safety, aesthetics and road longevity
Life.Traditional construction technology, cover seat of manhole directly can pass to inspection shaft well head end face the pressure perpendicular coming from above, with heavy type
It is increasing that vehicle travels, and after the impact being constantly under pressure, easily causes well lid fragmentation, sinking, destroys road surface knot
Structure, decreases the service life of road.Meanwhile, traditional construction technology is that absolute altitude lateral stay with reference to curb determines well mostly
The absolute altitude of lid, this method is simple, but have ignored the head fall of road, causes actual elevation and designed elevation to have
Enter, the situation of pavement roughness easily occurs.Patent No. zl200910230438.8, patent name are road inspection well coagulation
The patent of invention of native monolithic casting construction method and construction harness is improved to traditional construction technology, using fixed support
Suspention harness adjustment well lid elevation, pours into a mould, to walling crib foundation ditch, the globality that concrete improves structure, but still suffers from following aspect
Deficiency, such as: need in an installation to suspend harness adjustment well lid elevation in midair by fixed support, the process of adjustment not only needs to spend greatly
The time of amount, and it cannot be guaranteed that the concordance of construction quality.Meanwhile, need to pour substantial amounts of concrete at the scene, construction is made
Industry time length is it is impossible to timely complete installing and follow-up maintenance of well lid, the occupancy road surface time is long, affects traffic.
Content of the invention
The first object of the present invention is to overcome cover seat of manhole installation exercise time length of the prior art it is impossible to ensure construction
A kind of shortcoming of quality conformance, there is provided the well lid construction method of road surface inspection shaft.
The second object of the present invention is to overcome cover seat of manhole installation exercise time length of the prior art it is impossible to ensure construction
A kind of shortcoming of quality conformance, there is provided the auxiliary installation device of the well lid construction of road surface inspection shaft.
The present invention realizes the well lid construction method that the first goal of the invention the technical scheme is that a kind of road surface inspection shaft,
Specifically include following steps:
A, carry out the integral prefabricated of concrete walling crib and cover seat of manhole, cover seat of manhole is arranged in concrete walling crib and is fixedly connected
Integral;
B, dig walling crib foundation ditch, walling crib foundation ditch is with diameter greater than inspection shaft external diameter and concrete well loop diameter;
C, the well head support internal mould of reducing is installed in inspection shaft well head, well head support internal mould outer rim is close to inspection shaft well
Mouth inwall, well head support internal mould one end is arranged in inspection shaft well head, the other end upwardly extends;
D, the well head support internal mould described in step c and between walling crib foundation ditch filling design consumption concrete;
E, lifting levelling device will be mixed in walling crib foundation ditch to the concrete walling crib described in step a and cover seat of manhole integral hoisting
On solidifying soil, the axis of cover seat of manhole and the dead in line of inspection shaft, cover seat of manhole is levelling with road surface positioning;
F, into walling crib foundation ditch and precast concrete walling crib filling and compacted concrete, by the overfall of well head support internal mould
Observation panel observes the occupied state of concrete, makes concrete walling crib and inspection shaft upper surface viscous and integral, and by concrete well
The space filling being formed between circle and walling crib foundation ditch is full;
After g, concrete initial set to be filled, reduce well head support internal mould diameter, take out well head support internal mould and lifting is adjusted
Leveling device;
H, lay asphalt concrete pavement between walling crib and road surface.
Also include step i, according to train-passing through conditions needs, setting on road surface is more than the cover sheet of walling crib foundation ditch diameter,
After the completion for the treatment of asphalt concrete pavement maintenance, remove cover sheet, complete the construction of road surface inspection shaft entirety well lid.
Well head support internal mould upper end described in step c differs the height of asphalt concrete pavement with road surface.
In described step e, cover seat of manhole and road surface positioning are levelling, and concrete mode is that cover seat of manhole is arranged on lifting leveling dress
Put, the datum clamp face of lifting levelling device is fitted with the upper surface of cover seat of manhole, by the datum clamp face of lifting levelling device
It is placed on levelling on road surface.
In four head end of described lifting levelling device, cushion block is installed in advance, for well lid datum level and road surface it
Between settle pre- allowance.
Described concrete is fast rigid concrete.
The present invention realizes the auxiliary that the second goal of the invention the technical scheme is that a kind of well lid construction of road surface inspection shaft
Erecting device, auxiliary installation device includes well head support internal mould and lifting levelling device, and described well head support internal mould is cylinder
Shape, cylinder side wall is provided with the opening of insertion in the axial direction, and opening both sides form the structure of juxtaposition, the intersection weight of opening
Folded place is formed at diametrically opposite under external force effect or move toward one another structure, and lifting levelling device includes leveling die and lifting
Connector, hoisting connecting piece is respectively arranged at two ends with suspension hook and suspension ring, and the lower surface of leveling die is to connect with road surface during lifting well lid
Tactile datum clamp face, leveling die is detachably coupled with hoisting connecting piece.
The invention has the beneficial effects as follows: mix with the integral prefabricated of cover seat of manhole with using rigid soon due to carrying out concrete walling crib
Solidifying soil, pours too many concrete without in walling crib foundation ditch during in-site installation, decreases the time of pouring.Only need during actual installation
The datum clamp face of lifting levelling device is placed on road surface, the hoisting structure of the present invention ensure that the upper surface of cover seat of manhole
Fit with datum clamp face, so in installation process, the upper surface of cover seat of manhole remains fair with road surface, even if eliminating
The step of adjustment well lid elevation, still can ensure that the smooth of overall road surface after installation, improves the installation dimension precision of well lid.
Well head support internal mould can strut or retract for different construction procedures, beneficial to construction and dismounting.Using standardized components and hanging
Debug leveling device and carry out do mechanization operation, improve efficiency of construction it is ensured that the concordance of construction quality, can be high-quality and efficient
Complete installation and the maintenance construction of asphalt concrete pavement well lid.Have that construction is simple, the activity duration is short, well lid installation dimension essence
The advantages of spend high.
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings.
Brief description
Fig. 1 is the flow chart of the construction method of the present invention.
Fig. 2 is the assembling schematic diagram of the auxiliary installation device of the present invention.
Fig. 3 is lifting levelling device and cover seat of manhole, the assembling schematic diagram of concrete walling crib of the present invention.
Fig. 4 is the structural representation of the well head support internal mould of the present invention.
Fig. 5 is the a-a sectional view of Fig. 4.
Fig. 6 is the partial enlarged drawing of Fig. 5.
Fig. 7 is the structural representation of the cover sheet of the present invention.
Fig. 8 is the c direction view of Fig. 7.
In accompanying drawing, 1 is inspection shaft, 2 is well head support internal mould, 2-1 is controllable telescoping rod, 2-2 is anti-fall limited block, 2-3
For side wall, 2-4 be opening, 2-5 be overfall observation panel, 3 be road surface, 4 be cushion block, 5 be leveling die, 5-1 be datum clamp face,
5-2 is long beam, 5-3 is short beam, 6 is concrete walling crib, 6-1 is return pipe, 7 is cover seat of manhole, 8 is hoisting connecting piece, 8-1 is to hang
Ring, 8-2 are suspension hook, 9 is walling crib foundation ditch, 10 is asphalt concrete pavement, 11 is cover sheet, 11-1 is damping and slide-prevention offset plate.
Specific embodiment
As shown in Figure 1, the well lid construction method of a kind of road surface inspection shaft of the present embodiment, specifically includes following steps:
A, carry out the integral prefabricated of concrete walling crib and cover seat of manhole, pre-buried return pipe in concrete walling crib, by cover seat of manhole
It is arranged on and is fixedly connected integral in concrete walling crib, expand the area of cover seat of manhole by concrete walling crib, by car after installing
Wheel is transmitted to the roadbed around inspection shaft top to the impulsive force of well lid by concrete walling crib;
B, dig walling crib foundation ditch centered on inspection shaft well head, walling crib foundation ditch is with diameter greater than inspection shaft external diameter and concrete well
Loop diameter;
C, in inspection shaft well head install reducing well head support internal mould, radially strut well head support internal mould, well head
Support internal mould outer rim is close to inspection shaft well head inwall, well head support internal mould one end is arranged in inspection shaft well head, the other end upwards
Extend, the present embodiment preferred well head support internal mould upper end is differed the height of asphalt concrete pavement, fills up well head and prop up with road surface
The gap being formed after support internal model is softened, and in well head support internal mould outer rim smearing release agent;
D, the well head support internal mould described in step c and between walling crib foundation ditch filling design consumption concrete;
E, lifting levelling device will be mixed in walling crib foundation ditch to the concrete walling crib described in step a and cover seat of manhole integral hoisting
On solidifying soil, the axis of cover seat of manhole and the dead in line of inspection shaft, cover seat of manhole is levelling with road surface positioning, and the present embodiment preferably has
Body mode is that cover seat of manhole is arranged on lifting levelling device, lifts the datum clamp face of levelling device and the upper table of cover seat of manhole
Fit in face, by the datum clamp face of lifting levelling device be placed on road surface levelling it is contemplated that the problem of concrete settlement, this reality
Apply example and preferably in four head end of lifting levelling device, cushion block is installed in advance, for heavy between well lid datum level and road surface
Pre- allowance drops, during installation, cover seat of manhole can be slightly above road surface, after concrete settlement, cover seat of manhole is consistent with pavement-height;
F, into walling crib foundation ditch and precast concrete walling crib filling and compacted concrete, by the overfall of concrete walling crib
Pipe, the overfall observation panel of well head support internal mould observe the occupied state of concrete, so that concrete walling crib is glued with inspection shaft upper surface
With integral, and the space filling that will be formed between concrete walling crib and walling crib foundation ditch is full;
After g, concrete initial set to be filled, reduce well head support internal mould diameter, take out well head support internal mould and lifting is adjusted
Leveling device;
H, lay asphalt concrete pavement between walling crib and road surface.
For the situation repairing well lid, in order to reduce urban transportation blocking, traffic control department often requires that 12 points of constructions of midnight
6 points of open to traffic of morning, if not making proper treatment, not up to design strength to concrete and being open to traffic by force, are bound to cause
Inspection shaft periphery sinks, and the present embodiment preferably also includes step i, and according to train-passing through conditions needs, setting on road surface is more than well
Cycle basis cheats the cover sheet of diameter, after the completion for the treatment of asphalt concrete pavement maintenance, removes cover sheet, completes road surface inspection shaft whole
The construction of body well lid.
Connect concrete strength to improve concrete walling crib and inspection shaft, shorten setting time, the present embodiment is preferred
Concrete is fast rigid concrete.
As shown in accompanying drawing 2-6, a kind of auxiliary installation device of the well lid construction of road surface inspection shaft of the present embodiment, auxiliary peace
Assembling device includes well head support internal mould 2 and lifting levelling device.Described well head support internal mould 2 is cylindrical shape.Cylinder side wall 2-3
It is provided with the opening 2-4 of insertion in the axial direction.Opening 2-4 both sides form the structure of juxtaposition.The juxtaposition of opening 2-4
Place is formed at diametrically opposite under external force effect or move toward one another structure.The both sides of the present embodiment preferred opening 2-4 with can
Control expansion link 2-1 two ends hinge-coupled, controllable telescoping rod 2-1 passes through at the flexible juxtaposition driving opening 2-4 radially phase
To or move toward one another, control well head support internal mould 2 diameter change.Observe whether concrete is filled for convenience, the present embodiment
The cylinder side wall 2-3 of preferably well head support internal mould 2 is provided with overfall observation panel 2-5 vertically.In order to preferably well head be supported
Internal model 2 is fixed in inspection shaft 1 well head, and the outer rim of the present embodiment preferred well head support internal mould 2 is provided with anti-fall limited block 2-
2.Lifting levelling device includes leveling die 5 and hoisting connecting piece 8.Hoisting connecting piece 8 is respectively arranged at two ends with suspension hook 8-2 and suspension ring
8-1.The lower surface of leveling die 5 is the datum clamp face 5-1 contacting with road surface 3 during lifting cover seat of manhole 7, and the present embodiment is preferred
Leveling die 5 is to combine, by two long beam 5-2 and short beam 5-3, the framework being formed.Leveling die 5 is detachable with hoisting connecting piece 8
Connection.The preferred leveling die of the present embodiment 5 and hoisting connecting piece 8 are fixedly connected by nut.For the situation repairing well lid,
In order to reduce urban transportation blocking, traffic control department often requires that 12 points of construction 6 points of open to traffic of morning of midnight, if to concrete
Do not make proper treatment, not up to design strength and be open to traffic by force, be bound to cause inspection shaft periphery to sink, the present embodiment is preferred
Also include cover sheet 11, the diameter with diameter greater than walling crib foundation ditch 9 of cover sheet 11, the lower surface of cover sheet 11 is provided with one
Circle damping and slide-prevention offset plate 11-1.After the completion for the treatment of asphalt concrete pavement 10 maintenance, remove cover sheet 11, complete road surface inspection shaft
The construction of overall well lid.Cover sheet 11 improves new clothes well lid maintenance security reliability, usually can be used as site operation material
Mix backing plate, it is ensured that asphalt concrete pavement sanitation and hygiene, improves civilized construction grade.
Pour the time in order to reduce on-site concrete, carry out the integral prefabricated of concrete walling crib 6 and cover seat of manhole 7, by well
Cage 7 is arranged on and is fixedly connected integral in concrete walling crib 6, and concrete walling crib 6 is provided with pre-buried return pipe 6-1.Lifting
During levelling device clamping cover seat of manhole 7, the suspension hook 8-2 clamping cover seat of manhole 7 of lifting levelling device, suspension hook 8-2, well are adjusted by nut
Cage 7 and the relative distance of datum clamp face 5-1, make the upper surface of cover seat of manhole 7 and the datum clamp face 5-1 patch of leveling die 5
Close.At the construction field (site), well head support internal mould 2 one end is arranged in inspection shaft 1 well head, anti-fall limited block 2-2 is placed on inspection
On well 1 well head.Well head support internal mould 2 is strutted by controllable telescoping rod 2-1, makes well head support internal mould 2 outer rim be close to inspection shaft 1 well head
Inwall, fills up the softened rear gap being formed of well head support internal mould 2, and in well head support internal mould 2 outer rim smearing release agent.In well
The concrete of filling design consumption between mouth support internal mould 2 and the walling crib foundation ditch 9 having digged.Lifting levelling device is by concrete
Walling crib 6 and cover seat of manhole 7 integral hoisting on the concrete in walling crib foundation ditch 9, the axis of the axis of cover seat of manhole 7 and inspection shaft 1
Overlap.The datum clamp face 5-1 of lifting levelling device is placed on road surface 3 it is contemplated that the problem of concrete settlement, adjusts in lifting
Four head end of leveling device install cushion block 4 in advance, for settling pre- allowance between well lid datum level and road surface, well during installation
Cage 7 can be slightly above road surface 3, and after concrete settlement, cover seat of manhole 7 is highly consistent with road surface 3.To walling crib foundation ditch 9 and prefabricated mixed
Filling compacted concrete in solidifying soil walling crib 6, by returning of the pre-buried return pipe 6-1 of concrete walling crib 6 and well head support internal mould 2
Slurry observation panel 2-5 observes whether concrete is filled.After concrete setting, concrete by concrete walling crib 6 and walling crib foundation ditch 9 it
Between the space filling that formed full, concrete walling crib 6 is viscous and integral with inspection shaft 1 upper surface, improves the intensity of well lid.Due to
In installation process the upper surface on road surface 3, datum clamp face 5-1 and cover seat of manhole 7 all the time in one plane it is ensured that install after
Overall road surface smooth, improve the installation dimension precision of well lid.After the concrete initial set of filling, take out lifting levelling device,
Controllable telescoping rod 2-1 reduces well head support internal mould 2 diameter, and well head support internal mould 2 is taken out from inspection shaft 1 well head.Lay well
Asphalt concrete pavement 10 between circle and road surface 3.Carry out mechanization due to employing standardized components and lifting levelling device
Operation, improves efficiency of construction it is ensured that the concordance of construction quality.
Claims (11)
1. a kind of well lid construction method of road surface inspection shaft is it is characterised in that specifically include following steps:
A, carry out the integral prefabricated of concrete walling crib and cover seat of manhole, cover seat of manhole is arranged in concrete walling crib and is fixedly connected into one
Body;
B, dig walling crib foundation ditch, walling crib foundation ditch is with diameter greater than inspection shaft external diameter and concrete well loop diameter;
C, the well head support internal mould of reducing is installed in inspection shaft well head, well head support internal mould outer rim is close in inspection shaft well head
Wall, well head support internal mould one end is arranged in inspection shaft well head, the other end upwardly extends;
D, the well head support internal mould described in step c and between walling crib foundation ditch filling design consumption concrete;
E, the lifting levelling device concrete in walling crib foundation ditch by the concrete walling crib and cover seat of manhole integral hoisting described in step a
On, the axis of cover seat of manhole and the dead in line of inspection shaft, cover seat of manhole is levelling with road surface positioning;
F, into walling crib foundation ditch and precast concrete walling crib filling compacted concrete, observed by the overfall of well head support internal mould
Mouthful observe the occupied state of concrete, so that concrete walling crib and inspection shaft upper surface is glued and integral, and by concrete walling crib and
The space filling being formed between walling crib foundation ditch is full;
After g, concrete initial set to be filled, reduce well head support internal mould diameter, take out well head support internal mould and lifting leveling dress
Put;
H, lay asphalt concrete pavement between walling crib and road surface.
2. a kind of well lid construction method of road surface according to claim 1 inspection shaft is it is characterised in that also include step i,
According to train-passing through conditions needs, setting on road surface, more than the cover sheet of walling crib foundation ditch diameter, treats asphalt concrete pavement maintenance
After the completion of, remove cover sheet, complete the construction of road surface inspection shaft entirety well lid.
3. a kind of well lid construction method of road surface according to claim 1 inspection shaft is it is characterised in that described in step c
Well head support internal mould upper end differs the height of asphalt concrete pavement with road surface.
4. a kind of well lid construction method of road surface according to claim 1 inspection shaft is it is characterised in that described step e
Middle cover seat of manhole and road surface positioning are levelling, and concrete mode is that cover seat of manhole is arranged on lifting levelling device, lifting levelling device
Datum clamp face is fitted with the upper surface of cover seat of manhole, the datum clamp face of lifting levelling device is placed on levelling on road surface.
5. a kind of well lid construction method of road surface according to claim 4 inspection shaft is it is characterised in that in described lifting
Four head end of levelling device install cushion block in advance, for settling pre- allowance between well lid datum level and road surface.
6. a kind of well lid construction method of road surface according to claim 1 inspection shaft is it is characterised in that described concrete
For fast rigid concrete.
7. a kind of auxiliary installation device of the well lid construction of road surface inspection shaft is it is characterised in that auxiliary installation device includes well head
Support internal mould (2) and lifting levelling device, described well head support internal mould (2) is cylindrical shape, and cylinder side wall (2-3) is along axis side
To the opening (2-4) being provided with insertion, opening (2-4) both sides form the structure of juxtaposition, at the juxtaposition of opening (2-4)
It is formed at diametrically opposite under external force effect or move toward one another structure, lifting levelling device includes leveling die (5) and lifting
Connector (8), hoisting connecting piece is respectively arranged at two ends with suspension hook (8-2) and suspension ring (8-1), and the lower surface of leveling die (5) is to hang
The datum clamp face (5-1) contacting with road surface (3) during dress well lid, leveling die (5) is detachably coupled with hoisting connecting piece (8).
8. a kind of auxiliary installation device of the well lid construction of road surface according to claim 7 inspection shaft is it is characterised in that institute
The both sides of opening (2-4) stated and controllable telescoping rod (2-1) two ends hinge-coupled.
9. a kind of auxiliary installation device of the well lid construction of road surface according to claim 7 inspection shaft is it is characterised in that institute
The cylinder side wall (2-3) of the well head support internal mould (2) stated is provided with overfall observation panel (2-5) vertically, well head support internal mould (2)
Outer rim is provided with anti-fall limited block (2-2).
10. a kind of road surface according to claim 7 inspection shaft well lid construction auxiliary installation device it is characterised in that
Described leveling die (5) is the framework being formed by two long beams (5-2) and short beam (5-3) combination.
A kind of 11. road surface according to claim 7 inspection shafts well lid construction auxiliary installation device it is characterised in that
Also include cover sheet (11), the lower surface of described cover sheet (11) is provided with circle damping and slide-prevention offset plate (11-1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510550285.0A CN105133655B (en) | 2015-09-01 | 2015-09-01 | Construction method of well lid of road surface inspection well and auxiliary installation device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510550285.0A CN105133655B (en) | 2015-09-01 | 2015-09-01 | Construction method of well lid of road surface inspection well and auxiliary installation device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105133655A CN105133655A (en) | 2015-12-09 |
CN105133655B true CN105133655B (en) | 2017-01-18 |
Family
ID=54719202
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510550285.0A Active CN105133655B (en) | 2015-09-01 | 2015-09-01 | Construction method of well lid of road surface inspection well and auxiliary installation device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105133655B (en) |
Families Citing this family (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106948377B (en) * | 2017-04-07 | 2023-03-17 | 中泰国际高新技术有限公司 | Prefabricated road bed inspection shaft of assembled |
CN107227753A (en) * | 2017-07-04 | 2017-10-03 | 北京城建远东建设投资集团有限公司 | Municipal administration is mated formation bright dress inspection shaft and mat formation engineering attachment structure and method in engineering |
CN108487323B (en) * | 2018-03-21 | 2020-09-15 | 天津炬实科技发展股份有限公司 | Construction process of manhole cover device of inspection well on road |
CN108560684B (en) * | 2018-04-30 | 2023-06-27 | 安徽省公路桥梁工程有限公司 | Heavy-load traffic road inspection well ring and construction method thereof |
CN110820808A (en) * | 2018-08-10 | 2020-02-21 | 山东中宏路桥建设有限公司 | Method for installing rain sewage well cover on asphalt pavement |
CN110512651A (en) * | 2019-08-28 | 2019-11-29 | 安徽普瑞明精密机械有限公司 | A kind of noiseproof ductile cast iron manhole cover production technology |
BE1027314B1 (en) * | 2019-12-31 | 2020-12-21 | Viabuild Nv | USE OF A REUSABLE INSTALLATION DEVICE WHEN INSTALLING A SEWER FRAME |
CN111733887A (en) * | 2020-06-15 | 2020-10-02 | 中国一冶集团有限公司 | Construction method of asphalt concrete road inspection well first-rising structure |
CN112095668B (en) * | 2020-09-22 | 2022-04-08 | 齐力建设集团有限公司 | Municipal road anti-settlement manhole cover and rapid construction method thereof |
CN112376619B (en) * | 2020-11-30 | 2022-02-01 | 北京城建五建设集团有限公司 | Construction method of integrated structure of prefabricated well ring and well cover of asphalt concrete pavement |
CN117428918B (en) * | 2023-10-24 | 2024-04-19 | 江苏瀚能电气有限公司 | Prefabricated UHPC rainwater well integrated construction method and device |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9127430B2 (en) * | 2009-01-13 | 2015-09-08 | Andrew C. Mitchell | Method and apparatus for raising manhole castings |
CN101545268B (en) * | 2009-04-29 | 2010-09-01 | 陈良保 | Method for mounting well tools of inspection well on asphalt concrete pavement |
CN101718101B (en) * | 2009-11-19 | 2011-04-06 | 济南城建工程公司 | Concrete integral pouring construction method and device for road inspection well |
KR20130067976A (en) * | 2011-12-15 | 2013-06-25 | 한국주철산업주식회사 | Device for fixing of manhole cover |
CN104018523A (en) * | 2014-05-13 | 2014-09-03 | 武汉悍路威科技发展有限公司 | Well lid constructing method |
CN205062844U (en) * | 2015-09-01 | 2016-03-02 | 深圳市建设(集团)有限公司 | Supplementary installation device of well lid construction of road surface inspection shaft |
-
2015
- 2015-09-01 CN CN201510550285.0A patent/CN105133655B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN105133655A (en) | 2015-12-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105133655B (en) | Construction method of well lid of road surface inspection well and auxiliary installation device | |
CN105484157B (en) | Positioning device and construction method of capping beam of prefabricated bridge | |
CN106223360A (en) | Use the open cut cast in place and precast construction subway station construction method of stake supporting system | |
CN109837831A (en) | A kind of centrifugation prefabricated assembled concrete bridge pier and construction method | |
CN106930194B (en) | Inter-tie and pier stud global formation construction method and template used holder | |
CN103255717A (en) | Method for constructing hit-preventing wall | |
CN201762666U (en) | Bent cap construction support | |
CN107090908B (en) | A kind of vertical prefabricated components joint connecting method | |
CN108487630A (en) | Coagulation earth steps platform prefabrication and assembly construction construction method | |
CN102535353A (en) | Construction method for box beam swinging body striding on expressways and railways in rail transit | |
CN110468725A (en) | Installation engineering method after swivel bridges abutment pier support | |
CN109162204A (en) | A kind of construction method of the quick spelling of bridge substructure transverse direction piecemeal | |
CN113863166B (en) | Reverse order construction method for swivel-first and mounting support | |
CN109138457A (en) | For installing the support system and its construction method of assembled architecture | |
CN109594467A (en) | Precast pier and cushion cap connection structure, construction method, precast pier, cushion cap | |
CN201520942U (en) | Moving die carrier spreader for resolving problems of cast-in-site beam concrete construction | |
CN205062844U (en) | Supplementary installation device of well lid construction of road surface inspection shaft | |
CN108360570A (en) | Bituminous paving inspection shaft gug construction method | |
CN106381810B (en) | With the cast-in-place outstanding method for filling beam of beam-column type bracket | |
CN205171381U (en) | Prefabricated assembly bridge bent cap positioner | |
CN107059574A (en) | A kind of method of concrete structure and its prefabricated assembled cement concrete pavement of leveling | |
CN214992983U (en) | Fully-assembled bridge based on UHPC (ultra high performance polycarbonate) slab wall embedded pile foundation | |
CN107460793B (en) | Hang empty iron assembly interval structure system and its construction method | |
CN214656383U (en) | Line is alternately low headroom and is pieced together wide cast-in-place case roof beam support | |
CN206052565U (en) | A kind of beam-column type bracket |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |