CN105064695A - Secondary tensioning and releasing device and method for prestressed tendons - Google Patents

Secondary tensioning and releasing device and method for prestressed tendons Download PDF

Info

Publication number
CN105064695A
CN105064695A CN201510504273.4A CN201510504273A CN105064695A CN 105064695 A CN105064695 A CN 105064695A CN 201510504273 A CN201510504273 A CN 201510504273A CN 105064695 A CN105064695 A CN 105064695A
Authority
CN
China
Prior art keywords
steel
presstressed reinforcing
backing plate
steel cylinder
times tensioning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510504273.4A
Other languages
Chinese (zh)
Other versions
CN105064695B (en
Inventor
马亚飞
郭忠照
王磊
张建仁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha University of Science and Technology
Original Assignee
Changsha University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha University of Science and Technology filed Critical Changsha University of Science and Technology
Priority to CN201510504273.4A priority Critical patent/CN105064695B/en
Publication of CN105064695A publication Critical patent/CN105064695A/en
Application granted granted Critical
Publication of CN105064695B publication Critical patent/CN105064695B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a secondary tensioning and releasing device and a secondary tensioning and releasing method for prestressed tendons. The invention has the technical effects that after the prestressed tendon passes through the device, fine sand is filled in the steel cylinder, and then the prestressed tendon is tensioned and anchored. When the tensioning needs to be compensated, the jack and the secondary tensioning base are utilized, and the anchoring prestress loss of the prestressed tendon is reduced by rotating the adjusting nut. When tension is required to be released, the single-head bolt is unscrewed to release sand, so that the tension of the prestressed tendon is released. The device is simple to operate, low in manufacturing cost, strong in safety and good in using effect. The method has wide practicability in secondary tensioning anchoring and releasing of single medium and short prestressed tendons in actual engineering construction and laboratories.

Description

A kind of presstressed reinforcing steel two times tensioning with put an apparatus and method
Technical field
The present invention relates to a kind of presstressed reinforcing steel two times tensioning and put an apparatus and method, be particularly useful for single in Practical Project and laboratory in, benefit stretch-draw in short bundle tension of prestressed tendon anchoring procedure and to put.
Background technology
At present, in, short bundle presstressed reinforcing steel uses very extensive in actual engineering design, construction, reinforcing and laboratory research process.But, in, the loss of prestress that causes because ground tackle bounces back of short bundle presstressed reinforcing steel is very serious.There is improving one's methods of some presstressed reinforcing steel anchorings in recent years, such as, increased holding nut outward at traditional anchor cup, having kept the stress level after mending stretch-draw by mending stretch-draw screwed support nut.The method need make the ground tackle of band holding nut, costly.Also have device to adopt band breach pad to bounce back to prevent presstressed reinforcing steel, weak point to coordinate multi-thickness pad to use, and anchoring precision is difficult to control.In addition, open about putting of presstressed reinforcing steel, traditional method comprises sandbox method and jack method.The former device is complicated and uneconomical, and latter repeatedly need be put by hydraulic jack and open, and operational sequence is loaded down with trivial details, and tension stress is difficult to control, and sometimes must could realize under ultra stretching situation, there is potential safety hazard.
Summary of the invention
For solving the problems of the technologies described above, technical scheme of the present invention is, a kind of presstressed reinforcing steel two times tensioning with put a device, comprise nut, hollow stud, circular steel backing plate, steel cylinder, steel annulus, single ended bolt and two times tensioning pedestal, described hollow stud, circular steel backing plate, steel cylinder all has the through hole passed for presstressed reinforcing steel at the circle centre position of radial section, the diameter of hollow stud and circular steel backing plate is not less than the internal diameter of steel cylinder, the end of one end of steel cylinder stacks with circular steel backing plate and hollow stud concentric and is integrally fixed successively, described nut mates with hollow stud and is threaded connection, described steel annulus central authorities leave for the annular distance by presstressed reinforcing steel, the external diameter of steel annulus is equal with steel barrel bore and be arranged in the end of the steel cylinder other end, steel cylinder has at least one for screwing in the screw of single ended bolt on the sidewall near circular steel backing plate, injected fine sand by screw and screwed in single ended bolt during tension of prestressed tendon and close steel cylinder, fine sand is discharged by screw when to put, described two times tensioning pedestal covers in steel cylinder when carrying out two times tensioning outer with support jack.
Described a kind of presstressed reinforcing steel two times tensioning with put a device, the quantity of described screw is 4, and on steel cylinder side wall spaced set.
Presstressed reinforcing steel two times tensioning and a method of to put, the device described in employing, comprises the following steps:
Step one: the hollow stud be fixed as one, circular steel backing plate, steel cylinder are placed in stretching end, nut is threaded onto on hollow stud, supporting backing plate is located on concrete component, nut contact supports backing plate, steel annulus is located at the end of steel cylinder, and makes presstressed reinforcing steel pass support backing plate, nut, hollow stud, circular steel backing plate, steel cylinder and steel annulus;
Step 2: presstressed reinforcing steel is good in the anchoring of non-stretching end ground tackle;
Step 3: install anchor cup, intermediate plate and jack, before Shi Hanzhang, turn on a single ended bolt, pour into fine sand densely in steel cylinder, then twists good bolt;
Step 4: utilize jack and intermediate plate to carry out stretch-draw and the anchoring of presstressed reinforcing steel;
Step 5: when carrying out two times tensioning, two times tensioning pedestal is installed, base lugs is directly supported in and supports on backing plate, jack leading portion is supported in two times tensioning pedestal, be stretched to proof stress, can produce the gap of presstressed reinforcing steel axis direction in this process between anchor cup and steel annulus, tightening nut blind, to keep the stress level after mending stretch-draw, is put to open and is taken off jack and two times tensioning pedestal;
A step 6: when carrying out putting, single ended bolt is turned on and carries out unloading sand, after fine sand is unsnatched, namely produce the space of shrinking for presstressed reinforcing steel in steel cylinder, thus lay down the intermediate plate ground tackle at two ends smoothly, by intact for presstressed reinforcing steel taking-up.
The technique effect of patent of the present invention is: when carrying out two times tensioning, by jack and two times tensioning pedestal, by rotating adjusting nut blind, when making up stretch-draw first, ground tackle bounces back the loss of prestress caused, pass through regulating nut, the effect that loss of prestress is less than 2% can be reached, thus greatly improve prestress anchoraging precision.Carry out presstressed reinforcing steel when to put, without the need to ultra stretching, under original stress level, turn on single ended bolt by spanner and carry out unloading sand, can to put presstressed reinforcing steel.It is simple to operate, and cost is low, high safety, and result of use is good, can be widely used in Practical Project and laboratory single in, the two times tensioning of short bundle presstressed reinforcing steel with to put.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is sectional drawing of the present invention;
Fig. 3 is overall work schematic diagram of the present invention;
In figure, 1 be nut, 2 for hollow stud, 3 for circular steel backing plate, 4 for steel cylinder, 5 for steel annulus, 6 for single ended bolt, 7 for two times tensioning pedestal, 8 for anchor cup, 9 for intermediate plate, 10 for presstressed reinforcing steel, 11 for jack, 12 for support backing plate.
Detailed description of the invention
See Fig. 1, Fig. 2, the present invention includes nut 1, hollow stud 2, circular steel backing plate 3, steel cylinder 4, steel annulus 5, single ended bolt 6, two times tensioning pedestal 7.Described hollow stud 2, circular steel backing plate 3, steel cylinder 4 are welded into entirety, nut 1 and hollow stud 2 support the use, described circular steel backing plate 3 and steel annulus 5 are all in central openings, add hollow stud 2, the alignment of three's circular hole is passed for presstressed reinforcing steel 10, the external diameter of described steel annulus 5 and steel cylinder 4 internal diameter equal and opposite in direction, steel annulus 5 is for bearing the active force of presstressed reinforcing steel ground tackle 8, described steel cylinder 4 opens four circular holes equally spacedly on the sidewall near welding ends, and circular hole establishes screw thread to use to coordinate single ended bolt 6.
Work process is: the first step, and the present invention is placed in stretching end, and presstressed reinforcing steel is through this device; Second step is good in the anchoring of non-stretching end ground tackle; 3rd step, after the pulling preparation work of presstressed reinforcing steel completes, before Shi Hanzhang, turns on a single ended bolt 6, pours into fine sand and make it closely knit, then twists good bolt 6; 4th step, utilizes jack 11 and intermediate plate 9 to carry out the stretch-draw anchor of presstressed reinforcing steel 10, the now bang path of power: intermediate plate and anchor cup → this device → support backing plate → concrete component; 5th step, when carrying out two times tensioning, two times tensioning pedestal 7 is installed, make base lugs directly be supported on backing plate 12, jack leading portion is supported in two times tensioning pedestal 7, is stretched to proof stress, gap can be produced between anchor cup 8 and steel annulus 5 in this process, tightening nut 1 blind, to keep the stress level after mending stretch-draw, is put to open and is taken off jack 11 and two times tensioning pedestal 7, the now bang path of power: intermediate plate and anchor cup → this device → support backing plate → concrete component; 4 single ended bolt, when carrying out putting, are turned on and are carried out unloading sand by the 6th step.After fine sand is unsnatched, certain space can be reserved in device and shrink for presstressed reinforcing steel, thus lay down the intermediate plate ground tackle at two ends smoothly, by intact for presstressed reinforcing steel taking-up.

Claims (3)

1. a presstressed reinforcing steel two times tensioning with put a device, it is characterized in that, comprise nut, hollow stud, circular steel backing plate, steel cylinder, steel annulus, single ended bolt and two times tensioning pedestal, described hollow stud, circular steel backing plate, steel cylinder all has the through hole passed for presstressed reinforcing steel at the circle centre position of radial section, the diameter of hollow stud and circular steel backing plate is not less than the internal diameter of steel cylinder, the end of one end of steel cylinder stacks with circular steel backing plate and hollow stud concentric and is integrally fixed successively, described nut mates with hollow stud and is threaded connection, described steel annulus central authorities leave for the annular distance by presstressed reinforcing steel, the external diameter of steel annulus is equal with steel barrel bore and be arranged in the end of the steel cylinder other end, steel cylinder has at least one for screwing in the screw of single ended bolt on the sidewall near circular steel backing plate, injected fine sand by screw and screwed in single ended bolt during tension of prestressed tendon and close steel cylinder, fine sand is discharged by screw when to put, described two times tensioning pedestal covers in steel cylinder when carrying out two times tensioning outer with support jack.
2. a kind of presstressed reinforcing steel two times tensioning according to claim 1 with put a device, it is characterized in that, the quantity of described screw is 4, and on steel cylinder side wall spaced set.
3. presstressed reinforcing steel two times tensioning and a method of to put, is characterized in that, adopt device as claimed in claim 1 or 2, comprise the following steps:
Step one: the hollow stud be fixed as one, circular steel backing plate, steel cylinder are placed in stretching end, nut is threaded onto on hollow stud, supporting backing plate is located on concrete component, nut contact supports backing plate, steel annulus is located at the end of steel cylinder, and makes presstressed reinforcing steel pass support backing plate, nut, hollow stud, circular steel backing plate, steel cylinder and steel annulus;
Step 2: presstressed reinforcing steel is good in the anchoring of non-stretching end ground tackle;
Step 3: install anchor cup, intermediate plate and jack, before Shi Hanzhang, turn on a single ended bolt, pour into fine sand densely in steel cylinder, then twists good bolt;
Step 4: utilize jack and intermediate plate to carry out stretch-draw and the anchoring of presstressed reinforcing steel;
Step 5: when carrying out two times tensioning, two times tensioning pedestal is installed, base lugs is directly supported in and supports on backing plate, jack leading portion is supported in two times tensioning pedestal, be stretched to proof stress, can produce the gap of presstressed reinforcing steel axis direction in this process between anchor cup and steel annulus, tightening nut blind, to keep the stress level after mending stretch-draw, is put to open and is taken off jack and two times tensioning pedestal;
A step 6: when carrying out putting, single ended bolt is turned on and carries out unloading sand, after fine sand is unsnatched, namely produce the space of shrinking for presstressed reinforcing steel in steel cylinder, thus lay down the intermediate plate ground tackle at two ends smoothly, by intact for presstressed reinforcing steel taking-up.
CN201510504273.4A 2015-08-17 2015-08-17 Secondary tensioning and releasing device and method for prestressed tendons Active CN105064695B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510504273.4A CN105064695B (en) 2015-08-17 2015-08-17 Secondary tensioning and releasing device and method for prestressed tendons

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510504273.4A CN105064695B (en) 2015-08-17 2015-08-17 Secondary tensioning and releasing device and method for prestressed tendons

Publications (2)

Publication Number Publication Date
CN105064695A true CN105064695A (en) 2015-11-18
CN105064695B CN105064695B (en) 2017-07-04

Family

ID=54494180

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510504273.4A Active CN105064695B (en) 2015-08-17 2015-08-17 Secondary tensioning and releasing device and method for prestressed tendons

Country Status (1)

Country Link
CN (1) CN105064695B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105881737A (en) * 2016-06-02 2016-08-24 福建省大地管桩有限公司 Device and method for integrally releasing and stretching pre-stressed concrete sheet pile
CN106671268A (en) * 2016-06-16 2017-05-17 山西高行液压股份有限公司 Pre-tensioning track plate rebar stretch-draw and extending device
CN109507049A (en) * 2018-12-04 2019-03-22 中冶建筑研究总院有限公司 A kind of the prestressing force loading device and loading method of component
CN110565546A (en) * 2019-09-09 2019-12-13 长沙理工大学 Detachable device for assembling prestress for bridge structure and reinforcing method
CN111101713A (en) * 2020-01-14 2020-05-05 福建省大地管桩有限公司 Applying device and applying method for prestress of concrete member

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011184894A (en) * 2010-03-05 2011-09-22 Ps Mitsubishi Construction Co Ltd Anchorage device for prestressing tendon, and method for repairing existing prestressed concrete structure
CN203145324U (en) * 2013-03-15 2013-08-21 长沙理工大学 Controllable prestressed tendon tensioning anchorage for test
CN103556785A (en) * 2013-11-25 2014-02-05 哈尔滨工业大学 Retraction compensating type nut clamping piece anchor as well as anchor tensioning method
CN103850441A (en) * 2014-03-19 2014-06-11 郭成顺 Tensioning construction method and tensioning device of prestressed concrete structure
CN203665700U (en) * 2014-01-20 2014-06-25 郭成顺 Sandbox distributed pretensioning bed
CN104831634A (en) * 2015-05-18 2015-08-12 湖南路桥建设集团有限责任公司 Construction method for box type bridge vertical prestressed steel strand tension
CN204920236U (en) * 2015-08-17 2015-12-30 长沙理工大学 Secondary tensioning and releasing device for prestressed tendons

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011184894A (en) * 2010-03-05 2011-09-22 Ps Mitsubishi Construction Co Ltd Anchorage device for prestressing tendon, and method for repairing existing prestressed concrete structure
CN203145324U (en) * 2013-03-15 2013-08-21 长沙理工大学 Controllable prestressed tendon tensioning anchorage for test
CN103556785A (en) * 2013-11-25 2014-02-05 哈尔滨工业大学 Retraction compensating type nut clamping piece anchor as well as anchor tensioning method
CN203665700U (en) * 2014-01-20 2014-06-25 郭成顺 Sandbox distributed pretensioning bed
CN103850441A (en) * 2014-03-19 2014-06-11 郭成顺 Tensioning construction method and tensioning device of prestressed concrete structure
CN104831634A (en) * 2015-05-18 2015-08-12 湖南路桥建设集团有限责任公司 Construction method for box type bridge vertical prestressed steel strand tension
CN204920236U (en) * 2015-08-17 2015-12-30 长沙理工大学 Secondary tensioning and releasing device for prestressed tendons

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105881737A (en) * 2016-06-02 2016-08-24 福建省大地管桩有限公司 Device and method for integrally releasing and stretching pre-stressed concrete sheet pile
CN105881737B (en) * 2016-06-02 2018-04-27 福建省大地管桩有限公司 A kind of prestressed concrete plate stake Integral tension device and method
CN106671268A (en) * 2016-06-16 2017-05-17 山西高行液压股份有限公司 Pre-tensioning track plate rebar stretch-draw and extending device
CN109507049A (en) * 2018-12-04 2019-03-22 中冶建筑研究总院有限公司 A kind of the prestressing force loading device and loading method of component
CN110565546A (en) * 2019-09-09 2019-12-13 长沙理工大学 Detachable device for assembling prestress for bridge structure and reinforcing method
CN110565546B (en) * 2019-09-09 2024-04-16 长沙理工大学 Detachable device for assembling prestress for bridge structure and reinforcing method
CN111101713A (en) * 2020-01-14 2020-05-05 福建省大地管桩有限公司 Applying device and applying method for prestress of concrete member
CN111101713B (en) * 2020-01-14 2024-01-02 福建省大地管桩有限公司 Device and method for applying prestress to concrete member

Also Published As

Publication number Publication date
CN105064695B (en) 2017-07-04

Similar Documents

Publication Publication Date Title
CN105064695A (en) Secondary tensioning and releasing device and method for prestressed tendons
CN103343593B (en) Prestressed tendon anchorage device capable of being freely regulated and controlled at high precision
CN204920236U (en) Secondary tensioning and releasing device for prestressed tendons
CN101260741A (en) Short bundle cable stretching caging device and method for stretching and anchoring
US20170044734A1 (en) Foundation for a wind turbine
CN101235663A (en) Clip type anchorage applying to carbon fiber reinforced polymeric material prestressing force rib
CN112160506B (en) Secondary tensioning anchor for unbonded prestressed steel strand and tensioning device and method
CN103147468A (en) Method for testing bearing capacity of pile foundation
CN203373906U (en) Prestressed tendon anchorage device capable of being freely regulated and controlled at high precision
CN201241479Y (en) Stretching device of prestress FRP rib anchorage
CN203145324U (en) Controllable prestressed tendon tensioning anchorage for test
CN201033945Y (en) Short strand wire stretching stopping means
CN101713253A (en) Prestressed carbon cloth reinforced tensioner
CN111119029A (en) Low-retraction anchoring device for wedge-shaped prestressed tendons and using method
CN104805841A (en) FRP rib anchor rod anchoring head capable of applying prestress
CN105403454B (en) The anchor of single hole steel strand wires fatigue test clip type anchor
CN102912987B (en) Stress applying method and tool thereof for low retraction pre-stress concrete member
DE202013012224U1 (en) Arrangement for the high-strength anchoring of a tensioning rod having a tension member in a component
CN201162311Y (en) Clip type anchorage used for carbon fiber reinforced polymeric material pre-stress tendon
CN211815509U (en) Low-retraction anchoring device for wedge-shaped prestressed tendons
CN208899885U (en) For carrying out the device of two times tensioning to in-service presstressed reinforcing steel
CN105043738A (en) Anchor long-term load/crack repeated opening and closing constant tension load test device
CN204882047U (en) Open and shut invariable pulling force load test device repeatedly in long -term load / crack of crab -bolt
CN221460973U (en) Whole cable frock that trades of steel strand wires stay cable
CN206056951U (en) A kind of prestressed anchor fatigue experimental device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant