CN104625567A - Installation process of activated feeder - Google Patents
Installation process of activated feeder Download PDFInfo
- Publication number
- CN104625567A CN104625567A CN201510057285.7A CN201510057285A CN104625567A CN 104625567 A CN104625567 A CN 104625567A CN 201510057285 A CN201510057285 A CN 201510057285A CN 104625567 A CN104625567 A CN 104625567A
- Authority
- CN
- China
- Prior art keywords
- chain block
- activating feeder
- silo
- place
- installing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23P—METAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
- B23P11/00—Connecting or disconnecting metal parts or objects by metal-working techniques not otherwise provided for
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Auxiliary Methods And Devices For Loading And Unloading (AREA)
Abstract
The invention provides an installation process of an activated feeder. The installation processes includes the following steps of unloading, equipment conveying, chain block hoisting and rotating, installing of a support of the activated feeder, loosening of chain blocks, adjusting and controlling of wiring of cables, installing of a compressed air pipeline, and debugging after installing. According to chain block hoisting and rotating, the motor side is located on the outermost side when entering the opening of a silo, so a body needs to be rotated by 90 degrees through chain blocks, and the motor side is rotated to the drawing in-position side; the body is placed down at the moment, a round sleeper is cushioned below according to the selection fitting direction for selection fitting, and the body is rotated in position through the chain blocks on the periphery; it is guaranteed that the body is located under the opening of a hopper. According to the installation process, use is convenient, and the activated feeder can be successfully and safely installed in position under the circumstance that the size of the lower portion of the silo is small.
Description
Technical field
The present invention relates to equipment installing area, particularly relate to a kind of activating feeder mounting process.
Background technology
Large-scale closed silo cluster application is stored up in harbour bulk cargo terminals transfer, has reduction pollution to external world, reaches environment protecting.Silo cluster has just been applied to Coal-Transferring Base and harbour general cargo wharf, from now on, has larger development prospect at Coal-Transferring Base and general cargo wharf field, harbour.Silo bottom feed must be set to materials device, and activating feeder has activation and feed dual-use function, and can make material even drop down, and flow is controlled, have when motor quits work, in coal bunker, material is automatically locked and stops gliding simultaneously, does not need to arrange lock gate hatch.Guarantee that activating feeder body does not destroy by extraneous silo construction, therefore need install after silo construction completes, silo lower dimension is narrow and small, how the safe installation in position of activation material-extruding machine is become a great problem.
Summary of the invention
The object of the invention is to solve silo lower dimension narrow and small, activation material-extruding machine can not the difficult problem of safe installation in position, and provides a kind of activation material-extruding machine mounting process.
The present invention for achieving the above object, a kind of activation material-extruding machine mounting process is provided, the step comprised have unload, equipment is transported, jack lifting rotations, the loose hook of activating feeder support installing, chain block, adjustment and control cables wiring, compressed air line installation, install post debugging.
Unload: because motor is positioned at activating feeder side, therefore need, by crane lifting, select special hanger to lift, be transported to silo mouth place by Secondary Transport, debug after installing;
Equipment is transported: equipment is positioned at silo mouth place, is sling by activating feeder body by chain block, is pulled to silo inside, below bell mouth, completes in place by maintenance beam top walking dolly;
Jack lifting rotates: during because entering silo mouth, motor side in outermost, therefore needs by jack by body 90-degree rotation, and motor side rotates to drawing side in place; Now put down by body, circular sleeper is established according to choosing dress direction pad in below, for choosing dress, forwards body choosing to position by surrounding side chain block; Guarantee that body is in immediately below bell mouth;
Activating feeder support installing: by top chain block again pull-up after being rotated in place, installs activating feeder body lower part support, and after completing location, adjustment according to figure paper size, support bottom is intermittently welded with pre-embedded steel slab, jack pine hook after completing; Be adjusted to most rational position, subsequently the backing plate on mounting bracket top and spring;
The loose hook of chain block: according to figure paper size, after support installing completes, puts activating feeder body above support, completes the loose hook of chain block, and the now installation of connector and welding job complete;
The wiring of adjustment and control cables: in place, the installation that complete electric cabinet and Pneumatic controlled box according to on-site actual situations; Carry out the wiring of control cables and power cable according to drawing requirement, and complete proof-reading;
Compressed air line is installed: install air source box, air inlet and outlet pipe, ball valve;
Install post debugging: start on the spot, complete the debugging of activating feeder body, determine the choosing dress direction of motor.
The invention has the beneficial effects as follows: one activation material-extruding machine mounting process of the present invention, easy to use, when silo lower dimension is narrow and small, can will activate material-extruding machine success installation in position safely.
Accompanying drawing explanation
Fig. 1 is a kind of flow chart activating material-extruding machine mounting process of the present invention;
Detailed description of the invention
Be described in detail with reference to accompanying drawing below with reference to embodiments of the invention.
A kind of activation material-extruding machine mounting process, the step comprised have unload, equipment is transported, jack lifting rotations, the loose hook of activating feeder support installing, chain block, adjustment and control cables wiring, compressed air line installation, install post debugging.
Unload: because motor is positioned at activating feeder side, therefore need, by crane lifting, select special hanger to lift, be transported to silo mouth place by Secondary Transport, debug after installing;
Equipment is transported: equipment is positioned at silo mouth place, is sling by activating feeder body by chain block, is pulled to silo inside, below bell mouth, completes in place by maintenance beam top walking dolly;
Jack lifting rotates: during because entering silo mouth, motor side in outermost, therefore needs by jack by body 90-degree rotation, and motor side rotates to drawing side in place; Now put down by body, circular sleeper is established according to choosing dress direction pad in below, for choosing dress, forwards body choosing to position by surrounding side chain block; Guarantee that body is in immediately below bell mouth;
Activating feeder support installing: by top chain block again pull-up after being rotated in place, installs activating feeder body lower part support, and after completing location, adjustment according to figure paper size, support bottom is intermittently welded with pre-embedded steel slab, jack pine hook after completing; Be adjusted to most rational position, subsequently the backing plate on mounting bracket top and spring;
The loose hook of chain block: according to figure paper size, after support installing completes, puts activating feeder body above support, completes the loose hook of chain block, and the now installation of connector and welding job complete;
The wiring of adjustment and control cables: in place, the installation that complete electric cabinet and Pneumatic controlled box according to on-site actual situations; Carry out the wiring of control cables and power cable according to drawing requirement, and complete proof-reading;
Compressed air line is installed: install air source box, air inlet and outlet pipe, ball valve;
Install post debugging: start on the spot, complete the debugging of activating feeder body, determine the choosing dress direction of motor.
Claims (1)
1. an activating feeder mounting process, it is characterized in that, the step comprised have unload, equipment is transported, jack lifting rotations, the loose hook of activating feeder support installing, chain block, adjustment and control cables wiring, compressed air line installation, install post debugging;
Unload: because motor is positioned at activating feeder side, therefore need, by crane lifting, select special hanger to lift, be transported to silo mouth place by Secondary Transport, debug after installing;
Equipment is transported: equipment is positioned at silo mouth place, is sling by activating feeder body by chain block, is pulled to silo inside, below bell mouth, completes in place by maintenance beam top walking dolly;
Jack lifting rotates: during because entering silo mouth, motor side in outermost, therefore needs by jack by body 90-degree rotation, and motor side rotates to drawing side in place; Now put down by body, circular sleeper is established according to choosing dress direction pad in below, for choosing dress, forwards body choosing to position by surrounding side chain block; Guarantee that body is in immediately below bell mouth;
Activating feeder support installing: by top chain block again pull-up after being rotated in place, installs activating feeder body lower part support, and after completing location, adjustment according to figure paper size, support bottom is intermittently welded with pre-embedded steel slab, jack pine hook after completing; Be adjusted to most rational position, subsequently the backing plate on mounting bracket top and spring;
The loose hook of chain block: according to figure paper size, after support installing completes, puts activating feeder body above support, completes the loose hook of chain block, and the now installation of connector and welding job complete;
The wiring of adjustment and control cables: in place, the installation that complete electric cabinet and Pneumatic controlled box according to on-site actual situations; Carry out the wiring of control cables and power cable according to drawing requirement, and complete proof-reading;
Compressed air line is installed: install air source box, air inlet and outlet pipe, ball valve;
Install post debugging: start on the spot, complete the debugging of activating feeder body, determine the choosing dress direction of motor.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510057285.7A CN104625567A (en) | 2015-02-04 | 2015-02-04 | Installation process of activated feeder |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510057285.7A CN104625567A (en) | 2015-02-04 | 2015-02-04 | Installation process of activated feeder |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104625567A true CN104625567A (en) | 2015-05-20 |
Family
ID=53205045
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510057285.7A Pending CN104625567A (en) | 2015-02-04 | 2015-02-04 | Installation process of activated feeder |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104625567A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105773138A (en) * | 2016-04-12 | 2016-07-20 | 中交航局安装工程有限公司 | O-type four-car dumper installation technology |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4587703A (en) * | 1985-01-16 | 1986-05-13 | Apple Computer, Inc. | Method and apparatus using a multifaceted turret for robotic assembly |
US5572785A (en) * | 1994-07-27 | 1996-11-12 | Eastman Kodak Company | Apparatus and method for automated assembly of precision components |
KR20080101683A (en) * | 2007-05-18 | 2008-11-21 | 와일드 파르마 에스. 알. 엘. | An apparatus and method for continuously moving flexible containers from a rotary machine to a conveyor |
CN202063537U (en) * | 2011-04-29 | 2011-12-07 | 山东博润工业技术有限公司 | Flat rotary type activation feeder under material pile |
CN102502194A (en) * | 2011-07-02 | 2012-06-20 | 山东博润工业技术有限公司 | Square activation feeding machine |
CN203033354U (en) * | 2013-01-14 | 2013-07-03 | 秦皇岛优格玛工业技术有限公司 | Activating feeder |
-
2015
- 2015-02-04 CN CN201510057285.7A patent/CN104625567A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4587703A (en) * | 1985-01-16 | 1986-05-13 | Apple Computer, Inc. | Method and apparatus using a multifaceted turret for robotic assembly |
US5572785A (en) * | 1994-07-27 | 1996-11-12 | Eastman Kodak Company | Apparatus and method for automated assembly of precision components |
KR20080101683A (en) * | 2007-05-18 | 2008-11-21 | 와일드 파르마 에스. 알. 엘. | An apparatus and method for continuously moving flexible containers from a rotary machine to a conveyor |
CN202063537U (en) * | 2011-04-29 | 2011-12-07 | 山东博润工业技术有限公司 | Flat rotary type activation feeder under material pile |
CN102502194A (en) * | 2011-07-02 | 2012-06-20 | 山东博润工业技术有限公司 | Square activation feeding machine |
CN203033354U (en) * | 2013-01-14 | 2013-07-03 | 秦皇岛优格玛工业技术有限公司 | Activating feeder |
Non-Patent Citations (1)
Title |
---|
于鹏,韩伯涛: "筒仓下活化给料机安装工艺", 《中国港湾建设》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105773138A (en) * | 2016-04-12 | 2016-07-20 | 中交航局安装工程有限公司 | O-type four-car dumper installation technology |
CN105773138B (en) * | 2016-04-12 | 2020-04-28 | 中交一航局安装工程有限公司 | O-shaped four-tipping car dumper mounting process |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8250836B2 (en) | Apparatus and method for automatically loading drums into drum container | |
CN108049874A (en) | It is a kind of to lay recovery system for the water surface support of deep-sea mining engineering | |
CN204454554U (en) | A kind of boat coal special pneumatic oil filling riser | |
RU2012111698A (en) | FEEDER FOR MOVING BULK MATERIAL | |
CN104625567A (en) | Installation process of activated feeder | |
CN106966187A (en) | A kind of efficient dry ash bulk machine | |
CN105836491A (en) | Special bin valve for reducing dust quantity | |
CN212402751U (en) | Ore sand holding vessel | |
CN204701775U (en) | A kind of packing device of powdery emulsifying explosive | |
CN104477628A (en) | Absorbing type rotating hopper | |
CN110668123B (en) | Full-automatic conveying line for machining clamping pieces | |
CN107934265A (en) | The attaching/detaching apparatus and method of Full-automatic lock for container | |
CN209578727U (en) | A kind of stubborn valve machine | |
CN102678942A (en) | Single-layer single-gate heavy hammer type air-lock flap valve | |
CN206969555U (en) | A kind of feed opening can self-closed conveying worm | |
CN202717391U (en) | Automatic dustless bulk loader | |
CN108356714B (en) | A kind of shot-blasting machine rotary charging device | |
CN103224143A (en) | High-angle rotation wire feeding device of bucket wheel machine | |
JP2013534613A (en) | Feeder device | |
CN207107855U (en) | A kind of robot arm device for being used to reprint conveying egg plate | |
CN209291565U (en) | A kind of oblique anti-blocking hopper released of construction site fluent material | |
CN204161400U (en) | The adjustable buckle oil drum vehicle of a kind of handling | |
CN110498177A (en) | Hermetically sealed environment-friendly type material transfer device in bulk and its method | |
KR20130088387A (en) | Watering device for pay loader | |
CN203750617U (en) | Large-dip-angle belt automatic ball-feeding system for full-automatic tower mill |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150520 |