CN104868465A - Power system grid structure reconfiguration and optimization method based on fuzzy chance constraint - Google Patents

Power system grid structure reconfiguration and optimization method based on fuzzy chance constraint Download PDF

Info

Publication number
CN104868465A
CN104868465A CN201410073048.5A CN201410073048A CN104868465A CN 104868465 A CN104868465 A CN 104868465A CN 201410073048 A CN201410073048 A CN 201410073048A CN 104868465 A CN104868465 A CN 104868465A
Authority
CN
China
Prior art keywords
fuzzy
rack
optimization
grid structure
power system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410073048.5A
Other languages
Chinese (zh)
Other versions
CN104868465B (en
Inventor
李文云
梁海平
朱涛
顾雪平
赵川
刘艳
李玲芳
张雪丽
梁铃
马腾飞
张丹
叶华
左智波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YUNNAN ELECTRIC POWER DISPATCH CONTROL CENTER
North China Electric Power University
Original Assignee
YUNNAN ELECTRIC POWER DISPATCH CONTROL CENTER
North China Electric Power University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YUNNAN ELECTRIC POWER DISPATCH CONTROL CENTER, North China Electric Power University filed Critical YUNNAN ELECTRIC POWER DISPATCH CONTROL CENTER
Priority to CN201410073048.5A priority Critical patent/CN104868465B/en
Publication of CN104868465A publication Critical patent/CN104868465A/en
Application granted granted Critical
Publication of CN104868465B publication Critical patent/CN104868465B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/003Load forecast, e.g. methods or systems for forecasting future load demand

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Quality & Reliability (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Power Engineering (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a power system grid structure reconfiguration and optimization method based on fuzzy chance constraints, which belongs to the field of power system security defense and restoration control. The power system grid structure reconfiguration and optimization method comprises a grid structure reconfiguration and optimization model establishing module and a grid structure reconfiguration and optimization algorithm module. The power system grid structure reconfiguration and optimization method adopts triangular fuzzy variables for representing line operation time and restoration reliability, defines an restoration reliability index for evaluating performance of a target grid structure, considers unit start-up time limit, establishes a grid structure reconfiguration and optimization model based on fuzzy chance constraints under the framework of the fuzzy chance constraints, adopts a solution method of combining fuzzy simulation, a crossed particle swarm optimization algorithm and a Dijkstra algorithm, optimizes and determines unit start-up sequence, and reconfigures a restoration grid structure with shortest reconfiguration time and highest reliability. According to the power system grid structure reconfiguration and optimization method based on fuzzy chance constraints, the fuzziness of operation time and restoration reliability when the line is put into operation at the grid structure reconfiguration stage is reasonably considered, the optimized and determined optimal grid structure reconfiguration scheme takes both system reconfiguration speed and safety requirements into account, and the power system grid structure reconfiguration and optimization method has more practical significance.

Description

Based on the electric power system rack reconstruction and optimization method of Fuzzy Chance Constraint
Technical field
The present invention relates to a kind of electric power system rack reconstruction and optimization method based on Fuzzy Chance Constraint, belong to power system security defence and recover control field.
Technical background
The large-scale blackout constantly occurred in recent years shows, have a power failure on a large scale be modern power systems must faced by serious threat.Along with expanding day and society the improving constantly supply of electric power dependency degree of electric power system scale, the consequence that large-scale blackout causes is also more and more serious.The main task of rack reconstruction stage makes full use of the isolated mini system recovered previous stage, selects suitable plant stand to be restored and sets of lines to merge and determine the corresponding order that puts into operation, as early as possible for important plant stand power transmission also progressively sets up stable grid structure.The quality of rack reconstruction stage System recover directly has influence on the recovery efficiency of follow-up load restoration and whole electrical network.
The groundwork of current rack reconstruct research is concentrated both ways: the determination of target net and return to the determination of concrete restoration path sequence of target net.Under study for action most using the operating time of circuit as determining that number processes, but the element related to due to rack reconstruction stage and operate numerous, concerning circuit puts into operation, its operating time has uncertainty.This point that had scholar to recognize and random number process will be made the operating time, but random distribution rule is based upon on a large amount of statisticss, and historical data probably produces deviation because data volume is not enough, thus causes result inaccurate.And in conjunction with historical data and relevant operating experience, we are often easier to the scope determined its most probable value and may distribute, this uncertain condition of operating time is more suitable for representing by fuzzy variable, and can well represent its fuzzy behaviour with membership function.Therefore, the operating time is more pressed close to theoretical actual as fuzzy variable process.Equally, recovery reliability when circuit puts into operation also has uncertainty, and different line combination causes the recovery reliability of target net entirety also different, and based on the consideration of security of system, we often wish that the target net formed has high reliability, the also rare research to this respect before.
Summary of the invention
For above-mentioned background, the present invention considers its operating time and the uncertainty recovering reliability when circuit puts into operation, and proposes a kind of electric power system rack reconstruction and optimization method based on Fuzzy Chance Constraint, to obtain the more reasonable reconfiguration scheme of rack accurately.
For achieving the above object, what this rack reconstruction and optimization method comprised rack reconstruction and optimization model sets up module and rack reconstruction and optimization algoritic module.
The foundation of so-called rack reconstruction and optimization model, triangular fuzzy variable is assumed to be by line loop operation time and recovery reliability, define the recovery reliability index of whole rack on this basis, utilization Fuzzy Chance Constrained Programming is theoretical, successfully obtain within its startup time limit with unit and start power supply for constraint, reach with the recovery of rack in reconstitution time short as far as possible reliability and be up to target, set up the fuzzy chance constrained model of rack reconstruction and optimization, to being met the rack reconfiguration scheme of certain confidence level.
So-called rack reconstruction and optimization algorithm is combined into by shortest path first, fuzzy simulation and particle cluster algorithm three part of intersecting.Namely according to the model of aforementioned foundation and the feature of rack reconstruct, the method being applicable to this model solution is proposed, adopt the intersection particle cluster algorithm based on fuzzy simulation to be destination node optimization recovery to be restored order, adopt classical dijkstra's algorithm to be node determination restoration path to be restored simultaneously.
In addition, the present invention carries out trend verification to the recovery scheme obtained by algorithm optimization, only has to be verified by trend or the scheme of each regulated quantity in allowed band is just considered as feasible.
The concrete steps of the described electric power system rack reconstruction and optimization method based on Fuzzy Chance Constraint are as follows:
Step one, represents the fuzzy uncertain amounts such as the line loop operation time related in invention with triangular fuzzy variable;
Step 2, the recovery reliability defining node to be restored also determines the recovery reliability index of whole rack further;
Step 3, successfully obtains with unit and starts power supply for constraint, reach and be up to target, set up the rack reconstruction and optimization model based on Fuzzy Chance Constraint with the recovery of rack in reconstitution time short as far as possible reliability within its startup time limit;
Step 4, solving of rack reconstruction and optimization model, further:
(1) determine black starting-up power supply and destination node to be restored and initial parameter is set, forming N pindividual primary;
(2) loop iteration is carried out to particle, i=1:N p;
(3) get current particle i, call the restoration path of dijkstra's algorithm search each destination node under this recovery order;
(4) to machine group node, fuzzy simulation inspection Fuzzy Chance Constraint is adopted;
(5) judging whether by inspection, is carry out (6), otherwise, utilize mutation operation to upgrade particle, return step (3) afterwards;
(6) trend verification is carried out to the particle by verification;
(7) judge whether iteration completes all particles; Be carry out (8), otherwise return step (2);
(8) fuzzy simulation calculates the fitness of particle, and determines individual extreme value p best, global extremum g bestand the extreme value place p of their correspondences xbest, g xbest;
(9) utilize cross-iteration to operate to upgrade particle;
(10) maximum times reaching iteration is judged whether; Be carry out (11), otherwise return step (2);
(11) export the node restoration path of optimal particle and correspondence, namely obtain final rack reconfiguration scheme.
Accompanying drawing explanation
Fig. 1 is the flow chart of the electric power system rack reconstruction and optimization method based on Fuzzy Chance Constraint of the present invention.
Fig. 2 is the rack reconfiguration scheme of IEEE30 node system optimum.
Embodiment
Below in conjunction with accompanying drawing, the present invention will be further described in detail.
The foundation of 1 rack reconstruction and optimization model
The present invention represents the operating time of circuit with triangular fuzzy variable, and in conjunction with operating experience, for certain recoverable circuit, its operating time is between optimistic estimate value t 1with pessimistic estimated value t 3between, and t 2be its most probable recovery operation time, this ambiguity of operating time can represent with triangular fuzzy variable, and its membership function is such as formula shown in (1).Ambiguity for other parameters related in literary composition all can describe by similar method and process.
In system rack reconstruction stage, for each node to be restored, think that the node of process is completely reliably on its restoration path, it recovers the recovery reliability that reliability depends primarily on contained circuit on restoration path, and think that the recovery reliability of every bar circuit is relatively independent on path, so can be the reliability of the series system be made up of restoration path by the recovery certainty equivalence of node, namely to destination node i to be restored, if the recovery reliability of jth bar circuit be on its restoration path so the recovery reliability of node i is:
R ~ i = Π j = 1 N i R ~ ij - - - ( 2 )
Wherein N ifor the circuit number on node i restoration path.
And then for whole target net, it is that in rack, each destination node recovers the average of reliability within the system reconfiguration time that its index recovering reliability is evaluated in definition.Concrete definition is as follows:
R ~ = Σ i = 1 N 1 R ~ i N 1 = Σ i = 1 N 1 Π j = 1 N i R ~ ij N 1 - - - ( 3 )
Be wherein N 1the number of destination node to be restored.
The fuzzy chance constrained model that the present invention sets up is as follows:
max f ‾ - - - ( 4 )
Pos { R ~ T ~ ≥ f ‾ } ≥ β - - - ( 5 )
Pos { 0 ≤ Σ k = 1 N g t ~ gk ≤ T ~ g } ≥ α - - - ( 6 )
T ~ = Σ m = 1 N E t ~ m - - - ( 7 )
In above-mentioned model, formula (4) represents that optimization aim is the value maximizing target function target function value required by formula (5) ensures it is target function the maximum of getting when confidence level is at least β, wherein, for the time that whole rack reconstructs, namely from rack reconstruct, obtain the time starting power supply to all destination nodes, formula (7) is defined it, and the present invention's hypothesis only drops into a circuit in each step of rack reconstruction stage, so namely composition recovers the fuzzy operation time of each circuit of rack sum, the operating time due to circuit is Triangular Fuzzy Number, so also be Triangular Fuzzy Number.N efor recovering the number of lines that rack comprises.Formula (6) guarantees moment that every platform unit is restored to be no more than it, and to start the confidence level that time limit reaches be α, wherein, and t gkfor the fuzzy operation time of kth bar circuit on the restoration path of machine group node g, for the fuzzy startup time limit of unit g, be also set as Triangular Fuzzy Number, N gfor the circuit number on machine group node g restoration path to be restored, N gfor target machine group node number to be restored.
In addition, the present invention carries out trend verification to the recovery scheme obtained by algorithm optimization, only has to be verified by trend or the scheme of each regulated quantity in allowed band is just considered as feasible.
2 rack reconstruction and optimization algorithms
According to the feature of rack reconstruction stage, on the basis of known recovery target, need to obtain the recovery order of each node and corresponding restoration path.Rack reconstruction and optimization algorithm of the present invention, its main feature be by fuzzy simulation with intersect particle cluster algorithm and combine, be destination node optimization recovery to be restored order, adopt classical dijkstra's algorithm to be node determination restoration path to be restored simultaneously.
2.1 shortest path first
When optimization is reconstructed to recovery rack, utilize intersect the particle cluster algorithm recovery order different for destination node generates time, also need to determine concrete restoration path according to the recovery situation of network and node location.Especially, when adopting fuzzy simulation processing target function and constraints, the restoration path of node to be restored must be determined.So adopt the shortest path first-dijkstra's algorithm of classical topological sum circuit weights Network Based to carry out optimizing to path.
Because intercropping fuzzy number process during line loop operation is embodied by the present invention in target function and constraints condition of opportunity, thus only using the charging reactive power of every bar circuit as circuit weights.When system exists many loop lines, then get the idle minimum circuit of charging.During search, using black starting-up power supply or the initial stage black starting-up mini system starting point as each search.Especially, be accelerating algorithm search procedure, after searching restoration path for a destination node, the weights of the circuit be on restoration path be set to 0.Such process can not have an impact to choosing of restoration path.
2.2 fuzzy simulation
Fuzzy simulation relates to two aspects: the fuzzy system constraint in testing model and the For Fuzzy Objective Function in transaction module.
Due to the present invention set up model in constraints condition of opportunity for be machine group node, so employing dijkstra's algorithm be, after each destination node to be restored searches out restoration path, only fuzzy simulation inspection is carried out to machine group node to be restored.Specific practice is as follows:
(1) from fuzzy variable alpha levels cut set in produce clear variable t equably gk', T g';
(2) clear variable is brought in the middle of constraints condition of opportunity formula (6), if meet, thinks that this restoration path is feasible;
(3) if do not meet, then repeat step (1), (2) N time, N is the number of times of fuzzy simulation;
(4) if still constraint can not be met after N simulation, then think that machine group node can not start in the time limit at it and has efficient recovery under the restoration path obtained by this recovery order;
(5) for infeasible situation, the particle of representation node recovery order is carried out variation amendment, specific practice will not change to first by original position, i.e. priority restores by the position of machine group node in particle of inspection, is positioned at node before this node then slow astern position successively;
(6) particle after making a variation is adopted dijkstra's algorithm determination restoration path again, and repeat step (1) ~ (3).If now still return infeasible through N simulation, then think that this unit can not start in the time limit at it and recover;
(7) after to the aforementioned machine group node priority restores do not met the demands, if occur, other units do not meet the situation of constraints, then still adopt said method, repeat step (5), (6);
(8) if after multiple exchanging position, still cannot ensure that all units to be restored meet fuzzy constraint, then start the principle in time limit, the unit that the optimum choice warm start stage recovers according to meeting multicomputer as far as possible, for starting the unit recovered in the time limit, cold-start phase can not being arranged in and recovering.Only adopt dijkstra's algorithm for its search shortest path is as restoration path, and no longer consider the constraint in unit starting time limit, namely no longer fuzzy simulation inspection is carried out to it.
After all nodes to be restored are checked by fuzzy constraint, process For Fuzzy Objective Function, specific practice is as follows:
(1) put f ‾ = - ∞ ;
(2) from fuzzy variable β horizontal cut set on evenly produce clear variable R ij', t m';
(3) clear variable is brought in formula (4-4), formula (4-6) and formula (4-8), try to achieve target function value f, if f &OverBar; < f , Then put f &OverBar; = f ;
(4) repeat step (2), (3) N time, N is fuzzy simulation number of times;
(5) return be the maximum of the target function of trying to achieve.
2.3 intersection particle cluster algorithms
In algorithm, particle adopts integer coding, and particle is initialized as the difference recovery order of node.The fitness function instructing particle to carry out iteration renewal in algorithm is the target function in formula (4), namely
F = max f &OverBar; - - - ( 8 )
The present invention is by particle J irespectively with global extremum position g xbestwith individual extreme value place p xbestcarry out interlace operation, obtain new particle J i'.For 5 meshed networks, suppose that node 1 is for black starting-up power supply, all the other be node to be restored, currently carry out jth time iteration, wait to intersect the particle J of renewal 1(j)=[2 53 4], now global extremum position g xbest=[2 34 5], individual extreme value place p xbest=[5 23 4], the cross method so adopted is as follows:
First at g xbestrandom selecting intersection region C in=[2 34 5] 1=[4 5], afterwards by intersection region C 1be added to J 1before (j), and delete J 1at C in (j) 1the numeral of middle appearance, obtains particle J 1" (j)=[4 52 3]; Then by particle J 1" (j) and individual extreme value place p xbest=[5 23 4] intersect, and first choose intersection region C 2=[34], afterwards by intersection region C 2be added to J 1" before (j), and delete J 1" at C in (j) 1the numeral of middle appearance, finally obtains new particle: J 1' (j)=[3 45 2].
The detailed implementation of the present invention is as follows:
Verify the present invention with IEEE30 bus test system, as shown in Figure 2, this system comprises 6 generators to system wiring, 40 circuits.
Wherein, machine group node 1 is as black starting-up power supply, and machine group node to be restored is [213222327], and load bus to be restored is [6101215192130]; Be limited to Triangular Fuzzy Number (10,15,20) when supposing the warm start of unit 27, the warm start time limit of all the other each units is (25,30,35); The operating time of each bar circuit is Triangular Fuzzy Number (2,2.5,3), the recovery reliability of each circuit is set as follows: wherein the recovery reliability of circuit 3-4,4-6,8-28,10-20,10-17,22-24 is (0.9,0.95,1), the recovery reliability of all the other each circuits is (0.7,0.85,1).
Other optimum configurations are as follows: particle number N p=10, particle cluster algorithm allows the maximum times N of iteration max=60, times N=1000 of fuzzy simulation, confidence level α, β are 0.95.During trend verification, be resumed exerting oneself of unit and get 30% of maximum output.
Adopt the present invention to be optimized rack reconfiguration scheme, finally obtain optimum rack reconfiguration scheme as shown in Figure 2.In Fig. 2, solid line is the circuit forming target net, the target net that the part that solid line connects is namely optimum.Table 1 is depicted as the recovery order of destination node and concrete restoration path.
Table 1 system node recovery order and restoration path
According to the rack restructuring procedure that table 1 provides, can find out:
(1) the warm start time limit due to machine group node 27 is shorter, so under the restriction of chance constraint, the result obtained by algorithm is preferentially recovered unit 27, and other units also all obtain startup power supply within its warm start time limit, achieves and recovers generating to greatest extent.The fuzzy expected value of the optimal objective rack reconstitution time of final acquisition is 40min.
(2) target net finally obtained contains part circuit 4-6,10-20 and the 22-24 with higher reliability of setting in advance, these circuits is included into the reason of target net, does a simple analysis for circuit 10-20.For destination node 19, as can be seen from the network site residing for it, the destination node 10 or 15 that can be closed on by it is recovered it by path 10-20-19 or 15-18-19.So when node 10 and 15 was all restored, only from shortest path, because the weights of path 15-18-19 are less, so this paths is more excellent before node 19.But, what these chapters and sections were sought is have the high rack recovering reliability, circuit 10-20 has higher recovery reliability, so the result obtained by algorithm is preferentially recovered node 10, and select to be recovered node 19 by path 10-20-19, to reaching higher recovery reliability, this is consistent with expected results.The circuit analyzing other high reliability is not included into the reason of rack, and the first is higher due to the weights of circuit own, is not adopted based on during dijkstra's algorithm searching route; It two is because node is recovered the recovery reliability that certainty equivalence is series system by this model, although so certain shortest path contains the higher circuit of recovery reliability sometimes, cause because circuit on path is more destination node to recover reliability and reduce and abandoned.
By analyzing, describe the present invention by the line loop operation time with recover reliability to do fuzzy number process be reasonable.The method proposed not only can effectively according to recovery situation and the topological structure of electrical network, reasonably optimize the recovery order of node, start power supply for unit as much as possible provides and meet certain confidence level, the target net simultaneously making optimization obtain has higher recovery reliability, is conducive to the safe operation of rack reconstruction stage system.In addition, the theoretical frame that the present invention proposes has certain versatility, can be used to process that rack reconstruction stage relates to that other have the uncertain factor of ambiguity, also can further consider this thinking expansive approach other stage to black starting-up.

Claims (5)

1., based on an electric power system rack reconstruction and optimization method for Fuzzy Chance Constraint, what it is characterized in that the method comprises rack reconstruction and optimization model sets up module and rack reconstruction and optimization algoritic module.
2. the electric power system rack reconstruction and optimization method based on Fuzzy Chance Constraint according to claim 1, it is characterized in that, rack reconstruction and optimization model set up module, triangular fuzzy variable is assumed to be by line loop operation time and recovery reliability, define the recovery reliability index of whole rack on this basis, utilization Fuzzy Chance Constrained Programming is theoretical, successfully obtain within its startup time limit with unit and start power supply for constraint, reach with the recovery of rack in reconstitution time short as far as possible reliability and be up to target, set up the fuzzy chance constrained model of rack reconstruction and optimization, to being met the rack reconfiguration scheme of certain confidence level.
3. the electric power system rack reconstruction and optimization method based on Fuzzy Chance Constraint according to claim 1, is characterized in that, rack reconstruction and optimization algoritic module, is combined into by shortest path first, fuzzy simulation and particle cluster algorithm three part of intersecting.Namely according to the model of aforementioned foundation and the feature of rack reconstruct, the method being applicable to this model solution is proposed, adopt the intersection particle cluster algorithm based on fuzzy simulation to be destination node optimization recovery to be restored order, adopt classical dijkstra's algorithm to be node determination restoration path to be restored simultaneously.
4. the electric power system rack reconstruction and optimization method based on Fuzzy Chance Constraint according to claim 1, it is characterized in that, trend verification is carried out to the recovery scheme obtained by algorithm optimization, only has and to be verified by trend or the scheme of each regulated quantity in allowed band is just considered as feasible.
5., based on an electric power system rack reconstruction and optimization method for Fuzzy Chance Constraint, it is characterized in that, described concrete steps are as follows:
Step one, represents the fuzzy uncertain amounts such as the line loop operation time related in invention with triangular fuzzy variable;
Step 2, the recovery reliability defining node to be restored also determines the recovery reliability index of whole rack further;
Step 3, successfully obtains with unit and starts power supply for constraint, reach and be up to target, set up the rack reconstruction and optimization model based on Fuzzy Chance Constraint with the recovery of rack in reconstitution time short as far as possible reliability within its startup time limit;
Step 4, solving of rack reconstruction and optimization model, further:
(1) determine black starting-up power supply and destination node to be restored and initial parameter is set, forming N pindividual primary;
(2) loop iteration is carried out to particle, i=1:N p;
(3) get current particle i, call the restoration path of dijkstra's algorithm search each destination node under this recovery order;
(4) to machine group node, fuzzy simulation inspection Fuzzy Chance Constraint is adopted;
(5) judging whether by inspection, is carry out (6), otherwise, utilize mutation operation to upgrade particle, return step (3) afterwards;
(6) trend verification is carried out to the particle by verification;
(7) judge whether iteration completes all particles; Be carry out (8), otherwise return step (2);
(8) fuzzy simulation calculates the fitness of particle, and determines individual extreme value p best, global extremum g bestand the extreme value place p of their correspondences sbest, g sbest;
(9) utilize cross-iteration to operate to upgrade particle;
(10) maximum times reaching iteration is judged whether; Be carry out (11), otherwise return step (2);
(11) export the node restoration path of optimal particle and correspondence, namely obtain final rack reconfiguration scheme.
CN201410073048.5A 2014-02-26 2014-02-26 Power system rack reconstruction and optimization method based on Fuzzy Chance Constraint Expired - Fee Related CN104868465B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410073048.5A CN104868465B (en) 2014-02-26 2014-02-26 Power system rack reconstruction and optimization method based on Fuzzy Chance Constraint

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410073048.5A CN104868465B (en) 2014-02-26 2014-02-26 Power system rack reconstruction and optimization method based on Fuzzy Chance Constraint

Publications (2)

Publication Number Publication Date
CN104868465A true CN104868465A (en) 2015-08-26
CN104868465B CN104868465B (en) 2017-12-29

Family

ID=53914099

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410073048.5A Expired - Fee Related CN104868465B (en) 2014-02-26 2014-02-26 Power system rack reconstruction and optimization method based on Fuzzy Chance Constraint

Country Status (1)

Country Link
CN (1) CN104868465B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105610194A (en) * 2016-03-09 2016-05-25 西安交通大学 Power grid timing sequence recovery optimization method of considering potential damage probability of elements
CN106125074A (en) * 2016-08-16 2016-11-16 南京航空航天大学 A kind of antenna aperature method for managing resource based on Fuzzy Chance Constrained Programming
CN107808256A (en) * 2017-11-20 2018-03-16 四川大学 A kind of regional high voltage distribution network based on chance constrained programming turns supplier's method
CN108985561A (en) * 2018-06-08 2018-12-11 天津大学 A kind of active power distribution network isolated island division methods based on chance constraint
CN109149618A (en) * 2018-09-11 2019-01-04 北京交通大学 A kind of alternating current-direct current mixed connection electric system parallel recovery Study on Decision-making Method for Optimization
CN109995028A (en) * 2019-04-09 2019-07-09 国网山东省电力公司济南供电公司 A kind of Distribution Network Failure restoration methods and system based on optimal recovery sequence
CN110264722A (en) * 2019-07-03 2019-09-20 泰华智慧产业集团股份有限公司 The screening technique and system of warping apparatus in information collecting device
CN111628528A (en) * 2020-06-22 2020-09-04 华北电力大学(保定) Method and device for eliminating power flow out-of-limit during wind power participation system recovery
CN111756687A (en) * 2020-05-15 2020-10-09 国电南瑞科技股份有限公司 Defense measure configuration method and system for coping with network attack

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004248340A (en) * 2003-02-10 2004-09-02 Nippon Energy Network Kk Power supply method and power supply system

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004248340A (en) * 2003-02-10 2004-09-02 Nippon Energy Network Kk Power supply method and power supply system

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘艳等: "基于目标固话的网架重构路径优化方法", 《电力***自动化》 *
曾顺奇等: "计及操作时间不确定性的电力***网架重构策略优化", 《电力***自动化》 *
马瑞: "考虑风电随机模糊不确定性的电力***多目标优化调度计划研究", 《电力***保护与控制》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105610194B (en) * 2016-03-09 2018-12-07 西安交通大学 A kind of electric power rack timing recovery optimization method considering element potential damage probability
CN105610194A (en) * 2016-03-09 2016-05-25 西安交通大学 Power grid timing sequence recovery optimization method of considering potential damage probability of elements
CN106125074A (en) * 2016-08-16 2016-11-16 南京航空航天大学 A kind of antenna aperature method for managing resource based on Fuzzy Chance Constrained Programming
CN106125074B (en) * 2016-08-16 2018-11-23 南京航空航天大学 A kind of antenna aperature method for managing resource based on Fuzzy Chance Constrained Programming
CN107808256A (en) * 2017-11-20 2018-03-16 四川大学 A kind of regional high voltage distribution network based on chance constrained programming turns supplier's method
CN108985561B (en) * 2018-06-08 2021-09-07 天津大学 Active power distribution network island division method based on opportunity constraint
CN108985561A (en) * 2018-06-08 2018-12-11 天津大学 A kind of active power distribution network isolated island division methods based on chance constraint
CN109149618A (en) * 2018-09-11 2019-01-04 北京交通大学 A kind of alternating current-direct current mixed connection electric system parallel recovery Study on Decision-making Method for Optimization
CN109995028A (en) * 2019-04-09 2019-07-09 国网山东省电力公司济南供电公司 A kind of Distribution Network Failure restoration methods and system based on optimal recovery sequence
CN109995028B (en) * 2019-04-09 2023-05-12 国网山东省电力公司济南供电公司 Distribution network fault recovery method and system based on optimal recovery sequence
CN110264722A (en) * 2019-07-03 2019-09-20 泰华智慧产业集团股份有限公司 The screening technique and system of warping apparatus in information collecting device
CN111756687A (en) * 2020-05-15 2020-10-09 国电南瑞科技股份有限公司 Defense measure configuration method and system for coping with network attack
CN111628528A (en) * 2020-06-22 2020-09-04 华北电力大学(保定) Method and device for eliminating power flow out-of-limit during wind power participation system recovery

Also Published As

Publication number Publication date
CN104868465B (en) 2017-12-29

Similar Documents

Publication Publication Date Title
CN104868465A (en) Power system grid structure reconfiguration and optimization method based on fuzzy chance constraint
Zhao et al. A model predictive control based generator start-up optimization strategy for restoration with microgrids as black-start resources
CN107317334B (en) A kind of electric system rack reconstructing method and device
CN102928738B (en) Dynamic layer diagnostic device and method of smart power grid fault
Sun et al. An online generator start-up algorithm for transmission system self-healing based on MCTS and sparse autoencoder
CN104466959B (en) Power system critical circuits discrimination method and system
CN102799950B (en) Network of ship reconstruction and optimization method based on particle cluster algorithm
CN103746366B (en) A kind of power system recovery method based on pitch point importance
CN105553869A (en) Method and system for risk balancing for power communication network
CN103279620A (en) Method for restoring sequence and path of unit and simultaneously performing optimization
CN108616124B (en) Power distribution network reconstruction calculation method based on ordered binary decision diagram
CN107808200B (en) Short-time maintenance plan optimization method and device for power distribution network
Li et al. Optimization method of skeleton network partitioning scheme considering resilience active improvement in power system restoration after typhoon passes through
Aziz et al. Two-Stage MILP model for optimal skeleton-network reconfiguration of power system for grid-resilience enhancement
CN113346484B (en) Power distribution network elastic lifting method and system considering transient uncertainty
Pang et al. Two-stage self-healing restoration strategy considering operating performance
CN111030084A (en) Load recovery optimization method considering unit state in system recovery process
CN112152264B (en) Robust theory-based high renewable energy permeability power grid recovery optimization method
CN109103936A (en) Optimal unit starting order calculation method after a kind of electric system is had a power failure on a large scale
Zhao et al. Method to decide a multi-fault rush repair robust strategy in power distribution networks
CN102663227B (en) A kind of Reliability modeling of complicated voting system and calculation method
Hayes et al. Viable computation of the largest Lyapunov characteristic exponent for power systems
Gu Reconfiguration of network skeleton based on discrete particle-swarm optimization for black-start restoration
CN103746406A (en) Configuration method for fast cut back (FCB) thermo power set
CN103413194A (en) Regional power grid planning system containing high permeability intermittent energy and method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171229

Termination date: 20200226

CF01 Termination of patent right due to non-payment of annual fee