CN104634070B - The method for designing of a kind of coal-fired drying unit and device thereof - Google Patents
The method for designing of a kind of coal-fired drying unit and device thereof Download PDFInfo
- Publication number
- CN104634070B CN104634070B CN201410818775.XA CN201410818775A CN104634070B CN 104634070 B CN104634070 B CN 104634070B CN 201410818775 A CN201410818775 A CN 201410818775A CN 104634070 B CN104634070 B CN 104634070B
- Authority
- CN
- China
- Prior art keywords
- coal
- warm
- fired
- drying
- air
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Drying Of Solid Materials (AREA)
Abstract
The invention discloses method for designing and the device thereof of a kind of coal-fired drying unit, belong to drying plant technical field.The technical scheme is that the heating power source using coal-fired hot-blast stove as drying unit, combustion process to travel at the uniform speed, the dust of flue gas exports from outlet in being trapped in body of heater by partition wall together with cinder, flue gas in warm-air pipe as the draft of air-introduced machine is advanced forward and carries out second-time burning, warm-air pipe unrolls S-shaped and makes radiator and be arranged in drying baker, when the flue-gas temperature of warm-air pipe is close to when drying temperature, the end of warm-air pipe stretches out drying baker and is connected with the air-introduced machine arrival end being arranged on outside drying baker, the adapter that the port of export of air-introduced machine communicates with drying baker inner chamber is connected;The present invention compared with prior art, have and provide that a kind of design concept is novel, method for designing reliable, the prominent substantive distinguishing features of smokeless, thermal efficiency utilization rate 100% and significantly improving.
Description
Technical field
The present invention relates to drying plant technical field, particularly relate to method for designing and the device thereof of a kind of coal-fired drying unit
Technical field.
Background technology
For a long time, drying plant uses electrical heating or steam as the thermal source of drying plant always, and at thermal source
Course of conveying often configures multiple stage circulating fan, is allowed to finally still indirectly form hot blast and dries.This process is obvious
There is a large amount of waste energy and cause the shortcomings such as too much, the complex technical process of auxiliary device.And exist and be more difficult to solution
Technical problem is that, this thermal source needs higher temperature to be dried for those or toasts the engineering project of job requirements, then can not expire
Its technology using of foot requires.For these practical problems those skilled in the art by long-term production practices, by
Step is recognized and is only utilized hot blast could improve heat utilization efficiency and hot working effect to a greater extent as medium.And how to use
Fuel directly burns, and purified process forms hot blast, is dried with material Direct Contact Heating or toasts, used by this furnace drying method
Fuel Consumption about reduces about at least 50% than with steam-type or other indirect heaters.Therefore, drying product product are not being affected
In the case of matter, direct purification hot blast can be used completely.And under the guidance of this mentality of designing the technology of the art
Personnel design a series of coal-fired hot-blast stove, warm air oil furnace, fuel gas hot-blast stove etc.;Coal-fired hot-blast stove mainly includes: direct combustion
Formula coal-fired hot-blast stove, indirect type coal-fired hot-blast stove, separated type coal-fired hot-blast stove;Although coal-fired hot-blast stove is for meeting needs higher temperatures
Degree is dried or the engineering project of baking job requirements provides relatively reliable technical scheme, but current coal-fired hot-blast stove is still
There is following technological deficiency: dust contained in the flue gas of first coal-fired hot-blast stove and poisonous and harmful substance are still straight
Run in and put in atmosphere, air and environment are still being polluted and encroaching on;It is two owing to the exhanst gas outlet of coal-fired hot-blast stove is by cigarette
Chimney directly discharges in atmosphere, causes heat utilization efficiency to only reach about 70% at present, and the space that heat utilization efficiency saving is taped the latent power is very big.
Therefore, how to efficiently solve or reduce the discharge of poisonous and harmful substance contained in flue gas and the heat of raising coal-fired hot-blast stove
Efficiency, this is for from the point of view of those skilled in the art being still a technical task urgently to be resolved hurrily.
Content of the invention
The technical problem to be solved is to overcome the deficiencies in the prior art, and provide a kind of design concept novel,
Method for designing is reliable, the method for designing of the coal-fired drying unit of smokeless, thermal efficiency utilization rate 100%.
Another technical problem to be solved by this invention is to provide that a kind of design concept is novel, method for designing is reliable, mechanical
Dependable performance, smokeless, the coal-fired drying unit of thermal efficiency utilization rate 100%.
For solving above-mentioned technical problem, the present invention adopts the following technical scheme that: the design of a kind of coal-fired drying unit
Method, including use coal-fired hot-blast stove as the heating power source of drying unit, by the body of heater of hot-blast stove, warm-air pipe, drying baker
And the global design that carried out of mutual connection and the specific design to each parts, it is characterized in that described coal-fired dry
Equipment for drying arranges in a coal-fired hot-blast stove and combustion process and to travel at the uniform speed, and arranges at least 2 partition walls in coal-fired hot-blast stove furnace chamber,
The dust of flue gas is trapped in body of heater together with cinder from outlet output by partition wall, flue gas in warm-air pipe with air-introduced machine
Draft is advanced forward and carries out second-time burning, until its combustible containing that burnouts;Warm-air pipe unrolls S-shaped and makes heat radiation
Device is arranged in drying baker, when warm-air pipe flue-gas temperature close to dry temperature when, the end of warm-air pipe stretch out drying baker and with
Being arranged on the air-introduced machine arrival end outside drying baker to be connected, the adapter that the port of export of air-introduced machine communicates with drying baker inner chamber is connected
Connect;The length dimension of warm-air pipe is determined with drying temperature close by the flue-gas temperature of warm-air pipe;Drying baker both sides upper and lower side divides
The pipeline of the air circulation that She Zhi not communicate with drying baker inner chamber and installation blower fan between tubes.
For solving above-mentioned technical problem further, the preferred version of technique scheme is:
It is provided with a triple valve interface with drying baker inner chamber between the adapter that the port of export of air-introduced machine described above communicates.
Coal-fired hot-blast stove described above is horizontal chained hot-blast stove, and is provided with adjustable speed scope and is: 1.5-9M/ hour
Arrangements for speed regulation.
It is provided with radiating fin on the pipe outer wall of warm-air pipe described above.
Flue-gas temperature described above is to set according to the requirement drying temperature, and its interval range is: coal-fired hot-blast stove
Flue gas exit temperature be 800-1000 DEG C, the anterior temperature of warm-air pipe is 600-800 DEG C, and middle portion temperature is 300-500 DEG C, hot blast
The terminal temperature of pipe is for drying temperature.
For solving above-mentioned technical problem further, the present invention is to use to implement following technical scheme:
The coal-fired drying unit of the designed processing of a kind of method for designing according to coal-fired drying unit, including use coal fuel heating
Wind furnace is as the heating power source of drying unit, and the body of heater of coal-fired hot-blast stove, warm-air pipe, drying baker and mutual connection thereof, it is special
Different part is that described coal-fired drying unit arranges a coal-fired hot-blast stove, and the body of heater inner chamber of coal-fired hot-blast stove to smoke outlet is arranged
The dust partition wall that at least 2 can be detained in flue gas, the exhanst gas outlet of coal-fired hot-blast stove and warm-air pipe are communicated as one;Warm-air pipe returns
Around S-shaped and make radiator and be arranged in drying baker;The end of warm-air pipe stretch out drying baker and be arranged on outside drying baker
Air-introduced machine arrival end be connected, the adapter that the port of export of air-introduced machine communicates with drying baker inner chamber is connected;On drying baker both sides
Lower end is respectively provided with the air circulation duct communicating with drying baker inner chamber and installation blower fan between tubes.
For solving above-mentioned technical problem further, the preferred version of technique scheme is:
It is provided with a triple valve interface with drying baker inner chamber between the adapter that the port of export of air-introduced machine described above communicates.
Coal-fired hot-blast stove described above is horizontal chained hot-blast stove, and is provided with adjustable speed scope and is: 1.5-9M/ hour
Arrangements for speed regulation.
It is provided with radiating fin on the pipe outer wall of warm-air pipe described above.
Flue-gas temperature described above is to set according to the requirement drying temperature, and its interval range is: coal hot-air
The flue gas exit temperature of stove is 800-1000 DEG C, and the anterior temperature of warm-air pipe is 600-800 DEG C, and middle portion temperature is 300-500 DEG C, heat
The terminal temperature of airduct is for drying temperature.
It is progressive with significant that the present invention compared with prior art has following prominent substantive distinguishing features:
The method for designing of the first coal-fired drying unit of the present invention by coal-fired hot-blast stove as drying unit
Heating power source, arranges at least 2 partition walls in coal-fired hot-blast stove furnace chamber, the dust of flue gas by partition wall be trapped in body of heater with cinder one
Rise from outlet output, flue gas in warm-air pipe as the draft of air-introduced machine is advanced forward and carries out second-time burning, until burnouting it
The technical scheme of the combustible containing, so that the thermal-flame of coal-fired hot-blast stove and flue gas remove dust contained therein
And poisonous and harmful substance, the hot blast of warm-air pipe not only becomes the temperature required hot blast of dry materials and dissipating of being made up of warm-air pipe
Material is dried by flowing in hot device.The temperature of hot blast can need to adjust according to technique, and continuous heat supply air temperature stability is relatively
Good, this not only overcomes dust contained in flue gas of the prior art and poisonous and harmful substance is still discharged in atmosphere,
Air and environment are still being polluted and the disadvantage of infringement, and is being removed further by drying course is dried the absorption of material
Retentate in flue gas, makes coal-fired drying unit of the present invention achieve the zero-emission of flue gas, do not produce to environment and
Any pollution of air, this is that the method for designing of coal-fired drying unit of the present invention compared with prior art has prominent
Substantive distinguishing features and significant progress.
Its two be coal-fired drying unit of the present invention method for designing in when the flue-gas temperature of warm-air pipe is close to drying
During temperature, the end of warm-air pipe stretches out drying baker and is connected with the air-introduced machine arrival end being arranged on outside drying baker, air-introduced machine
The technical scheme that is connected of the adapter that communicates with drying baker inner chamber of the port of export, make setting of coal-fired drying unit of the present invention
Meter method is taked to dry temperature as design considerations, thermal-flame and the conveying by warm-air pipe for the flue gas of coal-fired hot-blast stove
Reach to dry temperature, make the length of warm-air pipe reach maximum design size, thus the thermal efficiency for coal-fired drying unit reaches
Optimum level provides reliable technical scheme;The adapter simultaneously taking the port of export of air-introduced machine and drying baker inner chamber to communicate is connected
The technical scheme connecing sends drying baker back to the flue gas with drying temperature close in warm-air pipe, is reached for realizing coal-fired drying unit
The utilization of the thermal efficiency 100% provide reliable technical guarantee, make coal-fired drying unit of the present invention method for designing and
Its device compared with prior art has prominent substantive distinguishing features and significant progress.
Brief description
Included accompanying drawing provides a further understanding of the present invention, and it is incorporated in this specification and constitutes this explanation
A part for book, described accompanying drawing shows embodiments of the invention and for explaining the principle of the present invention together with specification.?
Reference identical in accompanying drawing represents identical parts.
In the accompanying drawings:
Fig. 1 is the structural representation of a kind of coal-fired drying unit described in the embodiment of the present invention 1.
Fig. 2 is the structural representation of a kind of coal-fired drying unit described in the embodiment of the present invention 2.
Reference: 1-automatic coaling machine 2-coal hopper 3-horizontal chain grate 4-body of heater 5-partition wall 6-cigarette
11-warm-air pipe radiating fin in the middle part of gas outlet 7-warm-air pipe 8-drying baker 9-flue gas recirculation pipeline 10-warm-air pipe
Piece 12-blower fan 13 dries automatic cycle machine of 14-warm-air pipe end 15-air-introduced machine 16-adapter 17-ash can
18-flange union three way cock valve 19-smoke exhaust pipe.
Detailed description of the invention
Describe the method for designing of a kind of coal-fired drying unit of the present invention and the concrete knot of device thereof below in conjunction with the accompanying drawings in detail
Structure details and install and use process, must not be interpreted as the limiting to the claimed invention going up in all senses.
Embodiment 1:
A kind of coal-fired drying unit being applicable to the drying of pulp buffering Shockproof packaging goods of the embodiment of the present invention 1
Method for designing, including use coal-fired hot-blast stove as the heating power source of drying unit, by the body of heater of hot-blast stove, warm-air pipe, baking
Global design that dry case and mutual connection thereof are carried out and the specific design to each parts, described coal-fired drying unit sets
Put in a coal-fired hot-blast stove and combustion process and to travel at the uniform speed, in coal-fired hot-blast stove furnace chamber, be set to 2 partition walls, the dust of flue gas
Be trapped in body of heater together with cinder from outlet output by partition wall, flue gas in warm-air pipe as the draft of air-introduced machine is to moving ahead
Enter and carry out second-time burning, until its combustible containing that burnouts;Warm-air pipe unrolls S-shaped and makes radiator and be arranged on baking
In dry case, when warm-air pipe flue-gas temperature close to dry temperature when, the end of warm-air pipe stretch out drying baker and be arranged on drying
Air-introduced machine arrival end outside case is connected, and the adapter that the port of export of air-introduced machine communicates with drying baker inner chamber is connected;Warm-air pipe
Length dimension by the flue-gas temperature of warm-air pipe with dry temperature close and determine;Drying baker both sides upper and lower side is respectively provided with and dries
The pipeline of the air circulation that dry box cavity communicates and installation blower fan between tubes.
Coal-fired hot-blast stove described above is horizontal chained hot-blast stove, and is provided with adjustable speed scope and is: 1.5-9M/ hour
Arrangements for speed regulation.
It is provided with radiating fin on the pipe outer wall of warm-air pipe described above.
Flue-gas temperature described above is to set according to the requirement drying temperature, and its interval range is: coal-fired hot-blast stove
Flue gas exit temperature be 800-1000 DEG C, the anterior temperature of warm-air pipe is 600-800 DEG C, and middle portion temperature is 300-500 DEG C, hot blast
The terminal temperature of pipe is for drying temperature.
A kind of coal-fired drying unit (seeing Fig. 1) according to processing designed by the method for designing of above-mentioned coal-fired drying unit,
Including use coal-fired hot-blast stove as the heating power source of drying unit, the body of heater of coal-fired hot-blast stove the 4th, warm-air pipe the 7th, drying baker 7 and
Mutual connection, its described coal-fired drying unit arranges a coal-fired hot-blast stove, and coal-fired hot-blast stove is by automatic coaling machine the 1st, coal
Body of heater inner chamber to the smoke outlet 6 of hopper the 2nd, horizontal chain grate the 3rd, body of heater 4 and coal-fired hot-blast stove is provided with 2 and can be detained cigarette
Flue dust partition wall 5 in gas, the lower section of flue dust partition wall 5 is provided with can remove the most cinder of burning and flue dust to ash can automatically
In 17.The exhanst gas outlet 6 of coal-fired hot-blast stove and warm-air pipe 7 are communicated as one;In the middle part of warm-air pipe, 10 unroll S-shaped and make two
Radiator upper and lower both sides in being arranged on drying baker 8;The end 14 of warm-air pipe stretch out drying baker 8 and be arranged on outside drying baker
Air-introduced machine 15 arrival end is connected, and the adapter 16 that the port of export of air-introduced machine 15 communicates with drying baker inner chamber is connected;In warm-air pipe
The length dimension in portion 10 by the flue-gas temperature of warm-air pipe with dry temperature close and determine, with warm-air pipe in the middle part of 10 caliber also
Having certain relation, under general condition, caliber is between ∮ 60-300, in the middle part of its warm-air pipe 10 a length of 50-80M.Drying baker 8
Both sides upper and lower side is respectively provided with the flue gas recirculation pipeline 9 communicating with drying baker inner chamber and installation blower fan 12 between tubes.?
The inner chamber of drying baker 8 is provided with one and dries automatic cycle line 13.
Coal-fired hot-blast stove described above is horizontal chained hot-blast stove, and is provided with adjustable speed scope and is: 1.5-9M/ hour
Speed regulating control dish (not shown in Figure of description).
In the middle part of warm-air pipe described above 10 pipe outer wall on be provided with warm-air pipe radiating fin 11.
Flue-gas temperature described above is to set according to the requirement drying temperature, and its interval range is: coal hot-air
The temperature of the smoke outlet 6 of stove is 800-1000 DEG C, and the temperature of warm-air pipe front portion 7 is 600-800 DEG C, in the middle part of warm-air pipe 10
Temperature is 300-500 DEG C, and the temperature of warm-air pipe end 14 is for drying temperature.
One static state of the method for designing and device thereof that more than constitute the coal-fired drying unit described in the embodiment of the present invention 1 is tied
Structure.
Embodiment 2:
The method for designing of the coal-fired drying unit described in the embodiment of the present invention 2 is to be applicable to the shockproof bag of pulp buffering
The drying of dress goods based article, is also applied for the method for designing of the coal-fired drying unit of food, the use of fruits and vegetables field, including
Use coal-fired hot-blast stove as the heating power source of drying unit, by the body of heater of hot-blast stove, warm-air pipe, drying baker and each other
The global design that carried out of connection and the specific design to each parts, described coal-fired drying unit arranges a coal-fired hot-blast stove
And combustion process to travel at the uniform speed, it is set to 2 partition walls in coal-fired hot-blast stove furnace chamber, the dust of flue gas is trapped in by partition wall
From outlet output together with cinder in body of heater, flue gas in warm-air pipe as the draft of air-introduced machine is advanced forward and carries out secondary combustion
Burn, until its combustible containing that burnouts;Warm-air pipe unrolls S-shaped and makes radiator and be arranged in drying baker, works as hot blast
The flue-gas temperature of pipe close to dry temperature when, the end of warm-air pipe stretch out drying baker and with the air-introduced machine being arranged on outside drying baker
Arrival end is connected, and is provided with a triple valve interface with drying baker inner chamber between the adapter that the port of export of air-introduced machine communicates, described
Triple valve is flange union three way cock valve, and the port of export of air-introduced machine is connected with flange union three way cock valve;Three-way cock
The adapter that another interface of valve communicates with drying baker inner chamber is connected, another interface of flange union three way cock valve and smoke exhaust pipe
It is connected;The length dimension of warm-air pipe is determined with drying temperature close by the flue-gas temperature of warm-air pipe;Drying baker both sides are upper and lower
End is respectively provided with pipeline and the installation blower fan between tubes of the air circulation communicating with drying baker inner chamber.
Coal-fired hot-blast stove described above is horizontal chained hot-blast stove, and is provided with adjustable speed scope and is: 1.5-9M/ hour
Arrangements for speed regulation.
It is provided with radiating fin on the pipe outer wall of warm-air pipe described above.
Flue-gas temperature described above is to set according to the requirement drying temperature, and its interval range is: coal-fired hot-blast stove
Flue gas exit temperature be 800-1000 DEG C, the anterior temperature of warm-air pipe is 600-800 DEG C, and middle portion temperature is 300-500 DEG C, hot blast
The terminal temperature of pipe is for drying temperature.
A kind of coal-fired drying unit (seeing Fig. 2) according to processing designed by the method for designing of above-mentioned coal-fired drying unit,
Including use coal-fired hot-blast stove as the heating power source of drying unit, the body of heater of coal-fired hot-blast stove the 4th, warm-air pipe the 7th, drying baker 7 and
Mutual connection, its described coal-fired drying unit arranges a coal-fired hot-blast stove, and coal-fired hot-blast stove is by automatic coaling machine the 1st, coal
Body of heater inner chamber to the smoke outlet 6 of hopper the 2nd, horizontal chain grate the 3rd, body of heater 4 and coal-fired hot-blast stove is provided with 4 and can be detained cigarette
Flue dust partition wall 5 in gas, the lower section of flue dust partition wall 5 is provided with can remove the most cinder of burning and flue dust to ash can automatically
In 17.The exhanst gas outlet 6 of coal-fired hot-blast stove and warm-air pipe 7 are communicated as one;In the middle part of warm-air pipe, 10 unroll S-shaped and make two
Radiator upper and lower both sides in being arranged on drying baker 8;The end 14 of warm-air pipe stretch out drying baker 8 and be arranged on outside drying baker
Air-introduced machine 15 arrival end is connected, and is provided with a triple valve between the adapter 16 that the port of export of air-introduced machine 15 communicates with drying baker inner chamber
Interface 18, described triple valve 18 is flange union three way cock valve, and its model is at X44W-6;The port of export of air-introduced machine 15
It is connected with flange union three way cock valve 18;Adapter 16 phase that another interface of threeway plug valve 18 communicates with drying baker inner chamber
Connecting, another interface of flange union three way cock valve 18 is connected with smoke exhaust pipe 19.In the middle part of warm-air pipe 10 length dimension by
The flue-gas temperature of warm-air pipe with dry temperature close and determine, with warm-air pipe in the middle part of 10 caliber also have certain relation, typically
Under the conditions of caliber between ∮ 60-300, in the middle part of its warm-air pipe 10 a length of 50-80M.Drying baker 8 both sides upper and lower side is respectively
The flue gas recirculation pipeline 9 communicating with drying baker inner chamber and installation blower fan 12 between tubes are set.In the inner chamber of drying baker 8
It is provided with one and dry automatic cycle line 13.
It is provided with a triple valve interface with drying baker inner chamber between the adapter that the port of export of air-introduced machine 15 described above communicates
18, described triple valve 18 is flange union three way cock valve, its model for;X44W-6.
Coal-fired hot-blast stove described above is horizontal chained hot-blast stove, and is provided with adjustable speed scope and is: 1.5-9M/ hour
Speed regulating control dish (not shown in Figure of description).
In the middle part of warm-air pipe described above 10 pipe outer wall on be provided with warm-air pipe radiating fin 11.
Flue-gas temperature described above is to set according to the requirement drying temperature, and its interval range is: coal hot-air
The temperature of the smoke outlet 6 of stove is 800-1000 DEG C, and the temperature of warm-air pipe front portion 7 is 600-800 DEG C, in the middle part of warm-air pipe 10
Temperature is 300-500 DEG C, and the temperature of warm-air pipe end 14 is for drying temperature.
One static state of the method for designing and device thereof that more than constitute the coal-fired drying unit described in the embodiment of the present invention 2 is tied
Structure.
Claims (10)
1. a method for designing for coal-fired drying unit, including use coal-fired hot-blast stove as the heating power source of drying unit, passes through
The global design that the body of heater of hot-blast stove, warm-air pipe, drying baker and mutual connection thereof are carried out and the tool to each parts
Body designs, and it is characterized in that described coal-fired drying unit arranges in a coal-fired hot-blast stove and combustion process and to travel at the uniform speed, coal fuel heating
Arranging at least 2 partition walls in wind furnace furnace chamber, the dust of flue gas exports from outlet in being trapped in body of heater by partition wall together with cinder,
Flue gas in warm-air pipe as the draft of air-introduced machine is advanced forward and carries out second-time burning, until its combustible containing that burnouts
Matter;Warm-air pipe unrolls S-shaped and makes radiator and be arranged in drying baker, when the flue-gas temperature of warm-air pipe is close to drying temperature
When, the end of warm-air pipe stretches out drying baker and is connected with the air-introduced machine arrival end being arranged on outside drying baker, going out of air-introduced machine
The adapter that mouth end communicates with drying baker inner chamber is connected;The length dimension of warm-air pipe is by the flue-gas temperature of warm-air pipe and drying temperature
Close and determine;Drying baker both sides upper and lower side is respectively provided with the pipeline of the air circulation communicating with drying baker inner chamber and is arranged on pipe
Blower fan between road.
2. the method for designing of coal-fired drying unit according to claim 1, is characterized in that the port of export of described air-introduced machine
It is provided with a triple valve interface, the respectively port of export, the drying baker inner chamber phase with air-introduced machine between the adapter communicating with drying baker inner chamber
Logical adapter is connected with smoke exhaust pipe.
3. the method for designing of coal-fired drying unit according to claim 1, is characterized in that described coal-fired hot-blast stove is sleeping
Formula chain hot-blast stove, and be provided with adjustable speed scope and be: the arrangements for speed regulation of 1.5-9M/ hour.
4. the method for designing of coal-fired drying unit according to claim 1, is characterized in that the pipe outer wall of described warm-air pipe
On be provided with radiating fin.
5. the method for designing of coal-fired drying unit according to claim 1, is characterized in that described flue-gas temperature is basis
Drying the requirement of temperature and setting, its interval range is: the flue gas exit temperature of coal-fired hot-blast stove is 800-1000 DEG C, warm-air pipe
Anterior temperature is 600-800 DEG C, and middle portion temperature is 300-500 DEG C, and the terminal temperature of warm-air pipe is for drying temperature.
6. the coal-fired drying unit described in method for designing of coal-fired drying unit according to claim 1, including adopt
With coal-fired hot-blast stove as the heating power source of drying unit, the body of heater of coal-fired hot-blast stove, warm-air pipe, drying baker and mutual company thereof
Connecing, it is characterized in that described coal-fired drying unit arranges a coal-fired hot-blast stove, the body of heater inner chamber of coal-fired hot-blast stove is to smoke outlet
Arranging at least 2 dust partition walls can being detained in flue gas, the exhanst gas outlet of coal-fired hot-blast stove and warm-air pipe are communicated as one;Hot blast
Pipe unrolls S-shaped and makes radiator and be arranged in drying baker;The end of warm-air pipe stretch out drying baker and be arranged on drying baker
Outside air-introduced machine arrival end is connected, and the adapter that the port of export of air-introduced machine communicates with drying baker inner chamber is connected;Drying baker two
Side upper and lower side is respectively provided with the air circulation duct communicating with drying baker inner chamber and installation blower fan between tubes.
7. coal-fired drying unit according to claim 6, in is characterized in that the port of export and the drying baker of described air-introduced machine
Be provided with a triple valve interface between the adapter that chamber communicates, the adapter communicating with the port of export of air-introduced machine, drying baker inner chamber respectively and
Smoke exhaust pipe is connected.
8. the coal-fired drying unit according to claim 6 or 7, is characterized in that described coal-fired hot-blast stove is horizontal chained heat
Wind furnace, and be provided with adjustable speed scope and be: the arrangements for speed regulation of 1.5-9M/ hour.
9. the coal-fired drying unit according to claim 6 or 7, is characterized in that being provided with on the pipe outer wall of described warm-air pipe
Radiating fin.
10. coal-fired drying unit according to claim 6, is characterized in that described flue-gas temperature according to drying temperature
Requiring and setting, its interval range is: the flue gas exit temperature of coal-fired hot-blast stove is 800-1000 DEG C, the anterior temperature of warm-air pipe
For 600-800 DEG C, middle portion temperature is 300-500 DEG C, and the terminal temperature of warm-air pipe is for drying temperature.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410818775.XA CN104634070B (en) | 2014-12-25 | 2014-12-25 | The method for designing of a kind of coal-fired drying unit and device thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410818775.XA CN104634070B (en) | 2014-12-25 | 2014-12-25 | The method for designing of a kind of coal-fired drying unit and device thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104634070A CN104634070A (en) | 2015-05-20 |
CN104634070B true CN104634070B (en) | 2016-11-09 |
Family
ID=53213098
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410818775.XA Expired - Fee Related CN104634070B (en) | 2014-12-25 | 2014-12-25 | The method for designing of a kind of coal-fired drying unit and device thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104634070B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106931734A (en) * | 2017-04-20 | 2017-07-07 | 眉山市民威林产制品有限公司 | A kind of mosquito-repellent incense drying device and method for saving energy consumption |
CN106969598A (en) * | 2017-04-20 | 2017-07-21 | 眉山市民威林产制品有限公司 | A kind of mosquito-repellent incense drying device and dust-removing method |
CN106958990A (en) * | 2017-04-20 | 2017-07-18 | 眉山市民威林产制品有限公司 | A kind of waste heat slow descending device and method for improving mosquito-repellent incense quality |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2363255Y (en) * | 1999-02-11 | 2000-02-09 | 梁德才 | Energy-saving high-efficient dryer |
WO2004017004A1 (en) * | 2002-07-25 | 2004-02-26 | A. Monforts Textilmaschinen Gmbh & Co | Textile machine with recirculating air heating effected by gas-heated heat exchangers |
CN202371971U (en) * | 2011-11-04 | 2012-08-08 | 北京生态岛科技有限责任公司 | Paint slag drying equipment |
-
2014
- 2014-12-25 CN CN201410818775.XA patent/CN104634070B/en not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2363255Y (en) * | 1999-02-11 | 2000-02-09 | 梁德才 | Energy-saving high-efficient dryer |
WO2004017004A1 (en) * | 2002-07-25 | 2004-02-26 | A. Monforts Textilmaschinen Gmbh & Co | Textile machine with recirculating air heating effected by gas-heated heat exchangers |
CN202371971U (en) * | 2011-11-04 | 2012-08-08 | 北京生态岛科技有限责任公司 | Paint slag drying equipment |
Also Published As
Publication number | Publication date |
---|---|
CN104634070A (en) | 2015-05-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106024984A (en) | Drying sintering furnace and drying sintering method | |
CN104208995B (en) | A kind of thermal device improving boiler wet method desulfurization neat stress temperature and method | |
CN205090598U (en) | Coal -fired powder boiler of vertical extreme misery tubular construction | |
CN104634070B (en) | The method for designing of a kind of coal-fired drying unit and device thereof | |
CN103836788A (en) | Surrounding blowing-in integrated gas hot blast stove | |
CN103644561B (en) | A kind of high-efficiency energy-saving biomass steam generator system | |
CN205717142U (en) | Biomass double furnace thorax gas-steam boiler and combustion system thereof | |
CN105202753B (en) | Indirect chain-arranged type straw hot blast heater | |
CN104613641A (en) | Biomass particle combustion furnace for flue-cured tobaccos | |
CN204285782U (en) | Flue-cured tobacco biological particles combustion furnace | |
CN201724384U (en) | Energy-saving environment-friendly high temperature jet type hot blast stove | |
CN105444410A (en) | Biomass hot blast stove and application thereof | |
CN204421052U (en) | A kind of waste heat recovery furnace | |
CN208547225U (en) | A kind of high-efficient hot air furnace formula band drier | |
CN202792519U (en) | Energy-saving temperature control hot air furnace | |
CN205535967U (en) | Biomass burning device | |
CN204730243U (en) | The heating gas system of positive-pressure type biomass powder powder fluidized airflow bed gasification furnace | |
CN207247542U (en) | A kind of humic acid chelating fertilizer hot-blast stove | |
CN203550478U (en) | Roasting furnace | |
CN204693808U (en) | A kind of biomass granule fuel Low Temperature Thermal wind furnace | |
CN205425428U (en) | Hot blast stove | |
CN203758207U (en) | Burner type grain drying complete equipment | |
CN205351398U (en) | High -efficient anti - heating stove that burns | |
CN205641005U (en) | Energy -conserving hot air heater | |
CN205619734U (en) | Moulded coal fast drying system and moulded coal dry -off oven |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161109 Termination date: 20171225 |
|
CF01 | Termination of patent right due to non-payment of annual fee |