CN104790405B - A kind of method that steel reinforcement cage manually transfers that caisson is overweight - Google Patents

A kind of method that steel reinforcement cage manually transfers that caisson is overweight Download PDF

Info

Publication number
CN104790405B
CN104790405B CN201510201590.9A CN201510201590A CN104790405B CN 104790405 B CN104790405 B CN 104790405B CN 201510201590 A CN201510201590 A CN 201510201590A CN 104790405 B CN104790405 B CN 104790405B
Authority
CN
China
Prior art keywords
reinforcement cage
steel reinforcement
steel
pipe
pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510201590.9A
Other languages
Chinese (zh)
Other versions
CN104790405A (en
Inventor
张明星
王尔
程秋明
汪远翱
蒋婉
朱晶晶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANHE CONSTRUCTION GROUP CO Ltd
Original Assignee
SHANHE CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANHE CONSTRUCTION GROUP CO Ltd filed Critical SHANHE CONSTRUCTION GROUP CO Ltd
Priority to CN201510201590.9A priority Critical patent/CN104790405B/en
Publication of CN104790405A publication Critical patent/CN104790405A/en
Application granted granted Critical
Publication of CN104790405B publication Critical patent/CN104790405B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses the method that the overweight steel reinforcement cage of a kind of caisson is manually transferred, make steel pipe square bearer; U-shaped draw-in groove is set; Making first is put more energy into and is bound round also welded reinforcement cage lengthways main steel bar thereon; On steel pipe square bearer, fix nylon rope, first segment steel reinforcement cage level is shelved on nylon rope; Progressively upwards prosthomere steel reinforcement cage is worked as in colligation; By below nylon rope, steel reinforcement cage is transferred; Continue next joint steel reinforcement cage of colligation, until the bottom of steel reinforcement cage arrives projected depth. The lifting scope that the invention solves crane gear is difficult to cover that pile foundation position, hoisting machinery are difficult to put in place, caisson overhead is subject to inner support beam obstruction etc. and can not or be difficult to transfer the problem of steel reinforcement cage, only need two workmans just can complete the making of steel reinforcement cage and transfer, reduced engineering cost.

Description

A kind of method that steel reinforcement cage manually transfers that caisson is overweight
Technical field
The present invention relates to building trade pile foundation construction field, relate in particular to that the overweight steel reinforcement cage of a kind of caisson manually transfersMethod, the steel reinforcement cage that is applicable to caisson artificial colligation transferring at the construction field (site),
Background technology
Generally, steel reinforcement cage is after factory or on-the-spot colligation complete, then is sling and transferred by crane gear and be arranged onIn pile foundation, but in the time of practice of construction, often there will be scene cannot park crane gear, or the lifting scope of crane gear withoutMethod covers all pile foundation positions etc. and can not or be difficult to transfer the situation of steel reinforcement cage,
Summary of the invention
The object of this invention is to provide the method that the overweight steel reinforcement cage of a kind of caisson is manually transferred, solved construction siteCrane gear cannot put down the situation of steel reinforcement cage, utilizes under the square bearer and steel reinforcement cage on the armored concrete retaining wall that is shelved on pile foundationThe fixing nylon rope of four U-shaped draw-in grooves of portion, manually carries out the colligation of steel reinforcement cage and transfers, and this method has been avoided having used and resetedThe variety of issue occurring when standby has been saved construction cost simultaneously; Contrast other and manually transfer steel reinforcement cage method, this method only needs 2Individually manually just can complete the colligation of steel reinforcement cage and transfer, and utilizing four U-shaped draw-in grooves, providing four supports to steel reinforcement cagePoint, has ensured the balance and stability that framework of steel reinforcement is transferred,
To achieve these goals, the present invention is by the following technical solutions:
A method that steel reinforcement cage manually transfers that caisson is overweight, comprises the following steps:
Step 1, making steel pipe square bearer, prepare the steel pipe of four, and wherein two is pressure-bearing pipe, and pressure-bearing length of tube is greater than reinforced concreteThe diameter of soil retaining wall; Another two is tube connector, and tube connector length is less than the diameter of armored concrete retaining wall, by the end of four sleeve pipesMouth cuts into interior circular arc and is divided into two pairs, and every pressure-bearing pipe two ends are symmetrically welded a pair of sleeve pipe, then tube connector is inserted in sleeve pipe,Finally obtain steel pipe square bearer, finally steel pipe square bearer is placed on armored concrete retaining wall.
Step 2, four plain bars are curved to four U-shaped draw-in grooves with angle bender, the width of U-shaped draw-in groove will be wider than Buddhist nunLong Sheng,
Make first segment steel reinforcement cage:
The first hoop of putting more energy into is carried out decile and carries out gauge point, and isodisperse equates with steel reinforcement cage lengthways main steel bar quantity, according to gauge point,Put more energy into and bind round outside welded reinforcement cage lengthways main steel bar successively at first,
According to the position of steel reinforcement cage lengthways main steel bar, four U-shaped draw-in groove notches making are symmetrically welded to first of steel reinforcement cage downPut more energy into hoop below and a side of U-shaped draw-in groove be welded on steel reinforcement cage lengthways main steel bar in road, and at two adjoining U-shaped draw-in groovesOn be welded with reinforced steel.
Step 3, two nylon ropes of preparation, every nylon rope one end is fixed on a pressure-bearing pipe with fast knot, and the other end is successivelyThrough two U-shaped draw-in grooves, on another root pressure-bearing pipe, be wound around three circles and then remaining nylon rope after winding be fixed on to pressure-bearing pipeEnd, stretching two nylon ropes, are shelved on nylon rope the first hoop level of putting more energy into.
Step 4, progressively upwards colligation when prosthomere steel reinforcement cage.
Step 5, after the colligation of prosthomere steel reinforcement cage, untie respectively the slip-knot of two nylon ropes, simultaneously slowly loosen twoNylon rope, steel reinforcement cage is stressed and steadily decline by being wrapped in the nylon rope of pressure-bearing Guan Shangsan circle, until the suitable for reading of steel reinforcement cage put more energy intoHoop stops while falling hole, then remaining nylon rope after being wound around is fixed on to the end of pressure-bearing pipe, returns to step 4 and continues colligationNext saves steel reinforcement cage, and repeating step 4, step 5 are until the bottom of steel reinforcement cage arrives projected depth.
In step 4 as above, the connection of steel reinforcement cage lengthways main steel bar adopts sleeve to connect, and the rate of plugging in same cross section is not superCross 50%, the every 2m of hoop that puts more energy into upwards arranges one, and steel reinforcement cage tie hoop is wrapped in steel reinforcement cage lengthways main steel bar outside, steel reinforcement cageTie hoop is firm with the contact point welding of steel reinforcement cage lengthways main steel bar.
Four U-shaped draw-in grooves of steel reinforcement cage as above bottom are as four strong points of steel reinforcement cage.
Advantage of the present invention and beneficial effect are:
(1) in the lifting scope that has solved crane gear is difficult to cover that pile foundation position, hoisting machinery are difficult to put in place, caisson overhead is subject toBrace summer obstruction etc. and can not or be difficult to transfer the problem of steel reinforcement cage,
(2) steel reinforcement cage is in the vertical colligation in foundation ditch hole, low to the stockyard site environment requirement of steel reinforcement cage,
(3) making of square bearer and U-shaped draw-in groove is simple, and it is easy to operate that cooperation nylon rope is transferred,
(4) only need two workmans just can complete the making of steel reinforcement cage and transfer, reduced engineering cost,
(5) position of employing four point control steel reinforcement cages, the laborsaving balance that can ensure again steel reinforcement cage while transferring.
Brief description of the drawings
Fig. 1 is mounting plane figure of the present invention,
Fig. 2 is mounting vertical plane figure of the present invention,
Fig. 3 is steel reinforcement cage decentralization process schematic diagram,
Fig. 4 is the detail drawing of steel reinforcement cage bottom nylon rope through U-shaped draw-in groove.
In figure: 1: armored concrete retaining wall; 2: pressure-bearing pipe: 3: tube connector; 4: sleeve pipe: 5: nylon rope: 6:U typeDraw-in groove; 7: the first hoop of putting more energy into; 8: steel reinforcement cage lengthways main steel bar; 9: steel reinforcement cage tie hoop; 10:U type draw-in groove is reinforced steelMuscle.
Detailed description of the invention
Embodiment 1
Caisson is an overweight device that steel reinforcement cage manually transfers, the structure of this device as shown in Figure 3: two pressure-bearing pipes 2 and two companiesTake over 3 and link together by four sleeve pipes 4, form a square bearer, be placed in above pile foundation armored concrete retaining wall 1; FourIndividual U-shaped draw-in groove 6 be symmetrically welded at steel reinforcement cage first put more energy into hoop 7, a side and the steel reinforcement cage lengthways main steel bar 8 of draw-in groove 6 are welded onTogether, and on the draw-in groove 6 closing on, be welded with a reinforced steel 10; Two nylon ropes 5 are U-shaped through two respectivelyDraw-in groove 6, one end is fixed on a pressure-bearing pipe 2, and the other end is fixed on another root pressure-bearing pipe 2 by slip-knot.
Described pressure-bearing pipe 2 and tube connector 3 all adopt the steel pipe of diameter 83mm, and wherein pressure-bearing pipe 2 length are greater than steelThe diameter of reinforced concrete retaining wall 1, tube connector 3 length are slightly less than the diameter of armored concrete retaining wall 1.
Four described sleeve pipes 4 all adopt 101 sleeve pipes, the port of sleeve pipe 4 are cut into interior circular arc and are symmetrically welded at and holdIn pressure pipe 2, then tube connector 3 is inserted in sleeve pipe 4, the position of sleeve pipe is just in time placed in armored concrete retaining wall 1 with tube connector 3On wall, be as the criterion, the length of tube connector 3 is as the criterion to make pressure-bearing pipe 2 just enter hole, finally steel pipe square bearer is placed in to reinforcing barOn concrete guard wall 1.
Described four U-shaped draw-in grooves 6 are bent and are formed by angle bender by plain bar, and the width of U-shaped draw-in groove 6 is wantedSlightly be wider than nylon rope, the degree of depth reaches 8cm, makes nylon rope 5 and not depart from draw-in groove 6 in the interior smooth slip of draw-in groove 6, according toThe position of steel reinforcement cage lengthways main steel bar 8, the first that four U-shaped draw-in groove 6 vertical symmetry making are welded on to steel reinforcement cage addsBelow strength hoop 7, and a side of draw-in groove 6 is welded on steel reinforcement cage lengthways main steel bar 8, then adds on two adjoining draw-in grooves 6Weld a reinforced steel, draw-in groove 6 opening down.
Described two nylon ropes 5 adopt the nylon rope 5 of length 45m, and one end is fixed on a pressure-bearing pipe 2 with fast knot,The other end is successively through two U-shaped draw-in grooves 6, at pressure-bearing pipe 2 and tube connector 3 hands over after being wound around three circles on another root pressure-bearing pipe 2Point outside is beaten slip-knot and is fixed, stretching two nylon ropes 5, and hoop 7 levels that make to put more energy into are shelved on nylon rope 5, and two workmans are successivelyUpwards vertical assembling reinforcement cage, after the colligation of first segment steel reinforcement cage, two workmans untie respectively the slip-knot of two nylon ropes 5,Slowly loosen two nylon ropes 5, steel reinforcement cage is steadily declined, until the hoop of putting more energy into suitable for reading of first segment steel reinforcement cage is fallen hole simultaneouslyIn time, stops, and fastens after the nylon rope 5 of movable end, and workman starts colligation second section steel reinforcement cage again, and cycling successively, until steelThe bottom of muscle cage arrives projected depth.
Effect: on-the-spot caisson is overweight, and steel reinforcement cage transfers adopts after this artificial downward putting device, can realize multiple positionsConstruction simultaneously, ensure while transferring steadily, reduced construction cost, illustrate that the result of use of this artificial downward putting device is remarkable.
Embodiment 2
As shown in Figure 1, the caisson degree of depth is 20m, and armored concrete retaining wall 1 is highly 0.5m~1m, and designing requirement is every colligation2m steel reinforcement cage is a joint, then transfers 2m, until steel reinforcement cage reaches the height of design.
A method that steel reinforcement cage manually transfers that caisson is overweight, comprises the following steps:
Step 1, as shown in Figure 1, makes steel pipe square bearer, prepares the steel pipe of four diameter 83mm, and wherein two length are greater thanThe diameter of armored concrete retaining wall 1 is pressure-bearing pipe 2; Another two length are slightly less than the diameter of armored concrete retaining wall 1, for connectingTake over 3, the port of four sleeve pipes 4 is cut into interior circular arc and is divided into two pairs, every pressure-bearing pipe 2 two ends are symmetrically welded a pair of coverPipe 4, then tube connector 3 is inserted in sleeve pipe 4, the position of sleeve pipe 4 is just in time placed in armored concrete retaining wall 1 wall with tube connector 3On be as the criterion, the length of tube connector 3 is as the criterion to make pressure-bearing pipe 2 just enter hole bore scope, finally obtains steel pipe square frameFrame, is finally placed in steel pipe square bearer on armored concrete retaining wall 1.
Step 2, as shown in Figure 3, curves four U-shaped draw-in grooves 6, U-shaped draw-in groove by four plain bars with angle bender6 width will be wider than nylon rope, and the degree of depth reaches 8cm, makes nylon rope 5 and not depart from draw-in groove in the interior smooth slip of draw-in groove 66。
Make first segment steel reinforcement cage:
The first hoop of putting more energy into 7 is carried out to decile, and isodisperse equates with steel reinforcement cage lengthways main steel bar 8 quantity, and carries out mark, according to markPoint, puts more energy into and binds round 7 outsides welded reinforcement cage lengthways main steel bar 8 successively at first.
According to the position of steel reinforcement cage lengthways main steel bar 8, four U-shaped draw-in groove 6 notches making are symmetrically welded to steel downThe first of muscle cage is put more energy into hoop 7 below and a side of draw-in groove 6 is welded on steel reinforcement cage lengthways main steel bar, and at adjoining twoOn draw-in groove 6, be welded with a reinforced steel.
The nylon rope 5 of step 3, two length 45m of preparation, every nylon rope 5 one end are fixed on a pressure-bearing pipe with fast knotOn 2, the other end is successively through two U-shaped draw-in grooves 6, after being wound around three circles on another root pressure-bearing pipe 2 over there and being then wound aroundRemaining nylon rope 5 is fixed on the end of pressure-bearing pipe 2, stretching two nylon ropes 5, make first put more energy into hoop 7 levels be shelved onOn nylon rope 5.
Step 4, progressively upwards colligation is when prosthomere steel reinforcement cage, and the connection of steel reinforcement cage lengthways main steel bar 8 adopts sleeve to connect, sameThe rate of plugging in cross section is no more than 50%, and the every 2m of hoop that puts more energy into upwards arranges that together, it is vertical that steel reinforcement cage tie hoop 9 is wrapped in steel reinforcement cageTo main muscle 8 outsides, steel reinforcement cage tie hoop 9 is firm with the contact point welding of steel reinforcement cage lengthways main steel bar 8.
Step 5, after the colligation of prosthomere steel reinforcement cage, two workmans untie respectively the slip-knot of two nylon ropes 5, simultaneously slowSlowly loosen two nylon ropes 5, steel reinforcement cage is stressed and steadily decline by being wrapped on pressure-bearing pipe 2 nylon ropes 5 of three circles, untilThe hoop of putting more energy into suitable for reading of steel reinforcement cage stops while falling hole, then remaining nylon rope 5 after being wound around is fixed on to the end of pressure-bearing pipe 2Portion, returns to step 4 and continues next joint steel reinforcement cage of colligation, and repeating step 4, step 5 are until the bottom of steel reinforcement cage arrives design deeplyDegree.
Specific embodiment described herein is only to the explanation for example of the present invention's spirit, the technical field of the inventionTechnical staff can to described specific embodiment make various amendments supplement or adopt similar mode substitute, butCan't depart from spirit of the present invention or surmount the defined scope of appended claims.

Claims (3)

1. the method that the overweight steel reinforcement cage of caisson is manually transferred, is characterized in that, comprises the following steps:
Step 1, making steel pipe square bearer, prepare the steel pipe of four, and wherein two is pressure-bearing pipe (2), and pressure-bearing pipe (2) length is largeIn the diameter of armored concrete retaining wall (1); Another two is tube connector (3), and tube connector (3) length is less than armored concrete and protectsThe diameter of wall (1), cuts into the port of four sleeve pipes (4) interior circular arc and is divided into two pairs, every pressure-bearing pipe (2) two endsBe symmetrically welded a pair of sleeve pipe (4), then tube connector (3) is inserted in sleeve pipe (4), finally obtain steel pipe square bearer, finally handleSteel pipe square bearer is placed on armored concrete retaining wall (1),
Step 2, four plain bars are curved to four U-shaped draw-in grooves (6) with angle bender, the width of U-shaped draw-in groove (6) is wideIn nylon rope,
Make first segment steel reinforcement cage:
The first hoop (7) of putting more energy into is carried out decile and carries out gauge point, and isodisperse equates with steel reinforcement cage lengthways main steel bar (8) quantity, rootAccording to gauge point, at first hoop (7) the outside welded reinforcement cage lengthways main steel bar (8) successively of putting more energy into,
According to the position of steel reinforcement cage lengthways main steel bar (8), four U-shaped draw-in grooves (6) notch of making is symmetrically welded to steel downThe first of the muscle cage hoop (7) of putting more energy into is welded on steel reinforcement cage lengthways main steel bar below and by a side of U-shaped draw-in groove (6), andOn adjoining two U-shaped draw-in grooves (6), be welded with reinforced steel,
Step 3, two nylon ropes of preparation (5), it is upper that every nylon rope (5) one end is fixed on a pressure-bearing pipe (2) with fast knot, anotherOne end, successively through two U-shaped draw-in grooves (6), then will be wound around rear remaining Buddhist nun at upper three circles that are wound around of another root pressure-bearing pipe (2)Dragon rope (5) is fixed on the end of pressure-bearing pipe (2) by slip-knot, stretching two nylon ropes (5) make the first hoop of putting more energy into
(7) level is shelved on nylon rope (5) above,
Step 4, progressively upwards colligation when prosthomere steel reinforcement cage,
Step 5, after the colligation of prosthomere steel reinforcement cage, untie respectively the slip-knot of two nylon ropes (5), simultaneously slowly loosen twoNylon rope (5), steel reinforcement cage by be wrapped in pressure-bearing pipe (2) upper three circle nylon rope (5) stressed and steadily decline, until steelMuscle cage suitable for reading put more energy into and stops when hoop is fallen hole, then will be wound around remaining nylon rope (5) afterwards and be fixed on pressure-bearing pipe (2)End, returns to step 4 and continues next joint steel reinforcement cage of colligation, and repeating step 4, step 5 are until the bottom of steel reinforcement cage arrives designThe degree of depth.
2. the method that the overweight steel reinforcement cage of a kind of caisson according to claim 1 is manually transferred, is characterized in that described stepIn rapid 4, the connection of steel reinforcement cage lengthways main steel bar (8) adopts sleeve to connect, and the rate of plugging in same cross section is no more than 50%, the hoop of putting more energy intoEvery 2m upwards arranges one, and steel reinforcement cage tie hoop (9) is wrapped in steel reinforcement cage lengthways main steel bar (8) outside, steel reinforcement cage spiralStirrup (9) is firm with the contact point welding of steel reinforcement cage lengthways main steel bar (8).
3. the method that the overweight steel reinforcement cage of a kind of caisson according to claim 1 is manually transferred, is characterized in that, under steel reinforcement cageFour U-shaped draw-in grooves of portion are as four strong points of steel reinforcement cage.
CN201510201590.9A 2015-04-24 2015-04-24 A kind of method that steel reinforcement cage manually transfers that caisson is overweight Active CN104790405B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510201590.9A CN104790405B (en) 2015-04-24 2015-04-24 A kind of method that steel reinforcement cage manually transfers that caisson is overweight

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510201590.9A CN104790405B (en) 2015-04-24 2015-04-24 A kind of method that steel reinforcement cage manually transfers that caisson is overweight

Publications (2)

Publication Number Publication Date
CN104790405A CN104790405A (en) 2015-07-22
CN104790405B true CN104790405B (en) 2016-05-25

Family

ID=53555560

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510201590.9A Active CN104790405B (en) 2015-04-24 2015-04-24 A kind of method that steel reinforcement cage manually transfers that caisson is overweight

Country Status (1)

Country Link
CN (1) CN104790405B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110206037A (en) * 2019-04-30 2019-09-06 杭州市市政工程集团有限公司 A kind of flexible construction method of underground continuous wall of steel strand wires as main reinforcement
CN112359836B (en) * 2020-11-05 2022-02-01 江苏省交通工程集团有限公司 Large-diameter pile foundation reinforcement cage supporting device and construction method applying same
CN112482378B (en) * 2020-11-06 2022-02-01 一山(北京)岩土工程有限公司 Full-automatic steel reinforcement cage device that transfers of static pressure stake pile bolck

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS557310A (en) * 1978-06-29 1980-01-19 Nippon Kokan Kk <Nkk> Method of constructing underground continuous wall by use of steel-frame material with no joint
CN201439598U (en) * 2009-06-29 2010-04-21 浙江省舟山连岛工程建设指挥部 Lowering device for reinforcing cage of drilled pile
CN202298606U (en) * 2011-09-26 2012-07-04 中交第二航务工程局有限公司 Descending frame for mounting reinforcement cage of pile foundation
CN102518122B (en) * 2011-11-17 2014-07-09 中铁十五局集团有限公司 Leading-in method of bridge foundation reinforced concrete hole pile reinforcement cage
CN103556627B (en) * 2013-10-31 2016-08-17 中铁港航局集团有限公司 A kind of hanging cage structure for large diameter bored pile reinforcing bar cage hoisting
CN103556626B (en) * 2013-10-31 2015-06-17 中铁港航局集团有限公司 Hanging structure for hoisting large-diameter hole drilling filling pile steel bar cage

Also Published As

Publication number Publication date
CN104790405A (en) 2015-07-22

Similar Documents

Publication Publication Date Title
CN104790405B (en) A kind of method that steel reinforcement cage manually transfers that caisson is overweight
CN102828510B (en) H type soldier pile and preparation method thereof
CN201896456U (en) Straight screw sleeve connection mold for main reinforcement of filling pipe reinforcing cage
EP2239398B1 (en) Tower
EP3662122A1 (en) Foundation for a structure
CN104831818A (en) Connection node of precast reinforced concrete beam and laminated column
CN204753836U (en) Connected node of precast reinforced concrete roof beam and coincide post
CN106400784B (en) The construction method of bored concrete pile is made of filling pile cage of reinforcement
CN106400783B (en) The construction method of bored concrete pile is made of expansion steel reinforcement cage
CN202730755U (en) H-shaped support pile
CN204753567U (en) Reinforcement high-pressure jet grouting support pile structure
CN204040310U (en) A kind of bar planting structure adopting also muscle
CN204849737U (en) A stake of pre -buried formula combination stand for foundation ditch
CN204626383U (en) A kind of hole digging pile is overweight device that reinforcing cage manually transfers
CN208981895U (en) Lifting and self-climbing combined mechanism for erecting power transmission tower
JP6434349B2 (en) Pile reinforcement bar and its holding member
CN206843951U (en) Steel case arch bridge faces the anchor pushing tow system after pre-splicing
CN201809974U (en) Glass steel cylindrical formwork device
CN202220403U (en) Prefabricated reinforced concrete structural column used in fabricated building
CN204059609U (en) A kind of reinforcing steel bar connecting device of precast beam Column border node
CN109778806B (en) Construction method for integrally sliding and lifting pier wall with connecting beam
CN104859365A (en) Manufacturing method for cylindrical hillstone landscape
JPS6017449Y2 (en) Rebar cage
CN205362495U (en) Novel stirrup processing device
CN217352865U (en) Steel pipe concrete composite column beam column node structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PP01 Preservation of patent right
PP01 Preservation of patent right

Effective date of registration: 20240326

Granted publication date: 20160525