CN104851343A - Demonstration and training device for electric equipment - Google Patents

Demonstration and training device for electric equipment Download PDF

Info

Publication number
CN104851343A
CN104851343A CN201510311248.4A CN201510311248A CN104851343A CN 104851343 A CN104851343 A CN 104851343A CN 201510311248 A CN201510311248 A CN 201510311248A CN 104851343 A CN104851343 A CN 104851343A
Authority
CN
China
Prior art keywords
wall
current
terminal
electric energy
energy meter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510311248.4A
Other languages
Chinese (zh)
Inventor
王珂
张强
高洁
于竹
冯建勇
岳鹏
高林海
王文龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Jinan Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Jinan Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Jinan Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510311248.4A priority Critical patent/CN104851343A/en
Publication of CN104851343A publication Critical patent/CN104851343A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09BEDUCATIONAL OR DEMONSTRATION APPLIANCES; APPLIANCES FOR TEACHING, OR COMMUNICATING WITH, THE BLIND, DEAF OR MUTE; MODELS; PLANETARIA; GLOBES; MAPS; DIAGRAMS
    • G09B23/00Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes
    • G09B23/06Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics
    • G09B23/18Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics for electricity or magnetism
    • G09B23/183Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics for electricity or magnetism for circuits
    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09BEDUCATIONAL OR DEMONSTRATION APPLIANCES; APPLIANCES FOR TEACHING, OR COMMUNICATING WITH, THE BLIND, DEAF OR MUTE; MODELS; PLANETARIA; GLOBES; MAPS; DIAGRAMS
    • G09B23/00Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes
    • G09B23/06Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics
    • G09B23/18Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics for electricity or magnetism
    • G09B23/183Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics for electricity or magnetism for circuits
    • G09B23/185Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics for electricity or magnetism for circuits for building block systems
    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09BEDUCATIONAL OR DEMONSTRATION APPLIANCES; APPLIANCES FOR TEACHING, OR COMMUNICATING WITH, THE BLIND, DEAF OR MUTE; MODELS; PLANETARIA; GLOBES; MAPS; DIAGRAMS
    • G09B23/00Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes
    • G09B23/06Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics
    • G09B23/18Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics for electricity or magnetism
    • G09B23/188Models for scientific, medical, or mathematical purposes, e.g. full-sized devices for demonstration purposes for physics for electricity or magnetism for motors; for generators; for power supplies; for power distribution
    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09BEDUCATIONAL OR DEMONSTRATION APPLIANCES; APPLIANCES FOR TEACHING, OR COMMUNICATING WITH, THE BLIND, DEAF OR MUTE; MODELS; PLANETARIA; GLOBES; MAPS; DIAGRAMS
    • G09B9/00Simulators for teaching or training purposes

Landscapes

  • Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Educational Administration (AREA)
  • Educational Technology (AREA)
  • Computational Mathematics (AREA)
  • Algebra (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Mathematical Physics (AREA)
  • Pure & Applied Mathematics (AREA)
  • Power Engineering (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention provides a demonstration and training device for electric equipment, and the device comprises an installation platform and a remote computer. The data transmission between the installation platform and the remote computer is achieved through a wireless network. The installation platform comprises a wall body and a pedestal, and the pedestal is in a cavity structure with an opened front end. The interior of the cavity is provided with an on-site calibration instrument. The wall body is fixed on the upper surface of the pedestal, and the interior of the wall body is provided with voltage and current equipment. The surface of the front end of the wall body is provided with an electric energy meter, a wiring box, a current transformer, a power utilization information collection terminal, a load switch, a three-phase voltage wiring end, and a three-phase current wiring terminal. The three-phase voltage wiring end and the three-phase current wiring terminal are connected with the voltage and current equipment. The device simulates an on-site operation environment of a marketing major highly, can carry out the comprehensive exercise of a plurality of majors, can achieve remote simulation operation, and can comprehensively improve the practical training effect of power marketing.

Description

Power equipment demonstration training set
Technical field
The present invention relates to power marketing training field, particularly a kind of power equipment demonstration training set.
Background technology
Along with the development of power technology, power equipment function is also more and more diversified, requires that each associate power personnel must be familiar with grasping professional operation skill, and carrying out real training work is that improve specialized capability ability necessity of electric power personnel, effective mode.In the power marketing real training course of work in the past, personnel are field integrated real training condition for want of, and specialty is different with involved equipment, carries out real training work generally separately, does not have the application of comprehensive practical traning wall aspect.
Present marketing work not only professional division more and more refinement, and each specialty is connected contact closely mutually, independently carries out real training separately, can not complete embodiment result of training, causes teaching result undesirable.The real training demand that power marketing comprehensive practical traning wall of the present invention can concentrate marketing such as solving electric energy metrical, power utility check, data acquisition, spatial load forecasting multi-specialized.
Summary of the invention
For solving above-mentioned defect of the prior art, the invention provides a kind of power equipment demonstration training set, solving the problem that existing teaching result is single, teaching result is not good.
For solving the problems of the technologies described above, the present invention program comprises: power equipment demonstration training set, is characterized in that, comprise mounting platform and remote computer, carry out data transmission between mounting platform and remote computer by wireless network; Described mounting platform comprises body of wall and base, described base is the cavity body structure of front opening, on-site calibrator is provided with in cavity, described body of wall is fixed on base upper surface, body of wall inside is provided with electric current and voltage equipment, body of wall front-end surface is provided with electric energy meter, terminal box, current transformer, power information acquisition terminal, on-load switch, three-phase voltage terminals and three-phase current terminals, three-phase voltage terminals and three-phase current terminals and electric current and voltage equipment connection.
Further, the appliance case of top and the cable box of below is divided into by dividing plate in the cavity of described base, deposit the electric equipments such as on-site calibrator, electric energy meter, terminal box, current transformer, power information acquisition terminal, on-load switch in appliance case, in cable box, deposit the wire cable of various model.
Further, described electric energy meter, terminal box, current transformer, power information acquisition terminal, on-load switch are connected with surface of wall respectively by bolt, make electric energy meter, terminal box, current transformer, power information acquisition terminal, on-load switch can from surface of wall quick-detachment and installation.
Further, described surface of wall is provided with some T-shaped mounting holes, and electric energy meter, terminal box, current transformer, power information acquisition terminal, on-load switch are fixed on body of wall respectively by T-shaped mounting hole.
Further, the corner, four, bottom of described base is respectively equipped with a roller.
The invention has the beneficial effects as follows:
1, combination property is strong, applied widely.Relate to metering installation, power information collection, spatial load forecasting, the most of reality teaches pattern of power utility check four, each Marketing Major both can carry out real training separately, also can carry out comprehensive practical traning work.
2, high analogue simulation degree.Power marketing comprehensive practical traning wall can carry out the installation of measuring apparatus, existing school; Collecting device Installation and Debugging; The Installation and Debugging of load-control equipment; The multi-specialized integrated rehearsals such as meter, stealing Inspection and analysis are leaked in metering, contain the on-the-spot various practical training project of marketing, the on-the-spot running environment of altitude simulation Marketing Major.
3, can brick pattern disassembly and assembly.Each equipment utilization bolt is fixed, and body of wall has been provided with T-shaped mounting hole, and the installation that can adapt to the electric energy meter of dissimilar size, acquisition terminal, mutual inductor, terminal box and wiring etc. is fixed, and its dismounting is flexible.
4, operated from a distance is simulated.Utilize wireless network, the power information acquisition terminal on remote computer and mounting platform is connected as a single entity, the simulation training of the Marketing Major remote technologies such as remote meter reading, long-range negative control, teledata monitoring can be carried out.
5, whole mounting platform floor area is little, builds easily, conveniently moving, and can multiplely arrange, can meet the start-up of a greater number at same batch, save the training time.
Accompanying drawing explanation
Fig. 1 is the structural representation of mounting platform of the present invention;
Equipment connection theory diagram when Fig. 2 is training of the present invention.
In Fig. 1: 1 body of wall, 2 bases, 21 dividing plates, 22 appliance cases, 23 cable box, 3 on-site calibrators, 4 electric energy meters, 5 terminal boxes, 6 current transformers, 7 three-phase current terminals, 8 three-phase voltage terminals, 9 power information acquisition terminals, 10 on-load switches.
Embodiment
Below in conjunction with accompanying drawing, specific embodiment of the invention is described, should be appreciated that exemplifying embodiment described herein is only for instruction and explanation of the present invention, is not intended to limit the present invention.
Power equipment demonstration training set as shown in Figure 1, comprises mounting platform and remote computer, carries out data transmission between mounting platform and remote computer by wireless network; Described mounting platform comprises body of wall 1 and base 2, described base 2 is the cavity body structure of front opening, the appliance case 22 of top and the cable box 23 of below is divided into by dividing plate 21 in the cavity of described base 2, deposit the electric equipments such as on-site calibrator 3, electric energy meter, terminal box, current transformer, power information acquisition terminal, on-load switch in appliance case 22, in cable box 23, deposit the wire cable of various model; Described body of wall 1 is fixed on base 2 upper surface, body of wall 1 inside is provided with electric current and voltage equipment, body of wall 1 front-end surface is provided with electric energy meter 4, terminal box 5, current transformer 6, power information acquisition terminal 9, on-load switch 10, three-phase voltage terminals 8 and three-phase current terminals 7, three-phase voltage terminals and three-phase current terminals and electric current and voltage equipment connection.
Further, described electric energy meter, terminal box, current transformer, power information acquisition terminal, on-load switch are connected with surface of wall respectively by bolt, make electric energy meter, terminal box, current transformer, power information acquisition terminal, on-load switch can from surface of wall quick-detachment and installation.
Further, described surface of wall is provided with some T-shaped mounting holes, and electric energy meter, terminal box, current transformer, power information acquisition terminal, on-load switch are fixed on body of wall respectively by T-shaped mounting hole.
Further, the corner, four, bottom of described base is respectively equipped with a roller, and mounting platform can be facilitated to move integrally.
During training, can be divided into and install and be connected two parts and operate, concrete grammar is:
Before installation operation is carried out, the electric energy meter of surface of wall, terminal box, current transformer, power information acquisition terminal and on-load switch all need to unload from surface of wall, and be placed in appliance case, after installation operation starts, start-up identifies rapidly different equipment, and they are arranged on corresponding position, as shown in Figure 1, electric energy meter is positioned at the upper left corner, terminal box is positioned at the below of electric energy meter, current transformer is positioned at the below of terminal box, power information acquisition terminal is positioned at the upper right corner, on-load switch is positioned at the lower right corner, why arrange like this, be conducive to the carrying out of patching operations, can not be chaotic during wiring.
When patching operations starts, be divided into metering, power information collection, spatial load forecasting, power utility check 4 part to carry out, be specially:
When metering is carried out, by the primary circuit input end of three-phase current terminals and current transformer, three-phase voltage terminals are connected with the voltage interface of terminal box, the secondary circuit output terminal of current transformer is connected with the current interface of terminal box, current interface and the voltage interface of electric energy meter are connected current interface and the voltage interface of terminal box respectively, should with shown in Fig. 2 when wiring completes.After wiring completes, open electric current and voltage equipment, electric energy meter should start counting, occurs reading.
When carrying out power information measurement, access power information acquisition terminal provide working power by terminal box (or electric energy meter) shunt voltage, acquisition terminal 485 Interface Terminal access electric energy meter 485 Interface Terminal reading power meters data, wiring final effect as shown in Figure 2.After wiring completes, power information acquisition terminal is connected with remote computer power information system, by data upload system by wireless network.
When carrying out spatial load forecasting operation, power information acquisition terminal control loop Interface Terminal is connected with on-load switch control loop terminal, as shown in Figure 2.Now, computing machine power information system by wireless network to acquisition terminal transmitting order to lower levels, the tripping operation of control overhead switch and closed.
During power utility check, according to the operation of metering, have complete electric current and voltage equipment in body of wall, table top is provided with three-phase current terminals, can connect current transformer primary circuit input terminal, can inject primary current.Table top three-phase voltage terminals are by terminal box access electrical energy meter electricity hydraulic circuit simultaneously.On-site calibrator takes out in appliance case, and on-site calibrator voltage and current connection terminal thereto (or electric energy meter) corresponding voltage and current wiring terminal, can carry out check analysis work, wiring effect as shown in Figure 2.
Should be understood that; the above-mentioned description for preferred embodiment is comparatively detailed; therefore the restriction to scope of patent protection of the present invention can not be thought; those of ordinary skill in the art is under enlightenment of the present invention; do not departing under the ambit that the claims in the present invention protect; can also make the various deformation such as replacement, simple combination, these all fall within protection scope of the present invention, and request protection domain of the present invention should be as the criterion with claims.

Claims (5)

1. power equipment demonstration training set, is characterized in that, comprise mounting platform and remote computer, carry out data transmission between mounting platform and remote computer by wireless network; Described mounting platform comprises body of wall and base, described base is the cavity body structure of front opening, on-site calibrator is provided with in cavity, described body of wall is fixed on base upper surface, body of wall inside is provided with electric current and voltage equipment, body of wall front-end surface is provided with electric energy meter, terminal box, current transformer, power information acquisition terminal, on-load switch, three-phase voltage terminals and three-phase current terminals, three-phase voltage terminals and three-phase current terminals and electric current and voltage equipment connection.
2. power equipment demonstration training set according to claim 1, is characterized in that, be divided into the appliance case of top and the cable box of below in the cavity of described base by dividing plate.
3. power equipment demonstration training set according to claim 1, it is characterized in that, described electric energy meter, terminal box, current transformer, power information acquisition terminal, on-load switch are connected with surface of wall respectively by bolt.
4. power equipment demonstration training set according to claim 1, it is characterized in that, described surface of wall is provided with some T-shaped mounting holes, and electric energy meter, terminal box, current transformer, power information acquisition terminal, on-load switch are fixed on body of wall respectively by T-shaped mounting hole.
5. power equipment demonstration training set according to claim 1, it is characterized in that, the corner, four, bottom of described base is respectively equipped with a roller.
CN201510311248.4A 2015-06-09 2015-06-09 Demonstration and training device for electric equipment Pending CN104851343A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510311248.4A CN104851343A (en) 2015-06-09 2015-06-09 Demonstration and training device for electric equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510311248.4A CN104851343A (en) 2015-06-09 2015-06-09 Demonstration and training device for electric equipment

Publications (1)

Publication Number Publication Date
CN104851343A true CN104851343A (en) 2015-08-19

Family

ID=53850958

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510311248.4A Pending CN104851343A (en) 2015-06-09 2015-06-09 Demonstration and training device for electric equipment

Country Status (1)

Country Link
CN (1) CN104851343A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105845007A (en) * 2016-06-13 2016-08-10 国网辽宁省电力有限公司朝阳供电公司 Intelligent electric energy meter simulation application test stand and use method thereof
CN106935095A (en) * 2017-05-09 2017-07-07 刘学林 A kind of split type training on electric power equipment
CN108957069A (en) * 2018-06-08 2018-12-07 北京首都机场动力能源有限公司 A kind of massive quantity power supply and measurement emulation metering cabinet
CN111103448A (en) * 2019-11-15 2020-05-05 国网浙江省电力有限公司衢州供电公司 Wiring module for high-voltage electric energy metering new-installation user
CN111951648A (en) * 2020-08-12 2020-11-17 广东电网有限责任公司广州供电局 Three-phase four-wire system electric energy meter wiring demonstration device
CN115359691A (en) * 2022-07-27 2022-11-18 广东电网有限责任公司广州供电局 Operation and distribution integrated training platform

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105845007A (en) * 2016-06-13 2016-08-10 国网辽宁省电力有限公司朝阳供电公司 Intelligent electric energy meter simulation application test stand and use method thereof
CN106935095A (en) * 2017-05-09 2017-07-07 刘学林 A kind of split type training on electric power equipment
CN106935095B (en) * 2017-05-09 2019-11-05 南京昌合泰智能科技有限公司 A kind of split type training on electric power equipment
CN108957069A (en) * 2018-06-08 2018-12-07 北京首都机场动力能源有限公司 A kind of massive quantity power supply and measurement emulation metering cabinet
CN111103448A (en) * 2019-11-15 2020-05-05 国网浙江省电力有限公司衢州供电公司 Wiring module for high-voltage electric energy metering new-installation user
CN111951648A (en) * 2020-08-12 2020-11-17 广东电网有限责任公司广州供电局 Three-phase four-wire system electric energy meter wiring demonstration device
CN115359691A (en) * 2022-07-27 2022-11-18 广东电网有限责任公司广州供电局 Operation and distribution integrated training platform
CN115359691B (en) * 2022-07-27 2024-03-26 广东电网有限责任公司广州供电局 Marketing and distribution integrated training platform

Similar Documents

Publication Publication Date Title
CN104851343A (en) Demonstration and training device for electric equipment
CN103123758B (en) A kind of dispatching automation numeral physical mixed simulation training system
CN106935089B (en) Power information acquisition terminal installation training system and method
CN104483643B (en) Modeling method based on detection platform of fault indicator for physical simulation of power distribution network
CN106057005B (en) A kind of building power supply and distribution teaching processing simulation experience system
CN205068942U (en) Experimental hybrid simulation system of high -voltage electrical
CN104537936A (en) Low-voltage transformer area simulation practical training device for rural network low-voltage distribution box
CN105608966A (en) Electric power metering device simulated field multifunctional training working table
CN106383308A (en) Charge control circuit breaker automatic breaking/closing test device
CN103616574B (en) A kind of electric automobile anti-alone island detection system of energy storage combining inverter and detection method
CN204808689U (en) Power equipment demonstrates training set
CN104298127A (en) Micro-grid semi-digital semi-physical real-time simulation system based on RT-LAB
CN105608949A (en) Split type electric energy metering device and terminal installation wiring practical training apparatus
CN103487679A (en) AIS electronic transformer testing system and testing method thereof
CN104238371A (en) Portable electric system digital simulation instrument
CN104091502B (en) Low-tension centralized meter reading and installation training device based on carrier technology
CN205067670U (en) A anti -interference medium simulator for high -voltage electrical is experimental
CN112396906A (en) Comprehensive simulation system for professional post skills and examination of electricity inspection for actual operation
Gaouda et al. Developing educational smart grid laboratory
CN202285151U (en) Double-path working power supply of integrative experimental device with electricity-theft prevention for simulating working condition of metering of electric energy
CN102508052B (en) Test method for field band channel operation of automatic bus transfer system of area network
CN102707117A (en) Relaying multifunctional tester
CN204117459U (en) Typical low pressure fault handling training platform device
CN106023748A (en) Low-voltage metering training device
CN116008689A (en) Real simulation system of configuration type low-voltage distribution network and test method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20150819

RJ01 Rejection of invention patent application after publication