CN104631219B - Construction method for changing integral track bed into floating slab track bed in subway operation line tunnel - Google Patents

Construction method for changing integral track bed into floating slab track bed in subway operation line tunnel Download PDF

Info

Publication number
CN104631219B
CN104631219B CN201510001258.8A CN201510001258A CN104631219B CN 104631219 B CN104631219 B CN 104631219B CN 201510001258 A CN201510001258 A CN 201510001258A CN 104631219 B CN104631219 B CN 104631219B
Authority
CN
China
Prior art keywords
concrete
tunnel
construction
stage
operation line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510001258.8A
Other languages
Chinese (zh)
Other versions
CN104631219A (en
Inventor
殷业锁
贾炳义
何贤军
周登辉
段启楠
王薇
施海凤
朱炎新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201510001258.8A priority Critical patent/CN104631219B/en
Publication of CN104631219A publication Critical patent/CN104631219A/en
Application granted granted Critical
Publication of CN104631219B publication Critical patent/CN104631219B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B19/00Protection of permanent way against development of dust or against the effect of wind, sun, frost, or corrosion; Means to reduce development of noise
    • E01B19/003Means for reducing the development or propagation of noise

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

The invention discloses a construction method for changing an integral ballast bed into a floating slab ballast bed in a subway operation line tunnel, which comprises the following construction steps: 1) the first stage is concrete breaking; 2) second-stage concrete is broken, a temporary steel sleeper transition line is installed, and the travelling crane is recovered; 3) breaking concrete in a third stage; 4) constructing the concrete on the base: 5) binding reinforcing steel bars and pouring new base quick-hardening concrete; 6) and laying the floating plates. The method has the advantages that the construction noise is low, the operation line does not stop running, the construction is safe and reliable, and the requirements of urban civilized construction, operation line transportation, operation line safety and construction work efficiency are met.

Description

In metro operation circuit tunnel, solid concrete roabed changes floating plate ballast construction method
Technical field
The present invention relates to solid concrete roabed transformation floating plate railway roadbed construction field, overall specifically in metro operation circuit tunnel Railway roadbed changes floating plate ballast construction method.
Background technology
In city proper busy areas, close on residential block, shopping centre, in the process of moving it is done for reducing train Disturb, solid concrete roabed in existing tunnel need to be abolished, transform floating plate railway roadbed as, such construction at home, still belong to the first time outward, does not have Design, construction precedent can be used for reference.For under the conditions of not stopping transport construct, cutting mechanics lectotype selection, handling appliance research and develop and Equipment, the methods such as interim working line interim measure all targetedly select it is ensured that smooth, safe completes improvement project.
Content of the invention
It is an object of the invention to provide solid concrete roabed changes floating plate ballast construction method in a kind of metro operation circuit tunnel, Abolish existing solid concrete roabed, new floating plate railway roadbed of constructing, the construction method that temporary line transition is opened is efficient, quick, safe, low Noise, recovers to open operation state it is ensured that operation is unaffected with interim twilight orbit in block point.
Technical scheme is as follows:
In metro operation circuit tunnel, solid concrete roabed changes the construction method of floating plate railway roadbed, in metro operation circuit tunnel Block main points construction, block construction duration 4 hours, specific construction procedure is as follows:
1)First stage concrete is abolished:Sawed outside sleeper head along railway roadbed longitudinally by both sides with high frequency, low noise wall Ditch concrete cuts, and is divided into segment with Hand saw, is cut with electric pick and Hydraulic pick, pack outward transport, and depth of cut utilizes special Long 4.3m aluminium alloy ruler, according to tunnel radius and tunnel convergence value, collection in worksite facet apart from ruler vertical dimension and Apart from tunnel central horizontal distance, determine depth of cut;
2)Release existing gapless track:With internal combustion rail saw, existing gapless rail is made into 25m mark rail jointed track, and Jewel hole clamping plate connects;
3)Rope saw mounting groove cutting:Cut 25cm width rope saw mounting groove with wall sawing seam and electric pick in the middle of 3.6m plate, cut Cut depth for first stage excision mouth concrete surface to tunnel tube wall distance;
4)Second stage concrete is abolished and interim transition:Carry out second stage using two high frequencies, low noise rope saw to mix Solidifying soil cutting, and hang away the concrete slab of excision with cantilever crane in tunnel, sets up interim transition circuit using steel sleeper, two steel sleepers it Between have longitudinally connected bar to connect, steel sleeper adopts buttress form, position and the elevation of steel sleeper can be adjusted flexibly, so that temporary line is reached Design attitude, meets driving and requires;
5)Phase III concrete is abolished:Using high frequency, low noise wall saw cut substrate plain concrete, after the completion of cutting, Abolished using high frequency, low noise Hydraulic pick and electric pick, labor cleaning after the completion of abolishing;
6)Base concrete is constructed:The scene colligation of substrate reinforcing bar, after the completion of colligation, using interpolation fibre modification Site Fast hardening concrete pour substrate;
7)Floating plate is laid:Utilize cantilever crane handling, laying floating plate after substrate concrete reaches design strength, laying completes Jacking floating plate reaches design requirement afterwards, and steel rail laying simultaneously adjusts and reaches design altitude, recovers circuit.
The described long 4.3m of aluminium alloy ruler, measures depth of cut.
Described wall is sawed, saw belongs to high frequency to rope, noise devices carry out concrete cutting.
Described steel sleeper adopts buttress support modes, is connected it is ensured that steel sleeper twilight orbit with connecting rod between two steel sleepers The globality of structure.
Special jib crane is adopted, width is less than 2.6m, can pass through 150m sharp radius curve, full in described subway tunnel Sufficient working line gauge requires.
The construction method of the present invention solve in block point efficiently, quick, safety, low noise existing solid concrete roabed Abolish transformation and upgrade to construct for floating plate railway roadbed, do not affect operation it is ensured that work progress, operation security.
Brief description
Fig. 1 is that three stage transverse section abolished by the solid concrete roabed of the present invention.
In figure is numbered:1 excises area for the first stage, and 2 excise area for second stage, and 3 excise area for the phase III.
Specific embodiment
Change the construction method of floating plate railway roadbed referring to solid concrete roabed in accompanying drawing ferrum operating line tunnel, in metro operation circuit Block main points construction in tunnel, block construction duration 4 hours, specific construction procedure is as follows:
1)First stage concrete is abolished:Sawed outside sleeper head along railway roadbed longitudinally by both sides with high frequency, low noise wall Ditch concrete cuts, and is divided into fritter with Hand saw, is cut with electric pick and Hydraulic pick, pack outward transport, and depth of cut utilizes special Long 4.3m aluminium alloy ruler, according to tunnel radius and tunnel convergence value, collection in worksite facet apart from ruler vertical dimension and Apart from tunnel central horizontal distance, determine depth of cut;
2)Release existing gapless track:With internal combustion rail saw, existing gapless rail is made into 25m mark rail jointed track, and Jewel hole clamping plate connects;
3)Rope saw mounting groove cutting:Cut 25cm width rope saw mounting groove with wall sawing seam and electric pick in the middle of 3.6m plate, cut Cut depth for first stage excision mouth concrete surface to tunnel tube wall distance;
4)Second stage concrete is abolished and interim transition:Carry out second stage using two high frequencies, low noise rope saw to mix Solidifying soil cutting, and hang away the concrete slab of excision with cantilever crane in tunnel, sets up interim transition circuit using steel sleeper, two steel sleepers it Between have longitudinally connected bar to connect, steel sleeper adopts buttress form, position and the elevation of steel sleeper can be adjusted flexibly, so that temporary line is reached Design attitude, meets driving and requires;
5)Phase III concrete is abolished:Using high frequency, low noise wall saw cut substrate plain concrete, after the completion of cutting, Abolish base element concrete, labor cleaning after the completion of abolishing using high frequency, low noise Hydraulic pick and electric pick;
6)Base concrete is constructed:The scene colligation of substrate reinforcing bar, after the completion of colligation, using interpolation fibre modification Site Fast hardening concrete pour substrate;
7)Floating plate is laid:Utilize cantilever crane handling, laying floating plate after substrate concrete reaches design strength, laying completes Jacking floating plate reaches design requirement afterwards, and steel rail laying simultaneously adjusts and reaches design altitude, and recovers circuit.
The described long 4.3m of aluminium alloy ruler, measures depth of cut.Wall is sawed, saw belongs to high frequency to rope, noise devices are entered Row concrete cuts.Steel sleeper adopts buttress support modes, is connected it is ensured that steel sleeper globality with connecting rod between two steel sleepers.Ground Special jib crane is adopted, width is less than 2.6m, can pass through 150m sharp radius curve, meet working line gauge in ferrum tunnel Require.

Claims (2)

1. in metro operation circuit tunnel, solid concrete roabed changes the construction method of floating plate railway roadbed it is characterised in that in metro operation Block main points construction in circuit tunnel, block construction duration 4 hours, specific construction procedure is as follows:
1)First stage concrete is abolished:Sawed outside sleeper head along railway roadbed longitudinally by both sides ditch with high frequency, low noise wall Concrete cuts, and is divided into fritter with Hand saw, is cut with electric pick and Hydraulic pick, pack outward transport, and depth of cut utilizes long 4.3m aluminum Alloy ruler measures, and according to tunnel radius and tunnel convergence value, collection in worksite facet is apart from described long 4.3m aluminium alloy ruler Vertical dimension and apart from tunnel central horizontal distance, determines depth of cut;
2)Release existing gapless track:With internal combustion rail saw, existing gapless rail is made into 25m mark rail jointed track, and jewel hole Connected with clamping plate;
3)Rope saw mounting groove cutting:Dig out 25cm width rope saw mounting groove with wall sawing seam and electric pick in the middle of 3.6m plate, cutting is deep To abolish depth identical with first stage concrete for degree;
4)Second stage concrete is abolished and interim transition:Carry out second stage concrete using two high frequencies, low noise rope saw Cutting, and the concrete slab of excision is hung away with cantilever crane in tunnel, set up interim transition circuit using steel sleeper, have between two steel sleepers Longitudinally connected bar connects, and steel sleeper adopts buttress supporting form, position and the elevation of steel sleeper can be adjusted flexibly, so that temporary line is reached Design attitude, meets driving and requires;
5)Phase III concrete is abolished:Using high frequency, low noise wall saw cut substrate plain concrete, after the completion of cutting, use Substrate plain concrete abolished by high frequency, low noise Hydraulic pick and electric pick, labor cleaning after the completion of abolishing;
6)Base concrete is constructed:The scene colligation of substrate reinforcing bar is after the completion of colligation, fast using interpolation fibre modification Site Dry concrete pours substrate;
7)Floating plate is laid:Utilize cantilever crane handling, laying floating plate after substrate plain concrete reaches design strength, laid After one-tenth, jacking floating plate reaches design requirement, and steel rail laying simultaneously adjusts and reaches design altitude, and recovers circuit.
2. construction method according to claim 1 it is characterised in that:The cantilever crane adopting in described subway tunnel, width Less than 2.6m, 150m sharp radius curve can be passed through, meet working line gauge and require.
CN201510001258.8A 2015-01-04 2015-01-04 Construction method for changing integral track bed into floating slab track bed in subway operation line tunnel Active CN104631219B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510001258.8A CN104631219B (en) 2015-01-04 2015-01-04 Construction method for changing integral track bed into floating slab track bed in subway operation line tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510001258.8A CN104631219B (en) 2015-01-04 2015-01-04 Construction method for changing integral track bed into floating slab track bed in subway operation line tunnel

Publications (2)

Publication Number Publication Date
CN104631219A CN104631219A (en) 2015-05-20
CN104631219B true CN104631219B (en) 2017-03-08

Family

ID=53210420

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510001258.8A Active CN104631219B (en) 2015-01-04 2015-01-04 Construction method for changing integral track bed into floating slab track bed in subway operation line tunnel

Country Status (1)

Country Link
CN (1) CN104631219B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105274911A (en) * 2015-11-17 2016-01-27 中铁四局集团有限公司 Construction method for cutting, chiseling, pushing, breaking and transforming existing integral ballast bed of subway
CN105350408A (en) * 2015-11-17 2016-02-24 中铁四局集团有限公司 Construction method for cutting, splitting, breaking and reforming existing integral track bed of subway
ES2574538B1 (en) * 2015-12-09 2017-04-07 Redalsa, S.A. SYSTEM FOR CHANGE TO THREE RAILS IN ROADS IN PLATE OF POLIVALENT OR MONOVALENT TOUCH OF TWO RAILS AND PROCEDURE FOR SUCH SYSTEM
CN106014425A (en) * 2016-06-27 2016-10-12 中交公局第三工程有限公司 Dismounting method for metro section segments intruding into tunnel gauge
CN106835864B (en) * 2017-03-17 2019-04-05 中铁三局集团有限公司 High-speed rail non-fragment orbit repairs solid concrete roabed and cuts transportation resources
CN113529506A (en) * 2021-06-02 2021-10-22 北京铁科特种工程技术有限公司 Construction method for replacing and paving urban rail integral ballast bed
CN113529505A (en) * 2021-06-02 2021-10-22 北京铁科特种工程技术有限公司 Complete cutting equipment for ballastless track plate of urban rail

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1181201A (en) * 1997-09-05 1999-03-26 Kumagai Gumi Co Ltd Panel of subway track slab
CN102108658B (en) * 2009-12-29 2012-10-31 上海市城市建设设计研究院 Construction method for modifying conventional structural slab into subway bed foundation
CN103603241B (en) * 2013-07-26 2016-08-10 北京九州一轨隔振技术有限公司 Floating vibration isolation structure of track system
CN104233910A (en) * 2014-10-09 2014-12-24 徐州徐工铁路装备有限公司 Cable saw cutting control system and cable saw cutting device

Also Published As

Publication number Publication date
CN104631219A (en) 2015-05-20

Similar Documents

Publication Publication Date Title
CN104631219B (en) Construction method for changing integral track bed into floating slab track bed in subway operation line tunnel
CN102146796B (en) Construction technology for inverted arch of two-track tunnel of high-speed railway
CN103485288B (en) A kind ofly pass through both wired double-deck jacking culvert construction technology
CN101906768B (en) Panel construction method of concrete faced rock-fill dam
CN205934734U (en) Supplementary handing equipment of prefabricated T roof beam sideslip
CN104631231B (en) Construction method for breaking integral track bed in subway operation line tunnel
CN204940141U (en) The reinforcement system of existing line in Framed underpass bridge process
CN105672356A (en) Underground structure of municipal pipeline group spanning tunnel and construction method for underground structure
CN106835864A (en) The maintenance solid concrete roabed cutting transportation resources of high ferro non-fragment orbit
CN103967052B (en) A kind of method of protecting the new and old frame core-tube system substrate discrepancy in elevation soil body
CN106948350A (en) The rapid constructing method of deep basal pit accessory structure
CN101922296A (en) Jacking iron and method for propelling box culvert by utilizing jacking iron
CN202359511U (en) Subway tunnel ditch and track bed one-time pouring formwork structure
CN104652299A (en) Electrified railway existing bridge and culvert whole-hole moving-out construction method
CN208121485U (en) A kind of small-radius shield precast track plate
CN202482727U (en) Temporary road surface pavement structure for ultra-shallow burying excavation underground project
CN210621353U (en) Long-sleeper embedded type ballastless track bed slab reinforcing steel bar integral binding, hoisting and installing system
CN112962366A (en) Reverse paving construction method for CRTS III type track slab in mountainous area
CN205477663U (en) Synchronous lining cutting steel mould trolley of inverted arch
KR101234091B1 (en) Method of underground railway crossing over direct installation of precast concrete slab
CN105350408A (en) Construction method for cutting, splitting, breaking and reforming existing integral track bed of subway
CN204163103U (en) The track foundation of subway station straddle truck
CN206693039U (en) The attachment means of big longitudinal slope mountain highway halfway up the hill bridge plate beam and bent cap
CN217482134U (en) Reinforced concrete drain pipe with firm base
CN102535302A (en) Temporary pavement blanket structure for super-shallow buried subsurface-excavated underground engineering, and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Yin Yesuo

Inventor after: Jia Bingyi

Inventor after: He Xianjun

Inventor after: Zhou Denghui

Inventor after: Duan Qinan

Inventor after: Wang Wei

Inventor after: Shi Haifeng

Inventor after: Zhu Yanxin

Inventor before: Yin Yesuo

Inventor before: Jia Bingyi

Inventor before: Zhou Denghui

Inventor before: Duan Qinan

Inventor before: Wang Wei

Inventor before: Shi Haifeng

Inventor before: Zhu Yanxin

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant