CN104790964A - Construction method for shield tunneling machine moving-out on condition of tunnel portal deviation - Google Patents

Construction method for shield tunneling machine moving-out on condition of tunnel portal deviation Download PDF

Info

Publication number
CN104790964A
CN104790964A CN201510209732.6A CN201510209732A CN104790964A CN 104790964 A CN104790964 A CN 104790964A CN 201510209732 A CN201510209732 A CN 201510209732A CN 104790964 A CN104790964 A CN 104790964A
Authority
CN
China
Prior art keywords
shield machine
shield
hole
tunneling machine
shield tunneling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510209732.6A
Other languages
Chinese (zh)
Inventor
彭磊
刘晓树
岳长城
刘金峰
王家丁
王春辉
李鹏
熊恒坤
候晗
刘涛
姚赤峰
冯明艳
张经强
周诚
杜金峰
杨涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Rail Transit Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Rail Transit Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd, Rail Transit Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN201510209732.6A priority Critical patent/CN104790964A/en
Publication of CN104790964A publication Critical patent/CN104790964A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a construction method for shield tunneling machine moving-out on the condition of tunnel portal deviation, and belongs to the technical field of building construction. The method comprises the steps that 1, measuring and setting out are performed; 2, an injected hole and a prospect hole are drilled; 3, partial original facilities are removed; 4, a shield tunneling machine receiving base is installed; 5, a shield tunneling machine is propelled; 6, the shield tunneling machine stops propelling; 7, a gap between the shield tail and the pile lining is tamped; 8, the shield tunneling machine is moved out; 9, the shield tunneling machine is recovered. The construction method for the shield tunneling machine moving-out on the condition of the tunnel portal deviation has the advantages that on the condition that an original design tunnel portal and an actual moving-out portal of the shield tunneling machine are deviated but not exceed enclosure piles, the shield tunneling machine moving-out is achieved without needing to arrange a tunnel portal again, the construction efficiency is greatly improved, the construction cost is saved, and the constructional difficulty is reduced.

Description

The construction method that a kind of shield machine is appeared under situation is departed from hole
Technical field
The invention belongs to technical field of building construction, be specifically related to the construction method that a kind of shield machine is appeared under situation is departed from hole.
Background technology
Current China is just actively developing subway work operation in vast city, and subway is generally divided into station and the interval two parts of shield structure.Shield-tunneling construction section is generally divided into again shield launching well in operation, shield structure interval and shield machine to receive well in operation 3 major part.Subway station and shield structure interval are often divided into different bid sections, designed respectively by different designing units and unit in charge of construction and constructed, in shield-tunneling construction, often the pre-buried steel occurred in shield machine direction of propulsion and shield structure received well is irised out hole and is had deviation to cause shield structure can not normal through arrival.If when now again applying out hole by normally appearing, often delaying duration, increase expense, being thus badly in need of the construction method that a kind of shield machine of exploitation can be appeared when hole is departed from.
Summary of the invention
The object of the invention is to overcome prior art deficiency, provide a kind of when former design portal and the actual portal of appearing of shield structure depart from and be no more than fender post, the construction method that shield machine is appeared.
The present invention realizes in the following manner:
The construction method that shield machine is appeared under situation is departed from hole, is characterized in that: the method comprises the following steps:
A, surveying and locating: according to newly-designed portal position measurement setting-out;
B, brill injected hole and horizontal inspecting hole: around new portal, bore 8-15 injected hole, wherein 2 for using horizontal inspecting hole, injected hole distance cutterhead external diameter 0.2-0.4 m, the degree of depth is 4-8 m, then in injected hole, bury mini-valve tube underground, open plum blossom hole along caliber 0.8-1.2 m, in order to ensure that shield machine can be through safely, no matter after portal, whether horizontal inspecting hole finds that there is water, all will be reinforced by mini-valve tube grouting methol liquid in advance;
C, remove portion existing facility: cut off pre-buried steel loop, abolish former portal, cut steel reinforced concrete fender post;
D, installation shield machine receive pedestal: cleaned out by received well base plate, spread the steel plate of 20-30 mm, steel plate is laterally spread the i iron of I 25, with steel plate, i iron is welded into entirety, along shield machine direction of propulsion, i iron and structure top is real, and finally install at i iron end face and receive bracket, composition shield machine receives pedestal;
E, shield machine advance: shield machine is pushed ahead and by synchronous grouting pipe cementing slurries, stopped grouting methol liquid when cutterhead withstands fender post, reception pedestal welds counter-force block, and shield machine continues normal propelling;
F, shield machine stop advancing: when the distance between shield ventral brush and fender post is less than 1.2 m, and shield machine stops advancing, and stop guaranteeing that shield machine shield ventral brush can not leave fender post scope when advancing at shield machine;
G, tamp space between shield tail and pile lining: spray early strength concrete toward the space between shield machine shield tail and pile lining and tamp, leave standstill 6-10 h and solidify completely to concrete;
H, shield machine are appeared: by synchronous grouting pipe cementing slurries to full state, after cement grout solidifies completely, in the end the upper common brick of pad bottom an endless tube sheet, and when preventing from appearing, section of jurisdiction sinks, and is slowly released by shield machine from new portal;
I, shield machine reclaim: shield machine leaves portal, disintegrate and hang away.
Preferred further, described mini-valve tube is Ф 50 steel pipe.
Preferred further, during by mini-valve tube grouting methol liquid, the water/binder ratio of cement grout gets 1.0, and tunnel axis bottom grouting pressure is 0.25 Mpa, and tunnel axis top grouting pressure is 0.2 Mpa.
Preferred further, when cutting steel reinforced concrete fender post, first up and then down segmentation cuts.
Compared with prior art, tool has the following advantages in the present invention:
(1) when departing from appears in shield machine and hole, do not need again to make new portal and just can realize shield machine and appear safely.
(2) construction method ratio of the present invention normally through saving construction cost 20 ~ 300,000 yuan of appearing, remarkable in economical benefits.
(3) construction method of the present invention is appeared more than the 2 weeks engineering time of saving than normally through, fast effectively.
(4) construction method design science of the present invention, safe and reliable, simple to operate, is beneficial to and applies.
Accompanying drawing explanation
Fig. 1 is the layout schematic diagram of appearing under situation is departed from shield machine hole of the present invention.
Fig. 2 is shield machine of the present invention location arrangements schematic diagram when withstanding fender post.
Fig. 3 is that shield machine ventral brush of the present invention is shut down when fender post and sprayed and fills out concrete schematic diagram.
In Fig. 1,2,3: the former design portal of 1-; The newly-designed portal position of 2-; 3-fender post; 4-injected hole and horizontal inspecting hole; 5-station main body; 6-cutterhead; 7-shield body; 8-section of jurisdiction; 9-early strength concrete; 10-receives pedestal.
Detailed description of the invention
In conjunction with following case history, the specific embodiment of the present invention is described further.
embodiment 1
Project profile:
Station, Wuhan Rail Transit No. 6 line first stage of the project Zhong Jia villages-Qin station running tunnel engineering is made up of one group of diplopore shield tunnel interval, interval right Xian Chuzhongjia village is northwards walked along parrot main road behind station, walk with No. 4 left line parallels of line, under wear north row after Beijing-Guangzhou Railway embankment and arrive qin platform.Due to received well portal and tunnel axis deviation, portal needs again to construct.When shield machine enters the station discovery deviation, portal steel loop also has little time installation, therefore cannot enter the station by normal through step, needs when through appearing by construction method construction of the present invention.
Shield duct piece ring external diameter 6m, internal diameter 5.4m, wall thickness 0.3m, ring width 1.5m, strength grade of concrete C50, seepage-resistant grade P12.This engineering geology is clay soil.
In conjunction with this engineering, detailed construction method of the present invention is:
A, surveying and locating: according to newly-designed portal position 2 surveying and locating;
B, brill injected hole and horizontal inspecting hole 4: around new portal, bore 8 injected holes, wherein 2 for using horizontal inspecting hole, injected hole distance cutterhead external diameter 0.3 m, the degree of depth is 6 m, then in injected hole, buries mini-valve tube underground, and mini-valve tube is Ф 50 steel pipe, plum blossom hole is opened along caliber 1.0 m, in order to ensure that shield machine can be through safely, no matter after portal, whether horizontal inspecting hole finds that there is water, all will be reinforced by mini-valve tube grouting methol liquid in advance;
C, remove portion existing facility: cut off pre-buried steel loop, abolish former portal, cuts steel reinforced concrete fender post 3, and when cutting fender post 3, segmentation is carried out from top to bottom;
D, installation shield machine receive pedestal 10: cleaned out by received well base plate, spread the steel plate of 20 mm, steel plate is laterally spread the i iron of I 25, with steel plate, i iron is welded into entirety, along shield machine direction of propulsion, i iron and structure top is real, and finally install at i iron end face and receive bracket, composition shield machine receives pedestal 10;
E, shield machine advance: shield machine is pushed ahead and by synchronous grouting pipe cementing slurries, grouting methol liquid is stopped when cutterhead 6 withstands fender post, during shield machine arrival fender post, shield structure thrust reduces, when after tunnel holing through, shield structure front is without propulsive thrust, to be connected causing section of jurisdiction 8 with the circumferential weld between section of jurisdiction and closely not produce and leak, therefore be used for increasing the propulsive thrust of shield machine receiving 10 weldering counter-force blocks on pedestal, in arrival tunneling process, that strengthens segment bolt tightens up work, and shield machine continues normal propelling;
F, shield machine stop advancing: when the distance between shield ventral brush and fender post is less than 1.2 m, and shield machine stops advancing, and stop guaranteeing that shield machine shield ventral brush can not leave fender post scope when advancing at shield machine;
G, tamp space between shield tail and pile lining: spray early strength concrete 9 toward the space between shield machine shield tail and pile lining, the space between shield tail and former portal is comparatively large, needs multi-injection early strength concrete 9, until completely closely knit, leave standstill 8 h and solidifies completely to concrete;
H, shield machine are appeared: by synchronous grouting pipe cementing slurries to full state, after cement grout solidifies completely, in the end the upper common brick of pad bottom an endless tube sheet, and when preventing from appearing, section of jurisdiction sinks, and is slowly released by shield machine from new portal;
I, shield machine reclaim: shield machine leaves portal, disintegrate and hang away.
Time in said method by mini-valve tube grouting methol liquid, the water/binder ratio of cement grout gets 1.0, and tunnel axis bottom grouting pressure is 0.25 Mpa, and tunnel axis top grouting pressure is 0.2 Mpa.
By above-mentioned construction method, process site operation that shield machine and hole occur departing from and cannot appear and to have suddenlyd change situation.When departing from appears in shield machine and hole, use construction method of the present invention, shield machine overall safety is appeared and is only used 7 days, again portal normal through then minimum needs 25 days of appearing again are carried out, in addition, construction method of the present invention eliminates the expense of the processing of portal steel loop and fabrication and installation, and appear cost-saving 20 ~ 300,000 yuan than normally through, therefore construction method of the present invention is quicker, economical.

Claims (4)

1. a shield machine construction method of appearing under situation is departed from hole, is characterized in that: the method comprises the following steps:
A, surveying and locating: according to newly-designed portal position measurement setting-out;
B, brill injected hole and horizontal inspecting hole: around new portal, bore 8-15 injected hole, wherein 2 for using horizontal inspecting hole, injected hole distance cutterhead external diameter 0.2-0.4 m, the degree of depth is 4-8 m, then in injected hole, mini-valve tube is buried underground, open plum blossom hole along caliber 0.8-1.2 m, reinforced by mini-valve tube grouting methol liquid;
C, remove portion existing facility: cut off pre-buried steel loop, abolish former portal, cut steel reinforced concrete fender post;
D, installation shield machine receive pedestal: cleaned out by received well base plate, spread the steel plate of 20-30 mm, steel plate is laterally spread the i iron of I 25, with steel plate, i iron is welded into entirety, along shield machine direction of propulsion, i iron and structure top is real, and finally install at i iron end face and receive bracket, composition shield machine receives pedestal;
E, shield machine advance: shield machine is pushed ahead and by synchronous grouting pipe cementing slurries, stopped grouting methol liquid when cutterhead withstands fender post, reception pedestal welds counter-force block, and shield machine continues normal propelling;
F, shield machine stop advancing: when the distance between shield ventral brush and fender post is less than 1.2 m, and shield machine stops advancing, and stop guaranteeing that shield machine shield ventral brush can not leave fender post scope when advancing at shield machine;
G, tamp space between shield tail and pile lining: spray early strength concrete toward the space between shield machine shield tail and fender post pile lining and tamp, leave standstill 6-10 h and solidify completely to concrete;
H, shield machine are appeared: by synchronous grouting pipe cementing slurries to full state, after cement grout solidifies completely, and in the end the upper common brick of pad bottom an endless tube sheet, slowly releases shield machine from new portal;
I, shield machine reclaim: shield machine leaves portal, disintegrate and hang away.
2. a kind of shield machine according to claim 1 construction method of appearing under situation is departed from hole, is characterized in that: described mini-valve tube is Ф 50 steel pipe.
3. a kind of shield machine according to claim 1 construction method of appearing under situation is departed from hole, it is characterized in that: during by mini-valve tube grouting methol liquid, the water/binder ratio of cement grout gets 1.0, tunnel axis bottom grouting pressure is 0.25 Mpa, and tunnel axis top grouting pressure is 0.2 Mpa.
4. a kind of shield machine according to claim 1 construction method of appearing under situation is departed from hole, it is characterized in that: when cutting steel reinforced concrete fender post, first up and then down segmentation cuts.
CN201510209732.6A 2015-04-29 2015-04-29 Construction method for shield tunneling machine moving-out on condition of tunnel portal deviation Pending CN104790964A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510209732.6A CN104790964A (en) 2015-04-29 2015-04-29 Construction method for shield tunneling machine moving-out on condition of tunnel portal deviation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510209732.6A CN104790964A (en) 2015-04-29 2015-04-29 Construction method for shield tunneling machine moving-out on condition of tunnel portal deviation

Publications (1)

Publication Number Publication Date
CN104790964A true CN104790964A (en) 2015-07-22

Family

ID=53556099

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510209732.6A Pending CN104790964A (en) 2015-04-29 2015-04-29 Construction method for shield tunneling machine moving-out on condition of tunnel portal deviation

Country Status (1)

Country Link
CN (1) CN104790964A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105221158A (en) * 2015-10-28 2016-01-06 广州广隧机电设备有限公司 Shield structure export & import note dual slurry construction method
CN107060813A (en) * 2016-12-24 2017-08-18 中铁十八局集团第四工程有限公司 A kind of method of sharp radius curve shield duct piece type selecting
CN107143339A (en) * 2017-07-26 2017-09-08 北京城建中南土木工程集团有限公司 The tunnel shielding portal sealing device and its eccentrically mounted method of position adjustable
JP2017536490A (en) * 2015-11-04 2017-12-07 中鉄十八局集団有限公司 High water pressure compatible mud balance pipe propulsion device and construction method
CN112228084A (en) * 2020-10-29 2021-01-15 上海市基础工程集团有限公司 Shield tunnel portal expanding reconstruction construction method
CN116575928A (en) * 2023-07-13 2023-08-11 中铁九局集团第四工程有限公司 Shield receiving construction method based on slope foundation pit condition

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06129187A (en) * 1992-10-16 1994-05-10 Tokyo Gas Co Ltd Underground piping method for continuous length steel pipe
JPH09296681A (en) * 1996-05-02 1997-11-18 Taisei Corp Shield tunneling method
CN101608551A (en) * 2009-06-15 2009-12-23 广东华隧建设股份有限公司 The job practices of a kind of shield machine closed origin and arrival
CN101975067A (en) * 2010-10-20 2011-02-16 中铁隧道集团二处有限公司 Light-section mud shield powder fine sand layer receiving method
CN102635362A (en) * 2011-11-02 2012-08-15 中铁隧道集团有限公司 Secondary reception constructing method for shield arrival
CN103277108A (en) * 2013-04-19 2013-09-04 中铁隧道集团有限公司 Slurry shield tunneling machine underwater arrival construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06129187A (en) * 1992-10-16 1994-05-10 Tokyo Gas Co Ltd Underground piping method for continuous length steel pipe
JPH09296681A (en) * 1996-05-02 1997-11-18 Taisei Corp Shield tunneling method
CN101608551A (en) * 2009-06-15 2009-12-23 广东华隧建设股份有限公司 The job practices of a kind of shield machine closed origin and arrival
CN101975067A (en) * 2010-10-20 2011-02-16 中铁隧道集团二处有限公司 Light-section mud shield powder fine sand layer receiving method
CN102635362A (en) * 2011-11-02 2012-08-15 中铁隧道集团有限公司 Secondary reception constructing method for shield arrival
CN103277108A (en) * 2013-04-19 2013-09-04 中铁隧道集团有限公司 Slurry shield tunneling machine underwater arrival construction method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105221158A (en) * 2015-10-28 2016-01-06 广州广隧机电设备有限公司 Shield structure export & import note dual slurry construction method
JP2017536490A (en) * 2015-11-04 2017-12-07 中鉄十八局集団有限公司 High water pressure compatible mud balance pipe propulsion device and construction method
CN107060813A (en) * 2016-12-24 2017-08-18 中铁十八局集团第四工程有限公司 A kind of method of sharp radius curve shield duct piece type selecting
CN107143339A (en) * 2017-07-26 2017-09-08 北京城建中南土木工程集团有限公司 The tunnel shielding portal sealing device and its eccentrically mounted method of position adjustable
CN107143339B (en) * 2017-07-26 2023-05-30 北京城建中南土木工程集团有限公司 Position-adjustable shield tunnel portal sealing device and eccentric installation method thereof
CN112228084A (en) * 2020-10-29 2021-01-15 上海市基础工程集团有限公司 Shield tunnel portal expanding reconstruction construction method
CN112228084B (en) * 2020-10-29 2022-07-08 上海市基础工程集团有限公司 Shield tunnel portal expanding reconstruction construction method
CN116575928A (en) * 2023-07-13 2023-08-11 中铁九局集团第四工程有限公司 Shield receiving construction method based on slope foundation pit condition
CN116575928B (en) * 2023-07-13 2023-10-13 中铁九局集团第四工程有限公司 Shield receiving construction method based on slope foundation pit condition

Similar Documents

Publication Publication Date Title
CN104790964A (en) Construction method for shield tunneling machine moving-out on condition of tunnel portal deviation
CN102562075B (en) Large cross-section weak surrounding rock tunnel three-step and six-part short-distance construction method
CN101864959B (en) Method for tunneling construction of main structure of underground station
CN106194218B (en) shield end soil body reinforcing system in high-water-head deep-thick sand layer area
CN102425427B (en) Method for constructing tunnel by utilizing shield empty-pushing crossing mine method
CN107091101B (en) Superimposed joint structure of middle mine shield junction tunnel in sea area and construction method
CN102322027A (en) A kind of method that adopts the Mine Method expansion to dig shield tunnel construction subway station
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN201412163Y (en) Circular tunnel lining structure for construction of open-type tunnel boring machine
CN103375170A (en) Underground excavation construction deformation control method for three-hole small clear distance tunnel underpass trunk railway
CN108005660A (en) A kind of Optimization of Expressway Tunnel Construction method
CN105332710A (en) Construction method suitable for up-down overlapped tunnel with small clear space and long distance under weak geological condition
CN101788082A (en) Construction method for abutting jack pipe underground
CN102400694A (en) Reinforcement method for combined part of shield tunnel and mining-method tunnel
CN107489433A (en) A kind of tunnel CRD engineering methods anti-leakage structure and Antiseep method
CN108691552A (en) Big cross section shape of a hoof shield cutting receives construction method
CN103498697A (en) Filling and construction method for goaf below tunnel
CN111472801A (en) Construction method for passing existing line under shallow-buried underground excavation drainage gallery
CN207033463U (en) Mine shield handing-over tunnel folded type joint design in the middle part of marine site
CN205036380U (en) Block of four encircles PBA and secretly digs subway station major structure
CN204457789U (en) A kind of stake arch wall supports the subway station digging large diameter shield tunnel and build
Chen et al. Construction technology of large diameter underwater shield tunnel
CN113775344A (en) Tunnel in-situ unilateral extension construction method
CN101538832A (en) Construction method for controlling two-dimension jacking of large-scale case
CN109695457A (en) The enlarging large section tunnel in situ and step construction method of hard rock

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
AD01 Patent right deemed abandoned

Effective date of abandoning: 20171103

AD01 Patent right deemed abandoned