CN104778488B - Steel building site based on BIM - Google Patents

Steel building site based on BIM Download PDF

Info

Publication number
CN104778488B
CN104778488B CN201510113614.5A CN201510113614A CN104778488B CN 104778488 B CN104778488 B CN 104778488B CN 201510113614 A CN201510113614 A CN 201510113614A CN 104778488 B CN104778488 B CN 104778488B
Authority
CN
China
Prior art keywords
bim
information
quick response
component
response code
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510113614.5A
Other languages
Chinese (zh)
Other versions
CN104778488A (en
Inventor
魏鲁双
汤明
刘尚蔚
姜华
尹伟波
孙凯
魏群
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China University of Water Resources and Electric Power
Original Assignee
North China University of Water Resources and Electric Power
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China University of Water Resources and Electric Power filed Critical North China University of Water Resources and Electric Power
Priority to CN201510113614.5A priority Critical patent/CN104778488B/en
Publication of CN104778488A publication Critical patent/CN104778488A/en
Application granted granted Critical
Publication of CN104778488B publication Critical patent/CN104778488B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Length Measuring Devices By Optical Means (AREA)

Abstract

A kind of steel building site based on BIM, include the Quick Response Code or three-dimension code and the surveyor's beacon positioned at Quick Response Code or three-dimension code center of periphery, BIM information is included in Quick Response Code or three-dimension code.Design information, construction technology information, the material information of building element, and the link information between other adjacent members are included in the Quick Response Code or three-dimension code.The steel building site based on BIM is used for the both ends for being attached to steel structure member, its internal Quick Response Code or three-dimension code can provide the BIM information of component, construction worker selects suitable component according to these information, and the component is installed to accurate position, speed of application and construction quality can be greatly improved.Quick Response Code or the terminal of three-dimension code scanning, can come out the information scanning in Quick Response Code or three-dimension code, such testing staff significantly lifts detection efficiency with regard to that can abandon hand-held technical data on being installed additional on theodolite.

Description

Steel building site based on BIM
Technical field
The present invention relates to BIM technology field, more particularly to a kind of steel building site based on BIM.
Background technology
BIM spelling is Building Information Modeling, i.e.,:BIM.BIM is with three-dimensional Based on digital technology, the data model of the various relevant informations of construction-engineering project is integrated with, BIM is to engineering project The digital expression of infrastructure entities and functional characteristic.One perfect information model, being capable of connecting building project life cycle difference Data, process and the resource in stage, it is the complete description to engineering object, can be generally used by each participant of construction project.BIM With single project data source, can solve the uniformity between distributed, isomery project data and globally shared problem, support to build If the interim dynamic engineering information of project life is created, manages and shared.BIM is that one kind is applied to set again simultaneously Meter, build, the digitizing solution of management, this method supports the integrated management environment of architectural engineering, architectural engineering can be made to exist Efficiency is significantly improved in its whole process and is largely reduced risks.
In fact, it is a kind of new technology for leading Information industry technological direction higher level, its overall application, will be The scientific and technological progress for building industry produces beyond measure influence, greatly improves the integration degree of architectural engineering.Meanwhile also to build The development for building industry brings huge benefit, and the quality and efficiency for making design or even whole engineering significantly improve, and cost reduces.
But in practical engineering application, how simple builder is as the personnel directly contacted with building, BIM Them are passed to, and it is a problem to allow them to be applied in construction, special steel building field, builder is to component Familiarity is inadequate, and during installation, how the component of shaping selects all to be problem for them, has to be solved.
Surveyor's beacon as measurement indicate, be for detect building whether the important inspection constructed according to design drawing requirement Mark remembers that surveyor's beacon of the prior art is all a single mark, not comprising any information, also has while measurement and compares Technical data, it is cumbersome.
The content of the invention
The purpose of the present invention is:A kind of steel building positioning patch simple in construction, easy to use based on BIM is provided Piece.
The technical scheme is that:A kind of steel building site based on BIM, it is characterized in that:Including periphery Quick Response Code or three-dimension code and the surveyor's beacon positioned at Quick Response Code or three-dimension code center, include BIM information in Quick Response Code or three-dimension code.
Design information, construction technology information, the material information of building element are included in the Quick Response Code or three-dimension code, and With the link information between other adjacent members.
The design information include position in whole building of component name, component, component shape, component installation Position, the material of component, the engineering property of component.
The construction technology information includes working procedure, method, progress, cost, quality requirement.
The link information includes the title of coupled component, and link position and connected mode.
The spacer has the unique identification number being adapted with BIM in whole structural steelwork component.
The technique effect of the present invention:
The steel building site based on BIM is used for the both ends for being attached to steel structure member, its internal Quick Response Code Or three-dimension code can provide the BIM information of component, construction worker can be by obtaining, so as to root after special terminal scanning Select suitable component according to these information, and the component be installed to accurate position, can greatly improve speed of application and Construction quality.
After installation is complete, personnel's work can be detected to steel building by being somebody's turn to do the steel building site based on BIM Detected for surveyor's beacon, install the terminal of Quick Response Code or three-dimension code scanning additional on theodolite, can be by Quick Response Code or three-dimension code In information scanning come out, the technical data needed for testing staff is included in these information, such testing staff is with regard to that can abandon Hand-held technical data, significantly lifts detection efficiency.
Brief description of the drawings
Fig. 1 is the structural representation of the steel building site based on BIM;
1. Quick Response Codes or three-dimension code, 2. surveyor's beacons in figure.
Embodiment
Embodiment:Referring to Fig. 1, a kind of steel building site based on BIM in figure, including periphery Quick Response Code or Three-dimension code and the surveyor's beacon positioned at Quick Response Code or three-dimension code center, BIM information is included in Quick Response Code or three-dimension code.The Quick Response Code or Design information, construction technology information, the material information of building element are included in three-dimension code, and between other adjacent members Link information.The design information includes position in whole building of component name, component, shape, the peace of component of component Holding position, the material of component, the engineering property of component.The construction technology information include working procedure, method, progress, cost, Quality requirement.The link information includes the title of coupled component, and link position and connected mode.It is described fixed Bit slice has the unique identification number being adapted with BIM in whole structural steelwork component.
Worker according to the information of the carrying on the BIM digital figure pieces on connecting plate, can determine the position of location-plate with Angle;Ensure connection Board position and hole site correctly and precision;Construction manager can be carried out an acceptance inspection according to these information and Check.
Difference of the spacer according to purposes, entrained information is different, but all information be according to BIM form and Data organization enters in Quick Response Code or the three-dimension code of spacer, and is printed upon on spacer;
The application of the spacer, the Various types of data in BIM can be made accurately to transmit and identify,
The weld information needed for welding robot is also provided with the Quick Response Code or three-dimension code of spacer, can help to weld Robot completes the welding process of automation.
Described end of scan can be special end of scan or can identify Quick Response Code or the hand of three-dimension code Machine.
A nanometer microelectronics piece can also be added in the paster in addition, for the two-way corner of Real-time Feedback component.

Claims (6)

1. a kind of steel building site based on BIM, it is characterized in that:Including peripheral Quick Response Code or three-dimension code and it is located at Quick Response Code or the surveyor's beacon at three-dimension code center, BIM information is included in Quick Response Code or three-dimension code.
2. the steel building site according to claim 1 based on BIM, it is characterized in that:The Quick Response Code or three Design information, construction technology information, the material information of building element, and the company between other adjacent members are included in dimension code Connect information.
3. the steel building site according to claim 2 based on BIM, it is characterized in that:The design information bag Include position in whole building of component name, component, the shape of component, the installation site of component, the material of component, component Engineering property.
4. the steel building site according to claim 2 based on BIM, it is characterized in that:The construction technology letter Breath includes working procedure, method, progress, cost, quality requirement.
5. the steel building site according to claim 2 based on BIM, it is characterized in that:The link information bag Include the title of coupled component, and link position and connected mode.
6. the steel building site according to claim 1 based on BIM, it is characterized in that:The spacer is whole There is the unique identification number being adapted with BIM in individual structural steelwork component.
CN201510113614.5A 2014-11-28 2015-03-16 Steel building site based on BIM Active CN104778488B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510113614.5A CN104778488B (en) 2014-11-28 2015-03-16 Steel building site based on BIM

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN2014107015332 2014-11-28
CN201410701533 2014-11-28
CN201510113614.5A CN104778488B (en) 2014-11-28 2015-03-16 Steel building site based on BIM

Publications (2)

Publication Number Publication Date
CN104778488A CN104778488A (en) 2015-07-15
CN104778488B true CN104778488B (en) 2018-04-10

Family

ID=53619941

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201510113614.5A Active CN104778488B (en) 2014-11-28 2015-03-16 Steel building site based on BIM
CN201520147517.3U Withdrawn - After Issue CN205080575U (en) 2014-11-28 2015-03-16 Steel construction building locating pasting piece based on BIM

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201520147517.3U Withdrawn - After Issue CN205080575U (en) 2014-11-28 2015-03-16 Steel construction building locating pasting piece based on BIM

Country Status (1)

Country Link
CN (2) CN104778488B (en)

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104778488B (en) * 2014-11-28 2018-04-10 华北水利水电大学 Steel building site based on BIM
CN105976274B (en) * 2016-05-03 2019-06-18 郑州科技学院 It is a kind of for managing the site of ancient architecture building body
CN106296014A (en) * 2016-08-15 2017-01-04 上海宝冶集团有限公司 Steel construction based on BIM and Quick Response Code produces delivery system
CN106600137A (en) * 2016-12-08 2017-04-26 东莞华南设计创新院 Application method of steel structure BIM (building information modeling) informatization platform
CN106777751A (en) * 2016-12-30 2017-05-31 译筑信息科技(上海)有限公司 Architecture information processing method and processing device
WO2018143151A1 (en) * 2017-01-31 2018-08-09 三井住友建設株式会社 Surveying marker and surveying system
CN106869308B (en) * 2017-03-13 2019-06-11 同济大学 A kind of quick turnover method of assembled architecture support system based on BIM
CN106951939A (en) * 2017-03-22 2017-07-14 安固士(天津)建筑材料有限公司 A kind of antidetonation suspension and support identification Quick Response Code obtains information engineering method
CN107300723B (en) * 2017-08-01 2023-09-26 贺州学院 Assembly type building assembly detection device and method
CN108427811A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of PC components Life cycle tracking, apparatus and system
CN108428031A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of method and device of the status inquiry based on assembled architecture
CN109680924A (en) * 2018-12-31 2019-04-26 宁波二十冶建设有限公司 A kind of aluminum alloy mould plate and construction method with planar bar code technology
CN109653400A (en) * 2019-01-31 2019-04-19 陈志敏 Building and two dimensional code architectural image construct system
JP6693616B1 (en) 2019-12-11 2020-05-13 計測技研株式会社 Surveying system and surveying method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103473720A (en) * 2013-09-06 2013-12-25 上海大学 Shield tunnel construction management system based on BIM
CN103530827A (en) * 2013-09-26 2014-01-22 中铁建设集团有限公司 Assembly type building component intelligent management system based on BIM (building information modeling)
CN205080575U (en) * 2014-11-28 2016-03-09 华北水利水电大学 Steel construction building locating pasting piece based on BIM

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103473720A (en) * 2013-09-06 2013-12-25 上海大学 Shield tunnel construction management system based on BIM
CN103530827A (en) * 2013-09-26 2014-01-22 中铁建设集团有限公司 Assembly type building component intelligent management system based on BIM (building information modeling)
CN205080575U (en) * 2014-11-28 2016-03-09 华北水利水电大学 Steel construction building locating pasting piece based on BIM

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《钢结构节点详图的自动标注算法》;刘颖滨;《中国图象图形学报》;20010630;第6卷(第6期);第582-585页 *

Also Published As

Publication number Publication date
CN205080575U (en) 2016-03-09
CN104778488A (en) 2015-07-15

Similar Documents

Publication Publication Date Title
CN104778488B (en) Steel building site based on BIM
CN109612406B (en) Random detection method for ring splicing quality of splicing pipe pieces of shield tunnel
CN101907439A (en) Stimulated measurement and detection method in architectural steel structure fabrication
CN103336856A (en) Virtual steel structure pre-assembly method based on visual model
CN102538646A (en) Tolerance test template for master node of ship hull and detection method thereof
CN104764415A (en) Steel bridge structure three-dimensional measurement and detection system and measurement method
CN113374282B (en) Method for controlling embedded bolt by adopting assumed coordinate system
CN110345865A (en) A kind of steel construction digitizing detection method based on 3-D scanning
CN108489381A (en) A kind of ship fast accurate trepanning localization method
CN205785144U (en) Articulated flexible COMERO
CN202630840U (en) Online detection test gauge for end-surface-flared bend pipe parts
CN203479232U (en) Assembly measuring device
CN104567763B (en) Steel structure detection method based on BIM (building information modeling) system
CN204988223U (en) Detection apparatus for steel member preparation size precision
CN104729408A (en) Thin and long part assembling method
CN104318610B (en) Large-space three-dimensional entity line-putting method
CN204694208U (en) Bridge steel structure three-dimensional measurement detection system
CN110686594B (en) Workpiece size detection method and system
CN110919619A (en) Rapid scribing method for machining drill hole
CN107367249B (en) Prefabricated components assembling capacity detection method, method of adjustment and joining method
CN104848829A (en) Combination template detection system and method
CN110864625A (en) Method and system for installing, positioning and detecting construction site equipment
CN104880156A (en) Method for measuring large R value by using CAD technology
CN105115546B (en) A kind of particle concentration tuning on-line monitoring device
CN109443328B (en) Prestressed pipeline coordinate positioning ruler and use method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Wei Lushuang

Inventor after: Tang Ming

Inventor after: Liu Shangwei

Inventor after: Jiang Hua

Inventor after: Yin Weibo

Inventor after: Sun Kai

Inventor after: Wei Qun

Inventor before: Wei Qun

Inventor before: Wei Lushuang

Inventor before: Takateru Akiyo

Inventor before: Liu Shangwei

Inventor before: Ma Ying

Inventor before: Yin Weibo

Inventor before: Bo Xiangyun

Inventor before: Wang Weiyang

GR01 Patent grant
GR01 Patent grant