CN104652581A - Multi-stage slope anchoring structure for realizing rainwater and sewage separation - Google Patents

Multi-stage slope anchoring structure for realizing rainwater and sewage separation Download PDF

Info

Publication number
CN104652581A
CN104652581A CN201510039566.XA CN201510039566A CN104652581A CN 104652581 A CN104652581 A CN 104652581A CN 201510039566 A CN201510039566 A CN 201510039566A CN 104652581 A CN104652581 A CN 104652581A
Authority
CN
China
Prior art keywords
slope
cast
anchoring
hdpe
anchoring groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510039566.XA
Other languages
Chinese (zh)
Other versions
CN104652581B (en
Inventor
杜新辉
刘杰
杨菲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING TRUHERO ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd
Original Assignee
BEIJING TRUHERO ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING TRUHERO ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd filed Critical BEIJING TRUHERO ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd
Priority to CN201510039566.XA priority Critical patent/CN104652581B/en
Publication of CN104652581A publication Critical patent/CN104652581A/en
Application granted granted Critical
Publication of CN104652581B publication Critical patent/CN104652581B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The invention discloses a multi-stage slope anchoring structure for realizing rainwater and sewage separation, which is suitable for a multi-layer anti-seepage structure. The multi-stage slope anchoring structure is characterized in that an anchoring ditch is sequentially provided with a slope substrate (1), a sodium bentonite blanket (2), a first-layer HDPE (High-Density Polyethylene) anti-seepage film (3), a composite drainage net (4), a second-layer HDPE anti-seepage film (5), non-woven geotextile (6), cast-in-place concrete backfill materials (11), an HDPE screen pipe (9) and a crushed stone flow guiding layer (7) from bottom to top; the width and the height of the anchoring ditch are both greater than or equal to 800 mm, the height of concrete poured at the bottom part of the anchoring ditch is greater than or equal to 300 mm, and thus the cast-in-place concrete backfill materials (11) are formed; square brick protection layers (10) are arranged at two sides of the anchoring ditch above the cast-in-place concrete backfill materials (11) in a piling way until the height of a platform is reached; the HDPE screen pipe (9) is arranged above the cast-in-place concrete backfill materials (11) of the anchoring ditch and in the square brick protection layers (10) at two sides of the anchoring ditch, the crushed flow guiding layer (7) is paved until the height of the platform is reached, the multi-stage slope anchoring structure is used for guiding and discharging rainfall flood when a piled body is not buried to reach the platform, and the multi-stage slope anchoring structure is used for guiding and discharging leachate when the piled body is buried to reach the platform.

Description

Realize the Slope with multi-step anchor structure of rain dirt shunting
Technical field
The present invention relates to the Slope with multi-step anchor structure realizing rain dirt shunting, be particularly useful for the seepage control project of the solid waste landfill such as landfill yard, stope, Tailings Dam, Hui Chang, red mud dump, slag field having Slope with multi-step.
Background technology
Now China's solid waste landfill, to bank up etc. disposal time, the poisonous and harmful substance of storing up generation for a long time can enter soil in modes such as percolates, and direct consequence causes groundwater pollution.Seepage control project, for this situation of disposal of solid waste, avoids pollutant to enter earth's surface.Common impervious material mostly is based on HDPE antiseepage film, carries out anchoring at side slope place, ensures the steadiness of seepage prevention system.Inside at present relevant technical specification and standard, the anchor Design of slope anchored platform is: the impervious material of slope is laid to anchoring groove side 1/3 place far away, the impervious material extruding of upper side slope is soldered to above the slope impervious material on platform, this design can only be used for the individual layer leakage preventing structure of the HDPE antiseepage film only containing one deck, the structure containing multi-layer H DPE antiseepage film cannot be applicable to, i.e. multilayer leakage preventing structure.
Arrange the landfill yard of Slope with multi-step, stope, Tailings Dam, Hui Chang, red mud dump, slag field etc., place is comparatively large, more consideration rain dirt shunting.First, the anti-design of drainning off floodwaters such as Cut-off ditch, can improve the stability of reservoir area.Secondly, the sewage loads such as percolate can be reduced.And the dirty diversion design of the rain such as Cut-off ditch and anchoring groove when depositing, difficulty of construction is large, cost is high.
For above two problems, the Slope with multi-step anchor structure that the present invention's research realizes rain dirt shunting is necessary.
Summary of the invention
The technical problem to be solved in the present invention is for the solid waste landfill seepage control project of multilayer leakage preventing structure provides the Slope with multi-step anchor structure realizing rain dirt shunting, when waste height is less than plain stage of slope height as Cut-off ditch, be connected with storm sewer outside the venue, interception precipitation, prevents hillslope runoff from entering reservoir area; When waste height exceedes podium level, be incorporated to percolate process pipe network as percolate guide passage, improve the derivation ability of percolate.
The technical solution adopted for the present invention to solve the technical problems is: the Slope with multi-step anchor structure realizing rain dirt shunting, be applicable to multilayer leakage preventing structure, at anchoring groove, place is followed successively by from bottom to up: side slope substrate (1), sodium bentonite blanket (2), first floor HDPE antiseepage film (3), composite drainage network (4), second layer HDPE antiseepage film (5), non-woven geotextile (6), cast-in-situ concrete backfilling material (11), HDPE floral tube (9) and rubble guide layer (7).
Anchoring groove distance plain stage of slope edge >=800mm, impervious barrier material turning point is arcuate structure (8).
Anchoring groove width and highly all >=800mm, concreting height >=300mm bottom anchoring groove, form cast-in-situ concrete backfilling material (11).
In the anchoring groove both sides of cast-in-situ concrete backfilling material (11) top, pile up square brick topping (10) to podium level.
In anchoring groove cast-in-situ concrete backfilling material (11) top and both sides square brick topping (10); place HDPE floral tube (9); lay rubble guide layer (7) to podium level; at the non-landfill of heap body to being used for guide rain flood during podium level, be used for guide percolate when piling on body landfill to platform.
The impervious barrier material-paving of upper side slope is above slope impervious barrier material, integrally welded after anchoring groove overlaps with upper plain stage of slope place.
The beneficial effect that the present invention is arranged is: for the solid landfill seepage control project containing Slope with multi-step anchored platform, design a kind of multilayer leakage preventing structure also anchor structure applicatory, realizes rain dirt shunting.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, the present invention is described in further detail:
Fig. 1 is the Slope with multi-step anchor structure cross-sectional schematic that the present invention realizes rain dirt shunting.
1. side slope substrates, 2. sodium bentonite blanket, 3. first floor HDPE antiseepage film, 4. composite drainage network in figure; 5. second layer HDPE antiseepage film, 6. non-woven geotextile, 7. rubble guide layer, 8. arcuate structure; 9.HDPE floral tube, 10. square brick topping, 11. cast-in-situ concrete backfilling materials.
Detailed description of the invention
The present invention realizes the Slope with multi-step anchor structure of rain dirt shunting, excavation and anchorage ditch in Slope with multi-step anchored platform, width >=800mm, highly >=800mm.
After basal plane acceptance(check), in side slope substrate (1) upper laying two-layer barrier structure, from bottom to top be followed successively by: sodium bentonite blanket (2), first floor HDPE antiseepage film (3), composite drainage network (4), second layer HDPE antiseepage film (5), non-woven geotextile (6).
The two-layer barrier structure of slope, from the platform place near upper side slope toe, to lay to anchoring groove backward upper laying platform downwards and then to slope, leakage preventing structure all adopts arcuate structure (8) in turning point, anchoring groove both sides.
Laying anchoring groove underfill cast-in-situ concrete backfilling material (1) of two-layer barrier structure, concreting height is not less than 300mm.
The impervious barrier structure overlap joint of upper side slope is above the slope impervious barrier at toe platform place, integrally welded.
In inner cast-in-situ concrete backfilling material (1) top of anchoring groove, along anchoring groove both sides, pile up width square brick topping (10) to flushing with slope anchorage platform.
HDPE floral tube (9) is placed in the groove that square brick topping (10) and cast-in-situ concrete backfilling material (11) are formed.
Rubble guide layer (7) is filled up in the anchoring groove laying HDPE floral tube (9).
When solid waste landfill height does not arrive podium level, be connected by HDPE floral tube (9), as Cut-off ditch, retain slope head flowing water with drainage system outside the venue, guide surface flow and surperficial rain flood, reduce percolate treating capacity.
Time above solid waste landfill to platform, refuse of banking up after leakage preventing structure is laid sand pocket, is connected HDPE floral tube (9) with percolate guide system, for piling the percolate of body above guide.

Claims (6)

1. realize the Slope with multi-step anchor structure of rain dirt shunting, it is characterized in that: be applicable to multilayer leakage preventing structure, at anchoring groove, place is followed successively by from bottom to up: side slope substrate (1), sodium bentonite blanket (2), first floor HDPE antiseepage film (3), composite drainage network (4), second layer HDPE antiseepage film (5), non-woven geotextile (6), cast-in-situ concrete backfilling material (11), HDPE floral tube (9) and rubble guide layer (7).
2. the Slope with multi-step anchor structure realizing rain dirt shunting according to claim 1, is characterized in that: anchoring groove distance plain stage of slope edge >=800mm, impervious barrier material turning point is arcuate structure (8).
3. the Slope with multi-step anchor structure realizing rain dirt shunting according to claim 1, is characterized in that: anchoring groove width and highly all >=800mm, concreting height >=300mm bottom anchoring groove, form cast-in-situ concrete backfilling material (11).
4. the Slope with multi-step anchor structure realizing rain dirt shunting according to claim 1, is characterized in that: in the anchoring groove both sides of cast-in-situ concrete backfilling material (11) top, pile up square brick topping (10) to podium level.
5. the Slope with multi-step anchor structure realizing rain dirt shunting according to claim 1; it is characterized in that: in anchoring groove cast-in-situ concrete backfilling material (11) top and both sides square brick topping (10); place HDPE floral tube (9); lay rubble guide layer (7) to podium level; at the non-landfill of heap body to being used for guide rain flood during platform, be used for guide percolate when piling on body landfill to platform.
6. the Slope with multi-step anchor structure realizing rain dirt shunting according to claim 1, is characterized in that: the impervious barrier material-paving of upper side slope is above slope impervious barrier material, integrally welded after anchoring groove overlaps with upper plain stage of slope place.
CN201510039566.XA 2015-01-27 2015-01-27 Multi-stage slope anchoring structure for realizing rainwater and sewage separation Expired - Fee Related CN104652581B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510039566.XA CN104652581B (en) 2015-01-27 2015-01-27 Multi-stage slope anchoring structure for realizing rainwater and sewage separation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510039566.XA CN104652581B (en) 2015-01-27 2015-01-27 Multi-stage slope anchoring structure for realizing rainwater and sewage separation

Publications (2)

Publication Number Publication Date
CN104652581A true CN104652581A (en) 2015-05-27
CN104652581B CN104652581B (en) 2017-02-01

Family

ID=53244168

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510039566.XA Expired - Fee Related CN104652581B (en) 2015-01-27 2015-01-27 Multi-stage slope anchoring structure for realizing rainwater and sewage separation

Country Status (1)

Country Link
CN (1) CN104652581B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105019539A (en) * 2015-08-03 2015-11-04 中国市政工程西北设计研究院有限公司 System for shunting rainwater and sewage in reservoir area above crest elevation of valley type refuse landfill
CN107191677A (en) * 2017-06-22 2017-09-22 中交二公局第五工程有限公司 A kind of oil-gas pipeline protector and its construction method
CN109403356A (en) * 2018-11-09 2019-03-01 中国电建集团贵阳勘测设计研究院有限公司 Side slope supporting structure
CN109469056A (en) * 2018-12-28 2019-03-15 沈阳工业大学 Sanitary filling field laying assembled anchor structure
CN109594570A (en) * 2018-12-06 2019-04-09 贵阳铝镁设计研究院有限公司 Filter cake dry method red mud storage yard slope drainage structure and construction method
CN110029690A (en) * 2019-04-18 2019-07-19 中国电建集团贵阳勘测设计研究院有限公司 Leachate leakage detection collection structure and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3815232C1 (en) * 1988-05-05 1989-01-05 Hans Brochier Gmbh & Co, 8500 Nuernberg, De Pipe-widening apparatus, in particular for disposal lines in refuse landfills
EP0869917A1 (en) * 1995-04-20 1998-10-14 Egner, Andrea Process and device for treating screen from the mechanical cleaning stage of a sewage treatment plant
CN201459746U (en) * 2009-07-16 2010-05-12 中国水电顾问集团华东勘测设计研究院 Underground water guiding and draining structure of anchoring groove position of landfill site
CN101936013A (en) * 2010-09-07 2011-01-05 中国市政工程西北设计研究院有限公司 Base rock side slope middle seepage preventing layer anchoring structure of steep and hard rock double-layer seepage preventing structure
CN202755438U (en) * 2012-08-21 2013-02-27 上海市城市建设设计研究总院 Integrative structure with functions of anchoring, drainage and flood interception in refuse landfill
CN103835317A (en) * 2011-12-27 2014-06-04 杭州千禧环保科技有限公司 Refuse landfill seepage-proofing guide drainage system structure and laying method thereof
CN204626610U (en) * 2015-01-27 2015-09-09 北京锄禾环保技术有限公司 A kind of Slope with multi-step anchor structure realizing rain dirt shunting

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3815232C1 (en) * 1988-05-05 1989-01-05 Hans Brochier Gmbh & Co, 8500 Nuernberg, De Pipe-widening apparatus, in particular for disposal lines in refuse landfills
EP0869917A1 (en) * 1995-04-20 1998-10-14 Egner, Andrea Process and device for treating screen from the mechanical cleaning stage of a sewage treatment plant
CN201459746U (en) * 2009-07-16 2010-05-12 中国水电顾问集团华东勘测设计研究院 Underground water guiding and draining structure of anchoring groove position of landfill site
CN101936013A (en) * 2010-09-07 2011-01-05 中国市政工程西北设计研究院有限公司 Base rock side slope middle seepage preventing layer anchoring structure of steep and hard rock double-layer seepage preventing structure
CN103835317A (en) * 2011-12-27 2014-06-04 杭州千禧环保科技有限公司 Refuse landfill seepage-proofing guide drainage system structure and laying method thereof
CN202755438U (en) * 2012-08-21 2013-02-27 上海市城市建设设计研究总院 Integrative structure with functions of anchoring, drainage and flood interception in refuse landfill
CN204626610U (en) * 2015-01-27 2015-09-09 北京锄禾环保技术有限公司 A kind of Slope with multi-step anchor structure realizing rain dirt shunting

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105019539A (en) * 2015-08-03 2015-11-04 中国市政工程西北设计研究院有限公司 System for shunting rainwater and sewage in reservoir area above crest elevation of valley type refuse landfill
CN107191677A (en) * 2017-06-22 2017-09-22 中交二公局第五工程有限公司 A kind of oil-gas pipeline protector and its construction method
CN109403356A (en) * 2018-11-09 2019-03-01 中国电建集团贵阳勘测设计研究院有限公司 Side slope supporting structure
CN109403356B (en) * 2018-11-09 2024-03-19 中国电建集团贵阳勘测设计研究院有限公司 Side slope supporting structure
CN109594570A (en) * 2018-12-06 2019-04-09 贵阳铝镁设计研究院有限公司 Filter cake dry method red mud storage yard slope drainage structure and construction method
CN109469056A (en) * 2018-12-28 2019-03-15 沈阳工业大学 Sanitary filling field laying assembled anchor structure
CN109469056B (en) * 2018-12-28 2023-09-29 沈阳工业大学 Sanitary landfill liner layer assembled anchoring structure
CN110029690A (en) * 2019-04-18 2019-07-19 中国电建集团贵阳勘测设计研究院有限公司 Leachate leakage detection collection structure and construction method thereof
CN110029690B (en) * 2019-04-18 2024-03-19 中国电建集团贵阳勘测设计研究院有限公司 Percolate leakage detection and collection structure and construction method thereof

Also Published As

Publication number Publication date
CN104652581B (en) 2017-02-01

Similar Documents

Publication Publication Date Title
CN104652581B (en) Multi-stage slope anchoring structure for realizing rainwater and sewage separation
CN100460612C (en) Reticular blind drainage method for groundwater of sanitary landfill for disposing house refuse
CN103953008B (en) A kind of modified mixed dam being applicable to Tailings Dam
CN212404676U (en) Soft soil foundation anti-settlement structure
CN101148885B (en) Stereo drainage system structure for landfill underground water
CN213867863U (en) General industrial solid waste storage and disposal site structure based on abandoned mine
CN113107061A (en) Stratum reconstruction method for near-urban abandoned strip mine
CN101148886B (en) Drainage treatment structure for unbuilt or abuilding landfill slope underground water
CN204626610U (en) A kind of Slope with multi-step anchor structure realizing rain dirt shunting
CN219503430U (en) Vertical partition structure of household garbage landfill
CN204826140U (en) Dirty current drive system of reservoir area rain more than cheuch type landfill dam crest elevation
CN112343020A (en) Environmental risk prevention and control integrated system and method for historical legacy tailing pond
CN208455573U (en) Karst area reservoir basin seepage prevention processing structure
CN114457855B (en) Sinking type horizontal seepage-proofing and vertical seepage-proofing combined structure
CN105019539A (en) System for shunting rainwater and sewage in reservoir area above crest elevation of valley type refuse landfill
CN211472400U (en) Dam slag blocking structure
CN210288489U (en) Refuse landfill based on coal gangue
CN208777319U (en) A kind of mound field structure kept suitable for soil quality
CN101148887B (en) Drainage treatment structure for working landfill slope underground water
CN214301341U (en) Water drainage channel crossing temporary road on anti-seepage film of garbage pile
CN211948540U (en) Prevention of seepage membrane, anchor ditch and retaining wall merge structure of building
CN210658632U (en) Infiltration ditch structure
CN114439049B (en) Combined seepage-proofing body for preventing and controlling solid waste pile pollution and restoring ecology
CN217537080U (en) Karst refuse dump foundation treatment structure
CN217419751U (en) Slope slip casting reinforcement type protective structure of rubbish filling field

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170201

Termination date: 20220127

CF01 Termination of patent right due to non-payment of annual fee