CN104795813A - Method for constructing medium-voltage distribution network demonstration system accessed by adaptive distributed power source - Google Patents

Method for constructing medium-voltage distribution network demonstration system accessed by adaptive distributed power source Download PDF

Info

Publication number
CN104795813A
CN104795813A CN201510162857.8A CN201510162857A CN104795813A CN 104795813 A CN104795813 A CN 104795813A CN 201510162857 A CN201510162857 A CN 201510162857A CN 104795813 A CN104795813 A CN 104795813A
Authority
CN
China
Prior art keywords
distribution network
section
voltage distribution
cross
medium voltage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510162857.8A
Other languages
Chinese (zh)
Inventor
惠慧
屈高强
刘伟
董晓晶
宫建锋
惠飞翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Electric Power Research Institute Co Ltd CEPRI
Economic and Technological Research Institute of State Grid Ningxia Electric Power Co Ltd
Original Assignee
China Electric Power Research Institute Co Ltd CEPRI
Economic and Technological Research Institute of State Grid Ningxia Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Electric Power Research Institute Co Ltd CEPRI, Economic and Technological Research Institute of State Grid Ningxia Electric Power Co Ltd filed Critical China Electric Power Research Institute Co Ltd CEPRI
Priority to CN201510162857.8A priority Critical patent/CN104795813A/en
Publication of CN104795813A publication Critical patent/CN104795813A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

A method for constructing a medium-voltage distribution network demonstration system accessed by an adaptive distributed power source includes determining main transformer capacity by 50% of load rate according to the maximum load of a target area, selecting a radiative frame structure as a frame structure of the medium-voltage distribution network, determining feeder line section of the medium-voltage distribution network by a method of selecting lead section by economic load power supply distance, and finally constructing the medium-voltage distribution network demonstration system according to the determined main transformer capacity, the radiative frame structure and the feeder line section, so that planners of the power distribution network can accurately analyze influences of the power distribution network accessed by the distributed power source according to the constructed medium-voltage distribution demonstration system quantitatively.

Description

Build the method for the medium voltage distribution network example system adapting to distributed power source access
Technical field
The present invention relates to Distribution system design technical field, particularly a kind of method building the medium voltage distribution network example system adapting to distributed power source access.
Background technology
Deterioration and the human society of exhaustion, the earth environment day by day of fossil fuel increase the dependence of the energy, make the utilization of distributed power source become the important means of national governments' energy-saving and emission-reduction, development green energy resource.Distributed power source generally can access medium voltage distribution network on the spot, greatly changes the general layout of original power distribution network, brings deep effect to power distribution network.
When distribution network planning personnel carry out planning application work, need the calculation of distribution network model that holds water to support, distributed power source access centering could be assessed scientifically and rationally and be press-fitted the impact that power distribution network brings.But power distribution network is larger, multi-point and wide-ranging, complex structure, containing a fairly large number of feeder line, distribution transforming etc., makes to set up unified example system model and becomes extremely difficult.
Summary of the invention
In view of this, be necessary to provide a kind of method building the medium voltage distribution network example system adapting to distributed power source access, said method is utilized to set up a medium voltage distribution network example system adapting to distributed power source and access, to carry out quantitative analysis exactly on after distributed power source access to the impact of power distribution network.
Build a method for the medium voltage distribution network example system adapting to distributed power source access, comprise the steps:
According to the peak load of objective area, undertaken determining main transformer capacity by 50% load factor;
Selective radiation formula grid structure is the grid structure of medium voltage distribution network;
Economic load power supply distance is adopted to select the method for conductor cross-section to determine feeder line cross section in medium voltage distribution network, wherein, economic load power supply distance refers to when reaching the maximum voltage drop allowable value that electric power enterprise specifies, the maximum distance that can reach when predetermined cross-sectional wire bearing maximum economic load level;
Construct the medium voltage distribution network example system of objective area according to the main transformer capacity determined, radiant type grid structure and feeder line cross section, on after distributed power source access, quantitative analysis is exactly carried out on the impact of power distribution network according to the medium voltage distribution network example system built to make distribution network planning personnel.
Above-mentioned structure adapts to the method for the medium voltage distribution network example system of distributed power source access, according to the peak load of objective area, undertaken determining main transformer capacity by 50% load factor, selective radiation formula grid structure is the grid structure of medium voltage distribution network, economic load power supply distance is adopted to select the method for conductor cross-section to determine feeder line cross section in medium voltage distribution network, last according to the main transformer capacity determined, the medium voltage distribution network example system of objective area is constructed in radiant type grid structure and feeder line cross section, on after distributed power source access, quantitative analysis is exactly carried out on the impact of power distribution network according to the medium voltage distribution network example system built to make distribution network planning personnel.
Accompanying drawing explanation
Accompanying drawing 1 is the flow chart of steps of the method for the medium voltage distribution network example system of the structure adaptation distributed power source access of a better embodiment.
Fig. 2 is the peak load-cost curve of middle pressure feeder line cross section series.
Fig. 3 is the method concrete steps flow chart building the 10kV medium voltage distribution network example system adapting to distributed power source access.
Fig. 4 is 10kV medium voltage distribution network example system.
In figure: the method step S301 ~ S304 building the medium voltage distribution network example system adapting to distributed power source access.
Embodiment
Please refer to Fig. 1, it is the method flow diagram of the medium voltage distribution network example system of the structure adaptation distributed power source access of a better embodiment, and this structure adapts to the method for the medium voltage distribution network example system of distributed power source access, comprises the steps:
Step S301, according to the peak load of objective area, is undertaken determining main transformer capacity by 50% load factor.
Step S302, selective radiation formula grid structure is the grid structure of medium voltage distribution network.Wherein, the grid structure of domestic medium voltage distribution network is based on radiant type, and chain type and looped network, under normal operating conditions also based on open loop, are similar to the operational mode of radiant type grid structure, therefore the grid structure selective radiation formula of medium voltage distribution network example system.
Step S303, economic load power supply distance is adopted to select the method for conductor cross-section to determine feeder line cross section in medium voltage distribution network, wherein, economic load power supply distance refers to when reaching the maximum voltage drop allowable value that electric power enterprise specifies, the maximum distance that can reach when predetermined cross-sectional wire bearing maximum economic load level.Wherein, step S303 is specially: a. is serial according to the conductor cross-section that the distribution network planning Guidance Rule of electric power enterprise is given, calculate the economic load range of harness, that is: in a certain load range, the total cost of certain cross section wire is lower than the expense of other all optional wires, this load range is called the economic load range of this cross section wire, the expense computing formula of wire is as follows:, wherein, for wire total cost, for wire construction cost, comprise initial outlay and labour cost, for the wire wear and tear expense of the 1st year, , wherein, for electricity price, for circuit institute on-load, for line resistance, for circuit rated voltage, for line power factor, for cost coefficient, be multiplied by the present worth that this value can obtain internal loss expense project period, value is generally 0.9%, such as, for 10kV overhead transmission line LGJ model, expense-peak load curve as shown in Figure 2 can be obtained according to the formula in a step, the economic load range that can obtain LGJ model is thus as shown in table 1:
; B. according to the result of calculation in a step, in conjunction with different feeder line institutes on-load capacity, primary election conductor cross-section series, determines the conductor cross-section type of transformer station's output feeder; C. the economic load power supply distance of single conductor cross-section and conductor cross-section series is determined, computing formula is as follows:, wherein, for economic load power supply distance, for electrical network allows maximum pressure drop, be the upper limit of Conductor's Economic load range, such as, still for 10kV overhead transmission line LGJ model, economic load power supply distance as shown in table 2 below can be obtained:
According to every bar feeder line on-load situation, design example system line length is in the scope being not more than economic load power supply distance; D. according to the result of calculation in step c, the verification carrying out under N-1 condition to pressing feeder line cross section in primary election, if do not met N-1 requirement, then adjust conductor cross-section, choose the larger wire in harness middle section or perform step a after installing voltage regulating device or capacitor, and finally determine middle pressure feeder line cross section.
Step S304, construct the medium voltage distribution network example system of objective area according to the main transformer capacity determined, radiant type grid structure and feeder line cross section, on after distributed power source access, quantitative analysis is exactly carried out on the impact of power distribution network according to the medium voltage distribution network example system built to make distribution network planning personnel.
Below in conjunction with embodiment, the method building the medium voltage distribution network example system adapting to distributed power source access is described further, referring to Fig. 3:
Build 10kV medium voltage distribution network example system, wherein 10kV medium voltage distribution network example system comprises 110/10kV main transformer, grid structure and circuit, wherein circuit A and another substation line exist and get in touch with, this interconnector institute on-load is 1MW:(1) selection of main transformer capacity: the maximum supply load of this transformer is 25MW, and therefore 50MVA selected by 110/10kV main transformer; (2) selection of grid structure: issue for 2013 and " the distribution network planning designing technique directive/guide " implemented according to Guo Wang company, when 110kV main transformer capacity is 50MVA, 10kV outgoing line interval is 8 ~ 14, therefore go out number of lines and select 10, the number of lines can be changed according to actual demand, and grid structure takes radiant type; (3) selection of feeder line: calculate for simplifying, design 10kV power distribution network example system 10 returns back out line and is overhead transmission line, and wire type is LGJ, wherein circuit A ~ E is respectively with peak load to be 2MW, circuit F ~ J is respectively with peak load to be 3MW, and according to a step, circuit A ~ E can select 120 mm 2wire, circuit F ~ J can select 185 mm 2wire, consider circuit institute on-load situation according to step c, determine that circuit A ~ E length is 4km, determine that circuit F ~ J length is 3km; (4) N-1 verification: circuit A exists contact, if interconnector transformer station breaks down, need this line load to transfer to main transformer shown in this example system, then circuit A turns on-load is 3MW, and the wire of LGJ120 mm2 can be with peak load to be 6MW, meet N-1 verification; (5) suppose that circuit A ~ J institute on-load is uniformly distributed, and nodes is 5, thus constructs 10kV medium voltage distribution network example system as shown in Figure 4.
Based on the 10kV medium voltage distribution network example system of above-mentioned establishment, after investigation all kinds distributed power source (comprising inverter type, synchronous electric type and asynchronous machine type) accesses power distribution network, on the impact that power distribution network short circuit current produces.Distribution network planning personnel build simulation model according to the above-mentioned 10kV medium voltage distribution network example system provided, and carry out simulation calculation, result of calculation is as shown in table 3:
As shown in Table 3, distributed power source is after access 10kV medium voltage distribution network example system, if concentrate access distributed power source at system head end, when type is synchronous machine, the short circuit current produced key node is maximum.Short circuit current aspect, substation bus bar is the maximum node of out-of-limit possibility, therefore, time when considering distributed power source access on the affecting of system short-circuit electric current, after answering emphasis Computation distribution formula plant-grid connection, when substation bus bar place is short-circuited, to the percussion of system, dynamic and thermal effect check is carried out to substation bus bar and switch simultaneously.

Claims (2)

1. build a method for the medium voltage distribution network example system adapting to distributed power source access, comprise the steps:
According to the peak load of objective area, undertaken determining main transformer capacity by 50% load factor;
Selective radiation formula grid structure is the grid structure of medium voltage distribution network;
Economic load power supply distance is adopted to select the method for conductor cross-section to determine feeder line cross section in medium voltage distribution network, wherein, economic load power supply distance refers to when reaching the maximum voltage drop allowable value that electric power enterprise specifies, the maximum distance that can reach when predetermined cross-sectional wire bearing maximum economic load level;
Construct the medium voltage distribution network example system of objective area according to the main transformer capacity determined, radiant type grid structure and feeder line cross section, on after distributed power source access, quantitative analysis is exactly carried out on the impact of power distribution network according to the medium voltage distribution network example system built to make distribution network planning personnel.
2. the method building the medium voltage distribution network example system adapting to distributed power source access according to claim 1, it is characterized in that: the step of " adopting economic load power supply distance to select the method for conductor cross-section to determine feeder line cross section in medium voltage distribution network " is specially: a. is serial according to the conductor cross-section that the distribution network planning Guidance Rule of electric power enterprise is given, calculate the economic load range of harness, that is: in a certain load range, the total cost of certain cross section wire is lower than the expense of other all optional wires, this load range is called the economic load range of this cross section wire, the expense computing formula of wire is as follows:
Wherein, being wire total cost, is wire construction cost, comprising initial outlay and labour cost, is the wire wear and tear expense of the 1st year, wherein, being electricity price, is circuit institute on-load, for line resistance, for circuit rated voltage, being line power factor, is cost coefficient, be multiplied by the present worth that this value can obtain internal loss expense project period, value is generally 0.9%;
B. according to the result of calculation in a step, in conjunction with different feeder line institutes on-load capacity, primary election conductor cross-section series, determines the conductor cross-section type of transformer station's output feeder;
C. determine the economic load power supply distance of single conductor cross-section and conductor cross-section series, computing formula is as follows:
Wherein, being economic load power supply distance, for electrical network allows maximum pressure drop, is the upper limit of Conductor's Economic load range;
D. according to the result of calculation in step c, the verification carrying out under N-1 condition to pressing feeder line cross section in primary election, if do not met N-1 requirement, then adjust conductor cross-section, choose the larger wire in harness middle section or perform step a after installing voltage regulating device or capacitor, and finally determine middle pressure feeder line cross section.
CN201510162857.8A 2015-04-09 2015-04-09 Method for constructing medium-voltage distribution network demonstration system accessed by adaptive distributed power source Pending CN104795813A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510162857.8A CN104795813A (en) 2015-04-09 2015-04-09 Method for constructing medium-voltage distribution network demonstration system accessed by adaptive distributed power source

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510162857.8A CN104795813A (en) 2015-04-09 2015-04-09 Method for constructing medium-voltage distribution network demonstration system accessed by adaptive distributed power source

Publications (1)

Publication Number Publication Date
CN104795813A true CN104795813A (en) 2015-07-22

Family

ID=53560427

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510162857.8A Pending CN104795813A (en) 2015-04-09 2015-04-09 Method for constructing medium-voltage distribution network demonstration system accessed by adaptive distributed power source

Country Status (1)

Country Link
CN (1) CN104795813A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105914735A (en) * 2016-04-29 2016-08-31 国网辽宁省电力有限公司朝阳供电公司 Power distribution network economical load flow calculating method
CN106296466A (en) * 2016-08-29 2017-01-04 中国电力科学研究院 A kind of feeder system planing method based on reliability

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103401270A (en) * 2013-08-13 2013-11-20 国家电网公司 Method and device for determining accepting ability of medium and lower voltage distribution network to distributed power sources
CN103887792A (en) * 2014-03-21 2014-06-25 北京四方继保自动化股份有限公司 Modeling method of low-voltage distribution network with distributed power supply

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103401270A (en) * 2013-08-13 2013-11-20 国家电网公司 Method and device for determining accepting ability of medium and lower voltage distribution network to distributed power sources
CN103887792A (en) * 2014-03-21 2014-06-25 北京四方继保自动化股份有限公司 Modeling method of low-voltage distribution network with distributed power supply

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张键: "市政工程电气***节能降耗技术措施探讨", 《建筑工程》 *
杨帆: "分布式能源接入的主动配电网典型***构建与分析", 《中国优秀硕士学位论文全文数据库(电子期刊)工程科技II辑》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105914735A (en) * 2016-04-29 2016-08-31 国网辽宁省电力有限公司朝阳供电公司 Power distribution network economical load flow calculating method
CN105914735B (en) * 2016-04-29 2018-06-26 国网辽宁省电力有限公司朝阳供电公司 A kind of power distribution network economic load tidal current computing method
CN106296466A (en) * 2016-08-29 2017-01-04 中国电力科学研究院 A kind of feeder system planing method based on reliability

Similar Documents

Publication Publication Date Title
Al‐Jaafreh et al. Planning and operation of LV distribution networks: a comprehensive review
Kordkheili et al. Determining maximum photovoltaic penetration in a distribution grid considering grid operation limits
Einfalt et al. Controlling active low voltage distribution grids with minimum efforts on costs and engineering
Murty et al. Impact of D‐STATCOM in distribution systems with load growth on stability margin enhancement and energy savings using PSO and GAMS
CN102244677A (en) Green energy Cloud computing method and system
CN103997125A (en) Energy-saving optimization dispatching system of multi-source power distribution network
Wang et al. Feasibility of integrating large wind farm via fractional frequency transmission system a case study
Qi et al. Impacts of a medium voltage direct current link on the performance of electrical distribution networks
JP2016208826A (en) Systems and methods for improved stability of power systems
Antoniadou-Plytaria et al. Chalmers campus as a testbed for intelligent grids and local energy systems
Xie et al. Optimal power flow calculation of power system with wind farms
Safitri et al. Coordination of single-phase rooftop PVs in unbalanced three-phase residential feeders for voltage profiles improvement
CN106786607B (en) A kind of method of determining UPFC project installation position and installed capacity
Fotoohabadi et al. Evaluating the technical benefits of AC–DC hybrid distribution systems consisting of solid-state transformers using a multiobjective index
CN104795813A (en) Method for constructing medium-voltage distribution network demonstration system accessed by adaptive distributed power source
He et al. Research on AC & DC hybrid power supply system with high‐proportion renewable energy of data centre
CN105067877A (en) Method for calculating power loss average value of multi-transformer parallel power supply system
Niemi et al. Alternative ways for voltage control in smart grids with distributed electricity generation
US11159046B1 (en) Dynamic computation and control of distributed assets at the edge of a power grid
Cong et al. Optimal allocation of soft open points in distribution networks based on candidate location opitimization
Sakagami et al. Performance of a DC-based microgrid system in Okinawa
CN106786568B (en) A kind of distribution power automation terminal is layouted planning and configuration method
Golder Photovoltaic generator modeling for large scale distribution system studies
Kang et al. Demand response-based preventive-corrective control against short-term voltage instability in power systems
Wei et al. Research on the reactive power optimization of distribution network including DG

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20150722

RJ01 Rejection of invention patent application after publication