CN104809543A - Power grid operation mode generating method based on monthly power transmission and distribution equipment maintenance plan - Google Patents

Power grid operation mode generating method based on monthly power transmission and distribution equipment maintenance plan Download PDF

Info

Publication number
CN104809543A
CN104809543A CN201510045164.0A CN201510045164A CN104809543A CN 104809543 A CN104809543 A CN 104809543A CN 201510045164 A CN201510045164 A CN 201510045164A CN 104809543 A CN104809543 A CN 104809543A
Authority
CN
China
Prior art keywords
load
monthly
day
data
power transmission
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510045164.0A
Other languages
Chinese (zh)
Other versions
CN104809543B (en
Inventor
崔晓丹
李威
李碧君
王正风
方勇杰
李兆伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
State Grid Anhui Electric Power Co Ltd
Nari Technology Co Ltd
Nanjing NARI Group Corp
Original Assignee
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
State Grid Anhui Electric Power Co Ltd
Nari Technology Co Ltd
Nanjing NARI Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, State Grid Anhui Electric Power Co Ltd, Nari Technology Co Ltd, Nanjing NARI Group Corp filed Critical State Grid Corp of China SGCC
Priority to CN201510045164.0A priority Critical patent/CN104809543B/en
Publication of CN104809543A publication Critical patent/CN104809543A/en
Application granted granted Critical
Publication of CN104809543B publication Critical patent/CN104809543B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Abstract

The invention discloses a power grid operation mode generating method based on a monthly power transmission and distribution equipment maintenance plan, and belongs to the technical field of an electric power system and automation thereof. The power grid operation mode generating method is characterized by comprising the steps that original data of the operating mode is acquired from a power grid regulation and control center, a peak load operating mode and a valley load operating mode of each day having the power transmission and distribution equipment maintenance plan are monthly generated according to the monthly power transmission and distribution equipment maintenance plan and load rate distribution monthly electric quantity prediction data of different time periods of the corresponding historical period, influences of system network losses, spinning reserve requirements and planned outage units are considered in the process of generating the two modes, and power grid operating mode data under the power transmission and distribution equipment maintenance plan according to a date-load mode is finally acquired. The maintenance plan operating mode generated according to the method disclosed by the invention conforms to production requirements and habits of the electric power system, thereby being capable of providing a data basis for power grid operating risk evaluation and maintenance plan readjustment under the power transmission and distribution equipment maintenance equipment plan of the electric power system.

Description

Based on the power system operating mode generation method of monthly power transmission and transforming equipment turnaround plan
Technical field
The invention belongs to Power System and its Automation technical field, more precisely, the present invention relates to a kind of power system operating mode generation method based on monthly power transmission and transforming equipment turnaround plan.
Background technology
Power transmission and transforming equipment is the skeleton of electric power networks, once equipment goes wrong, may cause local and global system equipment out of service, cause the generation of power failure accident.Therefore power transmission and transforming equipment runs safely and reliably and seems particularly important.Along with electric system is to the development in high voltage, Large Copacity, interconnected direction, also more and more higher to the requirement of the safe reliability index of electric system, the maintenance amplitude that has high input of electric power enterprise rises, and existing troubleshooting system exposes its defect day by day significantly.Therefore, more advanced, more scientific management and troubleshooting system are carried out to equipment, turnaround plan is formed to the method for operation meeting management and running objective reality, and the safety and stability of carrying out rolling is checked, interests no matter from electric power enterprise self or the requirement from society, all imperative.
When considering that turnaround plan carries out safety and stability check, first need to generate the power system operating mode taking into account turnaround plan.Planned manner comprises the mode under one or more plan mixes such as turnaround plan, generation schedule, load prediction.Turnaround plan may comprise again generator maintenance plan and transmission of electricity substation equipment maintenance and repair plan and controller switching equipment turnaround plan etc.In addition, the basic data condition of the planned manner data of Different time scales is different, and it is also not quite similar to the requirement of the precision of the method for operation generated.
Under current existing turnaround plan, method of operation generation technique includes the generation of Different time scales turnaround plan, the plan type considered may be the combination of one or more plans, its target is all make planned manner be tending towards more meeting management and running reality, or makes the mode of arrangement reasonable more economically.But but do not have comprehensively effectively to utilize historical load data message and existing mode data message, this just makes the generation difficulty for planned manner large, and is difficult to reach the effect meeting management and running reality.In addition, in the generative process of the method for operation, existing technology, for impacts such as power transmission and transforming equipment turnaround plan, unit outage plan, system reserve constraint, the actual network loss of system, all only considers wherein some factors, and fails to synthesize and coordinate consideration.
Summary of the invention
The present invention seeks to: for deficiency of the prior art, provide a kind of power system operating mode generation method based on monthly power transmission and transforming equipment turnaround plan.The method is according to information such as monthly power transmission and transforming equipment turnaround plan, monthly power quantity predicting data, the actual conditions of the reference previous year electricity same period and load, generate monthly peak load mode and low ebb load method two kinds of methods of operation of having power transmission and transforming equipment turnaround plan each day.In the process generating these two kinds of modes, consider system losses, spinning reserve requires, the impact of planned outage unit, finally obtain power system operating mode data under the power transmission and transforming equipment turnaround plan by " date, load method " pattern.Meet electric system Production requirement and custom according to the turnaround plan method of operation that said method generates, data basis can be provided for the adjustment again of operation of power networks risk assessment and turnaround plan under electric system power transmission and transforming equipment turnaround plan.
Specifically, the present invention realizes by the following technical solutions, comprises the following steps:
1) obtain at power grid regulation center in next monthly power transmission and transforming equipment turnaround plan and unit outage plan, next monthly prediction electric quantity data, previous year with next monthly identical monthly monthly load statistics and each day realized load curve, this month electrical network off-line typical way data, all unit rated capacity data and system spinning reserve coefficient, be wherein divided into N with next monthly identical monthly monthly each day realized load curve by one day 24 hours in previous year pointthe network load performance number of individual period, every point data corresponding period;
2) by mode data based on the full mode of connection data in this month electrical network off-line typical way data of regulation and control center;
3) next monthly prediction electricity is shared each day of next month, and estimate peak load and the low ebb load of next month each day;
4) judge whether next month each day has turnaround plan successively, as then do not skipped, otherwise to there being each day of next month of turnaround plan task, generate respectively each day peak load and low ebb load under two kinds of methods of operation;
5) by final running mode data by being numbered, and be sent to dispatching management information system or other automated system corresponding data catalogues for its application.
Being further of technique scheme, described step 3) specifically comprise the following steps:
3-1) according in previous year with next monthly identical monthly monthly load statistics, calculate the prediction electricity of next month each day by formula (1), (2):
W i = W i ′ WP ′ × WP ( i = 1 ~ d ) - - - ( 1 )
WP ′ = Σ i = 1 d W i ′ ( i = 1 ~ d ) - - - ( 2 )
Wherein, d is monthly number of days; WP is next monthly prediction electricity; W ifor the prediction electricity on next month 1; WP ' in previous year with the previous year same month actual electricity in next monthly identical monthly monthly load statistics; W ' ifor in previous year with the previous year same month actual electricity on the same day in next monthly identical monthly monthly load statistics;
3-2) according in previous year with next monthly identical monthly monthly each day realized load curve, distribute in proportion by formula (3), obtain the prediction load power of next month each day day part:
P i , j = Σ j = 1 N point ( W i W i ′ · P i , j ′ ) ( i = 1 ~ d , j = 1 ~ N point ) - - - ( 3 )
Wherein, P i,jfor the electrical network prediction load power of jth period next month 1; P ' i,jfor in previous year with same month prior year in next monthly identical monthly monthly each day realized load curve on the same day with the actual load power of period;
3-3) calculate peak load on next month 1 by formula (4), (5) with low ebb load
P i max = k · max { P i , j } ( i = 1 ~ d , j = 1 ~ N point ) - - - ( 4 )
P i min = min { P i , j } k ( i = 1 ~ d , j = 1 ~ N point ) - - - ( 5 )
Wherein, k is constant coefficient.
Being further of technique scheme, described step 4) in generate each day peak load and low ebb load under the step of two kinds of methods of operation as follows:
4-1) according to the power transmission and transforming equipment turnaround plan that this day arranges, basal profile data are deleted the power transmission and transforming equipment of each scheduled overhaul one by one, obtains intermediate data;
4-2) based on intermediate data, unit outage plan in this day, step 3) peak load of this day that obtains and low ebb load, consideration system spinning reserve and network loss, adjustment unit output and load, make system power in a basic balance, generating run mode raw data;
4-3) Load flow calculation is carried out to method of operation raw data, if trend restrains, then acquisition pattern data, disperse if trend reports an error or calculates, then adjust according to information, and recalculate trend, iteration like this is until trend convergence or iterations exceed preset value (according to engineering experience, generally desirable 5 ~ 10 times) then stop, will the flow data of convergence be calculated as final mode data.
Being further of technique scheme, described step 4-2) specifically comprise the following steps:
4-2-1) generator gross capability and load total amount in statistical basis mode data, if generator gross capability is P gorg, load total amount is P lorg;
In intermediate data, 4-2-2) search the unit that this daily planning is stopped transport, and the gross capability adding up these units is P gstop, then in intermediate data, delete these units;
4-2-3) calculate the peak load of this day or low ebb load and P by formula (6) lorgdifference DELTA P l, and adjust each node load of the whole network and make the whole network load total amount be P llim:
ΔP l=P llim-P lorg(6)
Wherein, the P when calculating peak load mode llimfor the peak load of this day; The P when calculating low ebb load method llimfor the low ebb load of this day;
If Δ P l> 0, then increase load at equal pace at each load bus of the whole network, if Δ P l< 0, then in each load bus of the whole network load shedding at equal pace, make the whole network total load be P llim;
4-2-4) take into account the unit of planned outage, and consider network loss size in the ratio of generation load in raw data, computing system generator need increase exerts oneself or subtracts the total value Δ P that exerts oneself g, shown in (7):
&Delta;P g = P gorg &CenterDot; P llim P lorg - P gorg + P gstop - - - ( 7 )
A) if Δ P g>=0, to step 4-2-2) in deleted all generators in the intermediate data of planned outage unit and increase and exert oneself, making to increase the total amount of exerting oneself is Δ P g:
First, whether according to whether meeting formula (8), to judge to increase the space of exerting oneself when consideration system leaves necessarily for subsequent use enough:
&Sigma; k = 1 N ( p cap , k - p k ) - &Delta;P g &GreaterEqual; &lambda; &CenterDot; P llim - - - ( 8 )
Wherein, N is the whole network generator sum in intermediate data; p kfor initially the exerting oneself in raw data of a kth generator; p cap, kfor the rated capacity of a kth generator; λ is system spinning reserve coefficient, and peak load is different with its value under low ebb load method, determines respectively according to industry or enterprise's relevant criterion or specification;
If formula (8) meets, then in intermediate data, increase each generator output, each generator need increase to exert oneself and to calculate by (9) formula:
&Delta;p k = ( p cap , k - p k ) &Sigma; k = 1 N ( p cap , k - p k ) &CenterDot; &Delta;P g - - - ( 9 )
Wherein, Δ p kexert oneself for a kth generator need increase;
If formula (8) does not meet, then in intermediate data, establish unit newly one by one but except the unit of planned outage, make initially exerting oneself of unit of increase be 0, until formula (8) meets; During increase unit, the whole network generator sum N also upgrades thereupon one by one, and the numerical value often establishing a unit N newly adds 1;
In intermediate data, exerting oneself of unit of increase is adjusted to its minimum load value; Increase each generator output by formula (9) more on this basis, and be modified in intermediate data;
B) if Δ P g< 0, subtracts all generators of the whole network in intermediate data and exerts oneself, and subtracting the total amount of exerting oneself is Δ P g; Each generator need subtract strength and calculate by formula (10):
&Delta;p k = ( p k - &alpha; k &CenterDot; p cap , k ) &Sigma; k = 1 N ( p k - &alpha; k &CenterDot; p cap , k ) &CenterDot; &Delta;P g - - - ( 10 )
Now, Δ p kstrength, α for a kth generator need subtract kfor the minimum load scale-up factor of a kth generator;
4-2-5) after above-mentioned adjustment, intermediate data is defined as raw data.
Being further of technique scheme, described constant coefficient k value is 1.0 ~ 1.1.
Being further of technique scheme, the minimum load scale-up factor α of a described kth generator kvalue is 0.5 ~ 0.6.
Technique scheme is further characterized in that, described N pointbe 96, be divided into 96 periods with next monthly identical monthly monthly each day realized load curve by one day 24 hours in previous year, each period is 15 minutes, every point data network load performance number of corresponding 15 minutes.
Beneficial effect of the present invention is as follows: the present invention proposes power system operating mode generation method under monthly power transmission and transforming equipment turnaround plan, can be power system operation mode personnel turnaround plan is provided under mode data, and be the relevant automatic systems with data such as turnaround plan nucleus correcting system basis; In the process generating the method for operation under power transmission and transforming equipment turnaround plan, consider system losses, the influence factor such as spinning reserve requires, planned outage unit, make result data more reasonable, practical, and for the adjustment again of operation of power networks risk assessment and turnaround plan under electric system power transmission and transforming equipment turnaround plan provide data basis.
Accompanying drawing explanation
Fig. 1 is the process flow diagram of the inventive method.
Embodiment
With reference to the accompanying drawings the present invention is described in further detail.
What in Fig. 1, step 1 described is, obtain at power grid regulation center in next monthly power transmission and transforming equipment turnaround plan and unit outage plan, next monthly prediction electric quantity data, previous year with next monthly identical monthly monthly load statistics and each day realized load curve, this month electrical network off-line typical way data, all unit rated capacity data and system spinning reserve coefficient, be wherein divided into N with next monthly identical monthly monthly each day realized load curve by one day 24 hours in previous year pointthe network load performance number of individual period, every point data corresponding period.In reality, N pointgenerally get 96, be namely divided into 96 periods with next monthly identical monthly monthly each day realized load curve by one day 24 hours in previous year, each period is 15 minutes, every point data network load performance number of corresponding 15 minutes.
In Fig. 1, step 2 describes, by mode data based on the full mode of connection data in this month electrical network off-line typical way data of regulation and control center.
In Fig. 1, step 3 describes, and next monthly prediction electricity is shared each day of next month, and estimates peak load and the low ebb load of next month each day.Its computation process specifically comprises the steps.
3-1) according in previous year with next monthly identical monthly monthly load statistics, calculate the prediction electricity of each day by formula (1), (2):
W i = W i &prime; WP &prime; &times; WP ( i = 1 ~ d ) - - - ( 1 )
WP &prime; = &Sigma; i = 1 d W i &prime; ( i = 1 ~ d ) - - - ( 2 )
Wherein, d is monthly number of days; WP is next monthly prediction electricity; W ifor the prediction electricity on next month 1; WP ' in previous year with the previous year same month actual electricity in next monthly identical monthly monthly load statistics; W ' ifor in previous year with the previous year same month actual electricity on the same day in next monthly identical monthly monthly load statistics.
3-2) according in previous year with next monthly identical monthly monthly each day realized load curve, distribute in proportion by formula (3), obtain the prediction load power of next month each day day part:
P i , j = &Sigma; j = 1 N point ( W i W i &prime; &CenterDot; P i , j &prime; ) ( i = 1 ~ d , j = 1 ~ N point ) - - - ( 3 )
Wherein, P i,jfor the electrical network prediction load power of jth period next month 1; P ' i,jfor in previous year with same month prior year in next monthly identical monthly monthly each day realized load curve on the same day with the actual load power of period.
Especially, for N pointwhen getting 96, formula (3) is:
P i , j = &Sigma; j = 1 96 ( W i W i &prime; &CenterDot; P i , j &prime; ) ( i = 1 ~ d , j = 1 ~ 96 )
3-3) calculate peak load on next month 1 by formula (4), (5) with low ebb load
P i max = k &CenterDot; max { P i , j } ( i = 1 ~ d , j = 1 ~ N point ) - - - ( 4 )
P i min = min { P i , j } k ( i = 1 ~ d , j = 1 ~ N point ) - - - ( 5 )
Wherein, k is constant coefficient, determines according to engineering experience, and general value is 1.0 ~ 1.1.
In Fig. 1, step 4 describes, and judges whether next month each day has turnaround plan successively, as then do not skipped, otherwise to there being each day of next month of turnaround plan task, generate respectively each day peak load and low ebb load under two kinds of methods of operation.Its computation process comprises the steps.
4-1) according to the power transmission and transforming equipment turnaround plan that this day arranges, basal profile data are deleted the power transmission and transforming equipment of each scheduled overhaul one by one, obtains intermediate data;
4-2) based on intermediate data, unit outage plan in this day, step 3) peak load of this day that obtains and low ebb load, consideration system spinning reserve and network loss, adjustment unit output and load, make system power in a basic balance, generating run mode raw data.Its computation process comprises the steps.
4-2-1) generator gross capability and load total amount in statistical basis mode data, if generator gross capability is P gorg, load total amount is P lorg;
In intermediate data, 4-2-2) search the unit that this daily planning is stopped transport, and the gross capability adding up these units is P gstop, then in intermediate data, delete these units;
4-2-3) calculate the peak load of this day or low ebb load and P by formula (6) lorgdifference DELTA P l, and adjust each node load of the whole network and make the whole network load total amount be P llim:
ΔP l=P llim-P lorg(6)
Wherein, the P when calculating peak load mode llimfor the peak load of this day; The P when calculating low ebb load method llimfor the low ebb load of this day.
If Δ P l> 0, then increase load at equal pace at each load bus of the whole network, if Δ P l< 0, then in each load bus of the whole network load shedding at equal pace, make the whole network total load be P llim.
4-2-4) take into account the unit of planned outage, and consider network loss size in the ratio of generation load in raw data, computing system generator need increase exerts oneself or subtracts the total value Δ P that exerts oneself g, shown in (7):
&Delta;P g = P gorg &CenterDot; P llim P lorg - P gorg + P gstop - - - ( 7 )
A) if Δ P g>=0, to step 4-2-2) in deleted all generators in the intermediate data of planned outage unit and increase and exert oneself, making to increase the total amount of exerting oneself is Δ P g:
First, whether enough judge to increase the space of exerting oneself when consideration system leaves necessarily for subsequent use, namely judge whether formula (8) meets:
&Sigma; k = 1 N ( p cap , k - p k ) - &Delta;P g &GreaterEqual; &lambda; &CenterDot; P llim - - - ( 8 )
Wherein, N is the whole network generator sum in intermediate data; p kfor initially the exerting oneself in raw data of a kth generator; p cap, kfor the rated capacity of a kth generator; λ is system spinning reserve coefficient, and peak load is different with its value under low ebb load method, determines respectively according to industry or enterprise's relevant criterion or specification.
If formula (8) meets, then in intermediate data, increase each generator output.Each generator need increase to exert oneself and to calculate by (9) formula:
&Delta;p k = ( p cap , k - p k ) &Sigma; k = 1 N ( p cap , k - p k ) &CenterDot; &Delta;P g - - - ( 9 )
Wherein, Δ p kexert oneself for a kth generator need increase;
If formula (8) does not meet, in intermediate data, establish unit (except the unit of planned outage) one by one newly, the p that initially exerts oneself of order increase unit k=0, until formula (8) meets.Need to illustrate, during increase unit, the whole network generator sum N also upgrades thereupon one by one, and the numerical value often establishing a unit N newly adds 1.
In intermediate data, exerting oneself of unit of increase is adjusted to its minimum load value.Increase each generator output by formula (9) more on this basis, and be modified in intermediate data.
B) if Δ P g< 0, subtracts all generators of the whole network in intermediate data and exerts oneself, and subtracting the total amount of exerting oneself is Δ P g.Each generator need subtract strength and calculate by formula (10):
&Delta;p k = ( p k - &alpha; k &CenterDot; p cap , k ) &Sigma; k = 1 N ( p k - &alpha; k &CenterDot; p cap , k ) &CenterDot; &Delta;P g - - - ( 10 )
Now, Δ p kstrength, α for a kth generator need subtract kfor the minimum load scale-up factor of generator k, general value 0.5 ~ 0.6.
4-2-5) after above-mentioned adjustment, intermediate data is defined as raw data.
4-3) carry out Load flow calculation to raw data, Load flow calculation completes by existing ripe business software.If trend restrains, then acquisition pattern data, disperse if trend reports an error or calculates, then adjust according to information, and recalculating trend, iteration like this is until trend convergence or iterations exceed preset value (according to engineering experience, generally desirable 5 ~ 10 times) and then stop.To the flow data of convergence be calculated as final mode data.
In Fig. 1, step 5 describes, and final running mode data is numbered, and is sent to dispatching management information system or its application of other automated system corresponding data catalogues confession.Numbering can adopt, and " date and load method " carries out.
Although the present invention with preferred embodiment openly as above, embodiment is not of the present invention for limiting.Without departing from the spirit and scope of the invention, any equivalence change done or retouching, belong to the protection domain of the present invention equally.Therefore the content that protection scope of the present invention should define with the claim of the application is standard.

Claims (7)

1., based on the power system operating mode generation method of monthly power transmission and transforming equipment turnaround plan, it is characterized in that, comprise the steps:
1) obtain at power grid regulation center in next monthly power transmission and transforming equipment turnaround plan and unit outage plan, next monthly prediction electric quantity data, previous year with next monthly identical monthly monthly load statistics and each day realized load curve, this month electrical network off-line typical way data, all unit rated capacity data and system spinning reserve coefficient, be wherein divided into N with next monthly identical monthly monthly each day realized load curve by one day 24 hours in previous year pointthe network load performance number of individual period, every point data corresponding period;
2) by mode data based on the full mode of connection data in this month electrical network off-line typical way data of regulation and control center;
3) next monthly prediction electricity is shared each day of next month, and estimate peak load and the low ebb load of next month each day;
4) judge whether next month each day has turnaround plan successively, as then do not skipped, otherwise to there being each day of next month of turnaround plan task, generate respectively each day peak load and low ebb load under two kinds of methods of operation;
5) by final running mode data by being numbered, and be sent to dispatching management information system or other automated system corresponding data catalogues for its application.
2. the power system operating mode generation method based on monthly power transmission and transforming equipment turnaround plan according to claim 1, is characterized in that, described step 3) specifically comprise the following steps:
3-1) according in previous year with next monthly identical monthly monthly load statistics, calculate the prediction electricity of next month each day by formula (1), (2):
W i = W i &prime; WP &prime; &times; WP , ( i = 1 ~ d ) - - - ( 1 )
WP &prime; = &Sigma; i = 1 d W i &prime; , ( i = 1 ~ d ) - - - ( 2 )
Wherein, d is monthly number of days; WP is next monthly prediction electricity; W ifor the prediction electricity on next month 1; WP ' in previous year with the previous year same month actual electricity in next monthly identical monthly monthly load statistics; W ' ifor in previous year with the previous year same month actual electricity on the same day in next monthly identical monthly monthly load statistics;
3-2) according in previous year with next monthly identical monthly monthly each day realized load curve, distribute in proportion by formula (3), obtain the prediction load power of next month each day day part:
P i , j = &Sigma; j = 1 N point ( W i W i &prime; &CenterDot; P i , j &prime; ) , ( i = 1 ~ d , j = 1 ~ N point ) - - - ( 3 )
Wherein, P i,jfor the electrical network prediction load power of jth period next month 1; P ' i,jfor in previous year with same month prior year in next monthly identical monthly monthly each day realized load curve on the same day with the actual load power of period;
3-3) calculate peak load on next month 1 by formula (4), (5) with low ebb load
P i max = k &CenterDot; max { P i , j } , ( i = 1 ~ d , j = 1 ~ N point ) - - - ( 4 )
P i min = min { P i , j } k , ( i = 1 ~ d , j = 1 ~ N point ) - - - ( 5 )
Wherein, k is constant coefficient.
3. the power system operating mode generation method based on monthly power transmission and transforming equipment turnaround plan according to claim 1, is characterized in that, described step 4) in generate each day peak load and low ebb load under the step of two kinds of methods of operation as follows:
4-1) according to the power transmission and transforming equipment turnaround plan that this day arranges, basal profile data are deleted the power transmission and transforming equipment of each scheduled overhaul one by one, obtains intermediate data;
4-2) based on intermediate data, unit outage plan in this day, step 3) peak load of this day that obtains and low ebb load, consideration system spinning reserve and network loss, adjustment unit output and load, make system power in a basic balance, generating run mode raw data;
4-3) Load flow calculation is carried out to method of operation raw data, if trend restrains, then acquisition pattern data, disperse if trend reports an error or calculates, then adjust according to information, and recalculating trend, iteration like this, until trend convergence or iterations exceed preset value and then stop, will calculate the flow data of convergence as final mode data.
4. the power system operating mode generation method based on monthly power transmission and transforming equipment turnaround plan according to claim 3, is characterized in that, described step 4-2) specifically comprise the following steps:
4-2-1) generator gross capability and load total amount in statistical basis mode data, if generator gross capability is P gorg, load total amount is P lorg;
In intermediate data, 4-2-2) search the unit that this daily planning is stopped transport, and the gross capability adding up these units is P gstop, then in intermediate data, delete these units;
4-2-3) calculate the peak load of this day or low ebb load and P by formula (6) lorgdifference DELTA P l, and adjust each node load of the whole network and make the whole network load total amount be P llim:
ΔP l=P llim-P lorg(6)
Wherein, the P when calculating peak load mode llimfor the peak load of this day; The P when calculating low ebb load method llimfor the low ebb load of this day;
If Δ P l> 0, then increase load at equal pace at each load bus of the whole network, if Δ P l< 0, then in each load bus of the whole network load shedding at equal pace, make the whole network total load be P llim;
4-2-4) take into account the unit of planned outage, and consider network loss size in the ratio of generation load in raw data, computing system generator need increase exerts oneself or subtracts the total value Δ P that exerts oneself g, shown in (7):
&Delta;P g = P gorg &CenterDot; P llim p lorg - P gorg + P gstop - - - ( 7 )
A) if Δ P g>=0, to step 4-2-2) in deleted all generators in the intermediate data of planned outage unit and increase and exert oneself, making to increase the total amount of exerting oneself is Δ P g:
First, whether according to whether meeting formula (8), to judge to increase the space of exerting oneself when consideration system leaves necessarily for subsequent use enough:
&Sigma; k = 1 N ( p cap , k - p k ) - &Delta;P g &GreaterEqual; &lambda; &CenterDot; P llim - - - ( 8 )
Wherein, N is the whole network generator sum in intermediate data; p kfor initially the exerting oneself in raw data of a kth generator; p cap, kfor the rated capacity of a kth generator; λ is system spinning reserve coefficient, and peak load is different with its value under low ebb load method, determines respectively according to industry or enterprise's relevant criterion or specification;
If formula (8) meets, then in intermediate data, increase each generator output, each generator need increase to exert oneself and to calculate by (9) formula:
&Delta;p k = ( p cap , k - p k ) &Sigma; k = 1 N ( p cap , k - p k ) &CenterDot; &Delta;P g - - - ( 9 )
Wherein, Δ p kexert oneself for a kth generator need increase;
If formula (8) does not meet, then in intermediate data, establish unit newly one by one but except the unit of planned outage, make initially exerting oneself of unit of increase be 0, until formula (8) meets; During increase unit, the whole network generator sum N also upgrades thereupon one by one, and the numerical value often establishing a unit N newly adds 1;
In intermediate data, exerting oneself of unit of increase is adjusted to its minimum load value; Increase each generator output by formula (9) more on this basis, and be modified in intermediate data;
B) if Δ P g< 0, subtracts all generators of the whole network in intermediate data and exerts oneself, and subtracting the total amount of exerting oneself is Δ P g; Each generator need subtract strength and calculate by formula (10):
&Delta;p k = ( p k - - &alpha; k &CenterDot; p cap , k ) &Sigma; k = 1 N ( p k - &alpha; k &CenterDot; p cap , k ) &CenterDot; &Delta;P g - - - ( 10 )
Now, Δ p kstrength, α for a kth generator need subtract kfor the minimum load scale-up factor of a kth generator;
4-2-5) after above-mentioned adjustment, intermediate data is defined as raw data.
5. the power system operating mode generation method based on monthly power transmission and transforming equipment turnaround plan according to claim 2, is characterized in that, described constant coefficient k value is 1.0 ~ 1.1.
6. the power system operating mode generation method based on monthly power transmission and transforming equipment turnaround plan according to claim 4, is characterized in that, the minimum load scale-up factor α of a described kth generator kvalue is 0.5 ~ 0.6.
7. the power system operating mode generation method based on monthly power transmission and transforming equipment turnaround plan described arbitrarily according to claim 1 ~ 6, is characterized in that, described N pointbe 96, be divided into 96 periods with next monthly identical monthly monthly each day realized load curve by one day 24 hours in previous year, each period is 15 minutes, every point data network load performance number of corresponding 15 minutes.
CN201510045164.0A 2015-01-28 2015-01-28 Power system operating mode generation method based on monthly power transmission and transforming equipment repair schedule Active CN104809543B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510045164.0A CN104809543B (en) 2015-01-28 2015-01-28 Power system operating mode generation method based on monthly power transmission and transforming equipment repair schedule

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510045164.0A CN104809543B (en) 2015-01-28 2015-01-28 Power system operating mode generation method based on monthly power transmission and transforming equipment repair schedule

Publications (2)

Publication Number Publication Date
CN104809543A true CN104809543A (en) 2015-07-29
CN104809543B CN104809543B (en) 2018-06-05

Family

ID=53694351

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510045164.0A Active CN104809543B (en) 2015-01-28 2015-01-28 Power system operating mode generation method based on monthly power transmission and transforming equipment repair schedule

Country Status (1)

Country Link
CN (1) CN104809543B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105262088A (en) * 2015-11-25 2016-01-20 上海交通大学 System for optimizing unit maintenance plan by considering adjustment capacity of large-scale ultra-high-voltage power supply
CN105574323A (en) * 2015-12-07 2016-05-11 国网安徽省电力公司 Method for economically optimizing monthly overhaul schedule of equipment based on transmission loss decline index
CN113706014A (en) * 2021-08-27 2021-11-26 广东电网有限责任公司 Arrangement method and device for power failure construction period
CN116436002A (en) * 2023-06-13 2023-07-14 成都航空职业技术学院 Building electricity utilization prediction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101527454A (en) * 2009-04-27 2009-09-09 国网电力科学研究院 Method for automatically generating annual running mode report of power grid
CN104050300A (en) * 2014-07-08 2014-09-17 国家电网公司 Risk assessment method, device and system for power grid running method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101527454A (en) * 2009-04-27 2009-09-09 国网电力科学研究院 Method for automatically generating annual running mode report of power grid
CN104050300A (en) * 2014-07-08 2014-09-17 国家电网公司 Risk assessment method, device and system for power grid running method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
丁明 等: "可靠性评估在电网运行方式及设备检修中的应用", 《合肥工业大学学报(自然科学版)》 *
蔡璐璇: "浅谈地区电网设备停电检修的运行方式策划", 《科技资讯》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105262088A (en) * 2015-11-25 2016-01-20 上海交通大学 System for optimizing unit maintenance plan by considering adjustment capacity of large-scale ultra-high-voltage power supply
CN105574323A (en) * 2015-12-07 2016-05-11 国网安徽省电力公司 Method for economically optimizing monthly overhaul schedule of equipment based on transmission loss decline index
CN105574323B (en) * 2015-12-07 2018-08-31 国网安徽省电力公司 The monthly repair schedule economy optimization method of equipment based on decreasing concentration index under network loss
CN113706014A (en) * 2021-08-27 2021-11-26 广东电网有限责任公司 Arrangement method and device for power failure construction period
CN116436002A (en) * 2023-06-13 2023-07-14 成都航空职业技术学院 Building electricity utilization prediction method
CN116436002B (en) * 2023-06-13 2023-09-05 成都航空职业技术学院 Building electricity utilization prediction method

Also Published As

Publication number Publication date
CN104809543B (en) 2018-06-05

Similar Documents

Publication Publication Date Title
Carpinelli et al. Optimal integration of distributed energy storage devices in smart grids
CN109190777B (en) Multi-time scale coordinated maintenance plan optimization method
CN107947244B (en) New energy power station grid-connected power advanced control method
CN107491867B (en) Safety checking and evaluating method for multi-cycle transmission and transformation maintenance plan
Kryonidis et al. A coordinated droop control strategy for overvoltage mitigation in active distribution networks
CN105226708B (en) A kind of large scale electric network operation plan equivalence coordination optimizing method
Dalhues et al. Research and practice of flexibility in distribution systems: A review
CN110490363B (en) Multi-day unit combination optimization method and system
CN108493998B (en) Robust power transmission network planning method considering demand response and N-1 expected faults
CN110543696B (en) Method for small unmodeled unit to participate in electric power market clearing and safety check
CN103887813B (en) Based on the control method that the wind power system of wind power prediction uncertainty runs
Liu et al. Rapid assessment of maximum distributed generation output based on security distance for interconnected distribution networks
CN104809543A (en) Power grid operation mode generating method based on monthly power transmission and distribution equipment maintenance plan
Reshikeshan et al. Autonomous voltage regulation by distributed PV inverters with minimal inter-node interference
Chamana et al. Buildings participation in resilience enhancement of community microgrids: Synergy between microgrid and building management systems
CN112865107B (en) Regional power grid voltage reactive power day-ahead forecasting method based on load prediction
Wang et al. Day-ahead allocation of operation reserve in composite power systems with large-scale centralized wind farms
CN106651136B (en) Day-ahead power generation plan compiling method and device for bilateral transaction
CN105067877A (en) Method of calculating power consumption mean value of multiple transformer parallel power supply system
McGarrigle et al. Cost savings from relaxation of operational constraints on a power system with high wind penetration
Jiang et al. Impacts of industrial baseline errors in demand side management enabled enterprise control
Eltohamy et al. Power system flexibility metrics review with high penetration of variable renewable generation
CN105160411A (en) Optimization method for configuring reactive compensation capacity based on entire life-cycle management
Hinojosa Static generation capacity expansion planning using linear transmission distribution factors
EP3667851B1 (en) Creation of dynamic models of network nodes in a low and / or medium voltage distribution network by use of a self learning algorithm

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Cui Xiaodan

Inventor after: Hong Tianxin

Inventor after: Li Wei

Inventor after: Li Bijun

Inventor after: Wang Zhengfeng

Inventor after: Fang Yongjie

Inventor after: Li Zhaowei

Inventor before: Cui Xiaodan

Inventor before: Li Wei

Inventor before: Li Bijun

Inventor before: Wang Zhengfeng

Inventor before: Fang Yongjie

Inventor before: Li Zhaowei

GR01 Patent grant
GR01 Patent grant