CN104790977B - Tunnel just serves as a contrast formwork jumbo and its construction method - Google Patents
Tunnel just serves as a contrast formwork jumbo and its construction method Download PDFInfo
- Publication number
- CN104790977B CN104790977B CN201510092535.0A CN201510092535A CN104790977B CN 104790977 B CN104790977 B CN 104790977B CN 201510092535 A CN201510092535 A CN 201510092535A CN 104790977 B CN104790977 B CN 104790977B
- Authority
- CN
- China
- Prior art keywords
- door frame
- template
- bow member
- concrete
- frame assembly
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 20
- 238000009415 formwork Methods 0.000 title claims abstract description 19
- 238000005520 cutting process Methods 0.000 claims abstract description 18
- 238000009412 basement excavation Methods 0.000 claims abstract description 11
- 238000001802 infusion Methods 0.000 claims abstract description 10
- 238000005086 pumping Methods 0.000 claims abstract description 9
- 238000012423 maintenance Methods 0.000 claims abstract description 6
- 239000007788 liquid Substances 0.000 claims abstract description 5
- 238000009434 installation Methods 0.000 claims description 7
- 208000036829 Device dislocation Diseases 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 238000005266 casting Methods 0.000 description 2
- 230000010412 perfusion Effects 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009472 formulation Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 238000009416 shuttering Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The invention discloses a kind of tunnel just to serve as a contrast formwork jumbo and its construction method, and tunnel, which just serves as a contrast formwork jumbo, includes template mechanism and door frame assembly, and when pumping liquid concrete, template mechanism forms rigidity bow member in lining cutting position, and rigidity bow member is supported on door frame assembly;When during the concrete of infusion being in maintenance, the concrete support of infusion is on rigidity bow member, and rigidity bow member separates with door frame assembly.Using the present invention, realize during concrete curing while excavation operation can be carried out.
Description
Technical field
The present invention relates to a kind of working jumbo for tunnel lining, more particularly to a kind of tunnel just to serve as a contrast formwork jumbo and its construction party
Method, the tunnel lining cutting at initial stage on tunnel.
Background technology
Because country rock is poor from load in loess tunnel construction, it is impossible to which long drilling depth excavates, and general excavate every time is no more than 3 linear meter(lin.m.)s just
Preliminary bracing need to be carried out to tunnel immediately.Preliminary bracing typically has two kinds, and one kind carries out jet-anchor execution to hang bar-mat reinforcement, another
To carry out form concrete construction.
In form concrete construction is carried out, remaining core soil in advance is needed, construction space is small.At present steel is set up using artificial
Concreting is carried out after bow member, and gang form.The shortcomings that hand labor intensity is big be present in such a form of construction work.Simultaneously because
Steel arch-shelf need to manually set up thus use lighter section steel manufacture, and mechanical strength is low, can not be used in crown part and pour pressure
Big pump concrete mode casting concrete, thus crown concrete is owed to pour, and forms large area cavity, construction quality extreme difference.
In the prior art, the formwork jumbo for tunnel-liner is more, for example, China Patent No. " 201410596838.1 "
A kind of disclosed tunnel lining trolley, publication date 2015-02-18;For another example China Patent No. " 200520120695.3 " is open
A kind of portal frame tunnel lining form trolley, publication date 2007-02-14;And for example China Patent No.
One kind disclosed in " 201320088500.6 " is worked continuously overmolded dock working jumbo for tunnel lining, publication date 2013-09-
25.These formwork jumbos are to be used for Tunnel Second Lining concrete pouring construction operation, due to same during concrete curing
Shi Buneng influences to excavate, and is just served as a contrast if carrying out tunnel using existing formwork jumbo, can not be excavated during solidifying soil maintenance
Operation, thus existing formwork jumbo is not used to tunnel and just served as a contrast.
The content of the invention
It is an object of the invention to overcome above mentioned problem existing for prior art, there is provided a kind of tunnel just serve as a contrast formwork jumbo and
Its construction method.Using the present invention, realize during concrete curing while excavation operation can be carried out.
To achieve the above object, the technical solution adopted by the present invention is as follows:
A kind of tunnel just serves as a contrast formwork jumbo, it is characterised in that:Including template mechanism and door frame assembly, work as pumping liquid concrete
When, template mechanism forms rigidity bow member in lining cutting position, and rigidity bow member is supported on door frame assembly;At the concrete of infusion
When during maintenance, the concrete support of infusion is on rigidity bow member, and rigidity bow member separates with door frame assembly.
The template mechanism includes foundation forms and bow member template, and foundation forms, which is set in advance in, treats lining cutting position, bow member
Template is transported to foundation forms by door frame assembly and cooperatively forms rigidity bow member.
The bow member template includes crown template and side arch template, and crown template both sides are hinged with side arch template respectively, side
Encircle template and foundation forms bolt connection.
The door frame assembly includes door frame, walking mechanism, lifting body and translation mechanism, and walking mechanism is arranged on door frame
The motion of door frame assembly is driven, lifting body, which is arranged on door frame, drives the lifting of door frame assembly, and translation mechanism is arranged on band on door frame
Dynamic door frame assembly aligns tunnel center line.
The door frame includes door frame crossbeam, door frame column, door frame articulated beam and door frame longeron, and two door frame crossbeams pass through door
Frame articulated beam is fixedly connected, and door frame column is fixedly connected with door frame crossbeam, and door frame longeron is fixedly connected with door frame column.
The walking mechanism includes road wheel and the drive device moved by drive road wheel, and road wheel and drive device are equal
It is arranged on door frame longeron.
The lifting body includes jacking cylinder seat, longeron slide and jacking cylinder, and jacking cylinder seat is arranged on longeron cunning
In seat, jacking cylinder one end couples with jacking cylinder seat, and the other end couples with longeron slide, and longeron slide is fixedly installed on door frame
On longeron.
The translation mechanism includes chassis base and translation oil cylinder, and translation oil cylinder one end is hinged with jacking cylinder seat, another
End is hinged with chassis base, and jacking cylinder seat is slidably arranged on chassis base.
Stripper apparatus is additionally provided with the door frame column, stripper apparatus one end is connected with door frame column, the other end and side
Encircle template connection.The stripper apparatus is demoulding oil jar.
Support meanss are additionally provided with the door frame column, support meanss one end is connected with door frame column, the other end and base
Plinth template connects.The support meanss are very heavy to support.
A kind of tunnel just serves as a contrast the construction method of formwork jumbo, it is characterised in that comprises the following steps:
A, first treating lining cutting position both sides by manually laying foundation forms;
B, bow member template is transported to by lining cutting position by door frame assembly;
C, lifting body is moved, and door frame is risen into correct position;
D, translation mechanism moves, and door frame assembly is aligned tunnel center line;
E, stripper apparatus moves, and struts bow member template alignment foundation forms;
F, installation form mechanism and lock, and fittable slackening device;
G, pump concrete is finished to pouring, and concrete removes support meanss and stripper apparatus, falls door frame after steady,
The concrete that template mechanism support has just poured is left, and excavation operation is carried out after the door frame assembly that drives away, after the completion of excavation operation
Next group of template mechanism is transported again repeats above-mentioned work.
Using the advantage of the invention is that:
First, the present invention includes template mechanism and door frame assembly, and when pumping liquid concrete, template mechanism is formed in lining cutting position
Rigidity bow member, and rigidity bow member is supported on door frame assembly;When during the concrete of infusion being in maintenance, the concrete of infusion
It is supported on rigidity bow member, and rigidity bow member separates with door frame assembly;Using this structure, compared with existing secondary lining chassis,
Template mechanism and door frame assembly of the present invention is split-type structural, realizes during concrete curing while can carry out excavation work
Industry.
2nd, in the present invention, the template mechanism includes foundation forms and bow member template, and foundation forms, which is set in advance in, to be waited to serve as a contrast
Position is built, bow member template is transported to foundation forms by door frame assembly and cooperatively forms rigidity bow member;Using this structure, using voluntarily
Formula door frame sets up template, and mechanization degree is high, safe, labor intensity is low, construction speed also significantly improves.
3rd, in the present invention, the bow member template includes crown template and side arch template, and crown template both sides are encircleed with side respectively
Template is hinged, side arch template and foundation forms bolt connection;Using the combined type bow member template of this structure, be not only convenient for transport and
Installation, and be also easy to change.
4th, in the present invention, the door frame assembly includes door frame, walking mechanism, lifting body and translation mechanism, walking mechanism
It is arranged on door frame and drives the motion of door frame assembly, lifting body, which is arranged on door frame, drives the lifting of door frame assembly, and translation mechanism is set
Put on door frame drive door frame assembly align tunnel center line, this structure, realize chassis in tunnel front, back, left, right, up and
Under motion, can up and down and left and right adjustment chassis, chassis direction can be also corrected when chassis wanders off, improves efficiency of construction.
5th, in the present invention, the door frame includes door frame crossbeam, door frame column, door frame articulated beam and door frame longeron, two doors
Frame crossbeam is fixedly connected by door frame articulated beam, and door frame column is fixedly connected with door frame crossbeam, and door frame longeron is consolidated with door frame column
Fixed connection, using this structure, realizes combined type portal-framed structure, is easy to be adjusted door frame according to tunnel size.
6th, in the present invention, the walking mechanism includes road wheel and the drive device moved by drive road wheel, road wheel
It is arranged at drive device on door frame longeron, using this structure, realizes the mechanization movement of chassis, be easy to transport template.
7th, in the present invention, the lifting body includes jacking cylinder seat, longeron slide and jacking cylinder, jacking cylinder seat
It is arranged in longeron slide, jacking cylinder one end couples with jacking cylinder seat, and the other end couples with longeron slide, and longeron slide is consolidated
Surely it is arranged on door frame longeron, using this structure, drives door frame to lift by the way that oil cylinder is flexible, be easy to that mast height is adjusted flexibly,
So as to improve the installation joint efficiency of template.
8th, in the present invention, the translation mechanism includes chassis base and translation oil cylinder, translation oil cylinder one end and jacking cylinder
Seat is be hinged, and the other end is hinged with chassis base, and jacking cylinder seat is slidably arranged on chassis base, using this structure, by flat
Move the flexible drive door frame of oil cylinder to slide laterally relative to chassis base, be conveniently adjusted door frame and align tunnel center line.
9th, in the present invention, stripper apparatus is additionally provided with the door frame column, stripper apparatus one end connects with door frame column
Connect, the other end is connected with side arch template, and using this structure, the demoulding equally realizes mechanized operation, it is not necessary to it is artificial, reduce
Working strength.
Tenth, in the present invention, support meanss are additionally provided with the door frame column, support meanss one end connects with door frame column
Connect, the other end is connected with foundation forms, using this structure, adds the stability of rigidity bow member, concrete warehousing is using pumping
Mode, because the fast concrete lateral pressure of speed of perfusion is huge, this structure can avoid template from running mould.
To sum up, after using the present invention, the large form of big rigidity, big intensity can be used to carry out lining construction, using pumping
Concreting concrete, make concrete more closely knit, quality is significantly leaped.
Brief description of the drawings
Fig. 1 is main structure diagram of the present invention
Fig. 2 is side structure schematic view of the present invention
Fig. 3 is operating diagram of the present invention
Fig. 4 is door frame assembly of the present invention and template mechanism disengaged position schematic diagram
Fig. 5 is concrete curing view of the present invention
In figure mark for:1st, crown template, 2, template pin, 3, template locking bolt, 4, side arch template, 5, door frame longeron,
6th, foundation forms, 7, door frame articulated beam, 8, door frame crossbeam, 9, door frame column, 10, demoulding oil jar, 11, support it is very heavy, 12, chassis
Base, 13, translation oil cylinder, 14, jacking cylinder seat, 15, jacking cylinder, 16, road wheel.
Embodiment
Embodiment 1
A kind of tunnel just serves as a contrast formwork jumbo, including template mechanism and door frame assembly, and when pumping liquid concrete, template mechanism exists
Lining cutting position forms rigidity bow member, and rigidity bow member is supported on door frame assembly;When during the concrete of infusion being in maintenance,
The concrete support of infusion is on rigidity bow member, and rigidity bow member separates with door frame assembly.
The template mechanism includes foundation forms 6 and bow member template, and foundation forms 6, which is set in advance in, treats lining cutting position, arch
Frame template is transported to foundation forms 6 by door frame assembly and cooperatively forms rigidity bow member.
The bow member template includes crown template 1 and side arch template 4, and the both sides of crown template 1 are cut with scissors with side arch template 4 respectively
Connect, side arch template 4 and the bolt connection of foundation forms 6.
The door frame assembly includes door frame, walking mechanism, lifting body and translation mechanism, and walking mechanism is arranged on door frame
The motion of door frame assembly is driven, lifting body, which is arranged on door frame, drives the lifting of door frame assembly, and translation mechanism is arranged on band on door frame
Dynamic door frame assembly aligns tunnel center line.
The door frame includes door frame crossbeam 8, door frame column 9, door frame articulated beam 7 and door frame longeron 5, two door frame crossbeams 8
It is fixedly connected by door frame articulated beam 7, door frame column 9 is fixedly connected with door frame crossbeam 8, and door frame longeron 5 is fixed with door frame column 9
Connection.
The walking mechanism includes road wheel 16 and the drive device moved by drive road wheel 16, road wheel 16 and driving
Device is arranged on door frame longeron 5.
The lifting body includes jacking cylinder seat 14, longeron slide and jacking cylinder 15, and jacking cylinder seat 14 is arranged on
In longeron slide, the one end of jacking cylinder 15 couples with jacking cylinder seat 14, and the other end couples with longeron slide, and longeron slide is fixed
It is arranged on door frame longeron 5.
The translation mechanism includes chassis base 12 and translation oil cylinder 13, and the one end of translation oil cylinder 13 is cut with scissors with jacking cylinder seat 14
Connect, the other end is be hinged with chassis base 12, and jacking cylinder seat 14 is slidably arranged on chassis base 12.
Stripper apparatus is additionally provided with the door frame column 9, stripper apparatus one end is connected with door frame column 9, the other end with
Side arch template 4 connects.Preferably, the stripper apparatus is demoulding oil jar 10.
Support meanss are additionally provided with the door frame column 9, support meanss one end is connected with door frame column 9, the other end with
Foundation forms 6 connects.Preferably, the support meanss are support very heavy 11.
A kind of tunnel just serves as a contrast the construction method of formwork jumbo, comprises the following steps:
A, first treating lining cutting position both sides by manually laying foundation forms;
B, bow member template is transported to by lining cutting position by door frame assembly;
C, lifting body is moved, and door frame is risen into correct position;
D, translation mechanism moves, and door frame assembly is aligned tunnel center line;
E, stripper apparatus moves, and struts bow member template alignment foundation forms;
F, installation form mechanism and lock, and fittable slackening device;
G, pump concrete is finished to pouring, and concrete removes support meanss and stripper apparatus, falls door frame after steady,
The concrete that template mechanism support has just poured is left, and excavation operation is carried out after the door frame assembly that drives away, after the completion of excavation operation
Next group of template mechanism is transported again repeats above-mentioned work.
Embodiment 2
The present invention can match somebody with somebody more set templates and use designed for tunnel lining cutting at initial stage on tunnel.As shown in figure 1, at the present invention
In concrete casting condition.3 meters of chassis single group template length, multigroup template construction can be matched somebody with somebody.Chassis door frame is mobile and in place, template
Drive away after concrete cast terminates 3 hours, self-supported formwork bears alone concrete load.Basis is first laid when template is in place
Template 6 is simultaneously fixed, then lays side arch template 4 and crown template 1, is locked after being adjusted in place with template locking bolt 3.
The present invention is designed with lifting body and translation mechanism, can up and down and left and right adjustment chassis, may be used also when chassis wanders off
Correct chassis direction.
Concrete warehousing uses pumping mode, because the fast concrete lateral pressure of speed of perfusion is huge, to avoid template from running mould, to the greatest extent
Amount adds the concrete formulation of early strength agent using low slump, and poring rate is not more than:2 meters(Highly)/ hour.
Both sides foundation forms 6 of the present invention is manually installed, artificial leveling.Chassis uses rubber-tyred automatic traveling mechanism.
Embodiment 3
Jacking cylinder seat 14 of the present invention is installed in longeron slide, and the one end of jacking cylinder 15 couples with jacking cylinder seat 14,
The other end couples with longeron slide, and oil cylinder is flexible to drive door frame lifting.
Jacking cylinder seat 14 is slidably mounted on chassis base 12 simultaneously, and the one end of translation oil cylinder 13 is cut with scissors with jacking cylinder seat 14
Connect, the other end is be hinged with chassis base 12.Translation oil cylinder 13 is flexible to drive door frame to be slid laterally relative to chassis base 12.Tire
And drive mechanism is installed on door frame longeron 5.
The both sides of crown template 1 are be hinged with two sides arch template 4 respectively, while can also be bolted to connection, Huo Zhetong
Template pin 2 is crossed to connect.After crown template 1, side arch template 4, foundation forms 6 couple, a rigidity bow member is formed.
Construction method of the present invention is as follows:
First in lining cutting position both sides by manually laying foundation forms;
One group of 3 meters of long template is born by door frame assembly, starts drive mechanism to lining cutting position;
Operate jacking cylinder and rise door frame to correct position;
Translation oil cylinder is operated to median line;
Operation demoulding oil jar struts template alignment foundation forms;
Attachment bolt and locked on installation form;
Installation support is very heavy;
Begin pumping concrete and finish to pouring, wait concrete to remove and support very heavy, demoulding oil jar, fall door after steady
Frame, the concrete that shuttering supporting has just poured is left, and excavation operation is carried out after the chassis that drives away, born again after the completion of excavation operation
Next group of template repeats above-mentioned work.
Claims (4)
1. a kind of tunnel just serves as a contrast formwork jumbo, it is characterised in that:Including template mechanism and door frame assembly, when pumping liquid concrete,
Template mechanism forms rigidity bow member in lining cutting position, and rigidity bow member is supported on door frame assembly;When the concrete of infusion is in
When during maintenance, the concrete support of infusion is on rigidity bow member, and rigidity bow member separates with door frame assembly;
The door frame assembly includes door frame, walking mechanism, lifting body and translation mechanism, and walking mechanism is arranged on door frame and driven
Door frame assembly moves, and lifting body, which is arranged on door frame, drives the lifting of door frame assembly, and translation mechanism, which is arranged on door frame, drives door
Frame assembly aligns tunnel center line;
The lifting body includes jacking cylinder seat(14), longeron slide and jacking cylinder(15), jacking cylinder seat(14)Set
In longeron slide, jacking cylinder(15)One end and jacking cylinder seat(14)Connection, the other end couple with longeron slide, and longeron is slided
Seat is fixedly installed on door frame longeron(5)On;
The template mechanism includes foundation forms(6)With bow member template, foundation forms(6)It is set in advance in and treats lining cutting position, encircles
Frame template by door frame assembly transport to foundation forms(6)Cooperatively form rigidity bow member;
The bow member template includes crown template(1)Encircle template with side(4), crown template(1)Encircle template with side respectively in both sides(4)
Connection, side arch template(4)With foundation forms(6)Connection;
The door frame includes door frame crossbeam(8), door frame column(9), door frame articulated beam(7)With door frame longeron(5), two door frame horizontal strokes
Beam(8)Pass through door frame articulated beam(7)It is fixedly connected, door frame column(9)With door frame crossbeam(8)It is fixedly connected, door frame longeron(5)With
Door frame column(9)It is fixedly connected;
The translation mechanism includes chassis base(12)And translation oil cylinder(13), translation oil cylinder(13)One end and jacking cylinder seat
(14)It is be hinged, the other end and chassis base(12)Be hinged, jacking cylinder seat (14) is slidably arranged in chassis base(12)On.
2. tunnel according to claim 1 just serves as a contrast formwork jumbo, it is characterised in that:The walking mechanism includes road wheel
(16)With by drive road wheel(16)The drive device of motion, road wheel(16)Door frame longeron is arranged at drive device(5)
On.
3. tunnel according to claim 2 just serves as a contrast formwork jumbo, it is characterised in that:The door frame column(9)On also set up
There are stripper apparatus, stripper apparatus one end and door frame column(9)Connection, the other end and side arch template(4)Connection.
4. a kind of tunnel just serves as a contrast the construction method of formwork jumbo according to claim 1, it is characterised in that including following step
Suddenly:
A, first treating lining cutting position both sides by manually laying foundation forms;
B, bow member template is transported to by lining cutting position by door frame assembly;
C, lifting body is moved, and door frame is risen into correct position;
D, translation mechanism moves, and door frame assembly is aligned tunnel center line;
E, stripper apparatus moves, and struts bow member template alignment foundation forms;
F, installation form mechanism and lock, and fittable slackening device;
G, pump concrete is finished to pouring, and concrete removes support meanss and stripper apparatus, falls door frame, leave after steady
The concrete that template mechanism support has just poured, and excavation operation is carried out after the door frame assembly that drives away, transported again after the completion of excavation operation
Next group of template mechanism is sent to repeat above-mentioned work.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510092535.0A CN104790977B (en) | 2015-03-02 | 2015-03-02 | Tunnel just serves as a contrast formwork jumbo and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510092535.0A CN104790977B (en) | 2015-03-02 | 2015-03-02 | Tunnel just serves as a contrast formwork jumbo and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104790977A CN104790977A (en) | 2015-07-22 |
CN104790977B true CN104790977B (en) | 2018-04-10 |
Family
ID=53556111
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510092535.0A Expired - Fee Related CN104790977B (en) | 2015-03-02 | 2015-03-02 | Tunnel just serves as a contrast formwork jumbo and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104790977B (en) |
Families Citing this family (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106050270A (en) * | 2016-08-16 | 2016-10-26 | 北京康港工程技术有限公司 | Open cut tunnel forming construction device |
US10584502B2 (en) | 2016-09-09 | 2020-03-10 | Excel Project Management Ltd. | Arch-support system |
CN108240228B (en) * | 2016-12-26 | 2019-09-20 | 济南大学 | A kind of assembly equipment and construction technology of confined concrete arch |
CN107355237B (en) * | 2017-08-15 | 2023-06-30 | 中国路桥工程有限责任公司 | Walking type sliding mode concrete spraying and excavating multifunctional tunnel trolley |
CN107956490A (en) * | 2017-12-29 | 2018-04-24 | 中国铁道科学研究院铁道建筑研究所 | A kind of intelligent tunnel lining trolley |
CN109372547A (en) * | 2018-11-02 | 2019-02-22 | 中铁工程装备集团有限公司 | Narrow-bore tunnel rail-mounted lining trolley and lining methods |
CN109519197A (en) * | 2018-12-25 | 2019-03-26 | 中铁四局集团有限公司 | A kind of sliding formwork just dual-purpose trolley of lining excavation supporting and its application |
CN109538250B (en) * | 2019-01-28 | 2023-09-15 | 中南大学 | Device and method for quick construction of tunnel primary support with mould sprayed concrete |
CN110486052A (en) * | 2019-09-04 | 2019-11-22 | 中交天和机械设备制造有限公司 | A kind of press injecting type concrete support method and the supporting mechanism for implementing it |
CN112709162A (en) * | 2020-12-30 | 2021-04-27 | 中铁六局集团北京铁路建设有限公司 | Large-span thin-wall concrete sound barrier pouring trolley |
CN112726442A (en) * | 2020-12-30 | 2021-04-30 | 中铁六局集团北京铁路建设有限公司 | Construction method of large-span thin-wall concrete sound barrier pouring trolley |
Family Cites Families (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4224604B2 (en) * | 2003-03-25 | 2009-02-18 | 独立行政法人土木研究所 | Tunnel widening device |
CN201258747Y (en) * | 2008-08-26 | 2009-06-17 | 丁伟红 | Bottom placed continuous conveyor construction tunnel synchronization lining trolley |
CN201258746Y (en) * | 2008-08-26 | 2009-06-17 | 张新泉 | Overlapping type continuous conveyor construction tunnel synchronization lining trolley |
CN201627587U (en) * | 2010-03-25 | 2010-11-10 | 中国建筑第八工程局有限公司 | Overhang operating platform fixedly connected onto complete sectional hydraulic trolley |
CN102536261B (en) * | 2012-01-14 | 2014-06-18 | 湖南五新重型装备有限公司 | Retractable emergency car avoidance belt tunnel lining trolley |
CN203050728U (en) * | 2012-12-24 | 2013-07-10 | 重庆同展机械制造有限公司 | Lining template trolley |
CN103089278B (en) * | 2013-02-27 | 2015-05-20 | 中交隧道工程局有限公司 | Continuous operation rolling over docking type tunnel lining formwork trolley |
CN103114862B (en) * | 2013-02-27 | 2014-09-17 | 中交隧道工程局有限公司 | Loop butting tunnel lining construction method |
CN204627623U (en) * | 2015-03-02 | 2015-09-09 | 甘肃路桥建设集团有限公司 | Tunnel just serves as a contrast formwork jumbo |
-
2015
- 2015-03-02 CN CN201510092535.0A patent/CN104790977B/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN104790977A (en) | 2015-07-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104790977B (en) | Tunnel just serves as a contrast formwork jumbo and its construction method | |
CN105370298B (en) | Loess tunnel once lining hydraulic template trolley | |
CN102704949A (en) | No-pull rod side wall construction method for underground tunnel and formwork trolley for construction | |
CN104564102B (en) | A kind of tunnel lining concrete grouting device | |
CN204627623U (en) | Tunnel just serves as a contrast formwork jumbo | |
CN104533456A (en) | Super-large section chamber reinforced concrete modelling construction method | |
CN106593469B (en) | A kind of trolley for inverted arch construction | |
CN202596743U (en) | Formwork trolley for underground tunnel pull-rod-free side wall construction | |
CN207212365U (en) | A kind of wall arch is separable can Monolithic lining chassis | |
CN204662952U (en) | A kind of self-propelled tool single side formwork formwork system | |
CN103982200B (en) | Slide rail Mobile steel mould trolley in tunneling boring | |
CN110273695A (en) | A kind of Tunnel Second Lining formwork jumbo and its stage molding pouring procedure | |
CN110863855A (en) | Self-walking hydraulic trestle | |
CN105736012B (en) | A kind of tunnel lining concrete grouting device | |
CN203499697U (en) | Trolley used for concrete construction of various cross sections through mining method | |
CN110173281A (en) | A kind of sliding mode system for circular tunnel concreting | |
CN107829370A (en) | High pier is from climbing liquid press to turn over molds construction technology | |
CN204851287U (en) | Big section moving as a whole formula formwork support | |
CN107815971B (en) | High pier is from climbing liquid press to turn over molds system | |
CN204267046U (en) | A kind of tunnel lining concrete grouting device | |
CN110529146A (en) | A kind of equipment and its construction method for the construction of single-track tunnel inverted arch | |
CN107060831A (en) | One kind is used for tunnel groove constructing device | |
CN205955749U (en) | Tunnel invert construction equipment | |
CN206785405U (en) | One kind is used for tunnel groove constructing device | |
CN108150197A (en) | Radially overturning inverted arch trestle and its installation position method for demoulding to arc formwork |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180410 Termination date: 20210302 |
|