CN104894976A CN201510243948.4A CN201510243948A CN104894976A CN 104894976 A CN104894976 A CN 104894976A CN 201510243948 A CN201510243948 A CN 201510243948A CN 104894976 A CN104894976 A CN 104894976A
Authority
CN
China
Prior art keywords
concrete
bridge surface
vibrating beam
paving
deck paving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510243948.4A
Other languages
Chinese (zh)
Inventor
孙志远
盖青山
唐小军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority to CN201510243948.4A priority Critical patent/CN104894976A/en
Publication of CN104894976A publication Critical patent/CN104894976A/en
Pending legal-status Critical Current

Links

Landscapes

  • Road Paving Machines (AREA)

Abstract

The invention discloses a method for paving a bridge surface through four-machine linkage. The method comprises the following steps: (1), arranging a vibrating beam track: respectively and uniformly burying a plurality of track supporting bars on the inner side of the bridge surface along with an anti-collision guardrail base of the bridge surface, and paving the vibrating beam track on the track supporting bars; (2), pouring and paving concrete: transporting the concrete to the bridge surface by utilizing a concrete pump vehicle, firstly performing primary vibrating leveling, and then paving a vibrating beam, purifying syrup and performing fine leveling by utilizing a full-automatic roll shaft paver; (3), troweling the finished bridge surface: troweling the finished bridge surface by adopting a troweling machine after the initial set of the concrete until a top surface is smooth; (4), paving and maintaining the bridge surface: moisturizing and maintaining the troweled bridge surface by adopting an atomizer in an atomizing manner after the initial set of the concrete, and paving geotextile and performing water spraying maintenance after the concrete is troweled; (5), roughening the top surface of the paved bridge surface: after the strength of the concrete achieves 50-70%, removing epidermal laitance by adopting a milling machine, so that a rough surface is exposed. The method disclosed by the invention is high in mechanization level, the whole bridge surface pavement is formed at a time, the bridge surface is flawless, and the planeness is good.

Description

A kind of " four machine interlocks " deck paving method
Technical field:
The invention belongs to a kind of architectural construction technology, particularly a kind of " four machine interlocks " deck paving method.
Background technology:
Deck paving is the important component part of bridge vehicle-driving, and it bears the pressure of wheel, impact and shear action, and its quality and useful life longevity are directly connected to the safety of driving, comfortableness and bridge durability.At present, unit in charge of construction generally adopts vibration fine strain of millet+manually wipe one's face+artificial hacking construction technology to carry out deck paving, and this technique often there will be that seam is many, poor flatness, bridge floor cracking and the common quality defect such as end face is smooth.
Summary of the invention:
Object of the present invention is just to overcome above-mentioned the deficiencies in the prior art, and provides a kind of " four machines interlocks " deck paving method, and the method mechanization degree is high, the one-shot forming of deck paving view picture and free from flaw, and planeness is good.
As above conceive, technical scheme of the present invention is: a kind of " four machine interlocks " deck paving method, is characterized in that: comprise the steps:
1. vibrating beam track is set: along bridge floor anticollision barrier base respectively to pre-buried laying even inside bridge floor many rail supported muscle, vibrating beam track laying is on track brace rod;
2. build concrete of mating formation: utilize concrete mixer by concrete conveyance to bridge floor, first by leveling of shaking at the beginning of vibrating beam, recycle full-automatic roll shaft paver paving vibrating beam, carry slurry, essence is flat;
3. face troweling is received: adopt the floating receipts face of finisher after concrete initial set, until end face is smooth;
4. deck paving maintenance: adopt nebulizer moisture-keeping maintaining after concrete initial set, concrete-face closure terminates rear laying geotextiles watering maintenance;
5. end face dabbing of mating formation process: after concrete arrives intensity 50-70%, adopts milling machine to remove epidermis laitance, exposes rough surface.
Above-mentioned concrete vibrating beam orbit elevation of top surface is the elevation control of deck paving concrete.
Above-mentioned concrete vibrating beam orbit adopts [10 reinforcing bars.
Above-mentioned along bridge floor anticollision barrier base respectively to inner side every 0.5 meter lay one rail supported muscle.
Above-mentioned rail supported muscle is made up of two that are embedded on bridge deck vertical Φ 16 reinforcing bars and horizontal Φ 16 reinforcement welding.
The present invention has following advantage and good effect:
1, the present invention is by vibrating beam, full-automatic roll shaft paver and the mutual combination acts synergistically of finisher, and mechanization degree is high, can save a large amount of labour, improves construction precision.And make the one-shot forming of deck paving view picture, without longitudinal constuction joint, good integrity.
2, the present invention adopts finisher to smear pressure receipts face, and pave-load layer top of concrete smears the real free from flaw of densification, and planeness is good.
3, vibrating beam track of the present invention repeatedly can have enough to meet the need use, and material is fully used.
Accompanying drawing illustrates:
Fig. 1 is process chart of the present invention.
Detailed description of the invention:
As shown in the figure: a kind of " four machine interlocks " deck paving method, comprises the steps:
One, concrete vibrating beam orbit 1 is set: along anticollision barrier base respectively to 0.5 meter of pre-buried laying rail supported muscle inside bridge floor 2, brace rod is by Φ 16 reinforcement fabrication, for ensureing that vibrating beam track has enough rigidity and stability, lay one brace rod for every 0.5 meter, one brace rod is made up of two that are embedded on bridge deck vertical Φ 16 reinforcing bars and horizontal Φ 16 reinforcement welding.After the pre-buried end of vertical reinforcement of brace rod, in strict accordance with the altitude data welding transverse reinforcement that measurement class provides.Concrete vibrating beam orbit is laid on the transverse reinforcement of a welding, and its elevation of top surface is the elevation control of deck paving concrete.
Described concrete vibrating beam orbit adopts [10 reinforcing bars.
Two, build concrete of mating formation: concrete mixer is by concrete conveyance to bridge floor, and hand fit evenly shakeouts, leveling of shaking at the beginning of first vibrating beam, more full-automatic roll shaft paver 4 spreads vibrating beam 3, carries slurry, essence is put down.
Three, receive face troweling: adopt the floating receipts face of driving finisher 5 after concrete initial set, first carry out longitudinal direction twice, then carry out that transverse direction twice is just flat just smears, while frontier inspection survey planeness of wiping one's face, planeness carries out careful wiping one's face until end face is smooth after meeting specification again.
Four, deck paving maintenance: adopt nebulizer moisture-keeping maintaining after concrete initial set, concrete-face closure terminates rear laying geotextiles watering maintenance, and curing time is no less than 7 days.
Five, end face dabbing of mating formation process: after concrete arrives intensity 70%, adopts milling machine 6 laterally to remove epidermis laitance, exposes rough surface.

Claims (5)

1. " four machine interlocks " deck paving method, is characterized in that: comprise the steps:
1. vibrating beam track is set: along bridge floor anticollision barrier base respectively to pre-buried laying even inside bridge floor many rail supported muscle, vibrating beam track laying is on track brace rod;
2. build concrete of mating formation: utilize concrete mixer by concrete conveyance to bridge floor, first by leveling of shaking at the beginning of vibrating beam, recycle full-automatic roll shaft paver paving vibrating beam, carry slurry, essence is flat;
3. face troweling is received: adopt the floating receipts face of finisher after concrete initial set, until end face is smooth;
4. deck paving maintenance: adopt nebulizer moisture-keeping maintaining after concrete initial set, concrete-face closure terminates rear laying geotextiles watering maintenance;
5. end face dabbing of mating formation process: after concrete arrives intensity 50-70%, adopts milling machine to remove epidermis laitance, exposes rough surface.
2. one according to claim 1 " four machine interlocks " deck paving method, is characterized in that: above-mentioned concrete vibrating beam orbit elevation of top surface is the elevation control of deck paving concrete.
3. one according to claim 1 " four machine interlocks " deck paving method, is characterized in that: above-mentioned concrete vibrating beam orbit adopts [10 reinforcing bars.
4. one according to claim 1 " four machines interlock " deck paving method, is characterized in that: above-mentionedly lay one rail supported muscle along bridge floor anticollision barrier base respectively to every 0.5 meter of inner side.
5. one according to claim 1 " four machine interlocks " deck paving method, is characterized in that: above-mentioned rail supported muscle is made up of two that are embedded on bridge deck vertical Φ 16 reinforcing bars and horizontal Φ 16 reinforcement welding.
CN201510243948.4A 2015-05-14 2015-05-14 Method for paving bridge surface through four-machine linkage Pending CN104894976A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510243948.4A CN104894976A (en) 2015-05-14 2015-05-14 Method for paving bridge surface through four-machine linkage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510243948.4A CN104894976A (en) 2015-05-14 2015-05-14 Method for paving bridge surface through four-machine linkage

Publications (1)

Publication Number Publication Date
CN104894976A true CN104894976A (en) 2015-09-09

Family

ID=54027906

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510243948.4A Pending CN104894976A (en) 2015-05-14 2015-05-14 Method for paving bridge surface through four-machine linkage

Country Status (1)

Country Link
CN (1) CN104894976A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105401520A (en) * 2015-12-25 2016-03-16 广东冠粤路桥有限公司 Integrated layer whole-width construction device for light truss type bridge and construction method of construction device
CN105544407A (en) * 2016-02-23 2016-05-04 中国水利水电第十一工程局有限公司 Multifunctional integrated machine for secondary concrete paving and plastering of elevated bridge box beam
CN112458910A (en) * 2020-11-13 2021-03-09 唐山市星斗路桥机械有限公司 Mid-span outer membrane concrete paving process
CN113202031A (en) * 2021-04-19 2021-08-03 上海城建市政工程(集团)有限公司 Method for paving ultrahigh-performance concrete on bridge steel bridge deck

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1821491A (en) * 2006-03-20 2006-08-23 长安大学 Wag-resisting concrete bridge surface paving method
JP2009299418A (en) * 2008-06-17 2009-12-24 Kajima Corp Retreating and removing method and retreating device for travelling work vehicle for cantilever construction
CN102966037A (en) * 2012-12-14 2013-03-13 黑龙江省交通科学研究所 Installation and construction process of bridge expansion joints
CN104153296A (en) * 2014-07-29 2014-11-19 中建四局第五建筑工程有限公司 Method for increasing bridge deck pavement flatness and comb-shaped form board used by same

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1821491A (en) * 2006-03-20 2006-08-23 长安大学 Wag-resisting concrete bridge surface paving method
JP2009299418A (en) * 2008-06-17 2009-12-24 Kajima Corp Retreating and removing method and retreating device for travelling work vehicle for cantilever construction
CN102966037A (en) * 2012-12-14 2013-03-13 黑龙江省交通科学研究所 Installation and construction process of bridge expansion joints
CN104153296A (en) * 2014-07-29 2014-11-19 中建四局第五建筑工程有限公司 Method for increasing bridge deck pavement flatness and comb-shaped form board used by same

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105401520A (en) * 2015-12-25 2016-03-16 广东冠粤路桥有限公司 Integrated layer whole-width construction device for light truss type bridge and construction method of construction device
CN105544407A (en) * 2016-02-23 2016-05-04 中国水利水电第十一工程局有限公司 Multifunctional integrated machine for secondary concrete paving and plastering of elevated bridge box beam
CN112458910A (en) * 2020-11-13 2021-03-09 唐山市星斗路桥机械有限公司 Mid-span outer membrane concrete paving process
CN113202031A (en) * 2021-04-19 2021-08-03 上海城建市政工程(集团)有限公司 Method for paving ultrahigh-performance concrete on bridge steel bridge deck

Similar Documents

Publication Publication Date Title
CN105755915B (en) The plate-type unballasted track bed plate construction methods of CRTS III
CN104894976A (en) Method for paving bridge surface through four-machine linkage
CN105401520B (en) A kind of light truss formula bridge united layer full width constructing device and its construction method
CN102277817B (en) Asphalt wave roads construction method
CN107143111A (en) A kind of construction method of abrasion-proof terrace
EP3635176B1 (en) Method for producing a paving area
CN102966037A (en) Installation and construction process of bridge expansion joints
CN110172887A (en) One-step forming construction method for large-width large-thickness water stabilization layer
CN106381980A (en) Floor tile paving process
CN112282294A (en) Construction method of steel fiber wear-resistant terrace
CN106638183A (en) Urban rail transit assembly board type high precision rail base cast-in-place construction method
CN102071614B (en) Stone block road construction method and guiding rule for same
CN111608080A (en) Five-machine linkage bridge deck pavement construction method
CN103835205A (en) Construction method for road edge stone sliding mode
CN113005908B (en) Installation method of overline overbridge
CN102852066A (en) Precise installation method for expansion joint of concrete roadway type steel
CN111074703B (en) Maintenance method for uneven settlement of roadbed of embedded track steel groove type ballast bed
CN105735079A (en) Treatment method for bituminous pavement transverse reflection cracks
CN205295940U (en) Light -duty truss -like bridge wholeization layer full width construction equipment
CN102926322B (en) Construction method, hoisting tool, location tire and location support for installing comb-tooth-shaped expansion joint
CN106192699A (en) A kind of homophase out-phase road surface cutting method and device
CN203923832U (en) A kind of continuous reinforced concrete pavement
Chaddha et al. A study on the rigid pavement construction, joint and crack formation
CN204174495U (en) Embedded reinforcement bitumen layer transformation cement concrete pavement structure
CN113338103B (en) Premixed foamed asphalt in-situ cold regeneration base layer and bottom surface layer construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150909

WD01 Invention patent application deemed withdrawn after publication