CN104895174B - The construction method of heavy caliber rain sewage conduct assembled modular construction - Google Patents

The construction method of heavy caliber rain sewage conduct assembled modular construction Download PDF

Info

Publication number
CN104895174B
CN104895174B CN201510297169.2A CN201510297169A CN104895174B CN 104895174 B CN104895174 B CN 104895174B CN 201510297169 A CN201510297169 A CN 201510297169A CN 104895174 B CN104895174 B CN 104895174B
Authority
CN
China
Prior art keywords
pipeline
construction
pedestal
layer
pipeline pedestal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510297169.2A
Other languages
Chinese (zh)
Other versions
CN104895174A (en
Inventor
谢勇成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhou Construction Group Co Ltd
Original Assignee
Shenzhou Construction Group Co Ltd</en>
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhou Construction Group Co Ltd</en> filed Critical Shenzhou Construction Group Co Ltd</en>
Priority to CN201510297169.2A priority Critical patent/CN104895174B/en
Publication of CN104895174A publication Critical patent/CN104895174A/en
Application granted granted Critical
Publication of CN104895174B publication Critical patent/CN104895174B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The present invention relates to a kind of heavy caliber rain sewage conduct assembled modular construction, it is characterized in that bottom pipeline groove, arranging shallow-layer solidification cement soil layer, shallow-layer solidification cement soil layer top arranges prefabricated pipeline pedestal, pipeline pedestal is provided with hole for hoist, grouting behind shaft or drift lining hole, template groove and locating button, pipeline props up to be located on pipeline pedestal, in the pipeline space with pipeline pedestal, grouting behind shaft or drift lining obturator is formed by grouting behind shaft or drift lining pore pressure slurry, and on pipeline, it is uniformly arranged separate type hoop positioning belt, separate type hoop positioning belt two ends locating button with pipeline pedestal both sides respectively is connected, pipeline arranges concrete backfill layer, both sides arrange gravel backfill layer.The present invention is used prefabricated pipeline pedestal and is effectively enhanced globality and the stability of Pipe installing by a series of reinforcement measures, and structure hoisting is convenient, has preferable economic technology benefit.

Description

The construction method of heavy caliber rain sewage conduct assembled modular construction
Technical field
The present invention relates to the construction method of a kind of heavy caliber rain sewage conduct assembled modular construction.Belong to municipal works field, it is adaptable to the burial and construction of heavy caliber rain sewage conduct.
Background technology
Municipal administration rain sewage conduct is as infrastructure important in cities and towns, and daily life and work relationship with resident are close.At present in municipal administration rain sewage conduct construction, rain sewage pipe is layed in the both sides of town road more, work on the spot face is less, cause tubing to lift rear hanging belt in place and be not easy extraction, the globality of pipeline is poor, steadiness is low, and easily causes pipe skew, it is impossible to ensure the straight cis degree of Pipe installing, twice basis concrete construction cycle is long simultaneously, and pipeline is the most on the low side with the bonding strength on basis.
There is now multiple assembled pipe support structure, and under suitable operating mode, all achieve preferable project benefit, but remain and improve space, it is mainly reflected in: ground is not processed by (1), directly carry out pipe support installation, cause foundation bearing capacity deficiency that differential settlement occurs;(2) portion of standoff structure does not considers conduit section size, easily forms bigger space between pipeline and bearing, and support strength is on the low side after having constructed;(3) portion of standoff structure does not considers connectivity problem between bearing space grouting behind shaft or drift lining, split-type bearing, affects the overall stress of pipeline and bearing;(4) without adding epistasis connection measure, pipe shaft cracky etc. in the case of producing settlement after construction after lifting pipeline is completed by portion of standoff structure.
Given this, for lifting construction difficulty present in tradition heavy caliber rain sewage conduct construction, overall steadiness is low and pedestal bonding strength not enough, produces technological difficulties and the problems such as differential settlement drawing crack after pipeliner after Pipe installing, needs invention a kind of lifting construction simplicity, overall structure good stability, support strength height, rain sewage conduct assembled modular construction that economic benefit is excellent at present badly.
The heavy caliber rain sewage conduct assembled modular construction of the present invention is used prefabricated pipeline pedestal and is effectively enhanced globality and the stability of Pipe installing by a series of reinforcement measures, and structure hoisting is convenient, has preferable economic technology benefit.
Summary of the invention
It is an object of the invention to provide a kind of efficiency of construction height, the construction of the lifting pipeline heavy caliber rain sewage conduct assembled modular construction that steadiness is good, differential settlement is little simple, overall.
For realizing above-mentioned technical purpose, present invention employs techniques below scheme:
The construction method of heavy caliber rain sewage conduct assembled modular construction, it is characterized in that, shallow-layer solidification cement soil layer is set bottom pipeline groove, shallow-layer solidification cement soil layer top arranges prefabricated pipeline pedestal, pipeline pedestal is provided with hole for hoist, grouting behind shaft or drift lining hole, template groove and locating button, pipeline props up to be located on pipeline pedestal, in the pipeline space with pipeline pedestal, grouting behind shaft or drift lining obturator is formed by grouting behind shaft or drift lining pore pressure slurry, and on pipeline, it is uniformly arranged separate type hoop positioning belt, separate type hoop positioning belt two ends locating button with pipeline pedestal both sides respectively is connected, pipeline arranges concrete backfill layer, both sides arrange gravel backfill layer
The main construction procedure of described construction method is as follows:
1) preparation of construction: according to design drawing, processes job site, draws construction outline line, determines bench mark absolute altitude, position prefabricated pipeline pedestal, and construction material, machinery, personnel are in place;
2) tube seat excavation: according to design slot bottom width and cutting depth and put the slope gradient and calculate and determine excavation width, uses reverse shovel grab retrusive excavation, and carries out with inverse water pipe gradient direction;
3) flat base, the construction of cement solidification layer: after tube seat has excavated, absolute altitude at the bottom of pipe is measured, and tamp bottom soil body, then use pre-mixing lightweight concrete to carry out backfill to pave;
4) pipeline pedestal lifting: spill medium-sand seam solidification cement soil layer top paving before lifting, uses boom hoisting by prefabricated pipeline pedestal along being longitudinally equidistantly laid in tube seat;
5) Pipe installing: use hand fit's machinery down tube, requires steadily to install to pipeline pedestal rain sewage conduct according to design, arranges separate type hoop positioning belt after installation qualification, firm pipe shaft;
6) slip casting obturator construction: the cement mortar meeting match ratio requirement is carried out mud jacking, the space between fill pipe and pipeline pedestal by grouting behind shaft or drift lining hole by cement mortar pump;
7) concrete backfill construction: the template groove in prefabricated pipeline pedestal both sides is inserted into template, uses at two ends same template to enclose simultaneously, carries out concreting backfill, form removal after concrete initial set;
Gravel backfill construction: at both sides placement in layers gravel after concrete backfill layer acceptance(check), every layer thickness is less than 150mm, and compaction treatment.
Described pipeline groove excavated section can be set to inverted trapezoidal or rectangle.
Described prefabricated pipeline pedestal upper surface is provided with circular arc notch, notch radius is identical with pipe external surface radius, circular arc notch bilateral symmetry and set gradually compartment L-type grouting behind shaft or drift lining hole and template groove from inside to outside, the base top surface spaced set locating button between L-type grouting behind shaft or drift lining hole and template groove.
When described prefabricated pipeline pedestal volume is bigger, may be configured as symmetric double fraction structure, double-division type pipeline pedestal connects end and reserves screw limiting hole, and the junction steel plate being welded with positioning screw by bottom connects into entirety.
Described hole for hoist is horizontally placed between adjacent two grouting behind shaft or drift lining holes, and through template groove and circular arc notch.
Described separate type hoop positioning belt is along pipeline longitudinal direction spaced set, and two ends locating button with pipeline pedestal both sides respectively is connected.
Described concrete backfill layer is laterally located between the template groove of pipeline pedestal both sides, wraps rain sewage conduct completely, and arranges gravel backfill layer between concrete backfill layer and groove cell wall.
The present invention has following feature and a beneficial effect:
(1) present invention arranges shallow-layer solidification cement soil layer bottom pipeline groove, can be effectively improved foundation bearing capacity and stability, reduce the posterior settlement of rain sewage conduct.
(2) pipeline pedestal can select monoblock type or symmetric double fraction according to actual condition, pedestal upper surface is prefabricated into circular arc notch according to pipe radius, can be closely connected with pipeline, both integrally-built stability can have been strengthened, the difficulty of fixing quality control can be reduced again, pedestal is from setting template groove and hole for hoist simultaneously, can simplify lifting, formwork construction, accelerating construction progress.
(3) present invention slip casting in the prefabricated pipeline pedestal space with rain sewage conduct forms grouting behind shaft or drift lining obturator, contributes to the installation globality strengthening pipeline with pedestal.
(4) after lifting pipeline completes, at pipe shaft, hoop positioning belt is equidistantly installed, can effectively prevent rain sewage conduct from offseting during differential settlement in follow-up backfill construction and after work.
Accompanying drawing explanation
Fig. 1 is heavy caliber rain sewage conduct assembled modular construction schematic diagram of the present invention;
Fig. 2 is symmetric double fraction pipeline pedestal connection diagram in the present invention;
Fig. 3 is concrete backfill formwork schematic diagram in the present invention;
In figure: 1-pipe alley cell wall, 2-shallow-layer solidification cement soil layer, 3-pipeline pedestal plays pad part, 4-pipeline pedestal stable part, 5-template groove, 6-L type grouting behind shaft or drift lining hole, 7-screw limiting hole, 8-junction steel plate, 9-grouting behind shaft or drift lining obturator, 10-rain sewage conduct, 11-locating button, 12-hoop positioning belt, 13-concrete backfill layer, 14-gravel backfill layer, 15-template, 16-hole for hoist.
Detailed description of the invention
The construction technical requirement of tube seat excavation, solidified earth construction process requirement in present embodiment, cement injection proportioning etc. repeats no more, and emphasis illustrates the embodiment of the heavy caliber rain sewage conduct sewage conduct assembled modular construction the related to construction of the present invention.
Fig. 1 is heavy caliber rain sewage conduct assembled modular construction schematic diagram of the present invention, and Fig. 2 is symmetric double fraction pipeline pedestal connection diagram in the present invention, and Fig. 3 is concrete backfill formwork schematic diagram in the present invention.With reference to the heavy caliber rain sewage conduct sewage conduct assembled modular construction shown in Fig. 1, main pad part 3 by pipeline pedestal, pipeline pedestal stable part 4, grouting behind shaft or drift lining obturator 9, rain sewage conduct 10, hoop positioning belt 12 grade forms, and embodiment illustrates as a example by D=1000mm rain sewage conduct 10:
Using reverse shovel grab retrusive excavation tube seat, excavation width at the bottom of tube seat is 1200mm, and cutting depth is 1400mm, and it is 2.75 that pipe alley cell wall 1 puts the slope gradient.After tube seat has excavated, tamp bottom soil body, and formwork erection pours 100mm thickness, strength grade is the lightweight concrete of LC5.0, form shallow-layer solidification cement soil layer 2.
Pipeline pedestal is reinforced concrete structure, a width of 600mm of Separated type pipe base bottom surface, and pipeline pedestal plays the pad a height of 100mm of part 3, arranges the bolt spacing hole 7 of diameter 16mm, long 25mm at side 50mm;Pipeline pedestal stable part 4 height is 500mm, end face width 200mm, in the middle of end face, one locating button 11 is set every 1000mm, and arrange at arc-shaped side edges 30mm aperture be 20mm, specification be the L-type grouting behind shaft or drift lining hole 6 of 150 × 120mm, L-type grouting behind shaft or drift lining hole 6 arranges together every 2500mm, and the hole for hoist 16 of diameter 20mm is set between adjacent twice L-type grouting behind shaft or drift lining hole 6, the template groove 5 of wide 30mm, deep 300mm is set at outer side edges 50mm simultaneously.
Before pipeline pedestal is installed, the medium-sand seam of thick 150mm is spilt shallow-layer solidification cement soil layer 2 top paving, boom hoisting is used to be laid in tube seat along longitudinal proportional spacing by prefabricated pipeline pedestal again, then junction steel plate 8 is installed, and the screw rod that connects of junction steel plate 8 bottom is inserted in the screw limiting hole 7 that pipeline pedestal plays pad part 3.
Rain sewage conduct 10 is managed for HDPE, uses hand fit's machinery down tube, installs after the assay was approved, installs hoop positioning belt 12 at pipe shaft in time, and hoop positioning belt 12 two is connected with the locating button 11 at two ends, left and right on Separated type pipe pedestal successively.Rain sewage conduct 10 install in place after, carry out mud jacking by meeting the cement mortar that match ratio requires through L-type grouting behind shaft or drift lining hole 6 by cement mortar pump, fill the space between rain sewage conduct 10 and pipeline pedestal.
After rain sewage conduct 10 installation, template groove 5 in two side ducts pedestal stable part 4 is inserted into template 15, template 15 uses plank sheathing, thickness and template groove 5 width are all 30mm, use identical material, the template 15 of specification to enclose at rain sewage conduct 10 two ends simultaneously, the concrete using grade strength to be C30 again carries out backfill and pours, form removal 15 after concrete initial set, forms concrete backfill layer 13.
At both sides placement in layers gravel after concrete backfill layer 13 acceptance(check), every layer thickness is less than 150mm, and compaction treatment, forms gravel backfill layer 14.
The construction method key step of heavy caliber rain sewage conduct assembled modular construction is as follows:
1) preparation of construction: according to design drawing, processes job site, draws construction outline line, determines bench mark absolute altitude, position prefabricated pipeline pedestal, and construction material, machinery, personnel are in place.
2) tube seat excavation: according to design slot bottom width and cutting depth and put the slope gradient and calculate and determine excavation width, uses reverse shovel grab retrusive excavation, and carries out with inverse water pipe gradient direction.
3) flat base, the construction of cement solidification layer: after tube seat has excavated, absolute altitude at the bottom of pipe is measured, and tamp bottom soil body, then use pre-mixing lightweight concrete to carry out backfill to pave.
4) pipeline pedestal lifting: spill medium-sand seam solidification cement soil layer top paving before lifting, boom hoisting is used to be laid in tube seat along longitudinal proportional spacing by prefabricated pipeline pedestal, when pipeline pedestal is symmetric double fraction, should be according to pipeline location, symmetrical pipeline pedestal of laying, and junction steel plate 8 is installed in time.
5) Pipe installing: use hand fit's machinery down tube, requires steadily to install to pipeline pedestal rain sewage conduct 10 according to design, arranges separate type hoop positioning belt 12 after installation qualification in time, firm pipe shaft.
6) slip casting obturator construction: the cement mortar meeting match ratio requirement is carried out mud jacking, the space between fill pipe and pipeline pedestal by grouting behind shaft or drift lining hole 6 by cement mortar pump.
7) concrete backfill construction: the template groove 5 in prefabricated pipeline base both sides is inserted into template 15, uses at two ends same template 15 to enclose simultaneously, carries out concreting backfill, form removal 15 after concrete initial set.
8) gravel backfill construction: at both sides placement in layers gravel after concrete backfill layer 13 acceptance(check), every layer thickness is less than 150mm, and compaction treatment.

Claims (6)

1. the construction method of heavy caliber rain sewage conduct assembled modular construction, it is characterized in that, shallow-layer solidification cement soil layer is set bottom pipeline groove, shallow-layer solidification cement soil layer top arranges prefabricated pipeline pedestal, prefabricated pipeline pedestal is provided with hole for hoist, grouting behind shaft or drift lining hole, template groove and locating button, described prefabricated pipeline pedestal upper surface is provided with circular arc notch, notch radius is identical with pipe external surface radius, circular arc notch bilateral symmetry and set gradually compartment L-type grouting behind shaft or drift lining hole and template groove from inside to outside, base top surface spaced set locating button between L-type grouting behind shaft or drift lining hole and template groove;Pipeline props up to be located on prefabricated pipeline pedestal, in the pipeline space with prefabricated pipeline pedestal, grouting behind shaft or drift lining obturator is formed by grouting behind shaft or drift lining pore pressure slurry, and on pipeline, it is uniformly arranged separate type hoop positioning belt, separate type hoop positioning belt two ends locating button with prefabricated pipeline pedestal both sides respectively is connected, pipeline arranges concrete backfill layer, and both sides arrange gravel backfill layer;
The main construction procedure of described construction method is as follows:
1) preparation of construction: according to design drawing, processes job site, draws construction outline line, determines bench mark elevation location, prefabricated pipeline pedestal, and construction material, machinery, personnel are in place;
2) tube seat excavation: according to design slot bottom width and cutting depth and put the slope gradient and calculate and determine excavation width, uses reverse shovel grab retrusive excavation, and carries out with inverse water pipe gradient direction;
3) flat base, the construction of cement solidification layer: after tube seat has excavated, absolute altitude at the bottom of pipe is measured, and tamp bottom soil body, then use pre-mixing lightweight concrete to carry out backfill to pave;
4) prefabricated pipeline pedestal lifting: spill medium-sand seam solidification cement soil layer top paving before lifting, uses boom hoisting by prefabricated pipeline pedestal along being longitudinally equidistantly laid in tube seat;
5) Pipe installing: use hand fit's machinery down tube, requires steadily to install to prefabricated pipeline pedestal rain sewage conduct according to design, arranges separate type hoop positioning belt after installation qualification, firm pipe shaft;
6) slip casting obturator construction: the cement mortar meeting match ratio requirement is carried out mud jacking, the space between fill pipe and prefabricated pipeline pedestal by grouting behind shaft or drift lining hole by cement mortar pump;
7) concrete backfill construction: the template groove in prefabricated pipeline pedestal both sides is inserted into template, uses at two ends same template to enclose simultaneously, carries out concreting backfill, form removal after concrete initial set;
8) gravel backfill construction: at both sides placement in layers gravel after concrete backfill layer acceptance(check), every layer thickness is less than 150mm, and compaction treatment.
Construction method the most according to claim 1, it is characterised in that described pipeline groove excavated section is inverted trapezoidal or rectangle.
Construction method the most according to claim 1, it is characterized in that when described prefabricated pipeline pedestal volume is bigger, being set to symmetric double fraction structure, double-division type prefabricated pipeline pedestal connects end and reserves screw limiting hole, and the junction steel plate being welded with positioning screw by bottom connects into entirety.
Construction method the most according to claim 1, it is characterised in that described hole for hoist is horizontally placed between adjacent two grouting behind shaft or drift lining holes, and through template groove and circular arc notch.
Construction method the most according to claim 1, it is characterised in that described separate type hoop positioning belt is along pipeline longitudinal direction spaced set.
Construction method the most according to claim 1, it is characterised in that described concrete backfill layer is laterally located between the template groove of prefabricated pipeline pedestal both sides, wraps rain sewage conduct completely, and arranges gravel backfill layer between concrete backfill layer and groove cell wall.
CN201510297169.2A 2015-06-02 2015-06-02 The construction method of heavy caliber rain sewage conduct assembled modular construction Expired - Fee Related CN104895174B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510297169.2A CN104895174B (en) 2015-06-02 2015-06-02 The construction method of heavy caliber rain sewage conduct assembled modular construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510297169.2A CN104895174B (en) 2015-06-02 2015-06-02 The construction method of heavy caliber rain sewage conduct assembled modular construction

Publications (2)

Publication Number Publication Date
CN104895174A CN104895174A (en) 2015-09-09
CN104895174B true CN104895174B (en) 2016-08-24

Family

ID=54028100

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510297169.2A Expired - Fee Related CN104895174B (en) 2015-06-02 2015-06-02 The construction method of heavy caliber rain sewage conduct assembled modular construction

Country Status (1)

Country Link
CN (1) CN104895174B (en)

Families Citing this family (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105239660B (en) * 2015-11-09 2017-07-28 中建八局第四建设有限公司 Guiding gutter and water conservancy diversion groove construction method
CN106838461A (en) * 2017-03-08 2017-06-13 济南黄河路桥建设集团有限公司 A kind of cities and towns flexible duct rapid constructing method
CN107401207B (en) * 2017-09-11 2019-05-31 垠星建设有限公司 The construction method of drainage pipeline
CN107724499A (en) * 2017-09-27 2018-02-23 广东景源建设工程有限公司 The construction method and pedestal of sewage conduct
CN107630500A (en) * 2017-09-27 2018-01-26 广东景源建设工程有限公司 A kind of water supply and drainage construction method
CN108204030B (en) * 2017-12-13 2019-11-08 苍南县交通建设工程有限公司 Sewage conduct mounting structure and its construction method
CN108412016A (en) * 2018-03-15 2018-08-17 中建五局土木工程有限公司 Underground tube body assures construction method
CN108532717B (en) * 2018-04-23 2020-07-14 赣州市榕盛新型建材有限公司 Cement culvert pipe laying device for building engineering
CN109361188B (en) * 2018-08-31 2020-05-26 国网河南省电力公司兰考县供电公司 Environment self-adaptive cable trench and construction method thereof
CN109868881B (en) * 2019-02-25 2024-03-01 华昕设计集团有限公司 Repairing method of lining repairing mechanism of rainwater and sewage pipeline
CN110306644A (en) * 2019-05-23 2019-10-08 浙江沧海建设有限公司 The construction method of municipal rain sewage diversion pipeline
CN110485532A (en) * 2019-08-22 2019-11-22 浙江工业大学 A kind of urban discharging pipeline structure and construction method based on waste tire
CN111851700B (en) * 2020-06-16 2021-09-14 中交第三公路工程局有限公司 Municipal rainwater and sewage pipeline construction method
CN111794340B (en) * 2020-07-18 2021-06-04 福建大华建设工程股份有限公司 Drainage pipeline structure and construction method thereof
CN112049218A (en) * 2020-08-26 2020-12-08 中铁十局集团有限公司 Municipal concrete drainage pipeline laying construction method
CN113389946A (en) * 2021-07-02 2021-09-14 中国十七冶集团有限公司 Rainwater and sewage pipeline fixing device and construction method thereof
CN114045796A (en) * 2021-12-14 2022-02-15 四川省水利水电勘测设计研究院有限公司 Steep slope section inverted siphon pipe arrangement structure and construction method
CN114923032B (en) * 2022-04-08 2024-06-14 淮安市水利勘测设计研究院有限公司 Construction method for integrally installing large-diameter long-distance river-crossing pipeline
CN115111434B (en) * 2022-08-30 2022-11-15 天津建设发展集团有限公司 Construction method of underground pipeline
CN115450229A (en) * 2022-08-31 2022-12-09 上海城建市政工程(集团)有限公司 Pipeline groove excavation backfill construction method based on in-situ solidification of retaining wall slurry

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08105099A (en) * 1994-10-03 1996-04-23 Takeshi Ochi Bend straightener for embedding vinylchloride pipe
CN101775826A (en) * 2010-01-26 2010-07-14 济南金鼎信息技术有限公司 Construction method for laying water pipes
CN103114643A (en) * 2013-03-04 2013-05-22 济南城建集团有限公司 Large-caliber drainage pipeline construction assembly and construction method thereof
CN103603504A (en) * 2013-11-26 2014-02-26 中建二局第三建筑工程有限公司 Method of hoisting super high-rise building electrochemical large-diameter rises along with progress of main structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08105099A (en) * 1994-10-03 1996-04-23 Takeshi Ochi Bend straightener for embedding vinylchloride pipe
CN101775826A (en) * 2010-01-26 2010-07-14 济南金鼎信息技术有限公司 Construction method for laying water pipes
CN103114643A (en) * 2013-03-04 2013-05-22 济南城建集团有限公司 Large-caliber drainage pipeline construction assembly and construction method thereof
CN103603504A (en) * 2013-11-26 2014-02-26 中建二局第三建筑工程有限公司 Method of hoisting super high-rise building electrochemical large-diameter rises along with progress of main structure

Also Published As

Publication number Publication date
CN104895174A (en) 2015-09-09

Similar Documents

Publication Publication Date Title
CN104895174B (en) The construction method of heavy caliber rain sewage conduct assembled modular construction
CN103205978B (en) High-permeability zone under-water-level elevator foundation pit open caisson moulding bed construction method
CN104631440B (en) A kind of existing large-section in-situ concrete pile strength core increases foundation pit supporting construction and constructional method
CN206376276U (en) A kind of prefabricated pipe gallery
CN105937196B (en) A kind of roadbed peg board formula spells wide structure and construction method
CN102434717B (en) Construction method of joist steel pipe-jacking work pit
CN108842819B (en) Urban rail transit cable line tunnel construction method
CN207512745U (en) A kind of caisson device and its foundation pit structure
CN103343544A (en) Construction method for large-scale open caisson
CN102995659B (en) Method for constructing from central area to periphery of ultra-large type underground engineering
CN104727302B (en) Board wall cast-in-place construction technique between a kind of friction pile stake
CN104563146A (en) Construction method for open caisson engineering of fixed and direct burial type rainwater and sewage pumping station
CN110671131A (en) Loess tunnel substrate reinforcing structure and method based on high-pressure jet grouting pile
CN108560536A (en) The continuous piling wall construction method of Soil-cement
CN106894422A (en) Complex environment deep foundation pit supporting construction method
CN208702421U (en) The tunnel support structure of existing pile foundation building is worn under a kind of
CN108035379B (en) Comprehensive pipe gallery and construction method thereof
CN105953078A (en) Protection device and protection method of high-pressure gas pipeline
CN211258631U (en) Loess tunnel basement reinforcement construction structure based on high pressure jet grouting pile
CN114411756A (en) Construction method and construction device for water-rich sand layer subway station open excavation foundation pit without precipitation
CN110552371A (en) Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method
CN102561362A (en) Construction method for foundation pit supporting by dynamic compaction replacement of muddy soil
CN104695417B (en) A kind of manufacture method of grouting behind shaft or drift lining broken stone pile
CN204690912U (en) Heavy caliber rain sewage conduct assembling modular construction
CN113863268B (en) Construction and debugging process for fabricated sewage treatment station of epidemic prevention emergency engineering

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Xie Yongcheng

Inventor before: Wang Xinquan

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20160704

Address after: 350800, Fujian District, Minqing, Fuzhou Business Plaza A District 2

Applicant after: SHENZHOU CONSTRUCTION GROUP CO., LTD.

Address before: Gongshu District Shi Xiang Road Hangzhou city Zhejiang province 310015 and Hangzhou Road intersection C Wanda Plaza office building room 1901

Applicant before: Hangzhou Jiang Run Science and Technology Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160824

Termination date: 20210602