CN104863126B - 采用压浆技术处理大直径钻孔灌注桩塌孔的方法 - Google Patents

采用压浆技术处理大直径钻孔灌注桩塌孔的方法 Download PDF

Info

Publication number
CN104863126B
CN104863126B CN201510318302.8A CN201510318302A CN104863126B CN 104863126 B CN104863126 B CN 104863126B CN 201510318302 A CN201510318302 A CN 201510318302A CN 104863126 B CN104863126 B CN 104863126B
Authority
CN
China
Prior art keywords
bored pile
madjack pipe
hole
collapse hole
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510318302.8A
Other languages
English (en)
Other versions
CN104863126A (zh
Inventor
曹慧
许利东
王晓曙
涂伟
陈明
彭小毅
崔洪
潘延连
王向敏
余琨琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ycih Foundation Engineering Co ltd
Yunnan Construction Engineering Group Co ltd
Yunnan Construction and Investment Holding Group Co Ltd
Original Assignee
YUNNAN CONSTRUCTION ENGINEERING GROUP Co Ltd
YANTAI CONSTRUCTION ENGINEERING FOUNDATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YUNNAN CONSTRUCTION ENGINEERING GROUP Co Ltd, YANTAI CONSTRUCTION ENGINEERING FOUNDATION ENGINEERING Co Ltd filed Critical YUNNAN CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201510318302.8A priority Critical patent/CN104863126B/zh
Publication of CN104863126A publication Critical patent/CN104863126A/zh
Application granted granted Critical
Publication of CN104863126B publication Critical patent/CN104863126B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

采用压浆技术处理大直径钻孔灌注桩塌孔的方法,先在准备吊放到钻孔灌注桩(1)内的钢筋笼(9)内绑扎同心的内圈压浆管(5)和外圈压浆管(6);内圈压浆管和外圈压浆管的下端均超出钢筋笼5~10cm,顶端均超出后续准备浇筑于钻孔灌注桩顶部的承台(3)的顶面0.5~1.0m;钻孔灌注桩发生塌孔后立即清孔,然后将钢筋笼吊放到孔中,向孔中灌注混凝土,待钻孔灌注桩桩体质量趋于稳定后浇筑承台;最后采用高压旋喷施工方法通过内圈压浆管和外圈压浆管注浆至塌孔位置,形成压浆固结体(2),与上部的钻孔灌注桩共同构成复合桩基础,承担上部荷载。本发明可有效解决桥墩基础中的大直径钻孔灌注桩塌孔问题,施工简便快捷。

Description

采用压浆技术处理大直径钻孔灌注桩塌孔的方法
技术领域
本发明涉及建筑桩基工程技术领域。
背景技术
钻孔灌注桩因其施工速度快、占地小,同时对各种土层的适应性强、无挤土效应,无震害、无躁音、承载力高等优点,在桥墩桩基工程中得到广泛应用。而桥墩桩基工程的钻孔灌注桩通常直径较大,在地质条件较差地区或由于施工操作不当等原因,很容易在成孔施工过程中出现大范围的塌孔、埋钻现象。对于此,若采用加桩方案进行处理,不仅工期长,造价高,而且在桥墩桩基工程多采用群桩基础,没有加桩的施工条件,加之河床塌陷成桩率低等原因,该方法并不适用。
发明内容
本发明的目的在于克服桥墩基础施工过程中的钻孔灌注桩塌孔问题,提供一种能有效解决桥墩桩基础中的钻孔灌注桩塌孔问题,保证桩基承载力和稳定性的采用压浆技术的大直径钻孔灌注桩塌孔处理方法。
本发明的目的通过如下技术方案实现:
采用压浆技术处理大直径钻孔灌注桩塌孔的方法,方法步骤如下:
a.预先在准备吊放到钻孔灌注桩内的钢筋笼内绑扎同心的内圈压浆管和外圈压浆管;内圈压浆管和外圈压浆管的下端均超出钢筋笼5~10cm,顶端均超出后续准备浇筑于钻孔灌注桩顶部的承台的顶面0.5~1.0m;
b.在桩基的护筒中浇筑钻孔灌注桩,灌注桩发生塌孔后立即用钻杆和钻头进行清孔;
c.清孔完毕后,将钢筋笼连同捆扎的内圈压浆管和外圈压浆管一并吊放到孔中;
d.向孔中灌注混凝土,待混凝土逐渐凝固且钻孔灌注桩桩体质量趋于稳定后,在钻孔灌注桩顶部用混凝土浇筑承台;
e.承台施工完毕后,采用高压旋喷施工方法通过内圈压浆管和外圈压浆管注浆至塌孔位置,进行塌孔位置的旋喷固结施工,形成压浆固结体,与上部的钻孔灌注桩共同构成复合桩基础,承担上部荷载。
本发明所述内圈压浆管和外圈压浆管各自的接头均采用丝扣连接,两端分别采用丝堵封严。所述旋喷固结施工采用水泥水玻璃浆液或单一水泥浆或水泥粉煤灰浆液或水泥粘土浆液作为压浆材料,采用高压喷射灌浆中的定喷方式,将浆液压入塌孔位置,浆液穿透塌孔土体并与土体固结在一起,形成压浆固结体。所述水泥水玻璃浆液为水泥浆液中掺入水玻璃的复合注浆材料,其中,水泥浆液的水灰比为0.75:1~1:1,水玻璃掺入量为水泥浆液质量的2%~4%。
本发明的有益效果是:
(1)采用压浆技术对塌孔位置进行的旋喷固结施工,旋喷固结加固方案施工简便快捷,工期短,造价低。
(2)压浆固结体能与桩周土层有较好的结合,产生较大的摩擦力,并与上段钻孔灌注桩搭接形成复合桩基础,共同承担上部荷载,保证桩基承载力和桥墩稳定性。
本发明可有效解决桥墩基础中的大直径钻孔灌注桩塌孔问题,能满足桩基础承载力要求,并具有施工简便快捷的优点,避免了采用加桩方案时面临的工期长以及河床塌陷成桩率低的难题,相比常用的加桩方案,适用性更强,更具有优越性。
附图说明
图1为桥墩基础钻孔灌注桩塌孔示意图;
图2为采用本发明方法处理钻孔灌注桩塌孔示意图;
图3为旋喷压浆固结处理压浆管埋设和旋喷固结体示意图。
图中各标号为:1——钻孔灌注桩;2——压浆固结体;3——承台;4——护筒;5——内圈压浆管;6——外圈压浆管;7——钻杆;8——钻头;9——钢筋笼;A——河床;B——塌孔位置。
具体实施方式
下面通过附图和实施例对本发明作进一步详细说明,但本发明的保护范围不局限于所述内容。
采用压浆技术处理大直径钻孔灌注桩塌孔的方法,参见图1、图2、图3,方法步骤如下:
a.预先在准备吊放到钻孔灌注桩1内的钢筋笼9内绑扎同心的内圈压浆管5和外圈压浆管6;内圈压浆管5和外圈压浆管6的下端均超出钢筋笼5~10cm,顶端均超出后续准备浇筑于钻孔灌注桩顶部的承台3的顶面0.5~1.0m;内圈压浆管5和外圈压浆管6各自的接头均采用丝扣连接,两端分别采用丝堵封严;
b.在河床A确定的桩基位置的护筒4中浇筑钻孔灌注桩1,灌注桩发生如图1中塌孔位置B所示的塌孔后,根据场区勘察报告和设计要求,确定具体塌孔位置(深度和标高等)和所在地层,立即用钻杆7和钻头8进行清孔;浇筑混凝土灌注桩和清孔均可用现有技术方法;
c.清孔完毕后,将钢筋笼连同捆扎的内圈压浆管5和外圈压浆管6一并吊放到孔中;
d.向孔中灌注混凝土,待混凝土逐渐凝固且钻孔灌注桩桩体质量趋于稳定后,在钻孔灌注桩顶部用混凝土浇筑承台3;
e.承台3施工完毕后,采用高压旋喷施工方法通过内圈压浆管5和外圈压浆管6注浆至塌孔位置,进行塌孔位置的旋喷固结施工,形成压浆固结体2,与上部的钻孔灌注桩1共同构成复合桩基础,承担上部荷载。旋喷固结施工采用水泥水玻璃浆液或单一水泥浆或水泥粉煤灰浆液或水泥粘土浆液作为压浆材料,采用定喷穿透补充固结方式施工形成压浆固结体2,即用高压喷射灌浆中的定喷方式,将浆液压入塌孔位置,浆液穿透塌孔土体并与土体固结在一起,形成压浆固结体。所述水泥水玻璃浆液为水泥浆液中掺入水玻璃的复合注浆材料,其中,水泥浆液的水灰比为0.75:1~1:1,水玻璃掺入量为水泥浆液质量的2%~4%。高压旋喷施工可采用现有技术方法。

Claims (4)

1.采用压浆技术处理大直径钻孔灌注桩塌孔的方法,其特征在于,方法步骤如下:
a.预先在准备吊放到钻孔灌注桩(1)内的钢筋笼(9)内绑扎同心的内圈压浆管(5)和外圈压浆管(6);内圈压浆管(5)和外圈压浆管(6)的下端均超出钢筋笼5~10cm,顶端均超出后续准备浇筑于钻孔灌注桩顶部的承台(3)的顶面0.5~1.0m;
b.在桩基的护筒(4)中浇筑钻孔灌注桩(1),钻孔灌注桩发生塌孔后立即用钻杆(7)和钻头(8)进行清孔;
c.清孔完毕后,将钢筋笼连同捆扎的内圈压浆管(5)和外圈压浆管(6)一并吊放到孔中;
d.向孔中灌注混凝土,待混凝土逐渐凝固且钻孔灌注桩桩体质量趋于稳定后,在钻孔灌注桩顶部用混凝土浇筑承台(3);
e.承台(3)施工完毕后,采用高压旋喷施工方法通过内圈压浆管(5)和外圈压浆管(6)注浆至塌孔位置,进行塌孔位置的旋喷固结施工,形成压浆固结体(2),与上部的钻孔灌注桩(1)共同构成复合桩基础,承担上部荷载。
2.根据权利要求1所述的采用压浆技术处理大直径钻孔灌注桩塌孔的方法,其特征在于,所述内圈压浆管(5)和外圈压浆管(6)各自的接头均采用丝扣连接,两端分别采用丝堵封严。
3.根据权利要求1或2所述的采用压浆技术处理大直径钻孔灌注桩塌孔的方法,其特征在于,所述旋喷固结施工采用水泥水玻璃浆液或单一水泥浆或水泥粉煤灰浆液或水泥粘土浆液作为压浆材料,采用高压喷射灌浆中的定喷方式,将浆液压入塌孔位置,浆液穿透塌孔土体并与土体固结在一起,形成压浆固结体(2)。
4.根据权利要求3所述的采用压浆技术处理大直径钻孔灌注桩塌孔的方法,其特征在于,所述水泥水玻璃浆液为水泥浆液中掺入水玻璃的复合注浆材料,其中,水泥浆液的水灰比为0.75:1~1:1,水玻璃掺入量为水泥浆液质量的2%~4%。
CN201510318302.8A 2015-06-11 2015-06-11 采用压浆技术处理大直径钻孔灌注桩塌孔的方法 Active CN104863126B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510318302.8A CN104863126B (zh) 2015-06-11 2015-06-11 采用压浆技术处理大直径钻孔灌注桩塌孔的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510318302.8A CN104863126B (zh) 2015-06-11 2015-06-11 采用压浆技术处理大直径钻孔灌注桩塌孔的方法

Publications (2)

Publication Number Publication Date
CN104863126A CN104863126A (zh) 2015-08-26
CN104863126B true CN104863126B (zh) 2016-08-17

Family

ID=53909265

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510318302.8A Active CN104863126B (zh) 2015-06-11 2015-06-11 采用压浆技术处理大直径钻孔灌注桩塌孔的方法

Country Status (1)

Country Link
CN (1) CN104863126B (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108999198A (zh) * 2018-09-06 2018-12-14 蔡荪萍 一种新型模袋土钉桩施工工艺
CN114855783B (zh) * 2022-05-31 2023-10-13 中国建筑第八工程局有限公司 用于钻孔灌注桩塌孔部位的桩基施工装置及施工方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3720065A (en) * 1971-07-06 1973-03-13 J Sherard Making holes in the ground and freezing the surrounding soil
CN101545256A (zh) * 2008-03-28 2009-09-30 中铁十三局集团第三工程有限公司 钢筋笼护筒在淤泥层地质条件下处理钻孔桩塌孔方法
CN102071645A (zh) * 2010-12-31 2011-05-25 中铁大桥局集团有限公司 一种桥梁钻孔桩孔壁口防护方法
CN103510510A (zh) * 2013-10-22 2014-01-15 山东鸿顺集团有限公司 一种增强型长螺旋钻孔压灌混凝土桩及施工方法
CN103603340A (zh) * 2013-12-06 2014-02-26 中冶建工集团有限公司 柔性防护防止塌孔的旋挖成孔灌注桩施工方法
CN102691296B (zh) * 2012-05-22 2015-02-11 广州市建筑科学研究院有限公司 一种桩侧静压注浆桩底旋喷注浆的管桩基础及其施工方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3720065A (en) * 1971-07-06 1973-03-13 J Sherard Making holes in the ground and freezing the surrounding soil
CN101545256A (zh) * 2008-03-28 2009-09-30 中铁十三局集团第三工程有限公司 钢筋笼护筒在淤泥层地质条件下处理钻孔桩塌孔方法
CN102071645A (zh) * 2010-12-31 2011-05-25 中铁大桥局集团有限公司 一种桥梁钻孔桩孔壁口防护方法
CN102691296B (zh) * 2012-05-22 2015-02-11 广州市建筑科学研究院有限公司 一种桩侧静压注浆桩底旋喷注浆的管桩基础及其施工方法
CN103510510A (zh) * 2013-10-22 2014-01-15 山东鸿顺集团有限公司 一种增强型长螺旋钻孔压灌混凝土桩及施工方法
CN103603340A (zh) * 2013-12-06 2014-02-26 中冶建工集团有限公司 柔性防护防止塌孔的旋挖成孔灌注桩施工方法

Also Published As

Publication number Publication date
CN104863126A (zh) 2015-08-26

Similar Documents

Publication Publication Date Title
CN204112308U (zh) 一种基于大卵石、高渗透系数地层的简易袖阀注浆装置
CN102011399B (zh) 一种基于phc桩的多重高喷扩底桩施工方法
CN102852141B (zh) 一种桩芯灌注混凝土桩侧静压注浆的嵌岩管桩基础及其施工方法
CN103899351B (zh) 一种处理复杂采空区的充填加固方法
CN109763483B (zh) 一种厚第四系深埋采空塌陷破碎地层上行式分段注浆工艺
CN112392400B (zh) 复杂地质环境护坡桩成孔施工工艺
CN103993611A (zh) 一种深层旋喷水泥土板与锚杆组合抗浮桩筏结构及施工方法
CN102943466A (zh) 微型钢管混凝土桩穿透路基层加固软弱地基施工工法
CN203361143U (zh) 高压旋喷桩与预应力管桩组合结构
CN103572764A (zh) 超深人工挖孔桩护壁止水结构及其施工方法
CN102808407B (zh) 软土地基钢筋混凝土灌注桩施工方法
CN103485347A (zh) 一种建筑基坑支护用斜桩及其施工方法
CN104988914A (zh) 一种水域环境下的钻孔灌注桩断桩处理方法
CN104863126B (zh) 采用压浆技术处理大直径钻孔灌注桩塌孔的方法
CN203866852U (zh) 一种深层旋喷水泥土板与锚杆组合抗浮桩筏结构
CN206220101U (zh) 一种深基坑的支护加固结构
CN104846820A (zh) 一种端承型螺纹式挤土桩成桩设备及成桩施工方法
CN110792077A (zh) 一种适用于淤泥质软土中的支盘桩装置及其施工工艺
CN105672329A (zh) 深基坑大尺寸预制围护结构及施工方法
CN114086576B (zh) 钢管微型桩及使用该微型桩加固填土边坡的施工方法
CN106149726B (zh) 动态压力水下迁移性沙层基土的充填稳定灌浆方法
CN104532832A (zh) 一种钢护筒及其应用方法
CN204370413U (zh) 一种钢护筒
CN209603123U (zh) 一种消减负摩阻力的扩底灌注桩结构
CN106894418B (zh) 一种碎石层植预制桩的跑浆治理方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 650501 Yunnan city of Kunming Province Economic and Technological Development Zone Forest Road No. 188

Co-patentee after: YUNNAN CONSTRUCTION ENGINEERING GROUP Co.,Ltd.

Patentee after: YCIH FOUNDATION ENGINEERING CO.,LTD.

Address before: 650501 Yunnan city of Kunming Province Economic and Technological Development Zone Forest Road No. 188

Co-patentee before: YUNNAN CONSTRUCTION ENGINEERING GROUP Co.,Ltd.

Patentee before: YUNNAN CONSTRUCTION ENGINEERING FOUNDATION ENGINEERING CO.,LTD.

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20170525

Address after: Guandu information industry base in Yunnan province Kunming city forest road 650501 No. 188 construction development building

Co-patentee after: Yunnan Construction Investment Holding Group Co., Ltd.

Patentee after: YCIH FOUNDATION ENGINEERING CO.,LTD.

Address before: 650501 Yunnan city of Kunming Province Economic and Technological Development Zone Forest Road No. 188

Co-patentee before: YUNNAN CONSTRUCTION ENGINEERING GROUP Co.,Ltd.

Patentee before: YCIH FOUNDATION ENGINEERING CO.,LTD.

TR01 Transfer of patent right