CN104963293A - Anchoring method for grouting and anchoring reinforcing steel bar in corrugated pipe to anchor precast segmental beam and parking area stiffening strut - Google Patents

Anchoring method for grouting and anchoring reinforcing steel bar in corrugated pipe to anchor precast segmental beam and parking area stiffening strut Download PDF

Info

Publication number
CN104963293A
CN104963293A CN201510433090.8A CN201510433090A CN104963293A CN 104963293 A CN104963293 A CN 104963293A CN 201510433090 A CN201510433090 A CN 201510433090A CN 104963293 A CN104963293 A CN 104963293A
Authority
CN
China
Prior art keywords
bellows
energy
support
anchoring
corrugated pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510433090.8A
Other languages
Chinese (zh)
Other versions
CN104963293B (en
Inventor
葛斌斌
曾鸣
谭坤
周玲敏
周安龙
刘文广
刘继仁
宓浩
叶孔晟
张瑞诚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 11th Bureau Group Bridge Co Ltd
Original Assignee
China Railway 11th Bureau Group Bridge Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 11th Bureau Group Bridge Co Ltd filed Critical China Railway 11th Bureau Group Bridge Co Ltd
Priority to CN201510433090.8A priority Critical patent/CN104963293B/en
Publication of CN104963293A publication Critical patent/CN104963293A/en
Application granted granted Critical
Publication of CN104963293B publication Critical patent/CN104963293B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides an anchoring method for grouting and anchoring a reinforcing steel bar in a corrugated pipe to anchor a precast segmental beam and a parking area stiffening strut. The method comprises the following steps of pre-embedding the corrugated pipe in the segmental beam precasting process; inserting the anchored reinforcing steel bar into the corrugated pipe after the segmental beam is demolded; and casting the stiffening strut after the anchored reinforcing steel bar and the corrugated pipe are grouted and anchored. According to the invention, through applying the reinforcing steel bar anchoring method to a special structure in bridge precast construction, the traditional production process and template do not need to be changed; it is only required to pre-embed the corrugated pipe in the continuously production process; the process is simple while performing the construction of the stiffening strut in the later stage; the anchoring performance is reliable due to the use of non-shrinkage and high-strength grouting materials; and the construction progress is furthest accelerated on the premise of ensuring the construction quality.

Description

Precast segmental beam lay-by is put more energy into and is supportted bellows slurry anchor Bar Anchorage method
Technical field
The present invention relates to reinforced concrete prefabricated structure reinforcing bars anchoring field, particularly relate to a kind of precast segmental beam lay-by and to put more energy into support bellows slurry anchor Bar Anchorage method.
Background technology
The application of precast concrete segment beam technology in bridge engineering is very extensive, and short-term and long line method prefabricated subsection beam process are also tending towards ripe.Beam sections lay-by is arranged to be chosen arm and to put more energy into support structure, beam sections is had in the Urban Bridge engineering selection of more planning space and structure design.Support of putting more energy into roughly has 3 kinds of modes with the anchor connection of beam sections: embedded sleeve barrel is connected anchoring; Steel, mixed combination anchor and plant anchor.But these anchorage styles cannot meet the continuous seepage of beam sections when putting more energy into support element precast, at the bottom of the prefabricated construction feasibility of privileged sites, large to the loss of template, quality control difficulty is very big.Pre-buried oblique sleeve location difficulty and angle can not adjust; Steel, mixed combination anchor require high to steel, welding and corrosion-resistant and interface anchoring difficult; Plant anchor boring difficulty and reinforcing bar insert after the short time cannot colligation adjust to the right place.
Summary of the invention
Object of the present invention is exactly a kind of method providing bellows entoplasm anchor Bar Anchorage for the construction of privileged sites in bridge prefabrication engineering.In the lay-by prefabricated anchoring application of support of putting more energy into, this technology has that constructing operation is simple, anchoring property reliable, can ensure the advantages such as prefabricated continuous seepage without the need to reequiping model.
Object of the present invention realizes by following scheme: a kind of precast segmental beam lay-by is put more energy into and supportted bellows slurry anchor Bar Anchorage method, and its concrete technology step is as follows:
In step one, beam sections reinforcing bar binding process, put more energy at every root and support the pre-buried bellows in anchor bar position and grouting escape pipe.Bellows Length should meet design anchorage length of steel bar, and bellows diameter should meet the space requirement of anchor bar slurry anchor, and pre-buried escape pipe need support the use with bellows, and bellows utilizes network for location to locate, and shutoff is carried out at bellows two ends, prevents into slurry;
After step 2, beam sections bale handle to support construction area of putting more energy into, cut web outside corrugated pipe orifice concrete, and clear up bellows inwall;
Step 3, support anchor bar of putting more energy into penetrate in bellows, put more energy into shown in colligation drawing after arriving design attitude support stirrup and lay-by bridge deck reinforcing bar;
Step 4, the support and after the whole colligation of lay-by bridge deck reinforcing bar fixedly completes of putting more energy into, the bellows mouth of pipe penetrating anchor bar is carried out shutoff, installs inlet pipe in shutoff process, inlet pipe need be installed firmly seamless;
Step 5, by design mixture proportion stir grouting material, grouting material stir carry out in strict accordance with constructure scheme, degree of mobilization need meet design requirement;
Step 6, utilize pneumatic mortar machine to be in the milk in bellows, pneumatic mortar machine Stress control is in designing requirement, and slurry holds pressure 10s after filling pipeline, when confirming that pulp concentration is consistent with entering to starch concentration, carry out closed pressurize;
Carry out after step 7, slurry reach design strength putting more energy into support and lay-by bridge deck formwork erection, build.
The beneficial effect adopting technique scheme to produce is: Bar Anchorage method is applied in bridge prefabrication engineering special construction by the present invention, without the need to changing original production technology and template, pre-buried bellows is only needed in continuous flow procedure, when later stage carries out putting more energy into support construction, technique is simple, use ungauged regions high strength grout anchoring property reliable, under the prerequisite ensureing construction quality, accelerate construction speed to greatest extent.

Claims (1)

1. precast segmental beam lay-by is put more energy into and is supportted a bellows slurry anchor Bar Anchorage method, and its concrete technology step is as follows:
In step one, beam sections reinforcing bar binding process, put more energy at every root and support the pre-buried bellows in anchor bar position and grouting escape pipe, Bellows Length should meet design anchorage length of steel bar, bellows diameter should meet the space requirement of anchor bar slurry anchor, pre-buried escape pipe need support the use with bellows, bellows utilizes network for location to locate, and shutoff is carried out at bellows two ends, prevents into slurry;
After step 2, beam sections bale handle to support construction area of putting more energy into, cut web outside corrugated pipe orifice concrete, and clear up bellows inwall;
Step 3, support anchor bar of putting more energy into penetrate in bellows, put more energy into shown in colligation drawing after arriving design attitude support stirrup and lay-by bridge deck reinforcing bar;
Step 4, the support and after the whole colligation of lay-by bridge deck reinforcing bar fixedly completes of putting more energy into, the bellows mouth of pipe penetrating anchor bar is carried out shutoff, installs inlet pipe in shutoff process, inlet pipe need be installed firmly seamless;
Step 5, by design mixture proportion stir grouting material, grouting material stir carry out in strict accordance with constructure scheme, degree of mobilization need meet design requirement;
Step 6, utilize pneumatic mortar machine to be in the milk in bellows, pneumatic mortar machine Stress control is in designing requirement, and slurry holds pressure 10s after filling pipeline, when confirming that pulp concentration is consistent with entering to starch concentration, carry out closed pressurize;
Carry out after step 7, slurry reach design strength putting more energy into support and lay-by bridge deck formwork erection, build.
CN201510433090.8A 2015-07-22 2015-07-22 Prefabricated subsection beam lay-by is put more energy into and is supportted bellows slurry anchor Bar Anchorage method Active CN104963293B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510433090.8A CN104963293B (en) 2015-07-22 2015-07-22 Prefabricated subsection beam lay-by is put more energy into and is supportted bellows slurry anchor Bar Anchorage method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510433090.8A CN104963293B (en) 2015-07-22 2015-07-22 Prefabricated subsection beam lay-by is put more energy into and is supportted bellows slurry anchor Bar Anchorage method

Publications (2)

Publication Number Publication Date
CN104963293A true CN104963293A (en) 2015-10-07
CN104963293B CN104963293B (en) 2016-05-18

Family

ID=54217368

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510433090.8A Active CN104963293B (en) 2015-07-22 2015-07-22 Prefabricated subsection beam lay-by is put more energy into and is supportted bellows slurry anchor Bar Anchorage method

Country Status (1)

Country Link
CN (1) CN104963293B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108571121A (en) * 2018-05-16 2018-09-25 广西大学 The method for determining deformed bar anchorage length design value in concrete based on predetermined fraction

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006125011A (en) * 2004-10-28 2006-05-18 Railway Technical Res Inst Steel-pipe-column joint element, and construction method for beam section of viaduct using it
KR100782523B1 (en) * 2006-09-12 2007-12-06 현대건설주식회사 Prestressed concrete box girder bridge having struts
CN201132929Y (en) * 2007-11-26 2008-10-15 中铁大桥勘测设计院有限公司 Prestressed concrete continuous beam of box section of large- cantilever arc flange plate
CN102787560A (en) * 2012-08-24 2012-11-21 杭州市市政工程集团有限公司 Integrated construction method of support of large cantilevered capping beam and vertical column
CN103276662A (en) * 2013-05-13 2013-09-04 中交第二航务工程局有限公司 Large-cantilever steel web spinal box beam segment and construction technology
CN103741582A (en) * 2013-12-30 2014-04-23 郑州大学 Corrugated steel web polycarbonate (PC) combination box beam and construction method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006125011A (en) * 2004-10-28 2006-05-18 Railway Technical Res Inst Steel-pipe-column joint element, and construction method for beam section of viaduct using it
KR100782523B1 (en) * 2006-09-12 2007-12-06 현대건설주식회사 Prestressed concrete box girder bridge having struts
CN201132929Y (en) * 2007-11-26 2008-10-15 中铁大桥勘测设计院有限公司 Prestressed concrete continuous beam of box section of large- cantilever arc flange plate
CN102787560A (en) * 2012-08-24 2012-11-21 杭州市市政工程集团有限公司 Integrated construction method of support of large cantilevered capping beam and vertical column
CN103276662A (en) * 2013-05-13 2013-09-04 中交第二航务工程局有限公司 Large-cantilever steel web spinal box beam segment and construction technology
CN103741582A (en) * 2013-12-30 2014-04-23 郑州大学 Corrugated steel web polycarbonate (PC) combination box beam and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
许树壮、黄虹: "体外预应力梁在上海长江大桥施工中的应用", 《中国市政工程》, no. 2, 30 November 2007 (2007-11-30), pages 79 - 81 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108571121A (en) * 2018-05-16 2018-09-25 广西大学 The method for determining deformed bar anchorage length design value in concrete based on predetermined fraction
CN108571121B (en) * 2018-05-16 2020-07-17 广西大学 Method for determining design value of anchoring length of deformed reinforcing steel bar in concrete

Also Published As

Publication number Publication date
CN104963293B (en) 2016-05-18

Similar Documents

Publication Publication Date Title
CN102425310B (en) Assembly-type residential shear wall structural wall body vertical connection construction method
CN108952759A (en) A kind of tunnel lining structure and construction method using concrete filled steel tube and superimposed sheet
CN108560544B (en) Sleeve connection assembled pile foundation and construction method thereof
CN106894587A (en) Precast stair connection method
CN106481023B (en) Assembled steel-concrete composite beam structure and its implementation method
CN105201530A (en) Repairing and strengthening method for large cracks on rock tunnel lining
CN106284655A (en) Precast concrete beam stud connects node and method of attachment in succession
CN103410329A (en) Large-span basement concrete roof structure flat tube bonded prestressing force construction method
CN106337570A (en) The steel-tube grouting quick-stabilizing column structure and construction method
CN107642179A (en) Assembled frame-shear structure steel plate keyway attachment structure and assembling method
CN105525753A (en) Method and structure for simultaneously constructing constructional column and main body structure
CN108625477A (en) A kind of assembled beam-column node and its construction method
CN203668839U (en) Concrete-steel plate campsite cross section hoop closed main arch ring reinforcing structure
CN208267862U (en) A kind of bracing means at tunnel road surface crack
CN101270589B (en) Ultra-large span three-dimensional pre-stress beamless circular plate construction method
CN114483081A (en) Construction method of deflection-preventing structure of curved middle wall of multi-arch tunnel under terrain bias pressure
CN103924676B (en) Prestressing force connects beams of concrete concrete-filled circular steel tube column node
CN103866982B (en) A kind of petal art framework construction method
CN207260378U (en) A kind of assembled frame-shear structure curved scissors type combines keyway connection structure
CN104963293A (en) Anchoring method for grouting and anchoring reinforcing steel bar in corrugated pipe to anchor precast segmental beam and parking area stiffening strut
CN207891714U (en) Abdomen packet bottom is trapezoidal/corrugated sheet steel combined box beam
CN103410144A (en) Prestressed reinforcement rock-socketed cast-in-place pile and construction method thereof
CN106149877A (en) Docking structure at concrete frame structure prefabricated post and beam slab node and method
CN105386438A (en) Manual hole digging pile arm guard suspension construction formwork system and construction method thereof
CN106182361B (en) A kind of bolt pin type intersects tenon tooth precast concrete and preparation method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant