CN104763017B - Ground permeating rainwater recovery system utilizing building waste materials and construction method of ground permeating rainwater recovery system - Google Patents

Ground permeating rainwater recovery system utilizing building waste materials and construction method of ground permeating rainwater recovery system Download PDF

Info

Publication number
CN104763017B
CN104763017B CN201510186448.1A CN201510186448A CN104763017B CN 104763017 B CN104763017 B CN 104763017B CN 201510186448 A CN201510186448 A CN 201510186448A CN 104763017 B CN104763017 B CN 104763017B
Authority
CN
China
Prior art keywords
layer
ground
soil
permeating
waste material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510186448.1A
Other languages
Chinese (zh)
Other versions
CN104763017A (en
Inventor
姚锁平
陈卫连
崔荣兵
张静
沈健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU SHANSHUI ENVIRONMENT CONSTRUCTION GROUP Co Ltd
Original Assignee
JIANGSU SHANSHUI ENVIRONMENT CONSTRUCTION GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU SHANSHUI ENVIRONMENT CONSTRUCTION GROUP Co Ltd filed Critical JIANGSU SHANSHUI ENVIRONMENT CONSTRUCTION GROUP Co Ltd
Priority to CN201510186448.1A priority Critical patent/CN104763017B/en
Publication of CN104763017A publication Critical patent/CN104763017A/en
Application granted granted Critical
Publication of CN104763017B publication Critical patent/CN104763017B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/108Rainwater harvesting

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention discloses a ground permeating rainwater recovery system utilizing building waste materials. The ground permeating rainwater recovery system comprises a soil foundation, a permeating layer, a base layer, a planting soil layer and a face layer which are sequentially arranged from bottom to top. The permeating layer is a building waste material rough particle layer which is evenly distributed with the particle size of 30-50 mm, a permeating pipe is laid in the building waste material rough particle layer and permeating pipe is connected with a water collecting well through a connecting pipe. The base layer is a building waste material fine particle layer which is evenly distributed with the particle size of 1-10 mm. The face layer is lawn blocks and waste engineering stones, and the lawn blocks and the waste engineering stones are arranged alternately. The invention further discloses a construction method of the ground permeating rainwater recovery system utilizing building waste materials, and the method includes the steps of site flatting, soil foundation processing, building waste material crashing, permeating layer laying and the like. According to the ground permeating rainwater recovery system utilizing building waste materials and the construction method of the ground permeating rainwater recovery system, building waste is reasonably used, building resources are saved, the environment is protected, rainwater is recycled, and water resources are saved.

Description

Using ground infiltration system for reclaiming rainwater and its construction method of construction waste material
Technical field
The present invention relates to a kind of ground infiltration system for reclaiming rainwater of utilization construction waste material and its construction method, belong to Improvement of the ecological environment and resource conserving technique field.
Background technology
At present, the quantity of China's urban architecture garbage has accounted for the 30% ~ 40% of municipal refuse total amount, as urbanization is entered The quickening of journey, a large amount of engineering constructions are continuously increased can building castoff total amount.How to discharge and process urban architecture garbage Have become the important topic that enterprise in charge of construction and environmental protection department face.
Building castoff is usually in process of construction or old building maintenance, produces in demolishing process, including soil, Stone, concrete block, brickbat, culled wood, old metal, useless pipeline and electrical equipment waste material etc., it is wherein free of contamination directly to utilize Inorganic matters account for more than 90%;Metal, bamboo and wood material, various packaging material, decorations waste material etc. may have the garbage of contaminative Can be used as renewable resource utilization after sorting.The garbage produced in foundation construction is mainly the brick that soil, dregs and Old building are removed And concrete block, the building castoff produced in main structure construction be mainly masonry and broken concrete, the mortar for abandoning and Metal etc., the larger general nonstaining property of rubbish particle diameter that this two benches is produced, directly can utilize.
At present, China is equipped with two ways to the place of building castoff:One is most building castoffs without any Process directly transports countryside or rural area to carries out air storage landfill, and this will not only consume substantial amounts of soil, and need to pay soil Occupancy and rubbish clear expense etc., meanwhile, clear and polluted the environment with stacking process again.Two is will to build garbage through pretreatment Afterwards, transporting " renewable resources processing center " to be recycled, but build treatment plant needs to put into more cost of erection, operation management expense And the energy will be consumed.
Another important topic in city is that city has stable political situation the water shortage problem that hydraulic department faces, and hydropenia not only causes city to give birth to Short water supply living, also makes weather more drying, ecological deterioration, land subsidence etc., and will be substantial amounts of rainwater direct in rainy season Excrete out.Rainwater is a kind of valuable resource, and seeking effective rainwater disposal or Application way has become inexorable trend.
The content of the invention
For solving the deficiencies in the prior art, it is an object of the present invention to provide a kind of ground of utilization construction waste material Infiltration system for reclaiming rainwater and its construction method, building castoff rationally utilize, have both saved buildings and resources, protected ring again Border, and rainwater recycle is utilized, save water resource.
The technical scheme is that:Using the ground infiltration system for reclaiming rainwater of construction waste material, it is characterized in that, wrap Include set gradually from bottom to up soil matrix, permeable formation, basic unit, plantation soil layer dough-making powder layer, the permeable formation be equally distributed grain Footpath is the construction waste material coarse grain layer of 30~50mm, in the construction waste material coarse grain layer is equipped with osmos tube, described Osmos tube is connected with sump by connecting tube;The basic unit is the construction waste material that equally distributed particle diameter is 1~10mm Material particulate layer;The surface layer is lawn block and abandoned project stone material, the lawn block and abandoned project stone material interphase distribution.
The ground infiltration system for reclaiming rainwater of aforesaid utilization construction waste material, is characterized in that, the soil matrix and ooze Impermeable film is provided between permeable layers, and the material of the impermeable film is PVC.
The ground infiltration system for reclaiming rainwater of aforesaid utilization construction waste material, is characterized in that, in the permeable formation Sand control screens are provided with above osmos tube, and the aperture of the sand control screens is below 1mm.
The ground infiltration system for reclaiming rainwater of aforesaid utilization construction waste material, is characterized in that, in the basic unit and kind Plant permeable geotextiles are provided between soil layer.
The ground infiltration system for reclaiming rainwater of aforesaid utilization construction waste material, is characterized in that, the lawn block and useless The area for abandoning engineered stone is respectively 100~400cm2
The ground infiltration system for reclaiming rainwater of aforesaid utilization construction waste material, is characterized in that, the sump is served as reasons What armored concrete was built by laying bricks or stones builds well by laying bricks or stones, and the depth of the sump is 5~10m.
The invention also discloses a kind of construction method of the ground infiltration system for reclaiming rainwater of utilization construction waste material, its It is characterized in that, comprises the following steps:
(1)Levelling of the land:First ground is evened out, and clears up debris;
(2)Soil treatment:Original soil is compacted with road roller, forms original subgrade layer;
(3)Construction waste material fragmentation:Will be free of contamination broken in demolishing buildings, levelling of the land, basis and main body construction Masonry, concrete block are broken into the coarse grain of 30~50 mm particle diameters, and by the mortar of discarding, the brickbat and concrete block picked under chisel The particulate of 1~10mm is broken into, and is stacked respectively;
(4)Permeable formation is laid:Before laying permeable formation, one layer of impermeable film is laid on soil matrix, then by step(3)In The coarse grain of 30~50 mm particle diameters stacked paves on impermeable film, and first laying depth is the coarse grain of 50~100mm, Ran Hou Osmos tube and connecting tube is laid on coarse grain, connecting tube is connected with the sump for laying in advance, in osmos tube and connecting tube Upper one or more layers sand control screens of laying, finally re-lay the coarse grain that thickness is 100~200mm in sand control screens;
(5)Basic unit lays:After permeable formation lays, step is laid on coarse grain(3)1~10 mm particle diameters of middle stacking Particulate, laying depth are 200~300mm;
(6)Plantation soil layer laying:After basic unit lays, one or more layers permeable geotextiles is laid in basic unit, then will The soil that foundation construction is produced is puddled as planting soil with slag, peat and muck, is laid in permeable geotextiles, laying depth For 50~100mm;
(7)Topping laying:The interval laying lawn block and abandoned project stone material on plantation soil layer, and by abandoned project stone material Compacting, holding surface are smooth stable;
(8)Maintenance and management:Lawn block is carried out conserving, managed, is first disposably poured permeable, is then poured weekly 1~2 time Water.
The construction method of the ground infiltration system for reclaiming rainwater of aforesaid utilization construction waste material, is characterized in that, described Soil treatment is concretely comprised the following steps:
A. voltage stabilizing:First trimmed curb is rolled with road roller, come and go twice, be then depressed into from pavement edge again Lu Zhizheng, often rolls one time, just uses road camber bridge plate and little cotton rope inspection road camber and flatness, at out-of-flatness, will remove high pad It is low, after meeting elevation control, a small amount of water is spilt, is rolled again;
B. it is compacted:With the speed steamroller of 60~70m per minute, 4~6 times are rolled;
C. roll:Rolled 3~5 times with medium-sized road roller again, until surfacing is stable.
The beneficial effect reached by the present invention:
1. the ground infiltration system for reclaiming rainwater of the present invention sets gradually soil matrix, permeable formation, basic unit, plantation soil layer dough-making powder Layer, is equipped with osmos tube in permeable formation, improves the efficiency of rain penetration, and osmos tube is connected with sump by connecting tube, Rainwater recycle can be utilized, save water resource;
2. the present invention is by free of contamination garrulous bricks and stones, concrete block in demolishing buildings, levelling of the land, basis and main body construction The coarse grain and particulate of different-grain diameter is broken into, for laying ground infiltration system for reclaiming rainwater, building castoff is rationally utilized, Both buildings and resources had been saved, environment had been protected again.
Description of the drawings
Fig. 1 is the structural representation of the present invention.
Specific embodiment
The invention will be further described below in conjunction with the accompanying drawings.Following examples are only used for clearly illustrating the present invention Technical scheme, and can not be limited the scope of the invention with this.
As shown in figure 1, a kind of ground infiltration system for reclaiming rainwater of utilization construction waste material, including from bottom to up successively The soil matrix 1 of setting, permeable formation 2, basic unit 3, plantation soil layer 4 and surface layer, the permeable formation 2 be equally distributed particle diameter be 30~ The construction waste material coarse grain layer of 50mm, is equipped with osmos tube 21, the osmos tube in the construction waste material coarse grain layer 21 are connected with sump 6 by connecting tube 22;The basic unit 3 is the construction waste material that equally distributed particle diameter is 1~10mm Material particulate layer;Construct the soil of generation and the mixture of slag, peat and muck based on the plantation soil layer 4, the surface layer For lawn block 51 and abandoned project stone material 52, area respectively 100~400cm2, and 52 phase of lawn block 51 and abandoned project stone material Between arrange, both beautified environment, saved resource again.
Be provided with impermeable film 7 between the soil matrix 1 and permeable formation 2, the material of the impermeable film 7 is PVC, can in case Only rainwater is lost in subsurface wastewater infiltration system by soil matrix 1, rainwater is passed through osmos tube 21 and connecting tube 22 is collected, and stream enters to catchment Well 6 is stored for future use, and the water in sump 6 can be used for pouring soil in arid, or drink after purification.
The top of osmos tube 21 is provided with sand control screens 8 in the permeable formation 2, and the aperture of the sand control screens 8 is below 1mm, Can prevent the construction waste material granule in permeable formation 2 and basic unit 3 from blocking osmos tube 21, improve the infiltration effect of osmos tube 21 Rate.
The basic unit 3 and plantation soil layer 4 between be provided with permeable geotextiles 9, prevent plant soil layer 4 in fertile soil, excrement Fertilizer etc. are planted the fertile soil in soil layer 4, muck etc. and can provide nutrition for the lawn block 51 in surface layer, promote with rain water runoff Plant growing.
The sump 6 is to build well by laying bricks or stones by what armored concrete was built by laying bricks or stones, and the depth of the sump 6 is 5~10m, Substantial amounts of rainwater can be stored standby.
A kind of construction method of the ground infiltration system for reclaiming rainwater of utilization construction waste material, comprises the following steps:
(1)Levelling of the land:First ground is evened out, and clears up debris.
(2)Soil matrix 1 is processed:Original soil is compacted with road roller, forms original subgrade layer, the concrete step of the process of the soil matrix 1 Suddenly it is:
A. voltage stabilizing:First trimmed curb is rolled with road roller, come and go twice, be then depressed into from pavement edge again Lu Zhizheng, often rolls one time, just uses road camber bridge plate and little cotton rope inspection road camber and flatness, at out-of-flatness, will remove high pad It is low, after meeting elevation control, a small amount of water is spilt, is rolled again;
B. it is compacted:With the speed steamroller of 60~70m per minute, 4~6 times are rolled;
C. roll:Rolled 3~5 times with medium-sized road roller again, until surfacing is stable.
(3)Construction waste material fragmentation:Will be free of contamination broken in demolishing buildings, levelling of the land, basis and main body construction Masonry, concrete block are broken into the coarse grain of 30~50 mm particle diameters, and by the mortar of discarding, the brickbat and concrete block picked under chisel The particulate of 1~10mm is broken into, and is stacked respectively.
(4)Permeable formation 2 is laid:Before laying permeable formation 2, one layer of impermeable film 7 is laid on soil matrix 1, then by step (3)The coarse grain of 30~50 mm particle diameters of middle stacking paves on impermeable film 7, and first laying depth is the coarse grain of 50~100mm, Then osmos tube 21 and connecting tube 22 are laid on coarse grain, connecting tube 22 is connected with the sump 6 for laying in advance, is being oozed One or more layers sand control screens 8 is laid in pipe 22 and connecting tube 21 thoroughly, finally thickness is re-layed in sand control screens 8 for 100~200mm Coarse grain.
(5)Basic unit 3 lays:After permeable formation 2 lays, step is laid on coarse grain(3)1~10 mm particle diameters of middle stacking Particulate, laying depth be 200~300mm.
(6)Plantation soil layer 4 is laid:After basic unit 3 lays, one or more layers permeable geotextiles 9 is laid in basic unit 3, so The soil that afterwards foundation construction is produced is puddled as planting soil with slag, peat and muck, is laid in permeable geotextiles 9, is spread If thickness is 50~100mm.
(7)Topping laying:The interval laying lawn block 51 and abandoned project stone material 52 on plantation soil layer 4, and by discarded work Cheng Shicai 52 is compacted, and holding surface is smooth stable.
(8)Maintenance and management:Lawn block 51 is carried out conserving, managed, is first disposably poured permeable, is then poured weekly 1~2 time Water.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, on the premise of without departing from the technology of the present invention principle, some improvement and deformation can also be made, these improve and deform Also should be regarded as protection scope of the present invention.

Claims (2)

1., using the construction method of the ground infiltration system for reclaiming rainwater of construction waste material, the system is included from bottom to up successively The soil matrix of setting, permeable formation, basic unit, plantation soil layer dough-making powder layer, it is 30~50mm's that the permeable formation is equally distributed particle diameter Construction waste material coarse grain layer, is equipped with osmos tube in the construction waste material coarse grain layer, and the osmos tube is by connection Pipe is connected with sump;The basic unit is the construction waste material particulate layer that equally distributed particle diameter is 1~10mm;The face Layer is lawn block and abandoned project stone material, the lawn block and abandoned project stone material interphase distribution, in the soil matrix and permeable formation Between be provided with impermeable film, the material of the impermeable film is PVC;Sand control is being provided with above osmos tube in the permeable formation Net, the aperture of the sand control screens is below 1mm, be it is characterized in that, the construction method is comprised the following steps:
(1)Levelling of the land:First ground is evened out, and clears up debris;
(2)Soil treatment:Original soil is compacted with road roller, forms original subgrade layer;
(3)Construction waste material fragmentation:By free of contamination garrulous bricks and stones in demolishing buildings, levelling of the land, basis and main body construction, Concrete block is broken into the coarse grain of 30~50 mm particle diameters, and the mortar of discarding, the brickbat and concrete block picked under chisel are broken into The particulate of 1~10mm, and stack respectively;
(4)Permeable formation is laid:Before laying permeable formation, one layer of impermeable film is laid on soil matrix, then by step(3)Middle stacking The coarse grain of 30~50 mm particle diameters pave on impermeable film, first laying depth is the coarse grain of 50~100mm, then in coarse grain Upper laying osmos tube and connecting tube, connecting tube are connected with the sump for laying in advance, on osmos tube and connecting tube upper berth If one or more layers sand control screens, the coarse grain that thickness is 100~200mm is finally re-layed in sand control screens;
(5)Basic unit lays:After permeable formation lays, step is laid on coarse grain(3)The particulate of 1~10 mm particle diameters of middle stacking, Laying depth is 200~300mm;
(6)Plantation soil layer laying:After basic unit lays, one or more layers permeable geotextiles is laid in basic unit, then by basis The soil that construction is produced is puddled as planting soil with slag, peat and muck, is laid in permeable geotextiles, and laying depth is 50 ~100mm;
(7)Topping laying:The interval laying lawn block and abandoned project stone material on plantation soil layer, and by abandoned project stone material pressure Real, holding surface is smooth stable;
(8)Maintenance and management:Lawn block is carried out conserving, managed, is first disposably poured permeable, is then poured weekly 1~2 water.
2. the construction method of the ground infiltration system for reclaiming rainwater of utilization construction waste material according to claim 1, its It is characterized in that, the soil treatment is concretely comprised the following steps:
A. voltage stabilizing:First trimmed curb is rolled with road roller, come and go twice, be then depressed in road from pavement edge again The heart, often rolls one time, just uses road camber bridge plate and little cotton rope inspection road camber and flatness, at out-of-flatness, high pad will be gone low, directly To meeting after elevation control, a small amount of water is spilt, is rolled again;
B. it is compacted:With the speed steamroller of 60~70m per minute, 4~6 times are rolled;
C. roll:Rolled 3~5 times with medium-sized road roller again, until surfacing is stable.
CN201510186448.1A 2015-04-20 2015-04-20 Ground permeating rainwater recovery system utilizing building waste materials and construction method of ground permeating rainwater recovery system Active CN104763017B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510186448.1A CN104763017B (en) 2015-04-20 2015-04-20 Ground permeating rainwater recovery system utilizing building waste materials and construction method of ground permeating rainwater recovery system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510186448.1A CN104763017B (en) 2015-04-20 2015-04-20 Ground permeating rainwater recovery system utilizing building waste materials and construction method of ground permeating rainwater recovery system

Publications (2)

Publication Number Publication Date
CN104763017A CN104763017A (en) 2015-07-08
CN104763017B true CN104763017B (en) 2017-03-22

Family

ID=53645083

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510186448.1A Active CN104763017B (en) 2015-04-20 2015-04-20 Ground permeating rainwater recovery system utilizing building waste materials and construction method of ground permeating rainwater recovery system

Country Status (1)

Country Link
CN (1) CN104763017B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105350630B (en) * 2015-11-14 2017-06-06 常州大学 Oozed under a kind of urban rainwater is quick and reuse technology
CN106472056A (en) * 2016-04-14 2017-03-08 深圳文科园林股份有限公司 A kind of planting and establishing method on water-saving lawn
CN108273833B (en) * 2018-03-13 2020-07-31 上海市园林科学规划研究院 In-situ layered utilization of building solid waste and application of building solid waste in reducing soil saline-alkali
CN109468902A (en) * 2018-11-02 2019-03-15 江苏工程职业技术学院 Energy saving water storage type greening or pavement foundation construction technique
CN109574200A (en) * 2018-12-17 2019-04-05 北京建筑大学 A method of useless brick will be built and be used for biology delay facility

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1025966C (en) * 1992-12-15 1994-09-21 黄尊景 Construction of slope drain in geologically unstable area
GB0216485D0 (en) * 2002-07-16 2002-08-21 Tarmac Ltd Water management system
CN101283656A (en) * 2008-06-11 2008-10-15 沧州市农林科学院 Shallow water level double salt-affected soil raw soil planting and greening method
JP5091826B2 (en) * 2008-10-08 2012-12-05 武志 中川 Floor or road pavement structure
CN202338297U (en) * 2011-11-16 2012-07-18 龚雪峰 High-permeability and anti-blocking sand filtering pipe
CN103806500B (en) * 2012-11-14 2015-07-15 北京泰宁科创雨水利用技术股份有限公司 Snow mountain melt water collection and utilization device
CN203174665U (en) * 2013-04-03 2013-09-04 江苏山水环境建设集团股份有限公司 Urban rainwater collection and utilization system
CN103498506A (en) * 2013-10-22 2014-01-08 苏州合展设计营造有限公司 Rainwater collecting pool
CN203788831U (en) * 2014-04-21 2014-08-27 广东中绿园林集团有限公司 Automatic garden irrigation system
CN204259396U (en) * 2014-08-27 2015-04-15 湖北天蓝地绿生态科技有限公司 Film ditch infiltrating irrigation multiple tube
CN104294905A (en) * 2014-10-31 2015-01-21 北京建筑大学 Pervious concrete pavement system with filter material well
CN204590158U (en) * 2015-04-20 2015-08-26 江苏山水环境建设集团股份有限公司 Utilize the ground infiltration system for reclaiming rainwater of construction waste material

Also Published As

Publication number Publication date
CN104763017A (en) 2015-07-08

Similar Documents

Publication Publication Date Title
CN104763017B (en) Ground permeating rainwater recovery system utilizing building waste materials and construction method of ground permeating rainwater recovery system
CN202031001U (en) Compound water-permeable road structure
CN100439600C (en) Treatment method of newly built high way railway engineering soft foundation
CN104163550B (en) Cascading style ladder artificial wet land system and constructional method thereof
CN109594445A (en) A kind of ecology environmental protection color asphalt paving and its construction method
CN107034767A (en) A kind of full pervious concrete pavement structure of regeneration aggregate and its construction method
CN206289491U (en) A kind of pavement, greenery patches harvest water system
CN203295913U (en) Novel ecological permeable road structure
CN103553471B (en) Method for manufacturing water permeable brick from waste concrete, and pavement method of water permeable brick
CN106284495B (en) Collect rainfall pattern roof rain water garden
CN110629629A (en) Recycled aggregate permeable pavement structure and method
CN207062672U (en) A kind of permeable pavement structure
CN211646629U (en) Energy dissipation type flower bed suitable for drainage of sponge city high-rise building
CN110846968B (en) Permeable asphalt pavement structure
CN108532406A (en) Can rapid construction high-bearing capacity pervious surface and laying method
CN209338948U (en) A kind of water-permeable pavement structure
CN206359847U (en) A kind of asphalt pavement structure of clinker silty filler
CN213114892U (en) Functional rainwater garden suitable for sponge city
CN206052490U (en) It is a kind of suitable for footpath, the rainwater regulating pondage system of bicycle lane
CN210529400U (en) Solidified building residue soil road structure
CN203890824U (en) Recycled aggregate based total pervious concrete pavement structure
CN204590158U (en) Utilize the ground infiltration system for reclaiming rainwater of construction waste material
CN206828912U (en) A kind of full pervious concrete pavement structure of regeneration aggregate
CN104164822A (en) Process for paving pedestrian pavement by utilizing building debris
CN207176431U (en) A kind of permeable pavement structure based on sponge the idea of the city

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant