CN104863533B - Evaluation device and method of well cementation flushing efficiency - Google Patents

Evaluation device and method of well cementation flushing efficiency Download PDF

Info

Publication number
CN104863533B
CN104863533B CN201510188225.9A CN201510188225A CN104863533B CN 104863533 B CN104863533 B CN 104863533B CN 201510188225 A CN201510188225 A CN 201510188225A CN 104863533 B CN104863533 B CN 104863533B
Authority
CN
China
Prior art keywords
wellbore hole
simulation wellbore
inner core
valve
water tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510188225.9A
Other languages
Chinese (zh)
Other versions
CN104863533A (en
Inventor
王成文
孟仁洲
孟凡昌
徐伟祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Petroleum East China
Original Assignee
China University of Petroleum East China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Petroleum East China filed Critical China University of Petroleum East China
Priority to CN201510188225.9A priority Critical patent/CN104863533B/en
Publication of CN104863533A publication Critical patent/CN104863533A/en
Application granted granted Critical
Publication of CN104863533B publication Critical patent/CN104863533B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B21/00Methods or apparatus for flushing boreholes, e.g. by use of exhaust air from motor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B49/00Testing the nature of borehole walls; Formation testing; Methods or apparatus for obtaining samples of soil or well fluids, specially adapted to earth drilling or wells

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention provides an evaluation device and method of well cementation flushing efficiency. Designed according to the Reynolds number equality theory, the device comprises a simulated well casing, a heating water tank, a power pump and an electromagnetic flowmeter, wherein the simulated well casing mainly comprises an inner barrel and an outer barrel; the inner barrel comprises an inner barrel body, steel screen meshes with different mesh numbers and an inner barrel end cover; the inner barrel can simulate a stratum under the circumstance that the steel screen meshes are covered with filter paper or the inner barrel is filled with quartz sand; the outer barrel can rotate; guide vanes with different forms are designed to simulate a casing pipe. The method is easy to operate, high in comparability and low in workload, can effectively form a filter cake, simulate and evaluate the characteristics of the flushing efficiency under the circumstance that the casing pipe rotates or a spiral centralizer is used, can evaluate the flushing efficiency of flushing fluid for a first interface and a second interface, can evaluate and optimally select the flushing fluid system and design the dosage of the flushing fluid, and is wide in application.

Description

A kind of well cementation flush efficiency evaluating apparatus and method
Technical field
The present invention relates to oil gas well cementing operation field, more particularly to a kind of well cementation flush efficiency evaluating apparatus and evaluation methodology.
Background technology
Well cementation flushing liquor is typically surfactant etc. is added in water or is formed with drilling fluid dilution mixture.Can with isolate Liquid is used simultaneously, but before being located at insulating liquid.The main purpose of flushing liquor be clean the borehole wall and casing wall adhesion drilling fluid and Filter cake, improves well cementation interface cementing strength.When well is crept into, the filter cake of Bao Erren and densification is formed on the easy borehole wall of drilling fluid, Effective control drilling fluid filtration, reduces drilling engineering complex accident.But in well cementation, the drilling well of the borehole wall and casing wall residual Liquid and filter cake can prevent cement mortar and borehole wall directly contact, and are further dehydrated in cement mortar aquation, dry up or powder Change phenomenon, easily microannulus is formed in bore hole annulus interface, so as to reduce interface second contact surface cementing strength, have a strong impact on well cementation Quality, or even cause oil gas water channeling.Well cementation second interface problem is always one difficult problem of long-standing problem casing and cementing, its serious system About oil and gas exploration and developments.Therefore the flush efficiency to drilling fluid and filter cake is effectively improved, being that cement mortar is cementing carries Favourable environment is cleaned for one, is to improve interface cementing strength, it is ensured that the committed step of cementing quality.Flushing liquor to the borehole wall and The cleaning efficiency of the drilling fluid and filter cake of casing wall adhesion will be directly connected to success or not and the cementing quality height of well cementation, most Be related to Oil/gas Well service life and productivity effect eventually, serial well stimulation can be successfully carried out to the Oil/gas Well later stage also has pole Its great impact.
The flush efficiency evaluation methodology for being adopted at this stage mainly has 5 kinds, respectively conical flask method, drilling cuttings post method, large-scale Simulation wellbore hole method, rotating cylinder viscometer method, lab simulation well bore evaluation device etc..
Conical flask method:Conical flask method is using relatively early, relatively simple but also simpler and cruder.Concrete operation step is: 10mL drilling fluids are put into conical flask, are subsequently adding a certain amount of flushing liquor, cover bottle stopper, shake 30 seconds, mixing is poured out from bottle Thing, observes flushing situation.This method use is very easy, but has distinct disadvantage, and its measurement result affected by various factors is not Accurately, the control of strength size is as a result largely rocked, and is rocked strength size and cannot be ensured to unify, it is repeatable Difference, can only simply be observed to flushing situation, and on-the-spot guidance is poor, now using less.
Drilling cuttings post method:500g drilling cuttings is weighed, with mud soak, is made on drilling cuttings, to adhere to certain thickness drilling fluid, is then filled In glass infuser, allow flushing liquor drilling cuttings to be flow through with certain speed, which is rinsed, weigh the quality for rinsing out, calculate and rinse Efficiency.Relative to conical flask method, this method makes great progress, and flush efficiency simply can be calculated, but still Inaccurate, whole experiment process is not enough improved and complex operation.
Large-scale simulation wellbore hole method:Down-hole is simulated by setting up large-scale simulation wellbore hole device and rinses displacement process, but this Kind of method can not intuitively observe evaluations to actual developing result, and test, equipment it is larger, each side requirement is higher, Be not suitable for carrying out laboratory performance evaluation.
Rotating cylinder viscometer method:The method is to be stained with certain thickness drilling fluid in rotating cylinder viscometer outer tube, and one is equipped with cup Quantitative flushing liquor, setting speed, generally 200r/min, spin rinse certain hour observe developing result.The method can be right Developing result is intuitively observed, but is unable to quantitatively characterizing flush efficiency, and flushing process there is also with actual condition it is larger Gap.Therefore, on-the-spot guidance meaning not very big.Chinese utility model patent " well cementation flushing liquor flush efficiency quantitative simulation Evaluating apparatus " (CN203161216U), improve viscometer method, but the experimental situation of device can only be normal temperature and pressure, same to fashionable dress Put effect assessment can not be rinsed to drilling fluid filter cake.
Lab simulation well bore evaluation device:The borehole wall is simulated using artificial sandstone, flush efficiency evaluation experimental is in dynamic analog Carry out in intending pit shaft, in pit shaft, have analog casing and the simulation borehole wall.Be full of initially with drilling fluid and pit shaft pressurize, drilling fluid to Borehole wall dehydration forms filter cake.Then replaced with flushing liquor and rinse drilling fluid, reached and stop certain time of contact replacing, adopt Weight method calculates flush efficiency, has certain directive significance to scene.Such as article " high-temperature high-pressure clay cake agglutination simulating-estimating system The development of system and application " (《Oil instrument》The 37-40 page of the 1st phase of volume 22 in 2008) develop a kind of high-temperature high-pressure clay cake glue Knot simulation and evaluation system, the mud cake quality that wall building under the conditions of various can be formed, affect cementing slurry bonding quality because Element carries out more careful research;Article " a kind of evaluation methodology of tool of cementing preposed flush fluid flush efficiency " (《Drilling fluid and completion Liquid》The 47-48 page of the 6th phase of volume 26 in 2009) using sandstone simulating the flushing process of the borehole wall, simulation wellbore hole, evaluate and rinse The flush efficiency of liquid;Article " developments of DCX well cementation simulation flush efficiency evaluating apparatus " (《Oil drilling technology》2013 the 41st Roll up the 127-129 page of the 3rd phase) develop a kind of DXC well cementation simulation flush efficiency evaluating apparatus;Chinese utility model patent " one Plant cementing fluid flush efficiency evaluating apparatus " (Authorization Notice No.:CN203515574U a kind of small-sized simulation wellbore hole device) has been invented Carry out Simulation evaluation flush efficiency.But current simulation wellbore hole evaluating apparatus and flush efficiency evaluation methodology all exist it is following not Foot:Device design is complicated, and operation is relatively cumbersome, and function is relatively simple;Due to adopting artificial core, make workload larger, Repeatability is limited to, meanwhile, the design of the device is also unfavorable for the filter cake to form uniform compaction;Device can not mould completely Intend real filter cake to be formed and rinse displacement process, evaluation methodology does not have broad applicability.
The content of the invention
It is an object of the present invention to improve problems of the prior art, there is provided a kind of well cementation flush efficiency evaluation dress Put, the device has simple to operate, and comparative is strong, the characteristics of applied widely.
Another object of the present invention is to, there is provided method flushing liquor of cementing the well evaluated using said apparatus, principle It is reliable, it is simple to operate.Preferable flushing liquor system is evaluated according to flush efficiency, flushing liquor can be designed according to the measure of washing time Consumption, has a extensive future.
To solve above technical problem, technical scheme below provided by the present invention.
The present invention according to actual pit shaft and simulation wellbore hole Reynolds number principle, with filter paper and stainless steel mesh or quartz sand Simulated formation, forms filter cake, returns speed in combination with well cementation casing programme and annular space, and the evaluation to flushing liquor of cementing the well is relatively reliable.
A kind of well cementation flush efficiency evaluating apparatus, including simulation wellbore hole, kinetic pump, electromagnetic flowmeter and heating water tank, institute The inlet for stating simulation wellbore hole is connected with simulation wellbore hole liquid feed valve by articulation, and the liquid outlet of the simulation wellbore hole passes through loose joint Head is connected with simulation wellbore hole liquid valve;The import of the heating water tank is provided with heating water tank liquid feed valve, and the heating water tank goes out Mouth is provided with heating water tank liquid valve, and the water tank bottom is provided with water tank exhaust-valve;The heating water tank liquid valve passes through pipeline Be sequentially connected in series with the kinetic pump, the electromagnetic flowmeter and the simulation wellbore hole liquid feed valve, the simulation wellbore hole liquid valve with The water tank liquid feed valve is connected.
The simulation wellbore hole includes simulation wellbore hole outer wall, inner core and outer tube, and the outer tube passes top lid end central authorities, as Liquid outlet, the liquid outlet are connected with liquid valve by bearing, and outer tube is provided with drive plate and is connected with motor, revolve outer tube Turn;The inner core is threadably secured on interior tube stent, its inner hollow, is communicated with the external world by discharge outlet, the inside It is hollow to fill quartz sand;Pressurization mouth is provided with above the simulation wellbore hole outer wall, the pressurization mouth is provided with pressurizing valve, the mould Intend being provided with drain below pit shaft outer wall, the drain is provided with atmospheric valve.Remaining position in addition to the through hole that drilling fluid is flowed through Seal against each other, can be discharged from discharge outlet by the water that filter paper oozes out.
The simulation wellbore hole inner core includes cylinder, screen cloth and inside drum cover.The cylinder wall has made series of parallel inner core The trapezoidal seam of axis, stitches a length of 5-30mm, stitches a width of 0.5~2.5mm, and the gross area of seam accounts for inner core cylinder body outer wall gross area 30- 60%, two hypotenuse angles of trapezoidal seam are designed as 8-12 °, and the big base of trapezoidal seam is located at cylinder body outer wall, the little base of trapezoidal seam Positioned at cylinder inboard wall, it is to avoid quartz sand is spilt in cylinder, while not affecting the formation of filter cake, the screen cloth is a series of different mesh Number stainless steel mesh, scope are placed on outside the inner core between 40~400 mesh, are close to inner core cylinder, solid by the inside drum cover Fixed, the inside drum cover is threadedly secured on the inner core cylinder.
This device can simulated formation in the following manner:One kind is in one metafiltration paper of inner core screen cloth outer covering, by filter paper Carry out simulated formation with different eye mesh screens, filter cake is formed in its surface;It is another kind of varigrained in the filling of inner core hollow space Quartz sand, simulates the stratum of different permeabilities by screen cloth and varigrained quartz sand.
From filter paper and stainless steel mesh simulated formation, can effective control experiment variable, improve the repeatability of experiment And comparative;Design hollow in inner core in simulation wellbore hole, preferably can control to be formed magnitude of pressure differential during filter cake, make to be formed Filter cake compacting it is uniform.
The present invention is by forming a metafiltration cake, simulation well cementation second contact surface flush efficiency, using outer cylinder mould in inner cylindrical surface Intend the first interface flush efficiency of well cementation.Outer tube can rotate, and can be designed with different guide vanes in outer tube inner wall, simulate Sleeve rotating or using under the conditions of spiral centering device, the impact of produced different flow patterns to well cementation flushing liquor flush efficiency.
Experiment is rinsed using the device, flushing liquor carries out the row of returning from the bottom up, is consistent with well cementation displacement process.
Between simulation wellbore hole and actual pit shaft discharge speed, relation is determined according to Reynolds number principle:
In formula:vn、vmThe rate of flow of fluid of respectively actual pit shaft and simulation wellbore hole, unit is m/s;Dn、dnIt is respectively actual Borehole diameter, casing diameter, unit are m;Dm、dmRespectively simulation wellbore hole outer barrel diameter, inner diameter of steel flue;(D-d) it is straight for equivalent Footpath, unit are m;νn、νmFor prototype and the kinematic viscosity of model, m2/s。
According to experimental principle, with same well cementation flushing liquor used in simulation wellbore hole experiment under real well, so νnm, During simulation wellbore hole can be obtained, flow velocity is as follows with flow velocity relation under real well:
vn(Dn-dn)=vm(Dm-dm) (1)。
Flush efficiency η is calculated as follows:
η=(G1-G2)/(G1-G0) × 100% (2).
In formula:G0For inner core weight or outer tube weight, g;
G1Be formed filter cake after inner core together with filter cake weight or adhesion drilling fluid outer tube weight, g;
G2To form weight of outer tube of the inner core of filter cake together with filter cake or adhesion drilling fluid after a period of time is rinsed, g.
According to Reynolds number same principle, and flushing liquor flush efficiency is evaluated using this device, successively including following Step:
The first step, averagely returns speed according to casing programme and annular space, with reference to simulation wellbore hole size, calculates Reynolds number by following formula When identical, simulation wellbore hole returns speed:
vn(Dn-dn)=vm(Dm-dm);
Second step, by adding drilling fluid in simulation wellbore hole and pressurizeing, forms on wall on filter cake or outer tube outer tube and glues After attached drilling fluid, weighing formed the inner core of filter cake or after being stained with drilling fluid outer tube quality G1, g;
3rd step, the simulation wellbore hole calculated using flushing liquor are returned speed to be rinsed, after certain hour, weigh inner core or Quality G of outer tube2, g;
4th step, weighs clean inner core or outer tube quality G0, g;
5th step, calculates flush efficiency η of flushing liquor by following formula:
η=(G1-G2)/(G1-G0) × 100%.
Relative to prior art, the present invention achieves following beneficial effect:
(1) present invention returns row's mode according to down-hole casing programme and flushing liquor and is designed, and experimental result referential is strong, if Meter is succinct, it is easy to accomplish;
(2) present invention utilizes Reynolds number same principle, is not related to reheology model of fluid etc., calculates simple, and principle understands, It is applied widely;
(3) present invention utilizes filter paper and different meshes stainless steel mesh or quartz sand to simulate the ground of different permeabilities Layer, overcomes the deficiency of, high cost, operability difference big using workload during artificial core, with reproducible, comparative it is strong, Advantage simple to operate;
(4) in the present invention, outer tube design can rotate, for simulating impact of the down-hole casing rotation to flush efficiency of cementing the well, Meanwhile, outer tube inner wall can be designed with different guide vanes, to rinsing when being provided with spiral centering device for simulation wellbore hole middle sleeve The impact of efficiency.
Description of the drawings
The present invention is further detailed explanation with reference to the accompanying drawings and detailed description, accompanying drawing only provide with reference to Illustrate to use, be not used to limit the present invention.
Fig. 1 is the pipeline schematic diagram of present invention well cementation flush efficiency evaluating apparatus.
Fig. 2 is the structural representation of simulation wellbore hole in present invention well cementation flush efficiency evaluating apparatus.
Fig. 3 is simulation wellbore hole inner core longitudinal sectional drawing (left side) and seam eye section in present invention well cementation flush efficiency evaluating apparatus Figure (right side).
Fig. 4 designs longitudinal sectional drawing for a kind of guide vane of present invention well cementation flush efficiency evaluating apparatus inner core.
Fig. 5 designs longitudinal sectional drawing for a kind of guide vane of present invention well cementation flush efficiency evaluating apparatus inner core.
In figure:1. simulation wellbore hole;1a. simulation wellbore hole outer walls;1b. inner cores;1c. outer tube;End cap above 1d.;1e. simulates well Cylinder liquid outlet;1f. liquid valves;1g. drive plates;Tube stent in 1h.;1i. inner core cylinders;1j. inside drum covers;1k. stainless steel meshs; 1l. quartz sands;1m. inlets;1n. liquid feed valves;1a1. leakage fluid dram;1a2. pressurization mouths;1a3. drain;1b1. stitches eye;1c1、 1c2. guide vane;2. electromagnetic flowmeter;3. kinetic pump;4. heating water tank;4a. heating water tank liquid feed valves;4b. heating water tank goes out Liquid valve;4c. resistive heaters.
Specific embodiment
As shown in figure 1, present invention well cementation flush efficiency evaluating apparatus, including simulation wellbore hole 1, electromagnetic flowmeter 2, kinetic pump 3 and heating water tank 4, the inlet 1m of simulation wellbore hole be connected with analog casing liquid feed valve 1n by articulation, and simulation wellbore hole goes out Liquid mouth 1e is connected with simulation wellbore hole liquid valve 1f by articulation;The import of heating water tank is provided with heating water tank inlet valve 4a, Heating water tank outlet is provided with heating water tank outlet valve 4b, and water tank bottom is provided with water tank exhaust-valve;Heating water tank liquid valve passes through Pipeline is sequentially connected in series with the kinetic pump 3, electromagnetic flowmeter 2 and simulation wellbore hole liquid feed valve 1n, simulation wellbore hole liquid valve 1f and institute State water tank liquid feed valve 4a to be connected.
As shown in Fig. 2 simulation wellbore hole includes simulation wellbore hole outer wall 1a, inner core 1b and trocar sheath 1c, outer tube 1c passes top Used as liquid outlet 1e, liquid outlet is connected with liquid valve 1f by bearing, and outer tube is provided with drive plate 1g to be come and electricity in lid end 1d central authorities Machine is connected, and rotates outer tube;Inner core 1b is threadably secured on interior tube stent 1h, its inner hollow, by discharge outlet 1a1 with The external world communicates, and quartz sand 1l can be filled inside inner core;Pressurization mouth 1a2 is provided with above simulation wellbore hole outer wall, pressurization mouth is provided with and adds Pressure valve, is provided with drain 1a3 below simulation wellbore hole outer wall, drain is provided with atmospheric valve.In addition to the through hole that drilling fluid is flowed through its Remaining part position seals against each other, and can be discharged from discharge outlet by the water that filter paper oozes out.
Simulation wellbore hole inner core includes cylinder 1i, stainless steel mesh 1k and inside drum cover 1j.Cylinder 1i has been made in series of parallel The seam eye 1b1 of cylinder axis, a length of 50~100mm of seam eye, the seam eye gross area account for the 50% or so of internal barrel body total exterior surface area, seam Eye section is trapezoidal, and two hypotenuse angles are designed as 12 ° or so, and trapezoidal big base should be cylinder inner surface, little base correspondence Cylinder inner surface, it is to avoid quartz sand 1l is spilt in cylinder, while not affecting to form filter cake, stainless steel mesh can choose 40~400 Different meshes between mesh, are placed on outside inner core, are fixed by inside drum cover 1j, and inside drum cover is threadedly secured to the inner core cylinder On.
Flush efficiency or preferred flushing formula of liquid specific embodiment of the test flushing liquor to the stratum borehole wall:
The first step, returns flushing liquor of cementing the well when speed determines experiment according to (1) formula and casing programme and down-hole flushing liquor annular space Proper flow rates;Second step, fills quartz sand in one metafiltration paper of inner core stainless steel mesh outer covering or in its inner hollow;3rd Step, opens simulation wellbore hole liquid feed valve, simulation wellbore hole liquid valve, and drilling fluid is filled it up with pit shaft, closes liquid feed valve, liquid valve;The Four steps, are opened analog casing pressurizing valve, are then connected with nitrogen cylinder, arrange nitrogen pressure to require pressure;Open simulation well Cylinder tapping valve, forms filter cake;5th step, is then shut off pressurizing valve, opens simulation wellbore hole atmospheric valve, liquid valve, to simulation wellbore hole After being vented, atmospheric valve, liquid valve are closed, opening simulation wellbore hole removes inner core and filter cake carries out note of weighing for the first time thereon Record;6th step, simulation wellbore hole and heating water tank, pump, effusion meter etc. are sequentially connected in series, and closed heating water tank liquid feed valve, are gone out Liquid valve;7th step, injects flushing liquor in heating water tank, opens heating water tank liquid feed valve, liquid valve, simulation wellbore hole liquid feed valve, Liquid valve, starts kinetic pump, the filter cake for being formed is rinsed using flushing liquor, makes to reach using effusion meter coutroi velocity and wants Ask;8th step, takes out inner core and filter cake is weighed for the second time and recorded;9th step, calculates flush efficiency according to (2) formula;The Filter paper is reinstalled simulation wellbore hole after record of weighing for the second time by ten steps again, is carried out third time flushing and is weighed;So circulate and record, According to the change calculations flush efficiency of mud cake weight, finally give flushing of the flushing liquor used to simulated formation borehole wall filter cake and imitate Rate.
With same method, the flush efficiency of other flushing liquors, including the flush efficiency of oil base drilling fluid filter cake can be measured Deng.The flushing liquor efficiency surveyed is contrasted, the optimum flushing liquor system of preferable effect.
Determine flushing liquor consumption specific embodiment:
The first step, returns flushing liquor of cementing the well when speed determines experiment according to (1) formula and casing programme and down-hole flushing liquor annular space Proper flow rates;Second step, fills quartz sand in one metafiltration paper of inner core stainless steel mesh outer covering or in its inner hollow;3rd Step, opens simulation wellbore hole liquid feed valve, simulation wellbore hole liquid valve, and drilling fluid is filled it up with pit shaft, closes liquid feed valve, liquid valve;The Four steps, are opened analog casing pressurizing valve, are then connected with nitrogen cylinder, arrange nitrogen pressure to require pressure;Open simulation well Cylinder tapping valve, forms filter cake;5th step, is then shut off pressurizing valve, opens simulation wellbore hole atmospheric valve, liquid valve, to simulation wellbore hole After being vented, atmospheric valve, liquid valve are closed, opening simulation wellbore hole removes inner core and filter cake carries out note of weighing for the first time thereon Record;6th step, simulation wellbore hole and heating water tank, pump, effusion meter etc. are sequentially connected in series, and closed heating water tank liquid feed valve, are gone out Liquid valve;7th step, injects flushing liquor in heating water tank, opens heating water tank liquid feed valve, liquid valve, simulation wellbore hole liquid feed valve, Liquid valve, starts kinetic pump, the filter cake for being formed is rinsed using flushing liquor, makes to reach using effusion meter coutroi velocity and wants Ask;8th step, during flushing, takes out inner sleeve observation flushing situation at set intervals, when efficiency to be rinsed is up to more than 95%, recognizes To rinse well substantially, washing time is recorded;9th step, according to washing time and casing programme, calculates flushing liquor consumption.
Certainly, the above is only one embodiment of the present invention, it should be pointed out that the common skill of the art For art personnel, under the premise without departing from the principles of the invention, some improvements and modifications, these improvements and modifications can also be made Belong within the protection domain of the claims in the present invention.

Claims (1)

1. a kind of well cementation flush efficiency evaluating apparatus, including simulation wellbore hole, electromagnetic flowmeter, kinetic pump and heating water tank, which is special Levy is that the inlet of the simulation wellbore hole is connected with simulation wellbore hole liquid feed valve, the liquid outlet of the simulation wellbore hole by articulation Simulation wellbore hole liquid valve is connected with by articulation;The import of the heating water tank is provided with heating water tank liquid feed valve, described to add Boiler outlet is provided with heating water tank liquid valve, and the water tank bottom is provided with water tank exhaust-valve;The heating water tank liquid valve It is sequentially connected in series with the kinetic pump, the electromagnetic flowmeter and the simulation wellbore hole liquid feed valve by pipeline, the simulation wellbore hole Liquid valve is connected with the water tank liquid feed valve;
The simulation wellbore hole includes simulation wellbore hole outer wall, inner core and outer tube, and the outer tube passes top lid end central authorities, used as going out liquid Mouthful, the liquid outlet is connected with liquid valve by bearing, and outer tube is provided with drive plate and is connected with motor, rotates outer tube;Institute State inner core to be threadably secured on interior tube stent, its inner hollow is communicated with the external world by discharge outlet, and the inner hollow can Filling quartz sand;Pressurization mouth is provided with above the simulation wellbore hole outer wall, the pressurization mouth is provided with pressurizing valve, the simulation wellbore hole Drain is provided with below outer wall, the drain is provided with atmospheric valve;The simulation wellbore hole inner core includes cylinder, screen cloth and inner core Lid;The cylinder wall makes the trapezoidal seam of series of parallel inner core axis, stitches a length of 5-30mm, stitches a width of 0.5~2.5mm, The gross area of seam accounts for inner core cylinder body outer wall gross area 30-60%, and two hypotenuse angles of trapezoidal seam are designed as 8-12 °, and trapezoidal seam is big Base be located at cylinder body outer wall, the little base of trapezoidal seam be located at cylinder inboard wall, it is to avoid quartz sand spills cylinder, at the same do not affect filter The formation of cake, the screen cloth are a series of different meshes stainless steel meshs, and scope is placed on the inner core between 40~400 mesh Outside, is close to inner core cylinder, is fixed by the inside drum cover, and the inside drum cover is threadedly secured on the inner core cylinder;Dress Put by the outer tube analog casing, outer tube can rotate, and outer tube inner wall is designed with guide vane;Simulate ground in the following ways Layer:In the overcoating metafiltration paper of inner core screen cloth, by filter paper and screen cloth come simulated formation, in its surface formation filter cake, or including Cylinder hollow space fills varigrained quartz sand, and the ground of different permeabilities is simulated by screen cloth and different grain size quartz sand Layer.
CN201510188225.9A 2015-04-20 2015-04-20 Evaluation device and method of well cementation flushing efficiency Expired - Fee Related CN104863533B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510188225.9A CN104863533B (en) 2015-04-20 2015-04-20 Evaluation device and method of well cementation flushing efficiency

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510188225.9A CN104863533B (en) 2015-04-20 2015-04-20 Evaluation device and method of well cementation flushing efficiency

Publications (2)

Publication Number Publication Date
CN104863533A CN104863533A (en) 2015-08-26
CN104863533B true CN104863533B (en) 2017-04-19

Family

ID=53909657

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510188225.9A Expired - Fee Related CN104863533B (en) 2015-04-20 2015-04-20 Evaluation device and method of well cementation flushing efficiency

Country Status (1)

Country Link
CN (1) CN104863533B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110107235A (en) * 2019-06-14 2019-08-09 西南石油大学 A kind of compacting of drilling fluid filter cake and cleaning efficiency integration evaluating apparatus and method

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106555581B (en) * 2015-09-23 2020-05-15 中国石油化工股份有限公司 Manufacturing device and manufacturing method of shaft
CN106285526B (en) * 2016-09-23 2019-04-09 中国石油天然气集团公司 Simulate experimental provision and experimental method that Cementing rinses mud cake
CN108240185B (en) * 2016-12-27 2020-05-08 中国石油天然气股份有限公司 Evaluation device and method for well cementation flushing efficiency
CN108590570B (en) * 2018-03-14 2020-05-19 长江大学 Test device and test method for evaluating displacement efficiency of well cementation cement slurry
CN110658094B (en) * 2018-06-29 2022-08-30 中国石油天然气股份有限公司 Evaluation system and evaluation method for cleaning effect of slurry cleaning liquid
CN109406334A (en) * 2018-10-22 2019-03-01 中国石油集团渤海钻探工程有限公司 A method of flushing liquor flush efficiency is evaluated with weight method
CN109577956B (en) 2019-01-08 2023-09-26 中国石油大学(北京) Stratum respiratory effect simulation device and method
CN110965987B (en) * 2019-12-25 2024-07-19 中石化石油工程技术服务有限公司 Well wall reinforcing stability evaluation system
CN111577172B (en) * 2020-05-11 2022-11-04 中国石油天然气股份有限公司 Well cementation flushing fluid flushing efficiency evaluation device and method
CN113882852B (en) * 2020-06-18 2024-05-28 中国石油天然气集团有限公司 Well cementation pad fluid flushing efficiency evaluation device and evaluation method
CN111734405B (en) * 2020-06-29 2023-07-07 中国石油天然气集团有限公司 Device for improving accuracy of mud cake flushing efficiency by pad fluid in well cementation
CN116087434B (en) * 2023-03-13 2024-03-29 中国石油天然气集团有限公司 Testing device and testing method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3494188A (en) * 1967-01-10 1970-02-10 Schlumberger Technology Corp Well logging during drilling
CN201650172U (en) * 2010-01-28 2010-11-24 长江大学 Front flushing fluid evaluator for well cementation
CN202064863U (en) * 2011-06-03 2011-12-07 新疆贝肯能源工程股份有限公司 Evaluation tool of cementing preposed flush fluid
CN203161216U (en) * 2013-04-15 2013-08-28 中国石油天然气集团公司 Quantitative simulation evaluation device of flushing efficiency of well cementing flushing fluid
CN203515574U (en) * 2013-10-21 2014-04-02 中国石油化工股份有限公司 Cementing fluid washing efficiency evaluation device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3494188A (en) * 1967-01-10 1970-02-10 Schlumberger Technology Corp Well logging during drilling
CN201650172U (en) * 2010-01-28 2010-11-24 长江大学 Front flushing fluid evaluator for well cementation
CN202064863U (en) * 2011-06-03 2011-12-07 新疆贝肯能源工程股份有限公司 Evaluation tool of cementing preposed flush fluid
CN203161216U (en) * 2013-04-15 2013-08-28 中国石油天然气集团公司 Quantitative simulation evaluation device of flushing efficiency of well cementing flushing fluid
CN203515574U (en) * 2013-10-21 2014-04-02 中国石油化工股份有限公司 Cementing fluid washing efficiency evaluation device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
DCX固井模拟冲洗效率评价装置的研制;姜增东等;《石油钻探技术》;20130531;第41卷(第3期);127-129 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110107235A (en) * 2019-06-14 2019-08-09 西南石油大学 A kind of compacting of drilling fluid filter cake and cleaning efficiency integration evaluating apparatus and method
CN110107235B (en) * 2019-06-14 2021-03-19 西南石油大学 Drilling fluid filter cake pressing and cleaning efficiency integrated evaluation device and method

Also Published As

Publication number Publication date
CN104863533A (en) 2015-08-26

Similar Documents

Publication Publication Date Title
CN104863533B (en) Evaluation device and method of well cementation flushing efficiency
CN112903961B (en) Using method of device for simulating underground drilling fluid circulation to form mud cakes
CN102518432A (en) Test device capable of simulating plugging of high temperature and high pressure dropping strata
CN103161455B (en) HTHP shale well wall stability evaluation device
CN103352680B (en) Foam based on the integration of pit shaft oil reservoir is handled up sediment outflow experimental facilities and method
CN108240185B (en) Evaluation device and method for well cementation flushing efficiency
CN205538625U (en) Experimental device for be used for detecting and seal scurrying agent cementation intensity
CN103674593A (en) Device and method for simulating waterflood test in fracturing vertical shaft of low-permeability reservoir
CN104849404A (en) Well cementation flushing fluid evaluation device and experiment method thereof based on dynamic mud cake forming
CN105738277B (en) Method for detecting bonding strength of channeling sealing agent
CN104863541B (en) Cemented experimental method in one kind simulation well cementing process
CN106401577A (en) Visual testing device and method for simulating bottom water coning of bottom water gas reservoir gas well
CN103541675A (en) Well cementation flushing fluid evaluation device and method based on principle of identical shearing rate
CN104990776A (en) Device for simulating underground drilling fluid cake forming and flushing fluid flushing
CN104675344A (en) Well cementation simulated flushing efficiency evaluation device
CN201359590Y (en) Sand-layer seepage siltation stimulator
CN104563924B (en) Method for evaluating flushing efficiency of well cementation flushing fluid
CN105547665B (en) Screen pipe sand prevention test device and test method
CN104989348B (en) A kind of sub-prime dispenser and method of simulation field test
CN203515574U (en) Cementing fluid washing efficiency evaluation device
CN110107235A (en) A kind of compacting of drilling fluid filter cake and cleaning efficiency integration evaluating apparatus and method
CN110617018B (en) Device and method for evaluating flushing efficiency of filter cake of well cementation cement injection drilling fluid
CN204703802U (en) Device for evaluating flushing efficiency of well cementation flushing fluid
CN104835405B (en) The experimental method of kill-job during a kind of simulation overflow
CN106285526A (en) Simulation Cementing rinses experimental provision and the experimental technique of mud cake

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170419

Termination date: 20190420