CN104878914B CN201510141542.5A CN201510141542A CN104878914B CN 104878914 B CN104878914 B CN 104878914B CN 201510141542 A CN201510141542 A CN 201510141542A CN 104878914 B CN104878914 B CN 104878914B
Authority
CN
China
Prior art keywords
straight line
key
scaffold
region
longitudinal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510141542.5A
Other languages
Chinese (zh)
Other versions
CN104878914A (en
Inventor
张生雨
张鹏飞
刘学民
张树根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201510141542.5A priority Critical patent/CN104878914B/en
Publication of CN104878914A publication Critical patent/CN104878914A/en
Application granted granted Critical
Publication of CN104878914B publication Critical patent/CN104878914B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Movable Scaffolding (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Foundations (AREA)

Abstract

The present invention relates to a kind of be based on oblique abnormal load full hall scaffold erection method, step includes:(1), first find out in region in longitudinal straight line and region laterally straight line;(2), find out the horizontal straight line of edge longitudinal straight line and edge;(3), determine intersecting point coordinate;(4), key scaffold is set up on intersecting point coordinate;(5), key vertical rod is connected with key horizon bar;(6), determine the centre spot of support scaffolding;(7), according to centre spot, set up support scaffolding;(8), vertically and horizontally horizon bar connects for supported rod erecting and support;(9), vertical bridging is arranged on key scaffold and horizontal cross brace full hall scaffold is set up and finished.Present invention simplicity scaffold position is clearly demarcated, can quickly set up, and it is convenient to reinforce, safe and reliable.What the method effectively solved full hall scaffold under rhymed formula concave plane load action sets up a difficult problem.

Description

Based on oblique abnormal load full hall scaffold erection method
The application is number of patent application is 201310317898.0, and patent name is full based on irregularly distributed load ground Hall scaffold building method, the applying date be 2013.07.25, divisional application.
Technical field
The invention belongs to scaffold field, especially one kind are based on oblique abnormal load full hall scaffold erection method.
Background technology
Present public building is more to trend towards large space, Suresh Kumar.In its building construction process, floor and roofing Construction is frequently necessary to set up steel pipe full hall scaffold, is designed constructing according to the horizontal layout form of the load being supported.Steel Pipe full hall scaffold plane form has:(1) in plane it is entirely vertically and horizontally vertical checked spun antung full hall scaffold, this is by supporting Beam slab longitudinally determined with quadrature transverse in the plane, be modal;(2) two parts or multiple portion are divided on architectural plane Point, the beam slab of each section is all vertically and horizontally perpendicular in the plane, but needs between two parts to connect jail with brace Gu;(3) on architectural plane, most of full hall scaffold is vertically and horizontally perpendicular, and the scaffold of individual sites is full with major part Hall scaffold is non-orthogonal, only need to connect indivedual scaffolds and most of scaffold.The above scaffold is mainly with just Based on friendship well word is set up, run into load in the plane completely in when being randomly distributed, said method just cannot be carried out solving rhymed formula.Such as High-altitude dissipates when spelling spherical reticulated shells, due to ball node in the plane not point-blank, therefore when supporting ball node, foot handss Frame just cannot design according to conventional vertically and horizontally orthogonal mode in the plane and set up;The expiring of cast-in-situ steel reinforced concrete camber beam Hall scaffold or full hall bracing frame also cannot design according to conventional vertically and horizontally orthogonal mode and set up.
Content of the invention
It is an object of the invention to overcoming the deficiencies in the prior art, provide one kind based on the full hall foot handss of oblique abnormal load Frame erection method, the method is easy, and scaffold position is clearly demarcated, can quickly set up, and it is convenient to reinforce, safe and reliable, effectively solving lotus Carry be in the plane when being randomly distributed completely scaffold set up problem.
The present invention solves its technical problem and is achieved through the following technical solutions:
One kind is based on oblique abnormal load full hall scaffold erection method, and its method comprises the steps:
(1), first in the plane in the load being randomly distributed of scaffold building or line load region, find out area Horizontal straight line in longitudinal straight line and region in domain;
(2), outside the load being randomly distributed or line load region, find out edge longitudinal straight line and edge is horizontal Straight line;
(3) laterally straight-line intersection coordinate and edge longitudinal straight line and side, are determined in region in longitudinal straight line and region The intersecting point coordinate of the horizontal straight line of edge;
(4), key scaffold is set up on intersecting point coordinate, key scaffold includes key vertical rod and key transverse and longitudinal water Flat bar, each intersecting point coordinate is respectively provided with key vertical rod, laterally straight line and edge longitudinal in longitudinal straight line and region in region It is respectively provided with key transverse and longitudinal horizon bar on the horizontal straight line of straight line and edge;
(5), key vertical rod is connected with key horizon bar right-angle coupler, is connected with rotary buckle between key horizon bar;
(6), in the space of key scaffold, determine the centre spot of support scaffolding;
(7), according to centre spot, set up support scaffolding, support scaffolding includes supported rod erecting and supports in length and breadth To horizon bar, vertically and horizontally horizon bar is connected nearby with the key transverse and longitudinal horizon bar of key scaffold for the support of support scaffolding;
(8), vertically and horizontally horizon bar is connected with right-angle coupler for the supported rod erecting of support scaffolding and support, supports vertically and horizontally Horizon bar is connected with key transverse and longitudinal horizon bar rotary buckle;
(9), vertical bridging and horizontal cross brace, vertical bridging and horizontal cross are arranged on key scaffold Support rotary buckle is fixed on intersecting therewith key scaffold, and full hall scaffold is set up and finished.
And, in described region, longitudinal straight line is orthogonal orthogonal with straight line horizontal in region or oblique.
And, described edge longitudinal straight line straight line horizontal with edge is orthogonal orthogonal or oblique.
And, described support scaffolding includes four vertical rods supported above and supports horizon bar in length and breadth.
Advantages of the present invention and having the beneficial effect that:
This is based on oblique abnormal load full hall scaffold erection method simplicity scaffold position clearly, can quickly set up, It is convenient to reinforce, safe and reliable.What the method effectively solved full hall scaffold under rhymed formula concave plane load action sets up a difficult problem.
Brief description
Fig. 1 sets up schematic diagram for the present invention;
Fig. 2 is the A portion enlarged drawing (key scaffold connection support scaffolding) of Fig. 1.
Specific embodiment
Below by specific embodiment, the invention will be further described, and following examples are descriptive, is not limit Qualitatively it is impossible to protection scope of the present invention is limited with this.
One kind is based on oblique abnormal load full hall scaffold erection method, and its method comprises the steps:
(1), first in the plane in the load being randomly distributed of scaffold building or line load region, find out area Horizontal straight line in longitudinal straight line 3 and region in domain;In region longitudinal straight line orthogonal orthogonal with straight line horizontal in region or Oblique or multistage broken line.
(2), outside the load being randomly distributed or line load region, find out edge longitudinal straight line and edge is horizontal Straight line;Edge longitudinal straight line straight line horizontal with edge is orthogonal orthogonal or oblique.
(3), determine in region in longitudinal straight line and region that laterally straight line and edge longitudinal straight line and edge are laterally straight The intersecting point coordinate of line;If being multistage broken line, then also must determine break coordinate.
(4), key scaffold 5 is set up on intersecting point coordinate, key scaffold includes key vertical rod 8 and key transverse and longitudinal Horizon bar 6, each intersecting point coordinate is respectively provided with key vertical rod, and in longitudinal straight line and region in region, laterally straight line and edge are indulged It is respectively provided with key transverse and longitudinal horizon bar on the horizontal straight line of straight line and edge;If multistage broken line, then break is also provided with standing Bar;Vertical pole's span along straight line is laid according to design requirement;
(5), key vertical rod is connected with key horizon bar right-angle coupler, is connected with rotary buckle between key horizon bar;
(6), in the space of key scaffold, determine the centre spot of support scaffolding;
(7), according to centre spot, set up support scaffolding 4, support scaffolding includes supported rod erecting 9 and supports vertical Transverse horizontal bar 7, vertically and horizontally horizon bar and the key transverse and longitudinal horizon bar of key scaffold connect nearby for the support of support scaffolding Connect;Support scaffolding includes four or four vertical rods supported above and support horizon bar in length and breadth.
(8), vertically and horizontally horizon bar is connected with right-angle coupler for the supported rod erecting of support scaffolding and support, supports vertically and horizontally Horizon bar is connected with key transverse and longitudinal horizon bar rotary buckle;
(9), vertical bridging 2 and horizontal cross brace 1 are arranged on key scaffold, vertical bridging and level are cut Knife support rotary buckle is fixed on intersecting therewith key scaffold, and full hall scaffold is set up and finished.
Full hall scaffold of the present invention is included key scaffold and is combined with support scaffolding two parts, adds level simultaneously Bridging and vertical bridging, maintain stablizing of scaffold jointly.Wherein key scaffold is the trunk of whole full hall scaffold, Support scaffolding then acts primarily as the effect undertaking load.

Claims (2)

1. a kind of based on oblique abnormal load full hall scaffold erection method it is characterised in that:The method comprises the steps:
(1), first find out in region in the plane in the load being randomly distributed of scaffold building or line load region Horizontal straight line in longitudinal straight line and region;
(2), find out the horizontal straight line of edge longitudinal straight line and edge outside the load being randomly distributed or line load region;
(3) the laterally intersecting point coordinate of straight line and edge longitudinal straight line and edge, are determined in region in longitudinal straight line and region The laterally intersecting point coordinate of straight line;Longitudinal straight line and the mutual oblique of straight line horizontal in region in region;Edge longitudinal straight line and edge Laterally straight line is mutual oblique;
(4), key scaffold is set up on intersecting point coordinate, key scaffold includes key vertical rod and key transverse and longitudinal level Bar, each intersecting point coordinate is respectively provided with key vertical rod, and in longitudinal straight line and region in region, laterally straight line is straight with edge longitudinal It is respectively provided with key transverse and longitudinal horizon bar on the horizontal straight line of line and edge;
(5), key vertical rod is connected with key horizon bar right-angle coupler, is connected with rotary buckle between key horizon bar;
(6), in the space of key scaffold, determine the centre spot of support scaffolding;
(7), according to centre spot, set up support scaffolding, support scaffolding includes supported rod erecting and supports vertically and horizontally water Flat bar, vertically and horizontally horizon bar is connected nearby with the key transverse and longitudinal horizon bar of key scaffold for the support of support scaffolding;
(8), vertically and horizontally horizon bar is connected with right-angle coupler for the supported rod erecting of support scaffolding and support, supports vertically and horizontally level Bar is connected with key transverse and longitudinal horizon bar rotary buckle;
(9), vertical bridging and horizontal cross brace are arranged on key scaffold, vertical bridging and horizontal cross brace are used Rotary buckle is fixed on intersecting therewith key scaffold, and full hall scaffold is set up and finished.
2. according to claim 1 based on oblique abnormal load full hall scaffold erection method it is characterised in that:Described Support scaffolding include four vertical rods supported above and support horizon bar in length and breadth.
CN201510141542.5A 2013-07-25 2013-07-25 Based on oblique abnormal load full hall scaffold erection method Active CN104878914B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510141542.5A CN104878914B (en) 2013-07-25 2013-07-25 Based on oblique abnormal load full hall scaffold erection method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201510141542.5A CN104878914B (en) 2013-07-25 2013-07-25 Based on oblique abnormal load full hall scaffold erection method
CN201310317898.0A CN103343610B (en) 2013-07-25 2013-07-25 Ground full-space scaffold erecting method based on irregular distribution load

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201310317898.0A Division CN103343610B (en) 2013-07-25 2013-07-25 Ground full-space scaffold erecting method based on irregular distribution load

Publications (2)

Publication Number Publication Date
CN104878914A CN104878914A (en) 2015-09-02
CN104878914B true CN104878914B (en) 2017-03-01

Family

ID=49278435

Family Applications (3)

Application Number Title Priority Date Filing Date
CN201510139874.XA Active CN104878913B (en) 2013-07-25 2013-07-25 It is based on orthogonal full hall scaffold erection method
CN201510141542.5A Active CN104878914B (en) 2013-07-25 2013-07-25 Based on oblique abnormal load full hall scaffold erection method
CN201310317898.0A Active CN103343610B (en) 2013-07-25 2013-07-25 Ground full-space scaffold erecting method based on irregular distribution load

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201510139874.XA Active CN104878913B (en) 2013-07-25 2013-07-25 It is based on orthogonal full hall scaffold erection method

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201310317898.0A Active CN103343610B (en) 2013-07-25 2013-07-25 Ground full-space scaffold erecting method based on irregular distribution load

Country Status (1)

Country Link
CN (3) CN104878913B (en)

Family Cites Families (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CS199830B1 (en) * 1975-05-04 1980-08-29 Eduard Popelek Scaffolding for construction of circular,round or polygonal ground plan
US4122646A (en) * 1977-06-08 1978-10-31 Research-Cottrell, Inc. Equilateral derrick structure
JPH07111094B2 (en) * 1991-12-27 1995-11-29 小野 辰雄 Prop device
JPH08319716A (en) * 1995-05-25 1996-12-03 Murata Mach Ltd Trestle and trestle assembling method
JPH08326293A (en) * 1995-06-01 1996-12-10 Murata Mach Ltd Constituting member for assembly frame
US6652194B2 (en) * 2001-04-16 2003-11-25 Osl Offshore Systems & Deck Machinery, Llc Jack-up mobile offshore drilling units (MODUs) and jacking method and apparatus
CN100545367C (en) * 2007-08-02 2009-09-30 中国建筑第七工程局有限公司 The net-shell net-rack overhanging high altitude bulk construction method of bolted spherical node
CN100480481C (en) * 2007-10-30 2009-04-22 浙江大学 Quadrangular pyramid sphere net case falsework-free constructing and mounting method and hoisting machine tool
CN101372865A (en) * 2008-09-17 2009-02-25 浙江中成建工集团有限公司 Stay suspender multispan beam structure highly hollow-out formwork system and construction method
CN101435224A (en) * 2008-12-24 2009-05-20 河南中美铝业有限公司 High altitude suspension selecting bulk construction method of barrel shell type bolt ball node network frame
CN101718115B (en) * 2009-11-20 2011-06-22 山东宏跃网架钢结构有限公司 Method for mounting wide-span cylindrical reticulated shell
JP4936085B2 (en) * 2009-12-14 2012-05-23 Krh株式会社 Construction structure of rod-shaped member
CN101956426B (en) * 2010-04-13 2013-04-24 天津大学 Multi-hinge-line lifting-up spherical surface reticulated shell structure and construction method thereof
CN102182303B (en) * 2011-03-31 2012-07-04 西安建筑科技大学 Oblique annular closed structural template supporting method
CN102322134B (en) * 2011-06-14 2013-09-11 杭州二建建设有限公司 Method for determining difference in bearing capacities of fastener-type full space support frame and full space scaffold
CN202969887U (en) * 2012-12-21 2013-06-05 中铁一局集团有限公司 Bidirectional-stress full-house scaffold for structure construction of subway stations

Also Published As

Publication number Publication date
CN104878913B (en) 2017-03-15
CN104878913A (en) 2015-09-02
CN103343610A (en) 2013-10-09
CN103343610B (en) 2015-08-19
CN104878914A (en) 2015-09-02

Similar Documents

Publication Publication Date Title
CN104453197B (en) High Large Cantilever concrete structural steel shape supports platform
CN104480922B (en) Space truss formwork system and construction method thereof
CN105350639B (en) A kind of facade intersects grid structure peripheral frame and its installation method
CN104372967B (en) A kind of cooling stack inclined strut structure and construction method thereof
CN103603491B (en) Method for erecting beam plate post-cast strip template support frame
CN207700527U (en) A kind of building column that steel pipe is combined with batten plate
CN104878914B (en) Based on oblique abnormal load full hall scaffold erection method
CN205116768U (en) Superelevation layer instrument formula protection platform of encorbelmenting
CN203808249U (en) Column stirrup cage assembly for beam-column joint core region
CN202745062U (en) Foundation pit supporting structure closely adjacent to built-up underground structure
CN104120874A (en) Assembly type scaffold and wall connecting piece
CN204152527U (en) The combined type preliminary bracing system of wall multiple-arch tunnel in implicit expression
CN204001665U (en) A kind of scaffold assembling wall-connecting piece
CN203034615U (en) Novel outer sleeve tube type connecting node of cold-bending rectangular steel tube column and H-shaped steel girder
CN204212385U (en) Scaffold strengthened by truss
CN214739832U (en) Scaffold connecting and reinforcing structure
CN215168024U (en) Zigzag floor support node
CN204152199U (en) A kind of movable stencil sub-truss
CN205116776U (en) Support access structure
CN207988457U (en) It is protected outside skyscraper staggered floor balcony and operating platform sets up structure
CN203257080U (en) Adjustable overhang supporting device for building construction
CN207646865U (en) A kind of reinforced concrete frame structure
CN206468003U (en) A kind of Xin Jiamo guard bar structures
CN208441442U (en) A kind of outer steel mould constructing operation frame
CN205742936U (en) Steel pipe scaffold structure transfer can being controlled

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant