CN104658187A - Operational risk management and control reminding method and device for power transmission line of power grid - Google Patents

Operational risk management and control reminding method and device for power transmission line of power grid Download PDF

Info

Publication number
CN104658187A
CN104658187A CN201510065794.4A CN201510065794A CN104658187A CN 104658187 A CN104658187 A CN 104658187A CN 201510065794 A CN201510065794 A CN 201510065794A CN 104658187 A CN104658187 A CN 104658187A
Authority
CN
China
Prior art keywords
risk
point
management
transmission line
personnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510065794.4A
Other languages
Chinese (zh)
Other versions
CN104658187B (en
Inventor
唐光华
严志超
刘道聪
尹付光
郑达宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xishuangbanna Power Supply Bureau of Yunnan Power Grid Co Ltd
Original Assignee
Xishuangbanna Power Supply Bureau of Yunnan Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xishuangbanna Power Supply Bureau of Yunnan Power Grid Co Ltd filed Critical Xishuangbanna Power Supply Bureau of Yunnan Power Grid Co Ltd
Priority to CN201510065794.4A priority Critical patent/CN104658187B/en
Publication of CN104658187A publication Critical patent/CN104658187A/en
Application granted granted Critical
Publication of CN104658187B publication Critical patent/CN104658187B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B21/00Alarms responsive to a single specified undesired or abnormal condition and not otherwise provided for
    • G08B21/02Alarms for ensuring the safety of persons
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Public Health (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Health & Medical Sciences (AREA)
  • General Business, Economics & Management (AREA)
  • Water Supply & Treatment (AREA)
  • Theoretical Computer Science (AREA)
  • Emergency Management (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention relates to an operational risk management and control reminding method and device for a power transmission line of a power grid. The method comprises two parts, namely management and configuration of risk points and field operational risk management and control, wherein the configuration and management of the risk points can add information of the risk points through the ways of excel introduction and manual maintenance, support the manual maintenance way to realize modification and deletion of the risk points and support checking of the risk points based on a GIS (geographic information system) after maintenance; in an operation process of the power transmission line, when operation staff enter the information of the risk points which are pre-maintained, geolocation information of the current operation staff is obtained, the actual distance between the operation staff and the position of the center of the risk points is calculated by using a two-point coordinate distance algorithm, and if the actual distance is within 50 m, the operation staff is reminded of risk which may exist by voice, thereby helping management staff complete field operation safely. By adopting the method provided by the invention, the operation staff of the power transmission line can be assisted in taking measures in advance to respond to the risk after continuous perfection, and the incidence of unsafe accidents is reduced.

Description

A kind of grid power transmission circuit operating risk management and control based reminding method and device
Technical field
The invention belongs to a kind of grid power transmission circuit operating risk management and control based reminding method and device technique field thereof.
Background technology
Grid power transmission circuit carries the important task of region transmission of electricity, and the fault of transmission line of electricity can cause large-area power failure, and the safe and stable operation of transmission line of electricity is huge on daily productive life impact.For ensureing that the health of transmission line of electricity is run, electric power enterprise drops into a large amount of human and material resources resources, and management and control transmission of electricity site work quality, ensures that transmission line of electricity is healthy.
Because transmission line of electricity distributed areas are wide, region span is large, has the regions such as forest, high mountain, perilous peak, outside environmental elements complexity is various, have the danger such as poisonous snake, falling rocks, steep cliff, hornet, dog, the personal safety accident of site work personnel is subject to great threat, often has the generation of dangerous accident.
Summary of the invention
Object of the present invention provides a kind of grid power transmission circuit operating risk management and control based reminding method to overcome the defect of above-mentioned prior art existence just, ensure that site work personnel personal safety is starting point from the analysis of management and control site work, by the actual practice experience of site work personnel for many years, in conjunction with power grid enterprises' risk management and control requirement, a kind of method that transmission line operation risk management and control is reminded is proposed, and practical application has been carried out in reality transmission of electricity site work, through constantly perfect, transmission line operation personnel can be helped to carry out risk handling measurement in advance, reduce dangerous accident to occur.
The object of the invention is to realize by following technical solution.
Grid power transmission circuit operating risk management and control based reminding method, the present invention includes risk point administration configuration and site work risk management and control two parts; Risk point configuration management can be imported by excel and manual maintenance mode increases risk point information newly, supports that manual maintenance mode realizes amendment and the deletion of risk point, supports to check based on the risk point of GIS after safeguarding; In transmission line operation process, when operating personnel enters the risk point information safeguarded in advance, obtain current work personnel geographical location information, utilize two point coordinate distance algorithm computational tasks personnel and risk point center actual range, the risk that in 50 meters, voice reminder operating personnel may exist, helps managerial personnel to complete site work safely.
Risk point administration configuration flow process is:
Step 1: utilize excel data importing risk point infotech, risk point information is imported from excel document, comprise the information etc. such as the classification of risk point, detailed description, location expression, location geographic coordinate information, peripheral extent, and whether successful feedback operation imports;
Step 2: utilize the distributed areas, the type information that show dangerous point based on GIS visual presentation technology in a device, simultaneously support list exhibition method;
Step 3: transmission line of electricity site work personnel are at the scene in operation process, and to risk point management maintenance, newly-increased dangerous point increases maintenance in operation process;
Step 4: transmission of electricity site work risk point has managed, and derives lead-in mode simultaneously, realize the derivation of vulnerability database, import to other devices simultaneously by a key;
Transmission line of electricity site work risk management and control flow process is:
Step 1: transmission line of electricity site work starts, operating personnel's wearable device starts transmission line of electricity site work;
Step 2: distribution and the counter-measure of checking operation process risk based on GIS, carry out the instrument of risk resolution in advance, operating personnel knows the risk that may exist in operation process in advance;
Step 3: hazardous location identifies calculating automatically, when the personnel's operation of transmission line of electricity site work, device is by gps signal acquisition module, obtain the geographical position coordinates information of site work personnel, utilize two point coordinate distance algorithm computational tasks personnel and risk point actual ranges, in 50 meters, voice reminder notes risk prevention, enters hazardous location voice and worries and enter risk zones, carry out preventive measure;
Step 4: enter in hazardous location, real-time voice is reminded, and helps transmission line of electricity site work personnel to prevent the generation of dangerous accident, completes transmission line of electricity site work smoothly.
Site work risk management and control reminded contents is the information by site work personnel coordinate information and risk point, utilize GIS layer engineer's scale and coordinate combination, the actual range of computational tasks personnel and dangerous point, 50 meters of voice reminders in advance, after entering hazardous location, voice reminder notes the precautionary measures of risk again.
A kind of device of grid power transmission circuit operating risk management and control based reminding method, the present invention includes gps signal acquisition module, operating risk point administration module, dangerous point management and control prompting module, wherein gps signal acquisition module, operating risk point administration module connect dangerous point management and control prompting module respectively; The gps signal processor that gps signal acquisition module includes gps signal receiver and is attached thereto; In the display of geographic position, show dangerous point distribution and class Modules that operating risk point administration module includes power transmission work risk point administration module and is attached thereto; Dangerous point management and control prompting module includes the voice module calculating current location and whether enter hazardous location and be attached thereto.
Advantage of the present invention: the invention provides a kind of method that truly feasible transmission line operation risk management and control is reminded, power transmission work personnel effective management and control risk in operation process can be helped, reduce the generation of dangerous accident.The effective management and control of operating risk, in conjunction with the risk point in risk system, effective management early warning of risk point is realized by device, intelligent computation operating personnel in operation process and the positional distance of dangerous point, and carry out voice reminder, inform operating personnel's dangerous information, carry out the precautionary measures in advance, reduce the generation of dangerous accident.Device is simple and easy to using, and operating personnel only need simple knowledge can learn to use, and through having gone practice in actual transmission line of electricity site work, tackling risk have very great help to transmission line of electricity site work personnel.
Accompanying drawing explanation
Fig. 1 is transmission line of electricity site work risk pipe schematic diagram of the present invention;
Fig. 2 is transmission line of electricity site work risk management and control schematic diagram of the present invention;
Fig. 3 is apparatus of the present invention structural representation.
Embodiment
Grid power transmission circuit operating risk management and control based reminding method, the present invention includes risk point administration configuration and site work risk management and control two parts; Risk point configuration management can be imported by excel and manual maintenance mode increases risk point information newly, supports that manual maintenance mode realizes amendment and the deletion of risk point, supports to check based on the risk point of GIS after safeguarding; In transmission line operation process, when operating personnel enters the risk point information safeguarded in advance, obtain current work personnel geographical location information, utilize two point coordinate distance algorithm computational tasks personnel and risk point center actual range, the risk that in 50 meters, voice reminder operating personnel may exist, helps managerial personnel to complete site work safely.
Risk point administration configuration flow process is:
Step 1: utilize excel data importing risk point infotech, risk point information is imported from excel document, comprise the information etc. such as the classification of risk point, detailed description, location expression, location geographic coordinate information, peripheral extent, and whether successful feedback operation imports;
Step 2: utilize the distributed areas, the type information that show dangerous point based on GIS visual presentation technology in a device, simultaneously support list exhibition method;
Step 3: transmission line of electricity site work personnel are at the scene in operation process, and to risk point management maintenance, newly-increased dangerous point increases maintenance in operation process;
Step 4: transmission of electricity site work risk point has managed, and derives lead-in mode simultaneously, realize the derivation of vulnerability database, import to other devices simultaneously by a key;
Transmission line of electricity site work risk management and control flow process is:
Step 1: transmission line of electricity site work starts, operating personnel's wearable device starts transmission line of electricity site work;
Step 2: distribution and the counter-measure of checking operation process risk based on GIS, carry out the instrument of risk resolution in advance, operating personnel knows the risk that may exist in operation process in advance;
Step 3: hazardous location identifies calculating automatically, when the personnel's operation of transmission line of electricity site work, device is by gps signal acquisition module, obtain the geographical position coordinates information of site work personnel, utilize two point coordinate distance algorithm computational tasks personnel and risk point actual ranges, in 50 meters, voice reminder notes risk prevention, enters hazardous location voice and worries and enter risk zones, carry out preventive measure;
Step 4: enter in hazardous location, real-time voice is reminded, and helps transmission line of electricity site work personnel to prevent the generation of dangerous accident, completes transmission line of electricity site work smoothly.
Site work risk management and control reminded contents is the information by site work personnel coordinate information and risk point, utilize GIS layer engineer's scale and coordinate combination, the actual range of computational tasks personnel and dangerous point, 50 meters of voice reminders in advance, after entering hazardous location, voice reminder notes the precautionary measures of risk again.
See Fig. 3, a kind of device of grid power transmission circuit operating risk management and control based reminding method, the present invention includes gps signal acquisition module, operating risk point administration module, dangerous point management and control prompting module, wherein gps signal acquisition module, operating risk point administration module connect dangerous point management and control prompting module respectively; The gps signal processor that gps signal acquisition module includes gps signal receiver and is attached thereto; In the display of geographic position, show dangerous point distribution and class Modules that operating risk point administration module includes power transmission work risk point administration module and is attached thereto; Dangerous point management and control prompting module includes the voice module calculating current location and whether enter hazardous location and be attached thereto.

Claims (2)

1. a grid power transmission circuit operating risk management and control based reminding method, is characterized in that, comprises risk point administration configuration and site work risk management and control two parts; Risk point configuration management can be imported by excel and manual maintenance mode increases risk point information newly, supports that manual maintenance mode realizes amendment and the deletion of risk point, supports to check based on the risk point of GIS after safeguarding; In transmission line operation process, when operating personnel enters the risk point information safeguarded in advance, obtain current work personnel geographical location information, utilize two point coordinate distance algorithm computational tasks personnel and risk point center actual range, the risk that in 50 meters, voice reminder operating personnel may exist, helps managerial personnel to complete site work safely;
Risk point administration configuration flow process is:
Step 1: utilize excel data importing risk point infotech, risk point information is imported from excel document, comprise the information etc. such as the classification of risk point, detailed description, location expression, location geographic coordinate information, peripheral extent, and whether successful feedback operation imports;
Step 2: utilize the distributed areas, the type information that show dangerous point based on GIS visual presentation technology in a device, simultaneously support list exhibition method;
Step 3: transmission line of electricity site work personnel are at the scene in operation process, and to risk point management maintenance, newly-increased dangerous point increases maintenance in operation process;
Step 4: transmission of electricity site work risk point has managed, and derives lead-in mode simultaneously, realize the derivation of vulnerability database, import to other devices simultaneously by a key;
Transmission line of electricity site work risk management and control flow process is:
Step 1: transmission line of electricity site work starts, operating personnel's wearable device starts transmission line of electricity site work;
Step 2: distribution and the counter-measure of checking operation process risk based on GIS, carry out the instrument of risk resolution in advance, operating personnel knows the risk that may exist in operation process in advance;
Step 3: hazardous location identifies calculating automatically, when the personnel's operation of transmission line of electricity site work, device is by gps signal acquisition module, obtain the geographical position coordinates information of site work personnel, utilize two point coordinate distance algorithm computational tasks personnel and risk point actual ranges, in 50 meters, voice reminder notes risk prevention, enters hazardous location voice and worries and enter risk zones, carry out preventive measure;
Step 4: enter in hazardous location, real-time voice is reminded, and helps transmission line of electricity site work personnel to prevent the generation of dangerous accident, completes transmission line of electricity site work smoothly.
2. adopt a kind of device of grid power transmission circuit operating risk management and control based reminding method, it is characterized in that, comprise gps signal acquisition module, operating risk point administration module, dangerous point management and control prompting module, wherein gps signal acquisition module, operating risk point administration module connect dangerous point management and control prompting module respectively; The gps signal processor that gps signal acquisition module includes gps signal receiver and is attached thereto; In the display of geographic position, show dangerous point distribution and class Modules that operating risk point administration module includes power transmission work risk point administration module and is attached thereto; Dangerous point management and control prompting module includes the voice module calculating current location and whether enter hazardous location and be attached thereto.
CN201510065794.4A 2015-02-09 2015-02-09 Operational risk management and control reminding method and device for power transmission line of power grid Active CN104658187B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510065794.4A CN104658187B (en) 2015-02-09 2015-02-09 Operational risk management and control reminding method and device for power transmission line of power grid

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510065794.4A CN104658187B (en) 2015-02-09 2015-02-09 Operational risk management and control reminding method and device for power transmission line of power grid

Publications (2)

Publication Number Publication Date
CN104658187A true CN104658187A (en) 2015-05-27
CN104658187B CN104658187B (en) 2017-02-22

Family

ID=53249253

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510065794.4A Active CN104658187B (en) 2015-02-09 2015-02-09 Operational risk management and control reminding method and device for power transmission line of power grid

Country Status (1)

Country Link
CN (1) CN104658187B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105225410A (en) * 2015-08-31 2016-01-06 国网山东省电力公司淄博供电公司 Distribution line is close to method for early warning and equipment
CN106123947A (en) * 2016-06-12 2016-11-16 南宁思飞电子科技有限公司 Intelligent power detection system
CN108090701A (en) * 2018-01-10 2018-05-29 广东电网有限责任公司珠海供电局 A kind of field work safe risk management and control method based on geography information polymerization
CN109272203A (en) * 2018-08-24 2019-01-25 国网天津市电力公司电力科学研究院 A kind of transmission line parameter test auxiliary system
CN109508844A (en) * 2017-09-15 2019-03-22 全球能源互联网研究院 A kind of security risk analysis method and system for work compound
CN112435424A (en) * 2020-12-01 2021-03-02 国网辽宁省电力有限公司朝阳供电公司 Dangerous point warning device and warning method for power line operation site
CN112927412A (en) * 2021-01-30 2021-06-08 上海电机学院 Access control system for wind driven generator
CN113792658A (en) * 2021-09-15 2021-12-14 江苏迪赛司自动化工程有限公司 Fire operation closed-loop automatic control method and system based on intelligent overall process monitoring

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101901430A (en) * 2010-07-19 2010-12-01 北京恒泰实达科技发展有限公司 Power grid risk management and control method and device
CN103177396A (en) * 2012-12-31 2013-06-26 浙江省电力公司 Intelligentized whole-employee overall-process full-profession multidimensional risk management and control platform for site operations of power supply enterprises
CN103295164A (en) * 2013-05-31 2013-09-11 云南电网公司 Power grid safety monitoring management information system and management method
WO2014122930A1 (en) * 2013-02-07 2014-08-14 日本電気株式会社 Power control system
US20140344124A1 (en) * 2012-10-24 2014-11-20 Causam Energy, Inc. System, method, and apparatus for settlement for participation in an electric power grid
US20150025696A1 (en) * 2013-07-17 2015-01-22 Carnegie Mellon University Distributed Methods and Software For Balancing Supply and Demand In An Electric Power Network

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101901430A (en) * 2010-07-19 2010-12-01 北京恒泰实达科技发展有限公司 Power grid risk management and control method and device
US20140344124A1 (en) * 2012-10-24 2014-11-20 Causam Energy, Inc. System, method, and apparatus for settlement for participation in an electric power grid
CN103177396A (en) * 2012-12-31 2013-06-26 浙江省电力公司 Intelligentized whole-employee overall-process full-profession multidimensional risk management and control platform for site operations of power supply enterprises
WO2014122930A1 (en) * 2013-02-07 2014-08-14 日本電気株式会社 Power control system
CN103295164A (en) * 2013-05-31 2013-09-11 云南电网公司 Power grid safety monitoring management information system and management method
US20150025696A1 (en) * 2013-07-17 2015-01-22 Carnegie Mellon University Distributed Methods and Software For Balancing Supply and Demand In An Electric Power Network

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105225410A (en) * 2015-08-31 2016-01-06 国网山东省电力公司淄博供电公司 Distribution line is close to method for early warning and equipment
CN106123947A (en) * 2016-06-12 2016-11-16 南宁思飞电子科技有限公司 Intelligent power detection system
CN109508844A (en) * 2017-09-15 2019-03-22 全球能源互联网研究院 A kind of security risk analysis method and system for work compound
CN108090701A (en) * 2018-01-10 2018-05-29 广东电网有限责任公司珠海供电局 A kind of field work safe risk management and control method based on geography information polymerization
CN109272203A (en) * 2018-08-24 2019-01-25 国网天津市电力公司电力科学研究院 A kind of transmission line parameter test auxiliary system
CN112435424A (en) * 2020-12-01 2021-03-02 国网辽宁省电力有限公司朝阳供电公司 Dangerous point warning device and warning method for power line operation site
CN112927412A (en) * 2021-01-30 2021-06-08 上海电机学院 Access control system for wind driven generator
CN113792658A (en) * 2021-09-15 2021-12-14 江苏迪赛司自动化工程有限公司 Fire operation closed-loop automatic control method and system based on intelligent overall process monitoring
CN113792658B (en) * 2021-09-15 2023-09-01 江苏迪赛司自动化工程有限公司 Automatic control method and system for closed loop of fire operation in whole process intelligent monitoring

Also Published As

Publication number Publication date
CN104658187B (en) 2017-02-22

Similar Documents

Publication Publication Date Title
CN104658187A (en) Operational risk management and control reminding method and device for power transmission line of power grid
Yoo et al. Emergency evacuation plan for hazardous chemicals leakage accidents using GIS-based risk analysis techniques in South Korea
CN103558827B (en) Mine emergency command communication and management information system
CN104951585A (en) Grid equipment based typhoon warning method and device
RU2011149731A (en) SYSTEM AND METHOD FOR MAKING INFORMATION ABOUT FOLLOWING ESTABLISHED REQUIREMENTS AND TOXIC GAS WARNINGS
CN104952212A (en) Power-grid-GIS-based early warning method of geological disaster and apparatus thereof
CN103676857A (en) Solar ecological environment monitoring distributed-type system
CN205537756U (en) Monitoring system based on big dipper
CN205177077U (en) Crane operation real -time monitoring system
CN105184522A (en) Substation polling offside warning system and warning method
CN104951998A (en) Strong wind early warning modeling method and strong wind early warning modeling system based on power grid GIS (geographic information system)
CN112541684A (en) BIM-based emergency dispatching command method, system, computer equipment and readable medium
CN104794657A (en) Garden digital emergency command and dispatch system
CN103440347B (en) A kind of heterogeneous Disaster Event universal modeling method and system
CN107958343B (en) Hazardous chemical substance disaster situation material scheduling method and system
Buribayeva et al. An autonomous emergency warning system based on cloud servers and SNS
CN102488996A (en) Fire hazard on-site positioning transmission system and method thereof
CN204178393U (en) A kind of urban pipe network production and operation total management system
CN105512952A (en) Safety prewarning information system for key dangerous sites
JP2014232435A (en) Response system
CN203720982U (en) Remote disaster monitoring and personnel scheduling system based on Beidou internet of things
RU147524U1 (en) AUTOMATED INFORMATION SYSTEM TO SUPPORT MANAGEMENT DECISIONS IN THE CONDITIONS OF EMERGENCY SITUATION IN RAILWAY TRANSPORT
CN102013052A (en) Diffusion simulation analysis system using three-dimensional GIS (geographic information system) in environmental emergency
CN205596351U (en) Underground works safe risk real -time prewarning device of being under construction based on thing networking
CN103065194A (en) Method of hazardous waste emergency early warning and response through 3S technologies and system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant