CN104895064A - Deep cement mixing pile construction process - Google Patents

Deep cement mixing pile construction process Download PDF

Info

Publication number
CN104895064A
CN104895064A CN201510221604.3A CN201510221604A CN104895064A CN 104895064 A CN104895064 A CN 104895064A CN 201510221604 A CN201510221604 A CN 201510221604A CN 104895064 A CN104895064 A CN 104895064A
Authority
CN
China
Prior art keywords
pile
mixer
limit
pile construction
cement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510221604.3A
Other languages
Chinese (zh)
Inventor
沈建东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201510221604.3A priority Critical patent/CN104895064A/en
Publication of CN104895064A publication Critical patent/CN104895064A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a deep cement mixing pile construction process. The process at least comprises steps of pile testing, sampling and mixing; in the mixing process, the sinking speed of an agitator is 0.38-0.75 m/min; a mortar pump is started in the sinking process for spraying while rotating; and the water flushing is stopped. In the mixing process, the rising speed of the agitator is 0.3-0.5 m/min; and in the rising process, the mortar pump reversely rotates while spraying. The process has such advantages as short construction period, low manufacturing cost and prominent benefit, is wide in application prospect, and is prominent in effect on soft soil.

Description

A kind of deep cement-mixed pile construction technology
Technical field:
The present invention relates to a kind of engineering construction process, be specifically related to a kind of deep cement-mixed pile construction technology.
Background technology:
Soil-cement mixed pile foundation is current widely used foundation treatment technology, is characterized in friction, noiselessness in ground stabilization process, to soil without extruding of leaning to one side, little to closing on Influence on Architecture, can comparatively fast come into operation after process.But in work progress, how effectively to control the pile quality of agitation pile, guarantee that the effect for the treatment of of soft foundation has just become us to need the problem explored and study.
Summary of the invention:
The object of this invention is to provide a kind of deep cement-mixed pile construction technology, at least comprise test pile, setting-out, whipping step, in whipping process, mixer subsidence velocity 0.38-0.75m/min, opens mortar pump in sinking watching, and spray limit, limit rotates, and stops bath.
In whipping process, mixer hoisting velocity is 0.3-0.5m/min, in lifting process, and the spray limit despining of mortar pump limit.
When repeating to stir, can accelerate rotary speed, but be no more than 1.8m/min, spray pressure is not less than 0.5kPa.
The advantages such as construction period of the present invention short, cheap, remarkable benefit, have broad application prospects, to weak soil Be very effective.
Detailed description of the invention:
A kind of deep cement-mixed pile construction technology, main construction sequence is as follows:
Accurately release control stake according to drawing, make the stake position of agitation pile according to control stake, and adopt bamboo let to indicate the stake position of every stake, facilitate mixer contraposition.
Cement mixing pile tackles pile foundation performance after marching into the arena checks, and debugs, and guarantees that duty is good; Various instrument being demarcated simultaneously, preventing from being forbidden to cause quality accident because measuring in work progress.
After pre-blending machine is in place, start mixer motor, loosen crane rope, just mixer stirs along saddle and cuts soil sinking, the speed of sinking can be controlled (being generally 0.38m/min-0.75m/min) by the current monitoring table of motor, and operating current should not be greater than 40A.Opening mortar pump when mixer sinks is pressed in ground by cement paste, crosses spray limit and rotates.When mixer stirs sinking in advance, should not wash by water.Do not allow during stirring to occur that stirring pile crown does not arrive the phenomenon that stake top slurries have mixed.Once stop slurry for some reason, for preventing broken pile and lacking slurry, mixer should sink to stopping the following 0.5m of slurry point, to be restored for lifting of whitewashing again after slurry.
Configuration cement paste before boring under mixer, cement paste is prepared in strict accordance with design mixture proportion, and the various raw material strict measurement such as cement, Admixture, admixture, guarantee that match ratio is accurate.Mixing time is determined by test process, cement paste with mix with, stir without agglomerate, occur that the cement paste of initial set must not use.The cement slurry volume at every turn stirred slightly more than the consumption of a pile, should treat that mud jacking is front by cement paste correct copy aggregate bin.
After mixer sinks to arriving projected depth, opening mortar pump and cement paste is pressed in soil layer, limit spray limit despining, promoting mixer (being generally 0.3m/min-0.5m/min) in strict accordance with designing the hoisting velocity determined simultaneously.Pile will control the hoisting velocity of mixer, makes continuous uniform, to control grouting amount, ensures to stir, and simultaneous pumping must be continuously.
Repeat to stir up and down
After when mixer is promoted to the end face absolute altitude of the design reinforcement degree of depth, stir for making weak soil and cement paste, rotation limit, Dou mixer limit is sunk in soil again, again mixer spray is lifted out ground, so just completes the construction of an agitation pile to the design reinforcement degree of depth.
Essentials for Construction Control:
1., before pumps water mud, with all pipelines of clean water, guarantee that pipeline is without clogging, pipeline should be kept moistening, in order to defeated slurry simultaneously.
2. the perpendicularity deviation of agitation pile is not more than 1%, and the plan-position deviation of stake is not more than 5cm.For guaranteeing that cement mixing pile pile body verticality meets code requirement, an outstanding vertical on axle of stirrer frame, carries out by the distance measured between vertical line and drilling rod the verticality controlling pile body.
3. before mud jacking, cement paste can not be emanated, and the match ratio that cement paste will be determined in strict accordance with test pile is configured, and before mud jacking, cement constantly stirs in grey pulp grinder.
4. for guaranteeing that cement paste match ratio is accurate, scene should weigh cement weight in strict accordance with the match ratio determined, measure the volume of water.Be equipped with cement paste hydrometer at the scene, if special messenger measures cement paste water/binder ratio simultaneously.
5. bore under first time and must adopt low-grade rotation when carrying brill, prevent running into hard formation and twist into two parts drilling rod or damage drill bit, can accelerate rotary speed when stirring again, spray pressure is not less than 0.5kPa.But even for guaranteeing pile quality, speed-raising is unsuitable too fast, hoisting velocity should more than 1.8m/min, otherwise there will be that pile body cement amount is not enough or cement is uneven in soil, causes strength of the mixing pile uneven.
6. should not wash by water when mixer stirs sinking in advance, when run into hard formation resistance comparatively large or creep into slower time, mixer deadweight should be increased and then start water booster system pressurization, or input slurries limit, limit is stirred and is crept into.
7. for guaranteeing the pile quality at the bottom of stake top and stake, carry creep into can at the bottom of stake and stake top bit stop 30s, and drill bit continue whitewashing.

Claims (3)

1. a deep cement-mixed pile construction technology, at least comprises test pile, setting-out, whipping step, it is characterized in that, in whipping process, mixer subsidence velocity 0.38-0.75m/min, opens mortar pump in sinking watching, and spray limit, limit rotates, and stops bath.
2. a kind of deep cement-mixed pile construction technology according to claim 1, it is characterized in that: in whipping process, mixer hoisting velocity is 0.3-0.5m/min, in lifting process, the spray limit despining of mortar pump limit.
3. a kind of deep cement-mixed pile construction technology according to claim 1, is characterized in that: when repeating to stir, can accelerate rotary speed, but be no more than 1.8m/min, spray pressure is not less than 0.5kPa.
CN201510221604.3A 2015-04-30 2015-04-30 Deep cement mixing pile construction process Pending CN104895064A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510221604.3A CN104895064A (en) 2015-04-30 2015-04-30 Deep cement mixing pile construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510221604.3A CN104895064A (en) 2015-04-30 2015-04-30 Deep cement mixing pile construction process

Publications (1)

Publication Number Publication Date
CN104895064A true CN104895064A (en) 2015-09-09

Family

ID=54027993

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510221604.3A Pending CN104895064A (en) 2015-04-30 2015-04-30 Deep cement mixing pile construction process

Country Status (1)

Country Link
CN (1) CN104895064A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5631928A (en) * 1979-08-20 1981-03-31 Ryoji Morita Constructing method for soil pile
CN101864765A (en) * 2010-06-30 2010-10-20 东南大学 Two-way stirring based SMW construction method and tri-axial stirring equipment
CN102021906A (en) * 2010-12-16 2011-04-20 河南省新开元路桥工程咨询有限公司 Method for reinforcing soft soil foundation at deep mixing pile
CN103422497A (en) * 2013-08-21 2013-12-04 国家电网公司 Method for reinforcing soft soil foundation by using cement-soil mixing pile

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5631928A (en) * 1979-08-20 1981-03-31 Ryoji Morita Constructing method for soil pile
CN101864765A (en) * 2010-06-30 2010-10-20 东南大学 Two-way stirring based SMW construction method and tri-axial stirring equipment
CN102021906A (en) * 2010-12-16 2011-04-20 河南省新开元路桥工程咨询有限公司 Method for reinforcing soft soil foundation at deep mixing pile
CN103422497A (en) * 2013-08-21 2013-12-04 国家电网公司 Method for reinforcing soft soil foundation by using cement-soil mixing pile

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郝一鸣: "《深层水泥土搅拌桩在地基处理中的应用》", 《门窗》, no. 10, 20 October 2014 (2014-10-20), pages 113 *

Similar Documents

Publication Publication Date Title
CN106368214B (en) A kind of casing formula cement mixing method at pile operation method
CN108914929A (en) A kind of cement mixing pile construction method
CN101660309B (en) Construction method of multi-drill high-pressure jet agitation based anti-seepage reinforcing equipment
CN105239561A (en) Long spiral mix spray pre-grouting press concrete post-inserted steel reinforcement cage cast-in-place pile construction process
CN103556631A (en) Pile-forming operation method for stirring pile
CN107059960A (en) A kind of indoor full automatic simulates the experimental rig of cement mixing method
CN108396737A (en) The Soil-cement pile material of Strengthening Wet soil base
CN105040683A (en) Informatization construction method for cement mixing piles
CN204551447U (en) Mucky soil cement mixing pile drill bit of drilling machine
CN104480932B (en) Construction method of cement mixing pile for saline-alkali sludge soft foundation
KR102234214B1 (en) Fast permeating method and system for grouting of weak ground
CN109914401A (en) Superficial layer of sand or saturation layer of sand cement-soil stirring pile construction device and method
CN101649614A (en) Variable-diameter multi-direction anchor pile
Ibragimov Characteristics of Soil Grouting by Hydro-Jet Technology.
CN113605381A (en) Polypropylene fiber reinforced cement soil mixing pile and construction process thereof
CN105780762A (en) Chiseling-free pile head construction method
CN104895064A (en) Deep cement mixing pile construction process
CN206815410U (en) A kind of experimental rig of indoor full automatic simulation cement mixing method
CN100374657C (en) Construction method employing threaded stirring shaft to decrease ambient foundation deformation
CN103939020B (en) A kind of antiwind drilling bit of deep submerged agitation pile
CN101487251A (en) Construction method of premixing pouring soil cement pile used for strengthening ground and pile produced thereby
CN104452752A (en) Construction method for cement mixing pile in high-dense hardening clay layer
CN212358264U (en) Micro-disturbance cutting stirring grouting system
CN100363562C (en) Preventing plate with spreading and deep layer rotating spraying mixture head with diffusion preventing plate and guniting mouth
CN203531921U (en) Deep hole grouting device used for strengthening tunnel and underground engineering tunnel face

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150909

WD01 Invention patent application deemed withdrawn after publication